A Fairfax County, VA, publication
Department of Public Works and Environmental Services
Working for You!
Contract No. CN15125131
Project No. SD-000032-061
Lee District
Tax Map No. 91-4 and 100-2
1/14/2021
Hayfield Road Pipe Conveyance System
Hayfield Road Pipe Conveyance System
Capital Facilities/Utilities Design and Construction Division/Stormwater Construction Branch
Project Details
Project Overview:
• Replacement of sanitary sewer pipes and laterals in conflict with the new stormwater
pipe and culvert.
• Installation of approximately 2,200 linear feet of 48-inch reinforced concrete pipe and
approximately 1,210 linear feet of 7-foot by 4-foot concrete box culvert, including dozens
of gas, water, and electric utility relocations.
• Installation of culvert outfall, concrete weirs, and level spreader.
• Site rehabilitation including sidewalks, curbs and gutters, road paving, and landscaping.
Hayfield Road Pipe Conveyance System
Capital Facilities/Utilities Design and Construction Division/Stormwater Construction Branch
Project Description:
The Hayfield Road Pipe Conveyance System project has been substantially completed. The purpose
of this project was to alleviate an ongoing stormwater surcharge issue in the Hayfield Road
community by providing additional capacity to the stormwater sewer system through the
installation of a new stormwater sewer line and outlet into the woods.
Project Team:
• Dave Anglin – Project Manager, Stormwater Planning and Design Division
• Suzanne Foster – Landscape Architect, Stormwater Planning and Design Division
• David Simpson – Construction Inspector, Utilities Design and Construction Division (UDCD)
• Brendan Schillo – Construction Manager, UDCD
• Eric Lefcort – Right of Way Agent, Land Acquisition Division
Hayfield Road Pipe Conveyance System
Capital Facilities/Utilities Design and Construction Division/Stormwater Construction Branch
Hayfield Road, Alexandria – Tax Map 91-4 & 100-2
Hayfield Road Pipe Conveyance System
Capital Facilities/Utilities Design and Construction Division/Stormwater Construction Branch
Installation of 48-inch Reinforced Concrete Pipe
Hayfield Road Pipe Conveyance System
Capital Facilities/Utilities Design and Construction Division/Stormwater Construction Branch
Installation of 4-foot by 7-foot Box Culvert
Hayfield Road Pipe Conveyance System
Capital Facilities/Utilities Design and Construction Division/Stormwater Construction Branch
Microtunneling Under Telegraph Road
Hayfield Road Pipe Conveyance System
Capital Facilities/Utilities Design and Construction Division/Stormwater Construction Branch
Installation of Storm Sewer Outfall
Hayfield Road Pipe Conveyance System
Capital Facilities/Utilities Design and Construction Division/Stormwater Construction Branch
Replacement of Sidewalks, Curbs/Gutters & Driveway Aprons
Hayfield Road Pipe Conveyance System
Capital Facilities/Utilities Design and Construction Division/Stormwater Construction Branch
Paving of Hayfield Road
Before After
Hayfield Road Pipe Conveyance System
Capital Facilities/Utilities Design and Construction Division/Stormwater Construction Branch
Before After
Hayfield Road Pipe Conveyance System
Capital Facilities/Utilities Design and Construction Division/Stormwater Construction Branch
Additional Information
For additional Information, please call
www.fairfaxcounty.gov/publicworks
Hayfield Road Pipe Conveyance System
Capital Facilities/Utilities Design and Construction Division/Stormwater Construction Branch
Irene Haske, Public Information Officer
703-324-5821, TTY 711
Irene.Haske@fairfaxcounty.gov

Contenu connexe

Tendances

Forest Hill Station Open House - June 2017
Forest Hill Station Open House - June 2017Forest Hill Station Open House - June 2017
Forest Hill Station Open House - June 2017
Crosstown TO
 
Cedarvale Station Open House - March 2017
Cedarvale Station Open House - March 2017Cedarvale Station Open House - March 2017
Cedarvale Station Open House - March 2017
Crosstown TO
 
Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017
Crosstown TO
 
Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017
Crosstown TO
 
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
Crosstown TO
 
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...
Crosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017
Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017
Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017
Crosstown TO
 
