P7 : Define and implement future
service delivery model
Update to NVBIA/NAIOP
William Marsh, Land Development Services
November 8, 2018
1. Describe P7’s background
2. Summarize P7 work so far
3. Brief audience on future processes to review and review
methods
2
P7 background includes:
• A mandate to collaborate with industry
to improve permitting processes, begun
in 2017;
• A process of group interactions that
select which processes get reviewed
when: there are over 45 processes that
are classified;
3
P7 background includes:
• An expectation that the pace of this
process review is thorough yet timely;
and
• All permitting processes develop
continuous improvement mechanisms.
4
Completed process reviews include:
• Commercial building plans and permits;
• Rezoning and Proffered condition
amendments;
• Residential Use Permits (RUP);
• Site plan and bond approval.
5
Process changes include the following:
• Commercial building plans and permits: Created web page for fast track process
and display for fast track review time metrics
• Residential Use Permits (RUP): Extended cut-off time for calling in RUPs,
developing SOP for building and site inspectors’ roles.
• Site plan and bond approval: Letter to Industry in development for submitting bond
estimate with first site plan submittal, regular check-ins with ESI.
6
7
Processes
Commercial Building Plan/Permits (Inclusive of Trade
Permits)
Studies (Noise, ESA, EA, etc.) Parking Reduction
New Tenant Layout (Tenant Fit-Out or Improvement) Interpretation (Development, Proffers, Conditions) Special Permit/Amendment (BZA)
Rezoning/PCA Easement Plats/Record Plats Parking Studies (Change in Use)
Major Site Plan Comprehensive Sign Plan/Amendment Final Development Plan/Amendment
Tenant Occupancy (Non-RUP) Waivers (RPA, PFM, Art 17, 101, Ches Bay, etc.) Temporary Special Permit
Concurrent Processing (Zoning/Site) Public Facility Review- 6409 Variance (BZA)/Amendment
Public Facility Review- 2232 Process Traffic Impact Analysis Infill Grading Plan
Bond Approval (inclusive of extension and reduction) Residential Building Plan/Permits (Inclusive of Trades
Permits)
As-Built
Separation Permits Rough Grading Plan Use Determination
Tenant Occupancy (RUP) Modified Processing (Footing and Foundation) Simple Subdivision- Minor Lot Line Adjustment- Final
Subdivision
Board Authorized Plan Amendment Concurrent with a
Rezoning
Phased Occupancy (Core and Shell) Pre-Application Process
Site Specific Plan Amendment (SSPA) Minor Site Plan Setback Certification
Special Exception/SEA Preliminary Subdivision Plat Lot Validation
Application Acceptance Process (Zoning) Bond Release (Letter 18) Conservation Plan
Zoning Ordinance Amendment Subdivision Plan Height Certification
Home Occupation
8
Processes
Commercial Building Plan/Permits (Inclusive of Trade
Permits)
Studies (Noise, ESA, EA, etc.) Parking Reduction
New Tenant Layout (Tenant Fit-Out or Improvement) Interpretation (Development, Proffers, Conditions) Special Permit/Amendment (BZA)
Rezoning/PCA Easement Plats/Record Plats Parking Studies (Change in Use)
Major Site Plan Comprehensive Sign Plan/Amendment Final Development Plan/Amendment
Tenant Occupancy (Non-RUP) Waivers (RPA, PFM, Art 17, 101, Ches Bay, etc.) Temporary Special Permit
Concurrent Processing (Zoning/Site) Public Facility Review- 6409 Variance (BZA)/Amendment
Public Facility Review- 2232 Process Traffic Impact Analysis Infill Grading Plan
Bond Approval (inclusive of extension and reduction) Residential Building Plan/Permits (Inclusive of Trades
Permits)
As-Built
Separation Permits Rough Grading Plan Use Determination
Tenant Occupancy (RUP) Modified Processing (Footing and Foundation) Simple Subdivision- Minor Lot Line Adjustment- Final
Subdivision
Board Authorized Plan Amendment Concurrent with a
Rezoning
Phased Occupancy (Core and Shell) Pre-Application Process
Site Specific Plan Amendment (SSPA) Minor Site Plan Setback Certification
Special Exception/SEA Preliminary Subdivision Plat Lot Validation
Application Acceptance Process (Zoning) Bond Release (Letter 18) Conservation Plan
Zoning Ordinance Amendment Subdivision Plan Height Certification
Home Occupation
9
Processes
Commercial Building Plan/Permits (Inclusive of Trade
Permits)
Studies (Noise, ESA, EA, etc.) Parking Reduction
New Tenant Layout (Tenant Fit-Out or Improvement) Interpretation (Development, Proffers, Conditions) Special Permit/Amendment (BZA)
Rezoning/PCA Easement Plats/Record Plats Parking Studies (Change in Use)
Major Site Plan Comprehensive Sign Plan/Amendment Final Development Plan/Amendment
Tenant Occupancy (Non-RUP) Waivers (RPA, PFM, Art 17, 101, Ches Bay, etc.) Temporary Special Permit
Concurrent Processing (Zoning/Site) Public Facility Review- 6409 Variance (BZA)/Amendment
Public Facility Review- 2232 Process Traffic Impact Analysis Infill Grading Plan
Bond Approval (inclusive of extension and reduction) Residential Building Plan/Permits (Inclusive of Trades
Permits)
As-Built
Separation Permits Rough Grading Plan Use Determination
Tenant Occupancy (RUP) Modified Processing (Footing and Foundation) Simple Subdivision- Minor Lot Line Adjustment- Final
Subdivision
Board Authorized Plan Amendment Concurrent with a
Rezoning
Phased Occupancy (Core and Shell) Pre-Application Process
Site Specific Plan Amendment (SSPA) Minor Site Plan Setback Certification
Special Exception/SEA Preliminary Subdivision Plat Lot Validation
Application Acceptance Process (Zoning) Bond Release (Letter 18) Conservation Plan
Zoning Ordinance Amendment Subdivision Plan Height Certification
Home Occupation
Next steps include:
• Report out to Large stakeholder group about process
changes, November 2018;
• Gain Large group’s endorsement of next processes to review;
• Develop a more streamlined review process with Large
group’s blessing.
10

