Chapter 2:Chapter 2:
The Project Management andThe Project Management and
Information Technology ContextInformation Technology Context
Information TechnologyInformation Technology
Project Management,Project Management,
Fifth EditionFifth Edition
Information Technology Project Management, Fifth Edition, Copyright 2007
2
Learning Objectives
 Describe the systems view of project
management and how it applies to information
technology projects
 Understand organizations, including the four
frames, organizational structures, and
organizational culture
 Explain why stakeholder management and top
management commitment are critical for a
project’s success
Information Technology Project Management, Fifth Edition, Copyright 2007
3
Learning Objectives (continued)
Understand the concept of a project phase and
the project life cycle and distinguish between
project development and product development
Discuss the unique attributes and diverse nature
of information technology projects
Information Technology Project Management, Fifth Edition, Copyright 2007
4
Projects Cannot Be Run in Isolation
Projects must operate in a broad organizational
environment
Project managers need to use systems thinking
Taking a holistic view of carrying out projects within the
context of the organization
Senior managers must make sure projects
continue to support current business needs
Information Technology Project Management, Fifth Edition, Copyright 2007
5
A Systems View of Project
Management
A systems approach emerged in the 1950s to
describe a more analytical approach to
management and problem solving
Three parts include:
Systems philosophy: an overall model for thinking
about things as systems
Systems analysis: problem-solving approach
Systems management: address business,
technological, and organizational issues before making
changes to systems
Information Technology Project Management, Fifth Edition, Copyright 2007
6
Media Snapshot
The Press Association Ltd, the largest news agency
in the United Kingdom, hired a consulting firm to help
turn things around after management noticed its
profit margins were sliding
The consultants suggested using a holistic view and
a top-down strategy to make sure projects supported
key business goals
They also suggested releasing short-term results to
accrue benefits on an incremental basis and
reviewing projects on a regular basis to ensure
strategic alignment
Figure 2-1: Three Sphere Model for
Systems Management
Information Technology Project Management, Fifth Edition, Copyright 2007
7
Information Technology Project Management, Fifth Edition, Copyright 2007
8
Understanding Organizations
Structural frame:
Focuses on roles and
responsibilities,
coordination and control.
Organization charts help
define this frame.
Human resources frame:
Focuses on providing
harmony between needs of
the organization and needs
of people.
Political frame:
Assumes organizations
are coalitions composed
of varied individuals and
interest groups. Conflict
and power are key issues.
Symbolic frame: Focuses
on symbols and meanings
related to events. Culture
is important.
What Went Wrong?
Many enterprise resource planning (ERP) projects fail due to
organizational issues, not technical issues. For example, Sobey’s
Canadian grocery store chain abandoned its two-year, $90 million
ERP system due to organizational problems.
As Dalhousie University Associate Professor Sunny Marche states,
“The problem of building an integrated system that can
accommodate different people is a very serious challenge. You
can’t divorce technology from the sociocultural issues. They have
an equal role.” Sobey’s ERP system shut down for five days and
employees were scrambling to stock potentially empty shelves in
several stores for weeks. The system failure cost Sobey’s more
than $90 million and caused shareholders to take an 82-cent after-
tax hit per share.*
*Hoare, Eva. “Software hardships,” The Herald, Halifax, Nova Scotia (2001).
Information Technology Project Management, Fifth Edition, Copyright 2007
9
Information Technology Project Management, Fifth Edition, Copyright 2007
10
Organizational Structures
Three basic organization structures
Functional: functional managers report to the CEO
