SlideShare une entreprise Scribd logo
1  sur  18
Dulles Corridor Metrorail Project
Silver Line Phase 2 Implementation
Board Transportation Committee Update
December 11, 2018
Mark Canale, Fairfax County Project Manager
Fairfax County Department of Transportation
2
Project Status
Phase 1
• Old Meadow Road Realignment – 100% design complete.
• Construction completion scheduled for Summer 2019.
• VDOT punch list ongoing – MWAA and Bechtel to complete
• Phase 1 close out - $2.982B (no change)
Phase 2
• Overall Phase 2 – 88% complete
• Package A (Rail line, system, and stations) – 88%
• Package B (Rail yard at Dulles) – 90%
• Contractual Substantial Completion – August 2019
• WMATA Board to establish Revenue Operations Date
3
• Budget
• Total Budget $2.778B
• Total Forecast $2.778B
• Total Expenditures $1.868B
• Contingency Utilization
• Total Contingency $551.5M
• Total Contingency Utilized $270.2M
• Remaining Contingency $281.3M
Phase 2 – Cost Summary
4
• Reston Town Center Station – Mechanical/electrical/plumbing
rough-in, paver installation, and pavilion detailing.
• Herndon Station – Mechanical/electrical rough-in, station ceiling
grid, and elevator/escalator work.
• Innovation Station – Detailing for pavilion and escalators, station
finishes, electrical rough-in and plumbing continues.
Phase 2 – Station Construction
5
• Dulles Airport Station – Station lighting, ceiling grid framing, and
platform paver installation.
• Loudoun Gateway Station – Vault roof skylight framing and
glazing, pedestrian bridge detailing, and MEP rough-in.
• Ashburn Station - Station roof work, MEP rough-in, pavilion work,
and pedestrian bridge detailing.
Phase 2 – Station Construction
6
• Pulling power to aerial guideway
• Installation of guideway mounted equipment for Train Control and
switch operation
• Communication cables installed along the alignment and
communication rooms outfitted
• Rail and switches being installed along the at grade guideway in
the DIAAH median from the Reston Town Center Station to Yard
Leads.
Phase 2 – Aerial, Track, Utilities, Systems
7
• Gas line, concrete pavement, and perimeter fence
installation ongoing. MEP work for Service and Inspection
Building, Maintenance Way Building, and Transit Police
Building. Construction continues at Train Wash Facility,
Warehouse Facility, and Vehicle Storage Facility.
• Ongoing – Testing of Yard Train Control cabling, switch and
signal installation
Phase 2 – Rail Yard at Dulles Airport
8
• Total Project Estimate: $44.5M
• Construction Progress: 96% complete
• Existing garage repair work initiated in November 2018
Schedule
• Construction Award: October 2016
• Construction (new garage): November 2016 – March 2019
• Construction (existing garage): October 2018
• Ready for Occupancy: April 2019
Herndon Metrorail Garage
9
Herndon Metrorail Garage
Herndon Metrorail Garage
10
11
• Total Project Estimate: $52 million
• Construction Progress: 65% complete
Schedule
• Construction Award: March 2017
• Construction Start: April 2017
• Precast Erection Start: April 5, 2018
• Ready for Occupancy: Late 2019 (Prior to the start of
Revenue Operation)*
* Will be updated as needed pending the lifting of the stop work order
Innovation Metrorail Garage
12
Innovation Metrorail Garage
13
Reston Town Center Station
Reston Town Center Pavilions
Reston South Retaining Wall
14
Herndon Station
Herndon Station Pavilions
Herndon Station South Pavilion
Herndon Stair Tower Construction
15
Innovation Center Station
16
Dulles Airport Station
17
Rail Yard Dulles Airport
18
QUESTIONS?