Contenu connexe

Tendances

BlueScape UPDATE: The South Coast AQMD Moratorium on Permits 06/04/09
BlueScape UPDATE: The South Coast AQMD Moratorium on Permits 06/04/09BlueScape UPDATE: The South Coast AQMD Moratorium on Permits 06/04/09
BlueScape UPDATE: The South Coast AQMD Moratorium on Permits 06/04/09
BlueScape
 
2013 NEFCO ERTAC TANKS
2013 NEFCO ERTAC TANKS2013 NEFCO ERTAC TANKS
2013 NEFCO ERTAC TANKS
Timothy Antos
 

Tendances (20)

Land Subdivisions University Course
Land Subdivisions University CourseLand Subdivisions University Course
Land Subdivisions University Course
 
Substantial completion flatlick branch iii stream restoration
Substantial completion   flatlick branch iii stream restorationSubstantial completion   flatlick branch iii stream restoration
Substantial completion flatlick branch iii stream restoration
 
Fairfax County Zoning Open House July 26, 2017
Fairfax County Zoning Open House July 26, 2017Fairfax County Zoning Open House July 26, 2017
Fairfax County Zoning Open House July 26, 2017
 
BlueScape UPDATE: The South Coast AQMD Moratorium on Permits 06/04/09
BlueScape UPDATE: The South Coast AQMD Moratorium on Permits 06/04/09BlueScape UPDATE: The South Coast AQMD Moratorium on Permits 06/04/09
BlueScape UPDATE: The South Coast AQMD Moratorium on Permits 06/04/09
 
Storm Pipe Rehabilitation at Cider Barrel Circle and Orr Drive
Storm Pipe Rehabilitation at Cider Barrel Circle and Orr DriveStorm Pipe Rehabilitation at Cider Barrel Circle and Orr Drive
Storm Pipe Rehabilitation at Cider Barrel Circle and Orr Drive
 
Lee Chapel Rd. Walkway Burke Lake Rd. to Britford Dr. July 2020
Lee Chapel Rd. Walkway Burke Lake Rd. to Britford Dr. July 2020Lee Chapel Rd. Walkway Burke Lake Rd. to Britford Dr. July 2020
Lee Chapel Rd. Walkway Burke Lake Rd. to Britford Dr. July 2020
 
Alberta Transportation's First Design-Build (DB) Project - Stony Plain Road I...
Alberta Transportation's First Design-Build (DB) Project - Stony Plain Road I...Alberta Transportation's First Design-Build (DB) Project - Stony Plain Road I...
Alberta Transportation's First Design-Build (DB) Project - Stony Plain Road I...
 
Crosspointe Pond Retrofit 2014
Crosspointe Pond Retrofit 2014Crosspointe Pond Retrofit 2014
Crosspointe Pond Retrofit 2014
 
Long Branch Tributary at Long Branch Falls Park Public Meeting 1-20-2016
Long Branch Tributary at Long Branch Falls Park Public Meeting 1-20-2016Long Branch Tributary at Long Branch Falls Park Public Meeting 1-20-2016
Long Branch Tributary at Long Branch Falls Park Public Meeting 1-20-2016
 
2013 NEFCO ERTAC TANKS
2013 NEFCO ERTAC TANKS2013 NEFCO ERTAC TANKS
2013 NEFCO ERTAC TANKS
 
Northpoint Crossing Rezoning
Northpoint Crossing RezoningNorthpoint Crossing Rezoning
Northpoint Crossing Rezoning
 
Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...
Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...
Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...
 
