SlideShare une entreprise Scribd logo
1  sur  2
Status
• Overall Phase 1 Construction – 99% complete
• Primary Focus:
• Station Certificates of Occupancy
• Testing
• Punch List
• Achieve Substantial Completion by Dulles
Transit Partners
• System Performance Demonstration Test
Conducted – Jan 25-26
• Wiehle garage – Complete
• Record of Decision roadway improvements – 99%
complete (minor work remains)
• Connector bus testing at Wiehle north - Ongoing
• West Falls Church rail yard:
• Completion – 95%
• Community Meeting – Jan 29, 2014
• Sound Box Completion – Feb 2014
• Testing - Feb 2014
• Two noise studies / reports will be prepared
– Condition 7 and 8 (SEA)
• WMATA will provide FCDOT 30 day notice prior to start of
revenue operations to allow for Connector service changes
• Phase 1 project remains on budget - $ 2.906B
Schedule
• Substantial completion/MWAA turn-over to WMATA:
• MWAA continues to work with DTP on Scheduled
Substantial Completion Date (SSCD)
• System testing is ongoing
• Estimated passenger revenue service - date determined by
WMATA when testing, training, and safe operation is
achieved (WMATA has 90 days after SSCD for testing,
training, and acceptance)
• Tristate Oversight Committee Safety and Security
process concurrent with WMATA testing
• February 2014 Sound Box Testing WFCY
• Tax District Advisory & Commission Meetings – March
2014
Current Milestones – Past 30 Days
• Regional coordination for bus service and marketing
outreach ongoing
• WMATA lead for Phase 1 marketing and outreach;
public website: www. silverlinemetro.com
• Connector conducting operation testing Wiehle Garage
• Fit out activities ongoing
• Phase 1 Maintenance & Land Conveyance process ongoing;
“walk down” field visits ongoing for property being turned
over to the county
• Punch List and Testing – Ongoing
• Systems Performance Test Conducted
1
February 2013
Status
• Phase 2 fully in design stage
• 60% and some 90% design packages received
• Issued for Construction packets – Starting Spring
2014
• Coordination ongoing
• Town of Herndon
• Adjacent Land Owners
• Project Partners
• Herndon and Innovation Center Station (south) garages
• Fairfax County has committed to fund and
construct parking garages - Design ongoing
• Innovation Center Station Garage - Land use case
ongoing (June 2014)
• Herndon Garage - staff has developed a number of
concept designs (2232)
• Scheduled tracks completion of the garages to the
completion of Phase 2
• Town Center Parkway tunnel
• Final concept design received by consultant
November 2013
• FCDOT submits formal request to MWAA for
change order / pricing on Nov. 18, 2013
• Status of Phase 2 Bid Packages:
• Packet A - rail Line, station, and systems (includes
Innovation Center Station) - Awarded
• Packet B - Maintenance Facility at Dulles Airport
• Award – Summer 2014
• NTP – Summer 2014
• Completion Summer 2018
• MWAA’s Dulles Rail office to relocate to Herndon –
Completed on Jan 17, 2014
Budget/Schedule
• Cost Estimate: $3.093B
• Cost Estimate with value engineering , Packet A savings,
and garages funding outside the project: $2.6B
• Substantial Completion: Summer 2018
• Revenue Operations: Late 2018
• Tax District Advisory & Commission Meetings – March
2014
Current Milestones – Past 30 Days
• FTA oversight of Phase 2 similar to Phase 1
• TIFIA process – Ongoing
• Design – Ongoing
• Herndon Metrorail Station Access Management Study
(HMSAMS)
• Identify pedestrian, bicycle, bus transit and
roadway improvements to and from Herndon and
Innovation Center Station
• Public Meetings – Spring 2014
2
February 2013

Contenu connexe

Tendances

Silver Line Update-Board Transportation Committee: Oct. 13, 2015
Silver Line Update-Board Transportation Committee: Oct. 13, 2015Silver Line Update-Board Transportation Committee: Oct. 13, 2015
Silver Line Update-Board Transportation Committee: Oct. 13, 2015Fairfax County
 
Implementation of HB2 (2014) and HB 1887 (2015)
Implementation of HB2 (2014) and HB 1887 (2015)Implementation of HB2 (2014) and HB 1887 (2015)
Implementation of HB2 (2014) and HB 1887 (2015)Fairfax County
 
Board Transportation Committee Update: March 17, 2015
Board Transportation Committee Update: March 17, 2015Board Transportation Committee Update: March 17, 2015
Board Transportation Committee Update: March 17, 2015Fairfax County
 
