SlideShare une entreprise Scribd logo
1  sur  5
Télécharger pour lire hors ligne
WEEKLY REPORT
- - Ebbin Daniel
OCT 11 - OCT 16
Electrical Engineer
CONTENTS:
1. Maintenance and troubleshooting
a. Rewiring of the Hydraulic valve wire connecters for the Cuber Arm.
b. Troubleshooting and rewiring the power outage on the dry side.
c. Troubleshooting of the BSA panel.
d. Troubleshooting of the wrapper machine.
e. Troubleshooting for Cuber up/down mechanism.
2. Current Projects
a. Height adjustment for pavers on wet side.
b. Replacing limit switches on the conveyors on the block plant.
A.Rewiring of the Hydraulic valve wire connecters for the
Cuber Arm.
Cause of the Problem:
 Wear and tear of the wire connector.
 Delay in arm movements.
 Possible cause of a loose contact.
Troubleshooting:
 A new 120v connector was replaced with the old one.
 The connector was rewired from the junction box.
 New connectors were ordered for future use.
B. Troubleshooting and rewiring the power outage on the dry
side.
Cause of the Problem:
 No power on the dry side conveyor.
 Photocells inactive.
 Complete loss of power till the cuber.
Troubleshooting:
 Possibility of a cut wire during cleanup was troubleshot.
 All loose/cut ends were reconnected using wire nuts.
 Possible Fault at the BSA panel was troubleshot.
 The wire was found and was traced to the junction box.
 It was replaced with a new connection.
C.Troubleshooting of the BSA panel.
Cause of the Problem:
 BSA panel showing various fault conditions at the wet side control panel.
 BSA motor tripping.
 Fault at different intervals.
Troubleshooting:
 PLC program was used to find different error codes.
 Based on various inputs and outputs various wires were rewired.
 All loose joints were tightly connected.
 BSA working fine without any possible fault message.
 However a lot of wiring has to be labelled and tightened as they are not in proper condition.
D. Troubleshooting of the wrapper machine
Cause of the Problem:
 Wrapper was not moving.
 Error message at the wrapper panel.
Troubleshooting:
 The Error code was traced out to be the Safe position photo eye.
 It was readjusted to get the green light on top which determines that the switch is made.
 The metal frame is still loose and could cause future misalignment. Thereby in needs to be fixed
or replaced.
E.Troubleshooting for Cuber up/down mechanism.
Cause of the Problem:
 Cuber not going up and down.
 Manual/ auto operation cannot perform.
 Delay in dry side production.
Troubleshooting:
 A loose wire was found which was replaced.
 Eventually the fuse had also blown which was also replaced.
Current Projects:
A.Height adjustment for pavers on wet side.
 Different manufactures for height measurement were contacted and are attached.
 Informal quote was obtained.
 Old sensors for accurate reading are still being tested.
 Have to follow up with Mr. RED to inquire about height measurement system in arcadia.
B. Replacing limit switches on the conveyors on the block plant.
 Conveyor 1 on the batching side of the Block plant is sometimes pouring more
materials.
 The limit switch might be obsolete would need to be changed.
 Have to follow up with Mr. Raghu to replace it during the next cleanup time.

Contenu connexe

En vedette (9)

Renee martin resume 2016
Renee martin resume 2016Renee martin resume 2016
Renee martin resume 2016
 
img-519103314
img-519103314img-519103314
img-519103314
 
Test case
Test caseTest case
Test case
 
Begeleiding aanleg beheersmaatregel Ootmarsumsestraat Oldenzaal
Begeleiding aanleg beheersmaatregel Ootmarsumsestraat OldenzaalBegeleiding aanleg beheersmaatregel Ootmarsumsestraat Oldenzaal
Begeleiding aanleg beheersmaatregel Ootmarsumsestraat Oldenzaal
 
Scan_04072016105610
Scan_04072016105610Scan_04072016105610
Scan_04072016105610
 
Slideshare presentacion
Slideshare presentacion Slideshare presentacion
Slideshare presentacion
 
Sulfonated perfluorocyclopentenyl polymers and uses thereof
Sulfonated perfluorocyclopentenyl polymers and uses thereofSulfonated perfluorocyclopentenyl polymers and uses thereof
Sulfonated perfluorocyclopentenyl polymers and uses thereof
 
Roseroo inés bdiiit3
Roseroo inés  bdiiit3Roseroo inés  bdiiit3
Roseroo inés bdiiit3
 