Mount Pleasant Station Open House - April 2017
Mount Pleasant Station Open House - April 2017Mount Pleasant Station Open House - April 2017
Mount Pleasant Station Open House - April 2017
Crosstown TO
 
Leaside - Laird Construction Liaison Committee Meeting - July 2017
Leaside - Laird Construction Liaison Committee Meeting  - July 2017Leaside - Laird Construction Liaison Committee Meeting  - July 2017
Leaside - Laird Construction Liaison Committee Meeting - July 2017
Crosstown TO
 

Tendances (20)

Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 ImplementationDulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
 
Nancemond Street Outfall Stabilization
Nancemond Street Outfall StabilizationNancemond Street Outfall Stabilization
Nancemond Street Outfall Stabilization
 
Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE). Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
 
Forest Hill Station Open House - June 2017
Forest Hill Station Open House - June 2017Forest Hill Station Open House - June 2017
Forest Hill Station Open House - June 2017
 
Hayfield Road Project Citizens Association Meeting Jan. 17, 2018
Hayfield Road Project Citizens Association Meeting Jan. 17, 2018Hayfield Road Project Citizens Association Meeting Jan. 17, 2018
Hayfield Road Project Citizens Association Meeting Jan. 17, 2018
 
Cedarvale Station Open House - March 2017
Cedarvale Station Open House - March 2017Cedarvale Station Open House - March 2017
Cedarvale Station Open House - March 2017
 
Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017
 
Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017
 
Powerpoint - Langley School Pump Station and Force Main Project
Powerpoint  -  Langley School Pump Station and Force Main ProjectPowerpoint  -  Langley School Pump Station and Force Main Project
Powerpoint - Langley School Pump Station and Force Main Project
 
Integrated Sewer Metering Project 1
Integrated Sewer Metering Project 1Integrated Sewer Metering Project 1
Integrated Sewer Metering Project 1
 
Accotink Tributary at Danbury Forest
Accotink Tributary at Danbury ForestAccotink Tributary at Danbury Forest
Accotink Tributary at Danbury Forest
 
Old Keene Mill Emergency Gravity Sewer
Old Keene Mill Emergency Gravity SewerOld Keene Mill Emergency Gravity Sewer
Old Keene Mill Emergency Gravity Sewer
 
Holmes Run Weir Diversion Structure No. 417
Holmes Run Weir Diversion Structure No. 417Holmes Run Weir Diversion Structure No. 417
Holmes Run Weir Diversion Structure No. 417
 
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
 
Giles Run Pump Station Rehabilitation
Giles Run Pump Station RehabilitationGiles Run Pump Station Rehabilitation
Giles Run Pump Station Rehabilitation
 
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017
Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017
Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017
 
Mount Pleasant Station Open House - April 2017
Mount Pleasant Station Open House - April 2017Mount Pleasant Station Open House - April 2017
Mount Pleasant Station Open House - April 2017
 
Leaside - Laird Construction Liaison Committee Meeting - July 2017
Leaside - Laird Construction Liaison Committee Meeting  - July 2017Leaside - Laird Construction Liaison Committee Meeting  - July 2017
Leaside - Laird Construction Liaison Committee Meeting - July 2017
 
Celedon Lane Virtual Community Meeting Slipline Replacement August 19, 2020
Celedon Lane Virtual Community Meeting Slipline Replacement August 19, 2020Celedon Lane Virtual Community Meeting Slipline Replacement August 19, 2020
Celedon Lane Virtual Community Meeting Slipline Replacement August 19, 2020
 

Similaire à Hayfield Road Pipe Conveyance System January 2021

Similaire à Hayfield Road Pipe Conveyance System January 2021 (20)

Cinder Bed Road Realignment
Cinder Bed Road RealignmentCinder Bed Road Realignment
Cinder Bed Road Realignment
 
Great Passage Storm Sewer Improvement Project
Great Passage Storm Sewer Improvement ProjectGreat Passage Storm Sewer Improvement Project
Great Passage Storm Sewer Improvement Project
 
Colfax Ave Emergency Sewer Rehabilitation Project
Colfax Ave Emergency Sewer Rehabilitation ProjectColfax Ave Emergency Sewer Rehabilitation Project
Colfax Ave Emergency Sewer Rehabilitation Project
 