Contenu connexe

Tendances

Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017
Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017
Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017
Crosstown TO
 
rup-20151016-part-1-item07-victoria-station-upgrade
rup-20151016-part-1-item07-victoria-station-upgraderup-20151016-part-1-item07-victoria-station-upgrade
rup-20151016-part-1-item07-victoria-station-upgrade
Robert Lee - CEng, MICE, PMP
 
Arqiva 2008 Ops Conference - TWM Update by GHarris
Arqiva 2008 Ops Conference - TWM Update by GHarrisArqiva 2008 Ops Conference - TWM Update by GHarris
Arqiva 2008 Ops Conference - TWM Update by GHarris
Gavin Harris
 
Leaside - Laird Construction Liaison Committee - July 2018
Leaside - Laird Construction Liaison Committee - July 2018Leaside - Laird Construction Liaison Committee - July 2018
Leaside - Laird Construction Liaison Committee - July 2018
Crosstown TO
 
EMS Capabilities Overview
EMS Capabilities OverviewEMS Capabilities Overview
EMS Capabilities Overview
Ron Hawks
 

Tendances (20)

Confederation line quarterly memo to council q1 2017
Confederation line quarterly memo to council q1 2017Confederation line quarterly memo to council q1 2017
Confederation line quarterly memo to council q1 2017
 
95 Express Lanes Update
95 Express Lanes Update95 Express Lanes Update
95 Express Lanes Update
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017
Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017
Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017
 
Fort Bragg, NC
Fort Bragg, NCFort Bragg, NC
Fort Bragg, NC
 
rup-20151016-part-1-item07-victoria-station-upgrade
rup-20151016-part-1-item07-victoria-station-upgraderup-20151016-part-1-item07-victoria-station-upgrade
rup-20151016-part-1-item07-victoria-station-upgrade
 
McLean Metro Gravity Sewer Capacity Improvements
McLean Metro Gravity Sewer Capacity ImprovementsMcLean Metro Gravity Sewer Capacity Improvements
McLean Metro Gravity Sewer Capacity Improvements
 
Fairfax County Wastewater Collection Asset Management Program Oct 2020
Fairfax County Wastewater Collection Asset Management Program  Oct 2020Fairfax County Wastewater Collection Asset Management Program  Oct 2020
Fairfax County Wastewater Collection Asset Management Program Oct 2020
 
NEDA
NEDANEDA
NEDA
 
Fitchburg Commuter Rail Line Improvement Project
Fitchburg Commuter Rail Line Improvement ProjectFitchburg Commuter Rail Line Improvement Project
Fitchburg Commuter Rail Line Improvement Project
 
Managing Massive Updates - Using GIS to Fuel Gas Compliance
Managing Massive Updates - Using GIS to Fuel Gas ComplianceManaging Massive Updates - Using GIS to Fuel Gas Compliance
Managing Massive Updates - Using GIS to Fuel Gas Compliance
 
Telegraph Road Walkway Phase 1 August 2020
Telegraph Road Walkway Phase 1 August 2020Telegraph Road Walkway Phase 1 August 2020
Telegraph Road Walkway Phase 1 August 2020
 
Train Thursday Workshop August 4th 2015 EEOv2
Train Thursday Workshop August 4th 2015 EEOv2Train Thursday Workshop August 4th 2015 EEOv2
Train Thursday Workshop August 4th 2015 EEOv2
 
Arqiva 2008 Ops Conference - TWM Update by GHarris
Arqiva 2008 Ops Conference - TWM Update by GHarrisArqiva 2008 Ops Conference - TWM Update by GHarris
Arqiva 2008 Ops Conference - TWM Update by GHarris
 
Hayfield Road Pipe Conveyance System January 2021
Hayfield Road Pipe Conveyance System January 2021Hayfield Road Pipe Conveyance System January 2021
Hayfield Road Pipe Conveyance System January 2021
 
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarNorth West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
 
04 02-15 Caltrain Modernization Updates
04 02-15 Caltrain Modernization Updates04 02-15 Caltrain Modernization Updates
04 02-15 Caltrain Modernization Updates
 
Leaside - Laird Construction Liaison Committee - July 2018
Leaside - Laird Construction Liaison Committee - July 2018Leaside - Laird Construction Liaison Committee - July 2018
Leaside - Laird Construction Liaison Committee - July 2018
 
EMS Capabilities Overview
EMS Capabilities OverviewEMS Capabilities Overview
EMS Capabilities Overview
 
Nov 14 - Caltrain Modernization Cost and Schedule Update
Nov 14 - Caltrain Modernization Cost and Schedule UpdateNov 14 - Caltrain Modernization Cost and Schedule Update
Nov 14 - Caltrain Modernization Cost and Schedule Update
 
Leaside Laird Construction Liaison Committee (CLC) Meeting Presentation
Leaside  Laird Construction Liaison Committee (CLC) Meeting PresentationLeaside  Laird Construction Liaison Committee (CLC) Meeting Presentation
Leaside Laird Construction Liaison Committee (CLC) Meeting Presentation
 