Project: program managers report to the CEO
Matrix: middle ground between functional and project
structures; personnel often report to two or more
bosses; structure can be weak, balanced, or strong
matrix
Figure 2-2: Functional, Project, and
Matrix Organizational Structures
Information Technology Project Management, Fifth Edition, Copyright 2007
11
Information Technology Project Management, Fifth Edition, Copyright 2007
12
Table 2-1: Organizational Structure
Influences on Projects
Project
Characteristics
Organizational Structure Type
Functional Matrix Project
Weak Matrix Balanced
Matrix
Strong
Matrix
Project manager’s
authority
Little or none Limited Low to
Moderate
Moderate
to high
High to
almost total
Percent of
performing
organization’s
personnel assigned
full-time to project
work
Virtually none 0-25% 15-60% 50-95% 85-100%
Who controls the
project budget
Functional
manager
Functional
manager
Mixed Project
manager
Project
manager
Project manager’s
role
Part-time Part-time Full-time Full-time Full-time
Common title for
project manager’s
role
Project
Coordinator/
Project Leader
Project
Coordinator/
Project
Leader
Project
Manager/
Project
Officer
Project
Manager/
Program
Manager
Project
Manager/
Program
Manager
Project management
administrative staff
Part-time Part-time Part-time Full-time Full-time
PMBOK® Guide, 2000, 19, and PMBOK® Guide 2004, 28.
Information Technology Project Management, Fifth Edition, Copyright 2007
13
Organizational Culture
Organizational culture is a set of shared
assumptions, values, and behaviors that
characterize the functioning of an organization
Many experts believe the underlying causes of
many companies’ problems are not the structure
or staff, but the culture
Ten Characteristics of
Organizational Culture
Member identity*
Group emphasis*
People focus
Unit integration*
Control
Risk tolerance*
Reward criteria*
Conflict tolerance*
Means-ends
orientation
Open-systems focus*
*Project work is most successful in an organizational
culture where these items are strong/high and other
items are balanced
1414
Information Technology Project Management, Fifth Edition, Copyright 2007
Information Technology Project Management, Fifth Edition, Copyright 2007
15
Stakeholder Management
Project managers must take time to identify,
understand, and manage relationships with all
project stakeholders
Using the four frames of organizations can help
meet stakeholder needs and expectations
Senior executives/top management are very
important stakeholders
Best Practice
IT governance addresses the authority and
control for key IT activities in organizations,
including IT infrastructure, IT use, and project
management
A lack of IT governance can be dangerous, as
evidenced by three well-publicized IT project
failures in Australia (Sydney Water’s customer
relationship management system, the Royal
Melbourne Institute of Technology’s academic
management system, and One.Tel’s billing
system)
Information Technology Project Management, Fifth Edition, Copyright 2007
16
Information Technology Project Management, Fifth Edition, Copyright 2007
17
Need for Organizational Commitment to
Information Technology (IT)
If the organization has a negative attitude toward
IT, it will be difficult for an IT project to succeed
Having a Chief Information Officer (CIO) at a high
level in the organization helps IT projects
Assigning non-IT people to IT projects also
encourages more commitment
Information Technology Project Management, Fifth Edition, Copyright 2007
18
Need for Organizational Standards
Standards and guidelines help project managers
be more effective
Senior management can encourage:
The use of standard forms and software for project
management
The development and use of guidelines for writing
project plans or providing status information
The creation of a project management office or center
of excellence
Information Technology Project Management, Fifth Edition, Copyright 2007
19
Project Phases and the Project Life
Cycle
A project life cycle is a collection of project
phases that defines:
What work will be performed in each phase
What deliverables will be produced and when
Who is involved in each phase
How management will control and approve work
produced in each phase