Meadow Run Pond Improvement
Meadow Run Pond ImprovementMeadow Run Pond Improvement
Meadow Run Pond Improvement
 
Waynewood l Force Main Rehabilitation Project Jan 8, 2021
Waynewood l Force Main Rehabilitation Project Jan 8, 2021Waynewood l Force Main Rehabilitation Project Jan 8, 2021
Waynewood l Force Main Rehabilitation Project Jan 8, 2021
 
Fairfax County Old Courthouse Road Walkway Improvements August 2020
Fairfax County Old Courthouse Road Walkway Improvements August 2020Fairfax County Old Courthouse Road Walkway Improvements August 2020
Fairfax County Old Courthouse Road Walkway Improvements August 2020
 
Telegraph Road Walkway
Telegraph Road WalkwayTelegraph Road Walkway
Telegraph Road Walkway
 
Fairfax County Glade Dr. Walkway Improvements August 2020
Fairfax County Glade Dr. Walkway Improvements August 2020Fairfax County Glade Dr. Walkway Improvements August 2020
Fairfax County Glade Dr. Walkway Improvements August 2020
 
Chesterbrook Road Walkway Improvement Project August 2020
Chesterbrook Road Walkway Improvement Project August 2020Chesterbrook Road Walkway Improvement Project August 2020
Chesterbrook Road Walkway Improvement Project August 2020
 
Evermay Sec. 7b Underground Detention Facility Replacement Project
Evermay Sec. 7b Underground Detention Facility Replacement ProjectEvermay Sec. 7b Underground Detention Facility Replacement Project
Evermay Sec. 7b Underground Detention Facility Replacement Project
 
Spring Hill Metro Emergency Sewer Replacement
Spring Hill Metro Emergency Sewer ReplacementSpring Hill Metro Emergency Sewer Replacement
Spring Hill Metro Emergency Sewer Replacement
 
Difficult Run Tributary at Brittenford Drive Stream Restoration
Difficult Run Tributary at Brittenford Drive Stream RestorationDifficult Run Tributary at Brittenford Drive Stream Restoration
Difficult Run Tributary at Brittenford Drive Stream Restoration
 
Fort Hunt Road Emergency Gravity Sewer Project
Fort Hunt Road Emergency Gravity Sewer ProjectFort Hunt Road Emergency Gravity Sewer Project
Fort Hunt Road Emergency Gravity Sewer Project
 
Gadsen Drive Emergency Gravity Sewer Repairs
Gadsen Drive Emergency Gravity Sewer RepairsGadsen Drive Emergency Gravity Sewer Repairs
Gadsen Drive Emergency Gravity Sewer Repairs
 
Bradley Acres Pond Retrofit Project
Bradley Acres Pond Retrofit ProjectBradley Acres Pond Retrofit Project
Bradley Acres Pond Retrofit Project
 
Potomac Meadow Water Quality Improvement July 2016
Potomac Meadow Water Quality Improvement July 2016Potomac Meadow Water Quality Improvement July 2016
Potomac Meadow Water Quality Improvement July 2016
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IV
 
Slipline Replacement #2 - Waterway Drive
Slipline Replacement #2 - Waterway DriveSlipline Replacement #2 - Waterway Drive
Slipline Replacement #2 - Waterway Drive
 
Little River Turnpike, Backlick Rd. Emergency Sewer Repair Sept 2020
Little River Turnpike, Backlick Rd. Emergency Sewer Repair Sept 2020Little River Turnpike, Backlick Rd. Emergency Sewer Repair Sept 2020
Little River Turnpike, Backlick Rd. Emergency Sewer Repair Sept 2020
 
Pohick Road - South Run Road Walkway Pedestrian Improvements
Pohick Road - South Run Road Walkway Pedestrian ImprovementsPohick Road - South Run Road Walkway Pedestrian Improvements
Pohick Road - South Run Road Walkway Pedestrian Improvements
 

Plus de Fairfax County

Plus de Fairfax County (20)

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer Replacement
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction Progress
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick Offpptx
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing Council
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap Up
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction Project
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual Arts
 