Fairfax County Capital Bikeshare - TAC Presentation: June 21, 2016
Fairfax County Capital Bikeshare - TAC Presentation: June 21, 2016 Fairfax County Capital Bikeshare - TAC Presentation: June 21, 2016
Fairfax County Capital Bikeshare - TAC Presentation: June 21, 2016 Fairfax County
 
Fairfax County Parkway Trail at Dulles Toll Road EB Ramp Improvement Study
Fairfax County Parkway Trail at Dulles Toll Road EB Ramp Improvement StudyFairfax County Parkway Trail at Dulles Toll Road EB Ramp Improvement Study
Fairfax County Parkway Trail at Dulles Toll Road EB Ramp Improvement StudyFairfax County
 
Dulles Metrorail Silver Line Phase 2 Status and Funding
Dulles Metrorail Silver Line Phase 2 Status and FundingDulles Metrorail Silver Line Phase 2 Status and Funding
Dulles Metrorail Silver Line Phase 2 Status and FundingFairfax County
 
Dulles Metrorail Silver Line Phase 2 Status and Funding Update
Dulles Metrorail Silver Line Phase 2 Status and Funding UpdateDulles Metrorail Silver Line Phase 2 Status and Funding Update
Dulles Metrorail Silver Line Phase 2 Status and Funding UpdateFairfax County
 
Silver Line Update: Dec. 1, 2015
Silver Line Update: Dec. 1, 2015Silver Line Update: Dec. 1, 2015
Silver Line Update: Dec. 1, 2015Fairfax County
 
Citizens Information Meeting: Lee Chapel Road Walkway
Citizens Information Meeting: Lee Chapel Road WalkwayCitizens Information Meeting: Lee Chapel Road Walkway
Citizens Information Meeting: Lee Chapel Road WalkwayFairfax County
 
Silver Line Phase 1 Status Report-Sept. 16, 2014
Silver Line Phase 1 Status Report-Sept. 16, 2014Silver Line Phase 1 Status Report-Sept. 16, 2014
Silver Line Phase 1 Status Report-Sept. 16, 2014Fairfax County
 
Dulles Rail Phase 1-Status Report: June 21, 2013
Dulles Rail Phase 1-Status Report: June 21, 2013Dulles Rail Phase 1-Status Report: June 21, 2013
Dulles Rail Phase 1-Status Report: June 21, 2013Fairfax County
 
Transform 66: Inside the Beltway
Transform 66: Inside the BeltwayTransform 66: Inside the Beltway
Transform 66: Inside the BeltwayFairfax County
 
Reston Network Analysis: 2050 2nd Tier Mitigation Results
Reston Network Analysis: 2050 2nd Tier Mitigation ResultsReston Network Analysis: 2050 2nd Tier Mitigation Results
Reston Network Analysis: 2050 2nd Tier Mitigation ResultsFairfax County
 
Transportation Priorities Plan: Future Updates
Transportation Priorities Plan: Future UpdatesTransportation Priorities Plan: Future Updates
Transportation Priorities Plan: Future UpdatesFairfax County
 
Operational Analysis of Dulles Toll Road Ramps to Tysons
Operational Analysis of Dulles Toll Road Ramps to TysonsOperational Analysis of Dulles Toll Road Ramps to Tysons
Operational Analysis of Dulles Toll Road Ramps to TysonsFairfax County
 
Public Information Meeting: Realignment of Old Courthouse Road at Besley Road
Public Information Meeting: Realignment of Old Courthouse Road at Besley RoadPublic Information Meeting: Realignment of Old Courthouse Road at Besley Road
Public Information Meeting: Realignment of Old Courthouse Road at Besley RoadFairfax County
 
Reston Transportation Funding Plan: July 15, 2016
Reston Transportation Funding Plan: July 15, 2016Reston Transportation Funding Plan: July 15, 2016
Reston Transportation Funding Plan: July 15, 2016Fairfax County
 
Transportation Priorities: Project Timelines and the 2014 Bond Referendum
Transportation Priorities: Project Timelines and the 2014 Bond ReferendumTransportation Priorities: Project Timelines and the 2014 Bond Referendum
Transportation Priorities: Project Timelines and the 2014 Bond ReferendumFairfax County
 