A deliverable is a product or service produced or
provided as part of a project
Information Technology Project Management, Fifth Edition, Copyright 2007
20
More on Project Phases
In early phases of a project life cycle:
Resource needs are usually lowest
The level of uncertainty (risk) is highest
Project stakeholders have the greatest opportunity to
influence the project
In middle phases of a project life cycle:
The certainty of completing a project improves
More resources are needed
The final phase of a project life cycle focuses on:
Ensuring that project requirements were met
The sponsor approves completion of the project
Figure 2-3: Phases of the Traditional
Project Life Cycle
2121
Information Technology Project Management, Fifth Edition, Copyright 2007
Information Technology Project Management, Fifth Edition, Copyright 2007
22
Product Life Cycles
Products also have life cycles
The Systems Development Life Cycle (SDLC) is a
framework for describing the phases involved in
developing and maintaining information systems
Systems development projects can follow:
Predictive life cycle: the scope of the project can be
clearly articulated and the schedule and cost can be
predicted
Adaptive Software Development (ASD) life cycle:
requirements cannot be clearly expressed, projects are
mission driven and component based, using time-based
cycles to meet target dates
Information Technology Project Management, Fifth Edition, Copyright 2007
23
Predictive Life Cycle Models
Waterfall model: has well-defined, linear stages
of systems development and support
Spiral model: shows that software is developed
using an iterative or spiral approach rather than a
linear approach
Incremental build model: provides for progressive
development of operational software
Prototyping model: used for developing
prototypes to clarify user requirements
Rapid Application Development (RAD) model:
used to produce systems quickly without
sacrificing quality
Information Technology Project Management, Fifth Edition, Copyright 2007
24
The Importance of Project Phases
and Management Reviews
A project should successfully pass through each
of the project phases in order to continue on to
the next
Management reviews, also called phase exits or
kill points, should occur after each phase to
evaluate the project’s progress, likely success,
and continued compatibility with organizational
goals
What Went Right?
"The real improvement that I saw was in our ability toin the words
of Thomas Edisonknow when to stop beating a dead horse.…
Edison's key to success was that he failed fairly often; but as he said,
he could recognize a dead horse before it started to smell...In
information technology we ride dead horsesfailing projectsa long
time before we give up. But what we are seeing now is that we are
able to get off them; able to reduce cost overrun and time overrun.
That's where the major impact came on the success rate.”*
Many organizations, like Huntington Bancshares, Inc., use an
executive steering committee to help keep projects on track.
*Cabanis, Jeannette, "'A Major Impact': The Standish Group's Jim Johnson On
Project Management and IT Project Success," PM Network, PMI, Sep.1998, p. 7
2525
Information Technology Project Management, Fifth Edition, Copyright 2007
Information Technology Project Management, Fifth Edition, Copyright 2007
26
The Context of IT Projects
IT projects can be very diverse in terms of size,
complexity, products produced, application area,
and resource requirements
IT project team members often have diverse
backgrounds and skill sets
IT projects use diverse technologies that change
rapidly; even within one technology area, people
must be highly specialized
Information Technology Project Management, Fifth Edition, Copyright 2007
27
Chapter Summary
Project managers need to take a systems
approach when working on projects
Organizations have four different frames:
structural, human resources, political, and
symbolic
The structure and culture of an organization have
strong implications for project managers
Projects should successfully pass through each
phase of the project life cycle
Project managers need to consider several factors
due to the unique context of information
technology projects