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
 

Dernier

notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
MsecMca
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
dharasingh5698
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
ssuser89054b
 
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoorTop Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
dharasingh5698
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
dollysharma2066
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
ankushspencer015
 

Dernier (20)

ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
 
NFPA 5000 2024 standard .
NFPA 5000 2024 standard                                  .NFPA 5000 2024 standard                                  .
NFPA 5000 2024 standard .
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoorTop Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
 
Unit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfUnit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdf
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 

Hayfield Road Pipe Conveyance System January 2021

  • 1. A Fairfax County, VA, publication Department of Public Works and Environmental Services Working for You! Contract No. CN15125131 Project No. SD-000032-061 Lee District Tax Map No. 91-4 and 100-2 1/14/2021 Hayfield Road Pipe Conveyance System
  • 2. Hayfield Road Pipe Conveyance System Capital Facilities/Utilities Design and Construction Division/Stormwater Construction Branch
  • 3. Project Details Project Overview: • Replacement of sanitary sewer pipes and laterals in conflict with the new stormwater pipe and culvert. • Installation of approximately 2,200 linear feet of 48-inch reinforced concrete pipe and approximately 1,210 linear feet of 7-foot by 4-foot concrete box culvert, including dozens of gas, water, and electric utility relocations. • Installation of culvert outfall, concrete weirs, and level spreader. • Site rehabilitation including sidewalks, curbs and gutters, road paving, and landscaping. Hayfield Road Pipe Conveyance System Capital Facilities/Utilities Design and Construction Division/Stormwater Construction Branch Project Description: The Hayfield Road Pipe Conveyance System project has been substantially completed. The purpose of this project was to alleviate an ongoing stormwater surcharge issue in the Hayfield Road community by providing additional capacity to the stormwater sewer system through the installation of a new stormwater sewer line and outlet into the woods. Project Team: • Dave Anglin – Project Manager, Stormwater Planning and Design Division • Suzanne Foster – Landscape Architect, Stormwater Planning and Design Division • David Simpson – Construction Inspector, Utilities Design and Construction Division (UDCD) • Brendan Schillo – Construction Manager, UDCD • Eric Lefcort – Right of Way Agent, Land Acquisition Division
  • 4. Hayfield Road Pipe Conveyance System Capital Facilities/Utilities Design and Construction Division/Stormwater Construction Branch Hayfield Road, Alexandria – Tax Map 91-4 & 100-2
  • 5. Hayfield Road Pipe Conveyance System Capital Facilities/Utilities Design and Construction Division/Stormwater Construction Branch Installation of 48-inch Reinforced Concrete Pipe
  • 6. Hayfield Road Pipe Conveyance System Capital Facilities/Utilities Design and Construction Division/Stormwater Construction Branch Installation of 4-foot by 7-foot Box Culvert
  • 7. Hayfield Road Pipe Conveyance System Capital Facilities/Utilities Design and Construction Division/Stormwater Construction Branch Microtunneling Under Telegraph Road
  • 8. Hayfield Road Pipe Conveyance System Capital Facilities/Utilities Design and Construction Division/Stormwater Construction Branch Installation of Storm Sewer Outfall
  • 9. Hayfield Road Pipe Conveyance System Capital Facilities/Utilities Design and Construction Division/Stormwater Construction Branch Replacement of Sidewalks, Curbs/Gutters & Driveway Aprons
  • 10. Hayfield Road Pipe Conveyance System Capital Facilities/Utilities Design and Construction Division/Stormwater Construction Branch Paving of Hayfield Road
  • 11. Before After Hayfield Road Pipe Conveyance System Capital Facilities/Utilities Design and Construction Division/Stormwater Construction Branch
  • 12. Before After Hayfield Road Pipe Conveyance System Capital Facilities/Utilities Design and Construction Division/Stormwater Construction Branch
  • 13. Additional Information For additional Information, please call www.fairfaxcounty.gov/publicworks Hayfield Road Pipe Conveyance System Capital Facilities/Utilities Design and Construction Division/Stormwater Construction Branch Irene Haske, Public Information Officer 703-324-5821, TTY 711 Irene.Haske@fairfaxcounty.gov