Pardon Our Dust Meeting: Pedestrian Improvements at the Intersection of Old D...
Pardon Our Dust Meeting: Pedestrian Improvements at the Intersection of Old D...Pardon Our Dust Meeting: Pedestrian Improvements at the Intersection of Old D...
Pardon Our Dust Meeting: Pedestrian Improvements at the Intersection of Old D...Fairfax County
 
Reston Transportation Service District: Informational Meetings March 21 & 29,...
Reston Transportation Service District: Informational Meetings March 21 & 29,...Reston Transportation Service District: Informational Meetings March 21 & 29,...
Reston Transportation Service District: Informational Meetings March 21 & 29,...Fairfax County
 

Tendances (20)

Silver Line Update-Board Transportation Committee: Oct. 13, 2015
Silver Line Update-Board Transportation Committee: Oct. 13, 2015Silver Line Update-Board Transportation Committee: Oct. 13, 2015
Silver Line Update-Board Transportation Committee: Oct. 13, 2015
 
Implementation of HB2 (2014) and HB 1887 (2015)
Implementation of HB2 (2014) and HB 1887 (2015)Implementation of HB2 (2014) and HB 1887 (2015)
Implementation of HB2 (2014) and HB 1887 (2015)
 
Board Transportation Committee Update: March 17, 2015
Board Transportation Committee Update: March 17, 2015Board Transportation Committee Update: March 17, 2015
Board Transportation Committee Update: March 17, 2015
 
Fairfax County Capital Bikeshare - TAC Presentation: June 21, 2016
Fairfax County Capital Bikeshare - TAC Presentation: June 21, 2016 Fairfax County Capital Bikeshare - TAC Presentation: June 21, 2016
Fairfax County Capital Bikeshare - TAC Presentation: June 21, 2016
 
Fairfax County Parkway Trail at Dulles Toll Road EB Ramp Improvement Study
Fairfax County Parkway Trail at Dulles Toll Road EB Ramp Improvement StudyFairfax County Parkway Trail at Dulles Toll Road EB Ramp Improvement Study
Fairfax County Parkway Trail at Dulles Toll Road EB Ramp Improvement Study
 
Dulles Metrorail Silver Line Phase 2 Status and Funding
Dulles Metrorail Silver Line Phase 2 Status and FundingDulles Metrorail Silver Line Phase 2 Status and Funding
Dulles Metrorail Silver Line Phase 2 Status and Funding
 
Dulles Metrorail Silver Line Phase 2 Status and Funding Update
Dulles Metrorail Silver Line Phase 2 Status and Funding UpdateDulles Metrorail Silver Line Phase 2 Status and Funding Update
Dulles Metrorail Silver Line Phase 2 Status and Funding Update
 
Silver Line Update: Dec. 1, 2015
Silver Line Update: Dec. 1, 2015Silver Line Update: Dec. 1, 2015
Silver Line Update: Dec. 1, 2015
 
Citizens Information Meeting: Lee Chapel Road Walkway
Citizens Information Meeting: Lee Chapel Road WalkwayCitizens Information Meeting: Lee Chapel Road Walkway
Citizens Information Meeting: Lee Chapel Road Walkway
 
Silver Line Phase 1 Status Report-Sept. 16, 2014
Silver Line Phase 1 Status Report-Sept. 16, 2014Silver Line Phase 1 Status Report-Sept. 16, 2014
Silver Line Phase 1 Status Report-Sept. 16, 2014
 
Dulles Rail Phase 1-Status Report: June 21, 2013
Dulles Rail Phase 1-Status Report: June 21, 2013Dulles Rail Phase 1-Status Report: June 21, 2013
Dulles Rail Phase 1-Status Report: June 21, 2013
 
Transform 66: Inside the Beltway
Transform 66: Inside the BeltwayTransform 66: Inside the Beltway
Transform 66: Inside the Beltway
 
Reston Network Analysis: 2050 2nd Tier Mitigation Results
Reston Network Analysis: 2050 2nd Tier Mitigation ResultsReston Network Analysis: 2050 2nd Tier Mitigation Results
Reston Network Analysis: 2050 2nd Tier Mitigation Results
 
Transportation Priorities Plan: Future Updates
Transportation Priorities Plan: Future UpdatesTransportation Priorities Plan: Future Updates
Transportation Priorities Plan: Future Updates
 
Operational Analysis of Dulles Toll Road Ramps to Tysons
Operational Analysis of Dulles Toll Road Ramps to TysonsOperational Analysis of Dulles Toll Road Ramps to Tysons
Operational Analysis of Dulles Toll Road Ramps to Tysons
 