Contenu connexe

Tendances

Project integration management
Project integration management Project integration management
Project integration management
KU Leuven
 
Information Technology Project Management - part 04
Information Technology Project Management - part 04Information Technology Project Management - part 04
Information Technology Project Management - part 04
Rizwan Khurram
 
Software project management
Software project managementSoftware project management
Software project management
R A Akerkar
 
Information Technology Project Management - part 05
Information Technology Project Management - part 05Information Technology Project Management - part 05
Information Technology Project Management - part 05
Rizwan Khurram
 
Software Project Management( lecture 1)
Software Project Management( lecture 1)Software Project Management( lecture 1)
Software Project Management( lecture 1)
Syed Muhammad Hammad
 

Tendances (20)

PMP Lecture 4: Project Integration Management
PMP Lecture 4: Project Integration ManagementPMP Lecture 4: Project Integration Management
PMP Lecture 4: Project Integration Management
 
Project integration management
Project integration management Project integration management
Project integration management
 
Project Scope Management - PMBOK6
Project Scope Management - PMBOK6Project Scope Management - PMBOK6
Project Scope Management - PMBOK6
 
Project Management Tools and Techniques
Project Management Tools and TechniquesProject Management Tools and Techniques
Project Management Tools and Techniques
 
Information Technology Project Management - part 04
Information Technology Project Management - part 04Information Technology Project Management - part 04
Information Technology Project Management - part 04
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management Framework
 
Programme management and project evaluation
Programme management and project evaluationProgramme management and project evaluation
Programme management and project evaluation
 
Software engineering project management
Software engineering project managementSoftware engineering project management
Software engineering project management
 
Software project management
Software project managementSoftware project management
Software project management
 
1. project integration management
1. project integration management1. project integration management
1. project integration management
 
Project scope management 1
Project scope management 1Project scope management 1
Project scope management 1
 
Project Management Plan
Project Management PlanProject Management Plan
Project Management Plan
 
Information Technology Project Management - part 12
Information Technology Project Management - part 12Information Technology Project Management - part 12
Information Technology Project Management - part 12
 
Information Technology Project Management - part 05
Information Technology Project Management - part 05Information Technology Project Management - part 05
Information Technology Project Management - part 05
 
Project Resource Management
Project Resource ManagementProject Resource Management
Project Resource Management
 
Chapter 4 Project Integration Management.ppt
Chapter 4 Project Integration Management.pptChapter 4 Project Integration Management.ppt
Chapter 4 Project Integration Management.ppt
 
Project management IT Project Management
Project management IT Project Management Project management IT Project Management
Project management IT Project Management
 
Project time management
Project time managementProject time management
Project time management
 
Software Project Management( lecture 1)
Software Project Management( lecture 1)Software Project Management( lecture 1)
Software Project Management( lecture 1)
 
Lecture 05:Advanced Project Management PM Processes and Framework
Lecture 05:Advanced Project Management   PM Processes and FrameworkLecture 05:Advanced Project Management   PM Processes and Framework
Lecture 05:Advanced Project Management PM Processes and Framework
 

Similaire à Project management and information technology context

Chapter 2 The Project Management and Information Technology Context.ppt
Chapter 2 The Project Management and Information Technology Context.pptChapter 2 The Project Management and Information Technology Context.ppt
Chapter 2 The Project Management and Information Technology Context.ppt
AhmadTawfigAlRadaide
 
L02 pm & it context
L02 pm & it contextL02 pm & it context
L02 pm & it context
Asa Chan
 
L01 introduction to pm
L01 introduction to pmL01 introduction to pm
L01 introduction to pm
Asa Chan
 

Similaire à Project management and information technology context (20)

Lecture 2
Lecture 2 Lecture 2
Lecture 2
 
Ch02
Ch02Ch02
Ch02
 
02_Ch2a.pptx
02_Ch2a.pptx02_Ch2a.pptx
02_Ch2a.pptx
 
PM&IT_Ch02.pptx
PM&IT_Ch02.pptxPM&IT_Ch02.pptx
PM&IT_Ch02.pptx
 
Chapter 2 The Project Management and Information Technology Context.ppt
Chapter 2 The Project Management and Information Technology Context.pptChapter 2 The Project Management and Information Technology Context.ppt
Chapter 2 The Project Management and Information Technology Context.ppt
 
Project management by hamidun
Project management by hamidunProject management by hamidun
Project management by hamidun
 
An Investigation of Critical Failure Factors In Information Technology Projects
An Investigation of Critical Failure Factors In Information Technology ProjectsAn Investigation of Critical Failure Factors In Information Technology Projects
An Investigation of Critical Failure Factors In Information Technology Projects
 
Ch01
Ch01Ch01
Ch01
 
01 itpm6
01 itpm601 itpm6
01 itpm6
 
L02 pm & it context
L02 pm & it contextL02 pm & it context
L02 pm & it context
 
Ch01
Ch01Ch01
Ch01
 
L01 introduction to pm
L01 introduction to pmL01 introduction to pm
L01 introduction to pm
 