Similaire à Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation

Central Open House (Chaplin Station to Leaside Station) - spring 2018
Central Open House (Chaplin Station to Leaside Station) - spring 2018Central Open House (Chaplin Station to Leaside Station) - spring 2018
Central Open House (Chaplin Station to Leaside Station) - spring 2018
Crosstown TO
 
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
Crosstown TO
 

Similaire à Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation (20)

Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 ImplementationDulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
 
Dulles Metrorail Silver Line Phase 2 Status and Funding Update
Dulles Metrorail Silver Line Phase 2 Status and Funding UpdateDulles Metrorail Silver Line Phase 2 Status and Funding Update
Dulles Metrorail Silver Line Phase 2 Status and Funding Update
 
Silver Line Phase 1-Status Report: May 6, 2014
Silver Line Phase 1-Status Report: May 6, 2014Silver Line Phase 1-Status Report: May 6, 2014
Silver Line Phase 1-Status Report: May 6, 2014
 
Silver Line Phase 1 Status Report
Silver Line Phase 1 Status ReportSilver Line Phase 1 Status Report
Silver Line Phase 1 Status Report
 
Silver Line Phase 1-Status Report: Feb. 4, 2014
Silver Line Phase 1-Status Report: Feb. 4, 2014Silver Line Phase 1-Status Report: Feb. 4, 2014
Silver Line Phase 1-Status Report: Feb. 4, 2014
 
Silver Line Update-Board Transportation Committee: Oct. 13, 2015
Silver Line Update-Board Transportation Committee: Oct. 13, 2015Silver Line Update-Board Transportation Committee: Oct. 13, 2015
Silver Line Update-Board Transportation Committee: Oct. 13, 2015
 
Silver Line Update: Board Transportation Committee: Feb. 7, 2017
Silver Line Update: Board Transportation Committee: Feb. 7, 2017Silver Line Update: Board Transportation Committee: Feb. 7, 2017
Silver Line Update: Board Transportation Committee: Feb. 7, 2017
 
Addison Capital Projects Update
Addison Capital Projects UpdateAddison Capital Projects Update
Addison Capital Projects Update
 
Silver Line Phase 1-Status Report
Silver Line Phase 1-Status ReportSilver Line Phase 1-Status Report
Silver Line Phase 1-Status Report
 
Silver Line Phase 1 Status Report-Sept. 16, 2014
Silver Line Phase 1 Status Report-Sept. 16, 2014Silver Line Phase 1 Status Report-Sept. 16, 2014
Silver Line Phase 1 Status Report-Sept. 16, 2014
 
Central Open House (Chaplin Station to Leaside Station) - spring 2018
Central Open House (Chaplin Station to Leaside Station) - spring 2018Central Open House (Chaplin Station to Leaside Station) - spring 2018
Central Open House (Chaplin Station to Leaside Station) - spring 2018
 
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
 
Silver Line Update July 2016
Silver Line Update July 2016Silver Line Update July 2016
Silver Line Update July 2016
 
Board Transportation Committee Update: March 17, 2015
Board Transportation Committee Update: March 17, 2015Board Transportation Committee Update: March 17, 2015
Board Transportation Committee Update: March 17, 2015
 
Central Spring Open House Presentation Deck - March 23 2020
Central Spring Open House Presentation Deck - March 23 2020Central Spring Open House Presentation Deck - March 23 2020
Central Spring Open House Presentation Deck - March 23 2020
 
Silver Line Update: Board Transportation Committee May 24, 2016
Silver Line Update: Board Transportation Committee May 24, 2016Silver Line Update: Board Transportation Committee May 24, 2016
Silver Line Update: Board Transportation Committee May 24, 2016
 
Silver Line Update: Board Transportation Committee May 24, 2016
Silver Line Update: Board Transportation Committee May 24, 2016Silver Line Update: Board Transportation Committee May 24, 2016
Silver Line Update: Board Transportation Committee May 24, 2016
 
Silver Line Phase 1-Status Report: Sept. 2013
Silver Line Phase 1-Status Report: Sept. 2013Silver Line Phase 1-Status Report: Sept. 2013
Silver Line Phase 1-Status Report: Sept. 2013
 
Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure...
Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure...Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure...
Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure...
 