Public Information Meeting: Realignment of Old Courthouse Road at Besley Road
Public Information Meeting: Realignment of Old Courthouse Road at Besley RoadPublic Information Meeting: Realignment of Old Courthouse Road at Besley Road
Public Information Meeting: Realignment of Old Courthouse Road at Besley Road
 
Reston Transportation Funding Plan: July 15, 2016
Reston Transportation Funding Plan: July 15, 2016Reston Transportation Funding Plan: July 15, 2016
Reston Transportation Funding Plan: July 15, 2016
 
Transportation Priorities: Project Timelines and the 2014 Bond Referendum
Transportation Priorities: Project Timelines and the 2014 Bond ReferendumTransportation Priorities: Project Timelines and the 2014 Bond Referendum
Transportation Priorities: Project Timelines and the 2014 Bond Referendum
 
Pardon Our Dust Meeting: Pedestrian Improvements at the Intersection of Old D...
Pardon Our Dust Meeting: Pedestrian Improvements at the Intersection of Old D...Pardon Our Dust Meeting: Pedestrian Improvements at the Intersection of Old D...
Pardon Our Dust Meeting: Pedestrian Improvements at the Intersection of Old D...
 
Reston Transportation Service District: Informational Meetings March 21 & 29,...
Reston Transportation Service District: Informational Meetings March 21 & 29,...Reston Transportation Service District: Informational Meetings March 21 & 29,...
Reston Transportation Service District: Informational Meetings March 21 & 29,...
 

Similaire à Silver Line Phase 1-Status Report: Feb. 4, 2014

Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation : Boar...
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation : Boar...Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation : Boar...
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation : Boar...Fairfax County
 
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 ImplementationDulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 ImplementationFairfax County
 
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project: Silver Line Phase 2 ImplementationDulles Corridor Metrorail Project: Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project: Silver Line Phase 2 ImplementationFairfax County
 
Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...
Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...
Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...Fairfax County
 
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...Fairfax County
 
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 ImplementationDulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 ImplementationFairfax County
 
Silver Line Phase 1-Status Report: Sept. 2013
Silver Line Phase 1-Status Report: Sept. 2013Silver Line Phase 1-Status Report: Sept. 2013
Silver Line Phase 1-Status Report: Sept. 2013Fairfax County
 
Silver Line Update: December 1, 2015
Silver Line Update: December 1, 2015Silver Line Update: December 1, 2015
Silver Line Update: December 1, 2015Fairfax County
 
04 02-15 Caltrain Modernization Updates
04 02-15 Caltrain Modernization Updates04 02-15 Caltrain Modernization Updates
04 02-15 Caltrain Modernization UpdatesAdina Levin
 
Addison Capital Projects Update
Addison Capital Projects UpdateAddison Capital Projects Update
Addison Capital Projects UpdateTownofAddison
 
rup-20151016-part-1-item07-victoria-station-upgrade
rup-20151016-part-1-item07-victoria-station-upgraderup-20151016-part-1-item07-victoria-station-upgrade
rup-20151016-part-1-item07-victoria-station-upgradeRobert Lee - CEng, MICE, PMP
 
Dulles Metrorail Silver Line Phase 2 Update
Dulles Metrorail Silver Line Phase 2 UpdateDulles Metrorail Silver Line Phase 2 Update
Dulles Metrorail Silver Line Phase 2 UpdateFairfax County
 
Dulles Rail Silver Line Phase 2 Status and Funding
Dulles Rail Silver Line Phase 2 Status and FundingDulles Rail Silver Line Phase 2 Status and Funding
Dulles Rail Silver Line Phase 2 Status and FundingFairfax County
 
Lecture 8 monitoring & controlling (1)
Lecture 8  monitoring & controlling (1)Lecture 8  monitoring & controlling (1)
Lecture 8 monitoring & controlling (1)Nur Azwin
 
Sumter County FL Strategic Plan
Sumter County FL Strategic PlanSumter County FL Strategic Plan
Sumter County FL Strategic PlanTracy Quintana
 
May 26 LRSC - Trillium Line Extension.pdf
May 26 LRSC - Trillium Line Extension.pdfMay 26 LRSC - Trillium Line Extension.pdf
May 26 LRSC - Trillium Line Extension.pdfSteve Desroches
 

Similaire à Silver Line Phase 1-Status Report: Feb. 4, 2014 (20)

Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation : Boar...
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation : Boar...Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation : Boar...
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation : Boar...
 