2. cazatalentos
2. cazatalentos2. cazatalentos
2. cazatalentos
 

Similaire à Ebbin_oct11

wind turbine _ battery recharge controller
wind turbine _ battery recharge controller wind turbine _ battery recharge controller
wind turbine _ battery recharge controller
mussa_000
 
Conduit Lighting Project
Conduit Lighting ProjectConduit Lighting Project
Conduit Lighting Project
Michael Glover
 
Replacement and reconnection of breaker in 115 kV substation - Final (English)
Replacement and reconnection of breaker in 115 kV substation - Final (English)Replacement and reconnection of breaker in 115 kV substation - Final (English)
Replacement and reconnection of breaker in 115 kV substation - Final (English)
Pablo Miguel Jurado
 
Install an electric shower
Install an electric showerInstall an electric shower
Install an electric shower
Zulaiha Amaria
 
E. Flaws in the Resonant Cylinder and the Associated Design Iterations
E. Flaws in the Resonant Cylinder and the Associated Design IterationsE. Flaws in the Resonant Cylinder and the Associated Design Iterations
E. Flaws in the Resonant Cylinder and the Associated Design Iterations
Kurt Zeller
 

Similaire à Ebbin_oct11 (20)

Ebbin_oct3
Ebbin_oct3Ebbin_oct3
Ebbin_oct3
 
WHO final
WHO  finalWHO  final
WHO final
 
CV J LOWTHER WORD
CV J LOWTHER WORDCV J LOWTHER WORD
CV J LOWTHER WORD
 
Project involvement and construction.
Project involvement and construction.Project involvement and construction.
Project involvement and construction.
 
wind turbine _ battery recharge controller
wind turbine _ battery recharge controller wind turbine _ battery recharge controller
wind turbine _ battery recharge controller
 
CCD OPERATORS TRAINING PPT (1).pptx
CCD OPERATORS TRAINING PPT (1).pptxCCD OPERATORS TRAINING PPT (1).pptx
CCD OPERATORS TRAINING PPT (1).pptx
 
Lessons learnt electrical incident penrith wrp july 2019
Lessons learnt electrical incident penrith wrp july 2019Lessons learnt electrical incident penrith wrp july 2019
Lessons learnt electrical incident penrith wrp july 2019
 
Conduit Lighting Project
Conduit Lighting ProjectConduit Lighting Project
Conduit Lighting Project
 
Physics project chirag
Physics project chiragPhysics project chirag
Physics project chirag
 
Replacement and reconnection of breaker in 115 kV substation - Final (English)
Replacement and reconnection of breaker in 115 kV substation - Final (English)Replacement and reconnection of breaker in 115 kV substation - Final (English)
Replacement and reconnection of breaker in 115 kV substation - Final (English)
 
Case Study – How an Unchecked Capacitor can cause loss of revenue
Case Study – How an Unchecked Capacitor can cause loss of revenueCase Study – How an Unchecked Capacitor can cause loss of revenue
Case Study – How an Unchecked Capacitor can cause loss of revenue
 
Install an electric shower
Install an electric showerInstall an electric shower
Install an electric shower
 
VFD Trouble Shooting with Fluke ScopeMeter
VFD Trouble Shooting with Fluke ScopeMeterVFD Trouble Shooting with Fluke ScopeMeter
VFD Trouble Shooting with Fluke ScopeMeter
 
Equipment Audits for LV, MV, HV for annual mandatory record keeping by Niels
Equipment Audits for LV, MV, HV for annual mandatory record keeping by NielsEquipment Audits for LV, MV, HV for annual mandatory record keeping by Niels
Equipment Audits for LV, MV, HV for annual mandatory record keeping by Niels
 
Solar pv plant and india
Solar pv plant and indiaSolar pv plant and india
Solar pv plant and india
 
Physics investigatory project on RECTIFIER
Physics investigatory project on RECTIFIERPhysics investigatory project on RECTIFIER
Physics investigatory project on RECTIFIER
 
Michael Wood - Loader electric shocks, a case study
Michael Wood - Loader electric shocks, a case studyMichael Wood - Loader electric shocks, a case study
Michael Wood - Loader electric shocks, a case study
 
E. Flaws in the Resonant Cylinder and the Associated Design Iterations
E. Flaws in the Resonant Cylinder and the Associated Design IterationsE. Flaws in the Resonant Cylinder and the Associated Design Iterations
E. Flaws in the Resonant Cylinder and the Associated Design Iterations
 