Silver Line Update: December 1, 2015
Silver Line Update: December 1, 2015Silver Line Update: December 1, 2015
Silver Line Update: December 1, 2015
 

Plus de Fairfax County

Plus de Fairfax County (20)

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer Replacement
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction Progress
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IV
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick Offpptx
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing Council
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap Up
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction Project
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual Arts
 

Dernier

THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
Faga1939
 
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
hyt3577
 
9953056974 Call Girls In Pratap Nagar, Escorts (Delhi) NCR
9953056974 Call Girls In Pratap Nagar, Escorts (Delhi) NCR9953056974 Call Girls In Pratap Nagar, Escorts (Delhi) NCR
9953056974 Call Girls In Pratap Nagar, Escorts (Delhi) NCR
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
The political system of the united kingdom
The political system of the united kingdomThe political system of the united kingdom
The political system of the united kingdom
lunadelior
 

Dernier (20)

declarationleaders_sd_re_greens_theleft_5.pdf
declarationleaders_sd_re_greens_theleft_5.pdfdeclarationleaders_sd_re_greens_theleft_5.pdf
declarationleaders_sd_re_greens_theleft_5.pdf
 
Politician uddhav thackeray biography- Full Details
Politician uddhav thackeray biography- Full DetailsPolitician uddhav thackeray biography- Full Details
Politician uddhav thackeray biography- Full Details
 
Embed-4.pdf lkdiinlajeklhndklheduhuekjdh
Embed-4.pdf lkdiinlajeklhndklheduhuekjdhEmbed-4.pdf lkdiinlajeklhndklheduhuekjdh
Embed-4.pdf lkdiinlajeklhndklheduhuekjdh
 
05052024_First India Newspaper Jaipur.pdf
05052024_First India Newspaper Jaipur.pdf05052024_First India Newspaper Jaipur.pdf
05052024_First India Newspaper Jaipur.pdf
 
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
 
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
 
9953056974 Call Girls In Pratap Nagar, Escorts (Delhi) NCR
9953056974 Call Girls In Pratap Nagar, Escorts (Delhi) NCR9953056974 Call Girls In Pratap Nagar, Escorts (Delhi) NCR
9953056974 Call Girls In Pratap Nagar, Escorts (Delhi) NCR
 
Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...
Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...
Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...
 
America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...
America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...
America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...
 
06052024_First India Newspaper Jaipur.pdf
06052024_First India Newspaper Jaipur.pdf06052024_First India Newspaper Jaipur.pdf
06052024_First India Newspaper Jaipur.pdf
 
04052024_First India Newspaper Jaipur.pdf
04052024_First India Newspaper Jaipur.pdf04052024_First India Newspaper Jaipur.pdf
04052024_First India Newspaper Jaipur.pdf
 
Embed-2 (1).pdfb[k[k[[k[kkkpkdpokkdpkopko
Embed-2 (1).pdfb[k[k[[k[kkkpkdpokkdpkopkoEmbed-2 (1).pdfb[k[k[[k[kkkpkdpokkdpkopko
Embed-2 (1).pdfb[k[k[[k[kkkpkdpokkdpkopko
 
422524114-Patriarchy-Kamla-Bhasin gg.pdf
422524114-Patriarchy-Kamla-Bhasin gg.pdf422524114-Patriarchy-Kamla-Bhasin gg.pdf
422524114-Patriarchy-Kamla-Bhasin gg.pdf
 
KING VISHNU BHAGWANON KA BHAGWAN PARAMATMONKA PARATOMIC PARAMANU KASARVAMANVA...
KING VISHNU BHAGWANON KA BHAGWAN PARAMATMONKA PARATOMIC PARAMANU KASARVAMANVA...KING VISHNU BHAGWANON KA BHAGWAN PARAMATMONKA PARATOMIC PARAMANU KASARVAMANVA...
KING VISHNU BHAGWANON KA BHAGWAN PARAMATMONKA PARATOMIC PARAMANU KASARVAMANVA...
 