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 ImplementationDulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
 
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project: Silver Line Phase 2 ImplementationDulles Corridor Metrorail Project: Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation
 
Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...
Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...
Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...
 
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...
 
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 ImplementationDulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
 
Silver Line Phase 1-Status Report: Sept. 2013
Silver Line Phase 1-Status Report: Sept. 2013Silver Line Phase 1-Status Report: Sept. 2013
Silver Line Phase 1-Status Report: Sept. 2013
 
Silver Line Update: December 1, 2015
Silver Line Update: December 1, 2015Silver Line Update: December 1, 2015
Silver Line Update: December 1, 2015
 
04 02-15 Caltrain Modernization Updates
04 02-15 Caltrain Modernization Updates04 02-15 Caltrain Modernization Updates
04 02-15 Caltrain Modernization Updates
 
Addison Capital Projects Update
Addison Capital Projects UpdateAddison Capital Projects Update
Addison Capital Projects Update
 
Fitchburg Commuter Rail Line Improvement Project
Fitchburg Commuter Rail Line Improvement ProjectFitchburg Commuter Rail Line Improvement Project
Fitchburg Commuter Rail Line Improvement Project
 
State of Hawaii Digital Leveling Project
State of Hawaii Digital Leveling ProjectState of Hawaii Digital Leveling Project
State of Hawaii Digital Leveling Project
 
Resume Murali 1
Resume Murali 1 Resume Murali 1
Resume Murali 1
 
rup-20151016-part-1-item07-victoria-station-upgrade
rup-20151016-part-1-item07-victoria-station-upgraderup-20151016-part-1-item07-victoria-station-upgrade
rup-20151016-part-1-item07-victoria-station-upgrade
 
Dulles Metrorail Silver Line Phase 2 Update
Dulles Metrorail Silver Line Phase 2 UpdateDulles Metrorail Silver Line Phase 2 Update
Dulles Metrorail Silver Line Phase 2 Update
 
Mitigtion Plan Presentation
Mitigtion Plan PresentationMitigtion Plan Presentation
Mitigtion Plan Presentation
 
Dulles Rail Silver Line Phase 2 Status and Funding
Dulles Rail Silver Line Phase 2 Status and FundingDulles Rail Silver Line Phase 2 Status and Funding
Dulles Rail Silver Line Phase 2 Status and Funding
 
Lecture 8 monitoring & controlling (1)
Lecture 8  monitoring & controlling (1)Lecture 8  monitoring & controlling (1)
Lecture 8 monitoring & controlling (1)
 
Sumter County FL Strategic Plan
Sumter County FL Strategic PlanSumter County FL Strategic Plan
Sumter County FL Strategic Plan
 
May 26 LRSC - Trillium Line Extension.pdf
May 26 LRSC - Trillium Line Extension.pdfMay 26 LRSC - Trillium Line Extension.pdf
May 26 LRSC - Trillium Line Extension.pdf
 

Plus de Fairfax County

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementFairfax County
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS Fairfax County
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22Fairfax County
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxFairfax County
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19 Fairfax County
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationFairfax County
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction ProgressFairfax County
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxFairfax County
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IVFairfax County
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Fairfax County
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxFairfax County
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilFairfax County
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptxFairfax County
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT Fairfax County
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap UpFairfax County
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Fairfax County
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Fairfax County
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectFairfax County
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Fairfax County
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual ArtsFairfax County
 

Plus de Fairfax County (20)

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer Replacement
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction Progress
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IV
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick Offpptx
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing Council
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap Up
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction Project
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual Arts
 

Dernier

Verified Love Spells in Little Rock, AR (310) 882-6330 Get My Ex-Lover Back
Verified Love Spells in Little Rock, AR (310) 882-6330 Get My Ex-Lover BackVerified Love Spells in Little Rock, AR (310) 882-6330 Get My Ex-Lover Back
Verified Love Spells in Little Rock, AR (310) 882-6330 Get My Ex-Lover BackPsychicRuben LoveSpells
 
KAHULUGAN AT KAHALAGAHAN NG GAWAING PANSIBIKO.pptx
KAHULUGAN AT KAHALAGAHAN NG GAWAING PANSIBIKO.pptxKAHULUGAN AT KAHALAGAHAN NG GAWAING PANSIBIKO.pptx
KAHULUGAN AT KAHALAGAHAN NG GAWAING PANSIBIKO.pptxjohnandrewcarlos
 