1. introduction
1. introduction1. introduction
1. introduction
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Management
 
The project management process groups a case study
The project management process groups a case studyThe project management process groups a case study
The project management process groups a case study
 
CHAPTER FOUR.pptx
CHAPTER FOUR.pptxCHAPTER FOUR.pptx
CHAPTER FOUR.pptx
 
Lecture 3
Lecture 3Lecture 3
Lecture 3
 
Introduction to project management
Introduction to project managementIntroduction to project management
Introduction to project management
 
Software project management
Software project managementSoftware project management
Software project management
 
ch01.ppt
ch01.pptch01.ppt
ch01.ppt
 

Plus de Dhani Ahmad

Opportunities, threats, industry competition, and competitor analysis
Opportunities, threats, industry competition, and competitor analysisOpportunities, threats, industry competition, and competitor analysis
Opportunities, threats, industry competition, and competitor analysis
Dhani Ahmad
 
Information system
Information systemInformation system
Information system
Dhani Ahmad
 
Information resource management
Information resource managementInformation resource management
Information resource management
Dhani Ahmad
 

Plus de Dhani Ahmad (20)

Strategic planning
Strategic planningStrategic planning
Strategic planning
 
Strategic information system planning
Strategic information system planningStrategic information system planning
Strategic information system planning
 
Opportunities, threats, industry competition, and competitor analysis
Opportunities, threats, industry competition, and competitor analysisOpportunities, threats, industry competition, and competitor analysis
Opportunities, threats, industry competition, and competitor analysis
 
Information system
Information systemInformation system
Information system
 
Information resource management
Information resource managementInformation resource management
Information resource management
 
Types of islamic institutions and records
Types of islamic institutions and recordsTypes of islamic institutions and records
Types of islamic institutions and records
 
Islamic information seeking behavior
Islamic information seeking behaviorIslamic information seeking behavior
Islamic information seeking behavior
 
Islamic information management
Islamic information managementIslamic information management
Islamic information management
 
Islamic information management sources in islam
Islamic information management sources in islamIslamic information management sources in islam
Islamic information management sources in islam
 
The need for security
The need for securityThe need for security
The need for security
 
The information security audit
The information security auditThe information security audit
The information security audit
 
Security technologies
Security technologiesSecurity technologies
Security technologies
 
Security policy
Security policySecurity policy
Security policy
 
Security and personnel
Security and personnelSecurity and personnel
Security and personnel
 
Secure
SecureSecure
Secure
 
Risk management ii
Risk management iiRisk management ii
Risk management ii
 
Risk management i
Risk management iRisk management i
Risk management i
 
Privacy & security in heath care it
Privacy & security in heath care itPrivacy & security in heath care it
Privacy & security in heath care it
 
Physical security
Physical securityPhysical security
Physical security
 
Legal, ethical & professional issues
Legal, ethical & professional issuesLegal, ethical & professional issues
Legal, ethical & professional issues
 

Dernier

internship thesis pakistan aeronautical complex kamra
internship thesis pakistan aeronautical complex kamrainternship thesis pakistan aeronautical complex kamra
internship thesis pakistan aeronautical complex kamra
AllTops
 
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTECAbortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Riyadh +966572737505 get cytotec
 
Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptx
alinstan901
 
The Psychology Of Motivation - Richard Brown
The Psychology Of Motivation - Richard BrownThe Psychology Of Motivation - Richard Brown
The Psychology Of Motivation - Richard Brown
SandaliGurusinghe2
 
Beyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable developmentBeyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable development
Nimot Muili
 

Dernier (16)

Reviewing and summarization of university ranking system to.pptx
Reviewing and summarization of university ranking system  to.pptxReviewing and summarization of university ranking system  to.pptx
Reviewing and summarization of university ranking system to.pptx
 
internship thesis pakistan aeronautical complex kamra
internship thesis pakistan aeronautical complex kamrainternship thesis pakistan aeronautical complex kamra
internship thesis pakistan aeronautical complex kamra
 
