The Dolley Madison sidewalk project included 345 linear feet of concrete sidewalk, pedestrian ramps, curb and gutter, modification of existing median, pavement marking and signage, pavement mill and overlay and other associated work.
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Dolley Madison Sidewalk - Chain Bridge Road to Kurtz Road
1. A Fairfax County, VA, publication
Department of Public Works and Environmental Services
Working for You!
Dolley Madison Sidewalk
Chain Bridge Road to Kurtz Road
Contract No. CN17304122
Task Order No. 48
Project No. 5G25-060-015
Dranesville District
Tax Map No. 30-2
December 7, 2018
2. Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
Dolley Madison Sidewalk:
Chain Bridge Rd to Kurtz Rd
3. Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
Project Site
Dolley Madison Sidewalk: Chain Bridge Rd to Kurtz Rd
Tax Map No. 30-2
4. Project Details
Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
Description:
The Dolley Madison Sidewalk: Chain Bridge Road to Kurtz Road was substantially completed on
November 20, 2018. The project included 345 LF concrete sidewalk, pedestrian ramps, curb
and gutter, modification of existing median, pavement marking & signage, pavement mill and
overlay and other associated work.
Project Overview:
• Project Delivery: Annual Contract
• Contract: Unit Price
Project Team:
• Contractor
• Ashburn Contracting Corporation
• Fairfax County
• Department of Transportation – Shahla Zahirieh
• Utilities Design and Construction Division - Sanjala Bajracharya
• Project Inspector, UDCD – Jim Cooper
• Land Survey Branch, UDCD – Cody Harp-Taylor
Dolley Madison Sidewalk: Chain Bridge Rd to Kurtz Rd
5. Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
Dolley Madison Sidewalk: Chain Bridge Rd to Kurtz Rd
Installation of Sidewalk and Curb & Gutter Concrete Forming
6. Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
Dolley Madison Sidewalk: Chain Bridge Rd to Kurtz Rd
Installation of Concrete Sidewalk
7. Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
Dolley Madison Sidewalk: Chain Bridge Rd to Kurtz Rd
Soil Retention Mat (Jute Mesh)
9. Additional Information
For additional Information, please call
www.fairfaxcounty.gov/publicworks
Dolley Madison Sidewalk: Chain Bridge Rd to Kurtz Rd
Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
Matthew Kaiser, Public Information Officer
703-324-8455, TTY 711
Matthew.kaiser@fairfaxcounty.gov