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost LoverPowerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost LoverPsychicRuben LoveSpells
 
30042024_First India Newspaper Jaipur.pdf
30042024_First India Newspaper Jaipur.pdf30042024_First India Newspaper Jaipur.pdf
30042024_First India Newspaper Jaipur.pdfFIRST INDIA
 
AI as Research Assistant: Upscaling Content Analysis to Identify Patterns of ...
AI as Research Assistant: Upscaling Content Analysis to Identify Patterns of ...AI as Research Assistant: Upscaling Content Analysis to Identify Patterns of ...
AI as Research Assistant: Upscaling Content Analysis to Identify Patterns of ...Axel Bruns
 
Defensa de JOH insiste que testimonio de analista de la DEA es falso y solici...
Defensa de JOH insiste que testimonio de analista de la DEA es falso y solici...Defensa de JOH insiste que testimonio de analista de la DEA es falso y solici...
Defensa de JOH insiste que testimonio de analista de la DEA es falso y solici...AlexisTorres963861
 
2024 02 15 AZ GOP LD4 Gen Meeting Minutes_FINAL_20240228.docx
2024 02 15 AZ GOP LD4 Gen Meeting Minutes_FINAL_20240228.docx2024 02 15 AZ GOP LD4 Gen Meeting Minutes_FINAL_20240228.docx
2024 02 15 AZ GOP LD4 Gen Meeting Minutes_FINAL_20240228.docxkfjstone13
 
1971 war india pakistan bangladesh liberation.ppt
1971 war india pakistan bangladesh liberation.ppt1971 war india pakistan bangladesh liberation.ppt
1971 war india pakistan bangladesh liberation.pptsammehtumblr
 
Nara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's Development
Nara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's DevelopmentNara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's Development
Nara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's Developmentnarsireddynannuri1
 
2024 04 03 AZ GOP LD4 Gen Meeting Minutes FINAL.docx
2024 04 03 AZ GOP LD4 Gen Meeting Minutes FINAL.docx2024 04 03 AZ GOP LD4 Gen Meeting Minutes FINAL.docx
2024 04 03 AZ GOP LD4 Gen Meeting Minutes FINAL.docxkfjstone13
 
如何办理(BU学位证书)美国贝翰文大学毕业证学位证书
如何办理(BU学位证书)美国贝翰文大学毕业证学位证书如何办理(BU学位证书)美国贝翰文大学毕业证学位证书
如何办理(BU学位证书)美国贝翰文大学毕业证学位证书Fi L
 
Kishan Reddy Report To People (2019-24).pdf
Kishan Reddy Report To People (2019-24).pdfKishan Reddy Report To People (2019-24).pdf
Kishan Reddy Report To People (2019-24).pdfKISHAN REDDY OFFICE
 
BDSM⚡Call Girls in Sector 135 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 135 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 135 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 135 Noida Escorts >༒8448380779 Escort ServiceDelhi Call girls
 
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreie
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreieGujarat-SEBCs.pdf pfpkoopapriorjfperjreie
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreiebhavenpr
 
BDSM⚡Call Girls in Indirapuram Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Indirapuram Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Indirapuram Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Indirapuram Escorts >༒8448380779 Escort ServiceDelhi Call girls
 
Call Girls in Mira Road Mumbai ( Neha 09892124323 ) College Escorts Service i...
Call Girls in Mira Road Mumbai ( Neha 09892124323 ) College Escorts Service i...Call Girls in Mira Road Mumbai ( Neha 09892124323 ) College Escorts Service i...
Call Girls in Mira Road Mumbai ( Neha 09892124323 ) College Escorts Service i...Pooja Nehwal
 
TDP As the Party of Hope For AP Youth Under N Chandrababu Naidu’s Leadership
TDP As the Party of Hope For AP Youth Under N Chandrababu Naidu’s LeadershipTDP As the Party of Hope For AP Youth Under N Chandrababu Naidu’s Leadership
TDP As the Party of Hope For AP Youth Under N Chandrababu Naidu’s Leadershipanjanibaddipudi1
 
29042024_First India Newspaper Jaipur.pdf
29042024_First India Newspaper Jaipur.pdf29042024_First India Newspaper Jaipur.pdf
29042024_First India Newspaper Jaipur.pdfFIRST INDIA
 
BDSM⚡Call Girls in Greater Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Greater Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Greater Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Greater Noida Escorts >༒8448380779 Escort ServiceDelhi Call girls
 