Leaders enhance communication by actively listening, providing constructive f...
Leaders enhance communication by actively listening, providing constructive f...Leaders enhance communication by actively listening, providing constructive f...
Leaders enhance communication by actively listening, providing constructive f...
 
digital Human resource management presentation.pdf
digital Human resource management presentation.pdfdigital Human resource management presentation.pdf
digital Human resource management presentation.pdf
 
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTECAbortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
 
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot ModelGautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot Model
 
Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptx
 
The Psychology Of Motivation - Richard Brown
The Psychology Of Motivation - Richard BrownThe Psychology Of Motivation - Richard Brown
The Psychology Of Motivation - Richard Brown
 
Beyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable developmentBeyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable development
 
Intro_University_Ranking_Introduction.pptx
Intro_University_Ranking_Introduction.pptxIntro_University_Ranking_Introduction.pptx
Intro_University_Ranking_Introduction.pptx
 
Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siliguri
Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime SiliguriSiliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siliguri
Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siliguri
 
Safety T fire missions army field Artillery
Safety T fire missions army field ArtillerySafety T fire missions army field Artillery
Safety T fire missions army field Artillery
 
How Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptxHow Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptx
 
Marketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docxMarketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docx
 
International Ocean Transportation p.pdf
International Ocean Transportation p.pdfInternational Ocean Transportation p.pdf
International Ocean Transportation p.pdf
 
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professionalW.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
 