Chapter 7: Fluxtrol Induction Heating Case Studies and Success Stories
Chapter 7:  Fluxtrol Induction Heating  Case Studies and Success StoriesChapter 7:  Fluxtrol Induction Heating  Case Studies and Success Stories
Chapter 7: Fluxtrol Induction Heating Case Studies and Success Stories
 
Presentation: AC Mitigation Case Histories
Presentation: AC Mitigation Case HistoriesPresentation: AC Mitigation Case Histories
Presentation: AC Mitigation Case Histories
 

Plus de ebbin daniel

Plus de ebbin daniel (7)

New Microsoft PowerPoint Presentation
New Microsoft PowerPoint PresentationNew Microsoft PowerPoint Presentation
New Microsoft PowerPoint Presentation
 
TCIL_PROJECT
TCIL_PROJECTTCIL_PROJECT
TCIL_PROJECT
 
POWER ELECTRONICS
POWER ELECTRONICSPOWER ELECTRONICS
POWER ELECTRONICS
 
DFIG_report
DFIG_reportDFIG_report
DFIG_report
 
Presentation1
Presentation1Presentation1
Presentation1
 
EDS_REPORT_FINAL
EDS_REPORT_FINALEDS_REPORT_FINAL
EDS_REPORT_FINAL
 
tremron_ebbin
tremron_ebbintremron_ebbin
tremron_ebbin
 

Ebbin_oct11

  • 1. WEEKLY REPORT - - Ebbin Daniel OCT 11 - OCT 16 Electrical Engineer
  • 2. CONTENTS: 1. Maintenance and troubleshooting a. Rewiring of the Hydraulic valve wire connecters for the Cuber Arm. b. Troubleshooting and rewiring the power outage on the dry side. c. Troubleshooting of the BSA panel. d. Troubleshooting of the wrapper machine. e. Troubleshooting for Cuber up/down mechanism. 2. Current Projects a. Height adjustment for pavers on wet side. b. Replacing limit switches on the conveyors on the block plant.
  • 3. A.Rewiring of the Hydraulic valve wire connecters for the Cuber Arm. Cause of the Problem:  Wear and tear of the wire connector.  Delay in arm movements.  Possible cause of a loose contact. Troubleshooting:  A new 120v connector was replaced with the old one.  The connector was rewired from the junction box.  New connectors were ordered for future use. B. Troubleshooting and rewiring the power outage on the dry side. Cause of the Problem:  No power on the dry side conveyor.  Photocells inactive.  Complete loss of power till the cuber. Troubleshooting:  Possibility of a cut wire during cleanup was troubleshot.  All loose/cut ends were reconnected using wire nuts.  Possible Fault at the BSA panel was troubleshot.  The wire was found and was traced to the junction box.  It was replaced with a new connection. C.Troubleshooting of the BSA panel. Cause of the Problem:  BSA panel showing various fault conditions at the wet side control panel.  BSA motor tripping.  Fault at different intervals.
  • 4. Troubleshooting:  PLC program was used to find different error codes.  Based on various inputs and outputs various wires were rewired.  All loose joints were tightly connected.  BSA working fine without any possible fault message.  However a lot of wiring has to be labelled and tightened as they are not in proper condition. D. Troubleshooting of the wrapper machine Cause of the Problem:  Wrapper was not moving.  Error message at the wrapper panel. Troubleshooting:  The Error code was traced out to be the Safe position photo eye.  It was readjusted to get the green light on top which determines that the switch is made.  The metal frame is still loose and could cause future misalignment. Thereby in needs to be fixed or replaced. E.Troubleshooting for Cuber up/down mechanism. Cause of the Problem:  Cuber not going up and down.  Manual/ auto operation cannot perform.  Delay in dry side production. Troubleshooting:  A loose wire was found which was replaced.  Eventually the fuse had also blown which was also replaced.
  • 5. Current Projects: A.Height adjustment for pavers on wet side.  Different manufactures for height measurement were contacted and are attached.  Informal quote was obtained.  Old sensors for accurate reading are still being tested.  Have to follow up with Mr. RED to inquire about height measurement system in arcadia. B. Replacing limit switches on the conveyors on the block plant.  Conveyor 1 on the batching side of the Block plant is sometimes pouring more materials.  The limit switch might be obsolete would need to be changed.  Have to follow up with Mr. Raghu to replace it during the next cleanup time.