Group_5_US-China Trade War to understand the trade
Group_5_US-China Trade War to understand the tradeGroup_5_US-China Trade War to understand the trade
Group_5_US-China Trade War to understand the trade
 
Job-Oriеntеd Courses That Will Boost Your Career in 2024
Job-Oriеntеd Courses That Will Boost Your Career in 2024Job-Oriеntеd Courses That Will Boost Your Career in 2024
Job-Oriеntеd Courses That Will Boost Your Career in 2024
 
*Navigating Electoral Terrain: TDP's Performance under N Chandrababu Naidu's ...
*Navigating Electoral Terrain: TDP's Performance under N Chandrababu Naidu's ...*Navigating Electoral Terrain: TDP's Performance under N Chandrababu Naidu's ...
*Navigating Electoral Terrain: TDP's Performance under N Chandrababu Naidu's ...
 
China's soft power in 21st century .pptx
China's soft power in 21st century   .pptxChina's soft power in 21st century   .pptx
China's soft power in 21st century .pptx
 
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreie
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreieGujarat-SEBCs.pdf pfpkoopapriorjfperjreie
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreie
 
The political system of the united kingdom
The political system of the united kingdomThe political system of the united kingdom
The political system of the united kingdom
 

Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation

  • 1. Dulles Corridor Metrorail Project Silver Line Phase 2 Implementation Board Transportation Committee Update December 11, 2018 Mark Canale, Fairfax County Project Manager Fairfax County Department of Transportation
  • 2. 2 Project Status Phase 1 • Old Meadow Road Realignment – 100% design complete. • Construction completion scheduled for Summer 2019. • VDOT punch list ongoing – MWAA and Bechtel to complete • Phase 1 close out - $2.982B (no change) Phase 2 • Overall Phase 2 – 88% complete • Package A (Rail line, system, and stations) – 88% • Package B (Rail yard at Dulles) – 90% • Contractual Substantial Completion – August 2019 • WMATA Board to establish Revenue Operations Date
  • 3. 3 • Budget • Total Budget $2.778B • Total Forecast $2.778B • Total Expenditures $1.868B • Contingency Utilization • Total Contingency $551.5M • Total Contingency Utilized $270.2M • Remaining Contingency $281.3M Phase 2 – Cost Summary
  • 4. 4 • Reston Town Center Station – Mechanical/electrical/plumbing rough-in, paver installation, and pavilion detailing. • Herndon Station – Mechanical/electrical rough-in, station ceiling grid, and elevator/escalator work. • Innovation Station – Detailing for pavilion and escalators, station finishes, electrical rough-in and plumbing continues. Phase 2 – Station Construction
  • 5. 5 • Dulles Airport Station – Station lighting, ceiling grid framing, and platform paver installation. • Loudoun Gateway Station – Vault roof skylight framing and glazing, pedestrian bridge detailing, and MEP rough-in. • Ashburn Station - Station roof work, MEP rough-in, pavilion work, and pedestrian bridge detailing. Phase 2 – Station Construction
  • 6. 6 • Pulling power to aerial guideway • Installation of guideway mounted equipment for Train Control and switch operation • Communication cables installed along the alignment and communication rooms outfitted • Rail and switches being installed along the at grade guideway in the DIAAH median from the Reston Town Center Station to Yard Leads. Phase 2 – Aerial, Track, Utilities, Systems
  • 7. 7 • Gas line, concrete pavement, and perimeter fence installation ongoing. MEP work for Service and Inspection Building, Maintenance Way Building, and Transit Police Building. Construction continues at Train Wash Facility, Warehouse Facility, and Vehicle Storage Facility. • Ongoing – Testing of Yard Train Control cabling, switch and signal installation Phase 2 – Rail Yard at Dulles Airport
  • 8. 8 • Total Project Estimate: $44.5M • Construction Progress: 96% complete • Existing garage repair work initiated in November 2018 Schedule • Construction Award: October 2016 • Construction (new garage): November 2016 – March 2019 • Construction (existing garage): October 2018 • Ready for Occupancy: April 2019 Herndon Metrorail Garage
  • 11. 11 • Total Project Estimate: $52 million • Construction Progress: 65% complete Schedule • Construction Award: March 2017 • Construction Start: April 2017 • Precast Erection Start: April 5, 2018 • Ready for Occupancy: Late 2019 (Prior to the start of Revenue Operation)* * Will be updated as needed pending the lifting of the stop work order Innovation Metrorail Garage
  • 13. 13 Reston Town Center Station Reston Town Center Pavilions Reston South Retaining Wall
  • 14. 14 Herndon Station Herndon Station Pavilions Herndon Station South Pavilion Herndon Stair Tower Construction