Project management and information technology context

  • 1. Chapter 2:Chapter 2: The Project Management andThe Project Management and Information Technology ContextInformation Technology Context Information TechnologyInformation Technology Project Management,Project Management, Fifth EditionFifth Edition
  • 2. Information Technology Project Management, Fifth Edition, Copyright 2007 2 Learning Objectives  Describe the systems view of project management and how it applies to information technology projects  Understand organizations, including the four frames, organizational structures, and organizational culture  Explain why stakeholder management and top management commitment are critical for a project’s success
  • 3. Information Technology Project Management, Fifth Edition, Copyright 2007 3 Learning Objectives (continued) Understand the concept of a project phase and the project life cycle and distinguish between project development and product development Discuss the unique attributes and diverse nature of information technology projects
  • 4. Information Technology Project Management, Fifth Edition, Copyright 2007 4 Projects Cannot Be Run in Isolation Projects must operate in a broad organizational environment Project managers need to use systems thinking Taking a holistic view of carrying out projects within the context of the organization Senior managers must make sure projects continue to support current business needs
  • 5. Information Technology Project Management, Fifth Edition, Copyright 2007 5 A Systems View of Project Management A systems approach emerged in the 1950s to describe a more analytical approach to management and problem solving Three parts include: Systems philosophy: an overall model for thinking about things as systems Systems analysis: problem-solving approach Systems management: address business, technological, and organizational issues before making changes to systems
  • 6. Information Technology Project Management, Fifth Edition, Copyright 2007 6 Media Snapshot The Press Association Ltd, the largest news agency in the United Kingdom, hired a consulting firm to help turn things around after management noticed its profit margins were sliding The consultants suggested using a holistic view and a top-down strategy to make sure projects supported key business goals They also suggested releasing short-term results to accrue benefits on an incremental basis and reviewing projects on a regular basis to ensure strategic alignment
  • 7. Figure 2-1: Three Sphere Model for Systems Management Information Technology Project Management, Fifth Edition, Copyright 2007 7
  • 8. Information Technology Project Management, Fifth Edition, Copyright 2007 8 Understanding Organizations Structural frame: Focuses on roles and responsibilities, coordination and control. Organization charts help define this frame. Human resources frame: Focuses on providing harmony between needs of the organization and needs of people. Political frame: Assumes organizations are coalitions composed of varied individuals and interest groups. Conflict and power are key issues. Symbolic frame: Focuses on symbols and meanings related to events. Culture is important.
  • 9. What Went Wrong? Many enterprise resource planning (ERP) projects fail due to organizational issues, not technical issues. For example, Sobey’s Canadian grocery store chain abandoned its two-year, $90 million ERP system due to organizational problems. As Dalhousie University Associate Professor Sunny Marche states, “The problem of building an integrated system that can accommodate different people is a very serious challenge. You can’t divorce technology from the sociocultural issues. They have an equal role.” Sobey’s ERP system shut down for five days and employees were scrambling to stock potentially empty shelves in several stores for weeks. The system failure cost Sobey’s more than $90 million and caused shareholders to take an 82-cent after- tax hit per share.* *Hoare, Eva. “Software hardships,” The Herald, Halifax, Nova Scotia (2001). Information Technology Project Management, Fifth Edition, Copyright 2007 9
  • 10. Information Technology Project Management, Fifth Edition, Copyright 2007 10 Organizational Structures Three basic organization structures Functional: functional managers report to the CEO Project: program managers report to the CEO Matrix: middle ground between functional and project structures; personnel often report to two or more bosses; structure can be weak, balanced, or strong matrix
  • 11. Figure 2-2: Functional, Project, and Matrix Organizational Structures Information Technology Project Management, Fifth Edition, Copyright 2007 11
  • 12. Information Technology Project Management, Fifth Edition, Copyright 2007 12 Table 2-1: Organizational Structure Influences on Projects Project Characteristics Organizational Structure Type Functional Matrix Project Weak Matrix Balanced Matrix Strong Matrix Project manager’s authority Little or none Limited Low to Moderate Moderate to high High to almost total Percent of performing organization’s personnel assigned full-time to project work Virtually none 0-25% 15-60% 50-95% 85-100% Who controls the project budget Functional manager Functional manager Mixed Project manager Project manager Project manager’s role Part-time Part-time Full-time Full-time Full-time Common title for project manager’s role Project Coordinator/ Project Leader Project Coordinator/ Project Leader Project Manager/ Project Officer Project Manager/ Program Manager Project Manager/ Program Manager Project management administrative staff Part-time Part-time Part-time Full-time Full-time PMBOK® Guide, 2000, 19, and PMBOK® Guide 2004, 28.
  • 13. Information Technology Project Management, Fifth Edition, Copyright 2007 13 Organizational Culture Organizational culture is a set of shared assumptions, values, and behaviors that characterize the functioning of an organization Many experts believe the underlying causes of many companies’ problems are not the structure or staff, but the culture
  • 14. Ten Characteristics of Organizational Culture Member identity* Group emphasis* People focus Unit integration* Control Risk tolerance* Reward criteria* Conflict tolerance* Means-ends orientation Open-systems focus* *Project work is most successful in an organizational culture where these items are strong/high and other items are balanced 1414 Information Technology Project Management, Fifth Edition, Copyright 2007
