The document provides a progress presentation on a water pipe transmission project. It summarizes that site mobilization and contractor facilities are 100% ready. It also notes that approximately 30 km of engineering drawings have been approved and pipes for 27 km have been received on site. Some highlights and concerns are mentioned such as shop drawings not yet received and right of way issues to be addressed on some sections of the pipeline. Health and safety statistics for the reporting period are also included.
4. NOC & Engineering Status
NOCs Obtained from Authority
• Ministry of Oil and GAS
• ROP
• Municipality Permit
• Ministry of Transport
• Ministry of Environment & Climate
• Ooredoo
Engineering Status
• Approximately 30 Km of Approved drawing received from HEICO
• Chambers Drawings Yet to be received
5. Procurement Status
Pipes Received
• Approximately 27 km of pipes reached site as per the last procurement schedule
Bends & Accessories
• Couple Bends and T’s Received on Site on 27 November 2021
6. Projects Highlights & Concerns
• Shop Drawings for Air Valves, Washout and Butterfly Valves noy yet received
• Air Vents and Couplings not yet received
• Piping details inside Chambers not yet received
• FOC cable issue not yet finalized, affecting the pipe surround and backfilling works
• Site Obstructions issues ( Private Properties across the pipe path)
• Right of way to be properly executed ( e.g. stations 12 to 16 and Stations 18 to 21).
7. Project Resources
Plant & Equipment
Description Nos. Location Status Description Nos. Location Status
Excavator 15 S W
Dozer 2 S W
Shovel 5 S W
JCB 1 C W
Hiab 1 S W
Crane 1 C W
1 Ton Pick-up 5 S W
3 Ton Pick-up 3 S W
Hand Roller Compactor 1 C W
Plate Compactor 2 C W
Generator 5 kva 2 C W
Generator 275 kva 1 C W
Generator 86 kva 1 C W
Diesel tanker 1 S W
Service vehicle 1 C/S W
Bus 60 seater 2 C/S W
Water Tanker 2,000 Gallon 1 C/S W
Tipper 18cum 6 S W
Concrete Mixer 1 C W
Pressure Pump 2 C W
4X4 car 3 S W
Saloon car 2 C W
Partner Cutter 2 C W
Concrete Vibrator 2 C W
Bob Cat 1 C W
Location: C-Camp, S-Site
Status: W-working, I-Idle, B/D-Broken down
SUPERVISORY STAFF & OFFICE PERSONNEL
Project Manager 1
Section Engineer 2
Office Engineer & QA/QC 1
Planning Engineer 1
HSE Engineer 1
HSE Officer 1
Draftsman 1
Site In-charge/Foreman 8
Surveyor 4
PRO 1
Lab Technician
Secretary
Chainman 2
PMV Coordinator 1
Document Controller 1
Storekeeper 1
Watchman 1
Electrical Charge hand 1
Sub-total A 28
LABOUR
Carpenter 13
Steel fixer 4
Mason 12
Pipe Fitter/Plumber 17
Helper 14
Operator 24
Electrician 2
Mechanic/Tyre man 5
Driver 14
Sub-total B 105
Grand Total (A+B) 133
10. Project Controls – Project Execution Quantities
Date 25-Nov-21
Project Over all Progress
Planned Actual
Works Designated Total Qty Unit
Contractual
Weightage
Total Planned To date Total Actual To date Planned To date Actual To date 9.407% 10.48%
Excavation Works 90000Lm 32% 15,600.0 16,165.2 17.33% 17.96% 5.55% 5.75%
Pipe Laying Works 90000Lm 30% 7,971.4 11,847.0 8.86% 13.16% 2.66% 3.95%
Pipe Surround 90000Lm 7.5% 7,971.4 9,445.0 8.86% 10.49% 0.66% 0.79%
Backfilling 90000Lm 7.5% 1,371.4 - 1.52% 0.00% 0.11% 0.00%
Chambers Works 116Nos 7% 6 - 4.76% 0.00% 0.33% 0.00%
Wadi Works 5000Lm 8% - - 0.00% 0.00% 0.00% 0.00%
Hydro Testing 90000Lm 8% 1,022.9 - 1.14% 0.00% 0.09% 0.00%
11. Health & Safety Issues
HSE Indicators During the month (nos.) Cumulative (nos.)
Total Manpower at project site. (A)
(Including all Contractor, Consultant and Subcontractor
employees)
Total – 125
Monthly Average (Total
Manpower / No. of months
completed)
211/2=106
Total no. of Subcontractors in Project 0 0
Road Traffic Accidents 0 0
Utility Damages 0 0
Environmental accidents 0 0
First Aid cases 0 0
Restricted work case 0 0
Near miss cases 3 5
HSE Observations 24 26
Lost Time 0 0
Fatality 0 0
Property damage 0 0
Safe working Days without LTI (B) 27 55
Man hours worked without LTI = (A) X (B) X (Avg. working
hrs./day) 33,750 57,830
Average quantities of
waste generated
(Solid & Liquid)
During the month
(In Kg)
Total (up to date)
(In Kg)
Hazardous 0 kg 0 kg
Non-hazardous 0 kg 0 kg
Sewage 511030 kg 511030 kg
HSE Activity During the month Total (up to date)
HSE Meetings 0 2
HSE Audits 0 0
HSE Inspections 2 2
Tool Box talks 81 109
HSE Training
(by session)
3 4
Site Inductions
(no. of Employees)
37 123
Emergency Drills 0 0
HSE (NCR) 1 1