Julius Randle's Injury Status: Surgery Not Off the Table
Julius Randle's Injury Status: Surgery Not Off the TableJulius Randle's Injury Status: Surgery Not Off the Table
Julius Randle's Injury Status: Surgery Not Off the Tableget joys
 

Dernier (20)

Verified Love Spells in Little Rock, AR (310) 882-6330 Get My Ex-Lover Back
Verified Love Spells in Little Rock, AR (310) 882-6330 Get My Ex-Lover BackVerified Love Spells in Little Rock, AR (310) 882-6330 Get My Ex-Lover Back
Verified Love Spells in Little Rock, AR (310) 882-6330 Get My Ex-Lover Back
 
KAHULUGAN AT KAHALAGAHAN NG GAWAING PANSIBIKO.pptx
KAHULUGAN AT KAHALAGAHAN NG GAWAING PANSIBIKO.pptxKAHULUGAN AT KAHALAGAHAN NG GAWAING PANSIBIKO.pptx
KAHULUGAN AT KAHALAGAHAN NG GAWAING PANSIBIKO.pptx
 
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost LoverPowerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
 
30042024_First India Newspaper Jaipur.pdf
30042024_First India Newspaper Jaipur.pdf30042024_First India Newspaper Jaipur.pdf
30042024_First India Newspaper Jaipur.pdf
 
AI as Research Assistant: Upscaling Content Analysis to Identify Patterns of ...
AI as Research Assistant: Upscaling Content Analysis to Identify Patterns of ...AI as Research Assistant: Upscaling Content Analysis to Identify Patterns of ...
AI as Research Assistant: Upscaling Content Analysis to Identify Patterns of ...
 
Defensa de JOH insiste que testimonio de analista de la DEA es falso y solici...
Defensa de JOH insiste que testimonio de analista de la DEA es falso y solici...Defensa de JOH insiste que testimonio de analista de la DEA es falso y solici...
Defensa de JOH insiste que testimonio de analista de la DEA es falso y solici...
 
2024 02 15 AZ GOP LD4 Gen Meeting Minutes_FINAL_20240228.docx
2024 02 15 AZ GOP LD4 Gen Meeting Minutes_FINAL_20240228.docx2024 02 15 AZ GOP LD4 Gen Meeting Minutes_FINAL_20240228.docx
2024 02 15 AZ GOP LD4 Gen Meeting Minutes_FINAL_20240228.docx
 
1971 war india pakistan bangladesh liberation.ppt
1971 war india pakistan bangladesh liberation.ppt1971 war india pakistan bangladesh liberation.ppt
1971 war india pakistan bangladesh liberation.ppt
 
Nara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's Development
Nara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's DevelopmentNara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's Development
Nara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's Development
 
2024 04 03 AZ GOP LD4 Gen Meeting Minutes FINAL.docx
2024 04 03 AZ GOP LD4 Gen Meeting Minutes FINAL.docx2024 04 03 AZ GOP LD4 Gen Meeting Minutes FINAL.docx
2024 04 03 AZ GOP LD4 Gen Meeting Minutes FINAL.docx
 
如何办理(BU学位证书)美国贝翰文大学毕业证学位证书
如何办理(BU学位证书)美国贝翰文大学毕业证学位证书如何办理(BU学位证书)美国贝翰文大学毕业证学位证书
如何办理(BU学位证书)美国贝翰文大学毕业证学位证书
 
Kishan Reddy Report To People (2019-24).pdf
Kishan Reddy Report To People (2019-24).pdfKishan Reddy Report To People (2019-24).pdf
Kishan Reddy Report To People (2019-24).pdf
 
BDSM⚡Call Girls in Sector 135 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 135 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 135 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 135 Noida Escorts >༒8448380779 Escort Service
 
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreie
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreieGujarat-SEBCs.pdf pfpkoopapriorjfperjreie
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreie
 
BDSM⚡Call Girls in Indirapuram Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Indirapuram Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Indirapuram Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Indirapuram Escorts >༒8448380779 Escort Service
 
Call Girls in Mira Road Mumbai ( Neha 09892124323 ) College Escorts Service i...
Call Girls in Mira Road Mumbai ( Neha 09892124323 ) College Escorts Service i...Call Girls in Mira Road Mumbai ( Neha 09892124323 ) College Escorts Service i...
Call Girls in Mira Road Mumbai ( Neha 09892124323 ) College Escorts Service i...
 