  • 15. Information Technology Project Management, Fifth Edition, Copyright 2007 15 Stakeholder Management Project managers must take time to identify, understand, and manage relationships with all project stakeholders Using the four frames of organizations can help meet stakeholder needs and expectations Senior executives/top management are very important stakeholders
  • 16. Best Practice IT governance addresses the authority and control for key IT activities in organizations, including IT infrastructure, IT use, and project management A lack of IT governance can be dangerous, as evidenced by three well-publicized IT project failures in Australia (Sydney Water’s customer relationship management system, the Royal Melbourne Institute of Technology’s academic management system, and One.Tel’s billing system) Information Technology Project Management, Fifth Edition, Copyright 2007 16
  • 17. Information Technology Project Management, Fifth Edition, Copyright 2007 17 Need for Organizational Commitment to Information Technology (IT) If the organization has a negative attitude toward IT, it will be difficult for an IT project to succeed Having a Chief Information Officer (CIO) at a high level in the organization helps IT projects Assigning non-IT people to IT projects also encourages more commitment
  • 18. Information Technology Project Management, Fifth Edition, Copyright 2007 18 Need for Organizational Standards Standards and guidelines help project managers be more effective Senior management can encourage: The use of standard forms and software for project management The development and use of guidelines for writing project plans or providing status information The creation of a project management office or center of excellence
  • 19. Information Technology Project Management, Fifth Edition, Copyright 2007 19 Project Phases and the Project Life Cycle A project life cycle is a collection of project phases that defines: What work will be performed in each phase What deliverables will be produced and when Who is involved in each phase How management will control and approve work produced in each phase A deliverable is a product or service produced or provided as part of a project
  • 20. Information Technology Project Management, Fifth Edition, Copyright 2007 20 More on Project Phases In early phases of a project life cycle: Resource needs are usually lowest The level of uncertainty (risk) is highest Project stakeholders have the greatest opportunity to influence the project In middle phases of a project life cycle: The certainty of completing a project improves More resources are needed The final phase of a project life cycle focuses on: Ensuring that project requirements were met The sponsor approves completion of the project
  • 21. Figure 2-3: Phases of the Traditional Project Life Cycle 2121 Information Technology Project Management, Fifth Edition, Copyright 2007
  • 22. Information Technology Project Management, Fifth Edition, Copyright 2007 22 Product Life Cycles Products also have life cycles The Systems Development Life Cycle (SDLC) is a framework for describing the phases involved in developing and maintaining information systems Systems development projects can follow: Predictive life cycle: the scope of the project can be clearly articulated and the schedule and cost can be predicted Adaptive Software Development (ASD) life cycle: requirements cannot be clearly expressed, projects are mission driven and component based, using time-based cycles to meet target dates
  • 23. Information Technology Project Management, Fifth Edition, Copyright 2007 23 Predictive Life Cycle Models Waterfall model: has well-defined, linear stages of systems development and support Spiral model: shows that software is developed using an iterative or spiral approach rather than a linear approach Incremental build model: provides for progressive development of operational software Prototyping model: used for developing prototypes to clarify user requirements Rapid Application Development (RAD) model: used to produce systems quickly without sacrificing quality
  • 24. Information Technology Project Management, Fifth Edition, Copyright 2007 24 The Importance of Project Phases and Management Reviews A project should successfully pass through each of the project phases in order to continue on to the next Management reviews, also called phase exits or kill points, should occur after each phase to evaluate the project’s progress, likely success, and continued compatibility with organizational goals
  • 25. What Went Right? "The real improvement that I saw was in our ability toin the words of Thomas Edisonknow when to stop beating a dead horse.… Edison's key to success was that he failed fairly often; but as he said, he could recognize a dead horse before it started to smell...In information technology we ride dead horsesfailing projectsa long time before we give up. But what we are seeing now is that we are able to get off them; able to reduce cost overrun and time overrun. That's where the major impact came on the success rate.”* Many organizations, like Huntington Bancshares, Inc., use an executive steering committee to help keep projects on track. *Cabanis, Jeannette, "'A Major Impact': The Standish Group's Jim Johnson On Project Management and IT Project Success," PM Network, PMI, Sep.1998, p. 7 2525 Information Technology Project Management, Fifth Edition, Copyright 2007
  • 26. Information Technology Project Management, Fifth Edition, Copyright 2007 26 The Context of IT Projects IT projects can be very diverse in terms of size, complexity, products produced, application area, and resource requirements IT project team members often have diverse backgrounds and skill sets IT projects use diverse technologies that change rapidly; even within one technology area, people must be highly specialized
  • 27. Information Technology Project Management, Fifth Edition, Copyright 2007 27 Chapter Summary Project managers need to take a systems approach when working on projects Organizations have four different frames: structural, human resources, political, and symbolic The structure and culture of an organization have strong implications for project managers Projects should successfully pass through each phase of the project life cycle Project managers need to consider several factors due to the unique context of information technology projects