TDP As the Party of Hope For AP Youth Under N Chandrababu Naidu’s Leadership
TDP As the Party of Hope For AP Youth Under N Chandrababu Naidu’s LeadershipTDP As the Party of Hope For AP Youth Under N Chandrababu Naidu’s Leadership
TDP As the Party of Hope For AP Youth Under N Chandrababu Naidu’s Leadership
 
29042024_First India Newspaper Jaipur.pdf
29042024_First India Newspaper Jaipur.pdf29042024_First India Newspaper Jaipur.pdf
29042024_First India Newspaper Jaipur.pdf
 
BDSM⚡Call Girls in Greater Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Greater Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Greater Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Greater Noida Escorts >༒8448380779 Escort Service
 
Julius Randle's Injury Status: Surgery Not Off the Table
Julius Randle's Injury Status: Surgery Not Off the TableJulius Randle's Injury Status: Surgery Not Off the Table
Julius Randle's Injury Status: Surgery Not Off the Table
 

Silver Line Phase 1-Status Report: Feb. 4, 2014

  • 1. Status • Overall Phase 1 Construction – 99% complete • Primary Focus: • Station Certificates of Occupancy • Testing • Punch List • Achieve Substantial Completion by Dulles Transit Partners • System Performance Demonstration Test Conducted – Jan 25-26 • Wiehle garage – Complete • Record of Decision roadway improvements – 99% complete (minor work remains) • Connector bus testing at Wiehle north - Ongoing • West Falls Church rail yard: • Completion – 95% • Community Meeting – Jan 29, 2014 • Sound Box Completion – Feb 2014 • Testing - Feb 2014 • Two noise studies / reports will be prepared – Condition 7 and 8 (SEA) • WMATA will provide FCDOT 30 day notice prior to start of revenue operations to allow for Connector service changes • Phase 1 project remains on budget - $ 2.906B Schedule • Substantial completion/MWAA turn-over to WMATA: • MWAA continues to work with DTP on Scheduled Substantial Completion Date (SSCD) • System testing is ongoing • Estimated passenger revenue service - date determined by WMATA when testing, training, and safe operation is achieved (WMATA has 90 days after SSCD for testing, training, and acceptance) • Tristate Oversight Committee Safety and Security process concurrent with WMATA testing • February 2014 Sound Box Testing WFCY • Tax District Advisory & Commission Meetings – March 2014 Current Milestones – Past 30 Days • Regional coordination for bus service and marketing outreach ongoing • WMATA lead for Phase 1 marketing and outreach; public website: www. silverlinemetro.com • Connector conducting operation testing Wiehle Garage • Fit out activities ongoing • Phase 1 Maintenance & Land Conveyance process ongoing; “walk down” field visits ongoing for property being turned over to the county • Punch List and Testing – Ongoing • Systems Performance Test Conducted 1 February 2013
  • 2. Status • Phase 2 fully in design stage • 60% and some 90% design packages received • Issued for Construction packets – Starting Spring 2014 • Coordination ongoing • Town of Herndon • Adjacent Land Owners • Project Partners • Herndon and Innovation Center Station (south) garages • Fairfax County has committed to fund and construct parking garages - Design ongoing • Innovation Center Station Garage - Land use case ongoing (June 2014) • Herndon Garage - staff has developed a number of concept designs (2232) • Scheduled tracks completion of the garages to the completion of Phase 2 • Town Center Parkway tunnel • Final concept design received by consultant November 2013 • FCDOT submits formal request to MWAA for change order / pricing on Nov. 18, 2013 • Status of Phase 2 Bid Packages: • Packet A - rail Line, station, and systems (includes Innovation Center Station) - Awarded • Packet B - Maintenance Facility at Dulles Airport • Award – Summer 2014 • NTP – Summer 2014 • Completion Summer 2018 • MWAA’s Dulles Rail office to relocate to Herndon – Completed on Jan 17, 2014 Budget/Schedule • Cost Estimate: $3.093B • Cost Estimate with value engineering , Packet A savings, and garages funding outside the project: $2.6B • Substantial Completion: Summer 2018 • Revenue Operations: Late 2018 • Tax District Advisory & Commission Meetings – March 2014 Current Milestones – Past 30 Days • FTA oversight of Phase 2 similar to Phase 1 • TIFIA process – Ongoing • Design – Ongoing • Herndon Metrorail Station Access Management Study (HMSAMS) • Identify pedestrian, bicycle, bus transit and roadway improvements to and from Herndon and Innovation Center Station • Public Meetings – Spring 2014 2 February 2013