Indian Run Restoration Project
Indian Run Restoration ProjectIndian Run Restoration Project
Indian Run Restoration Project
 
zMOD: Proposed Restaurant Amendment
zMOD: Proposed Restaurant AmendmentzMOD: Proposed Restaurant Amendment
zMOD: Proposed Restaurant Amendment
 
High Ridge Lakevale Estates Langley Oaks and Weid Pump Stations Project
  High Ridge Lakevale Estates Langley Oaks and Weid Pump Stations Project  High Ridge Lakevale Estates Langley Oaks and Weid Pump Stations Project
High Ridge Lakevale Estates Langley Oaks and Weid Pump Stations Project
 
SOME OF THE PROJECTS HANDLED
SOME OF THE PROJECTS HANDLEDSOME OF THE PROJECTS HANDLED
SOME OF THE PROJECTS HANDLED
 
Oct 13 rosehill reservoir_preliminary_overview_
Oct 13 rosehill reservoir_preliminary_overview_Oct 13 rosehill reservoir_preliminary_overview_
Oct 13 rosehill reservoir_preliminary_overview_
 
Engineering Services RFP - PEC VDOT Rappahannock Fish-Passage Pilot Project -...
Engineering Services RFP - PEC VDOT Rappahannock Fish-Passage Pilot Project -...Engineering Services RFP - PEC VDOT Rappahannock Fish-Passage Pilot Project -...
Engineering Services RFP - PEC VDOT Rappahannock Fish-Passage Pilot Project -...
 
Rosehill Vision Committee May 31 2017 Meeting Presentation
Rosehill Vision Committee May 31 2017 Meeting PresentationRosehill Vision Committee May 31 2017 Meeting Presentation
Rosehill Vision Committee May 31 2017 Meeting Presentation
 
Thomas Pool Options
Thomas Pool OptionsThomas Pool Options
Thomas Pool Options
 

Similaire à P7: Define and Implement Future Service Delivery Model - Update to NVBIA/NAIOP

3 swpp ps for const sites tonning ksa apr 2010
3 swpp ps for const sites   tonning ksa apr 20103 swpp ps for const sites   tonning ksa apr 2010
3 swpp ps for const sites tonning ksa apr 2010
guest7dbf4
 
GregPhilpott__CV_ProcLeader
GregPhilpott__CV_ProcLeaderGregPhilpott__CV_ProcLeader
GregPhilpott__CV_ProcLeader
Greg Philpott
 
Visio-Planning FlowChart-3
Visio-Planning FlowChart-3Visio-Planning FlowChart-3
Visio-Planning FlowChart-3
Allan Leyte
 
Rajgir Sports Complex_Project Kick Off Presentation.pptx
Rajgir Sports Complex_Project Kick Off Presentation.pptxRajgir Sports Complex_Project Kick Off Presentation.pptx
Rajgir Sports Complex_Project Kick Off Presentation.pptx
syedaliabl2023
 
Project Management Services
Project Management ServicesProject Management Services
Project Management Services
Bruce Tharp
 
Attachement 3 61T01411 - Construction Execution Plan
Attachement 3 61T01411 - Construction Execution PlanAttachement 3 61T01411 - Construction Execution Plan
Attachement 3 61T01411 - Construction Execution Plan
James Zhang (Chi, Zhang)
 

Similaire à P7: Define and Implement Future Service Delivery Model - Update to NVBIA/NAIOP (20)

Springfield, MA City Council
Springfield, MA  City CouncilSpringfield, MA  City Council
Springfield, MA City Council
 
Approval Process Summary for Major Subdivisions and Planned Developments
Approval Process Summary for Major Subdivisions and Planned DevelopmentsApproval Process Summary for Major Subdivisions and Planned Developments
Approval Process Summary for Major Subdivisions and Planned Developments
 
District Standards
District StandardsDistrict Standards
District Standards
 
Public sector planning club, January 2017
Public sector planning club, January 2017Public sector planning club, January 2017
Public sector planning club, January 2017
 
3 swpp ps for const sites tonning ksa apr 2010
3 swpp ps for const sites   tonning ksa apr 20103 swpp ps for const sites   tonning ksa apr 2010
3 swpp ps for const sites tonning ksa apr 2010
 
zMOD: Proposed Minor Modification Amendment
zMOD: Proposed Minor Modification AmendmentzMOD: Proposed Minor Modification Amendment
zMOD: Proposed Minor Modification Amendment
 
Railroad Commission of Texas - Regulations for Geologic Storage of Carbon Dio...
Railroad Commission of Texas - Regulations for Geologic Storage of Carbon Dio...Railroad Commission of Texas - Regulations for Geologic Storage of Carbon Dio...
Railroad Commission of Texas - Regulations for Geologic Storage of Carbon Dio...
 
111009 102 N. Federal Highway
111009 102 N. Federal Highway111009 102 N. Federal Highway
111009 102 N. Federal Highway
 
Malaysian Property Development
Malaysian Property DevelopmentMalaysian Property Development
Malaysian Property Development
 
GregPhilpott__CV_ProcLeader
GregPhilpott__CV_ProcLeaderGregPhilpott__CV_ProcLeader
GregPhilpott__CV_ProcLeader
 
Visio-Planning FlowChart-3
Visio-Planning FlowChart-3Visio-Planning FlowChart-3
Visio-Planning FlowChart-3
 
Rajgir Sports Complex_Project Kick Off Presentation.pptx
Rajgir Sports Complex_Project Kick Off Presentation.pptxRajgir Sports Complex_Project Kick Off Presentation.pptx
Rajgir Sports Complex_Project Kick Off Presentation.pptx
 
KJGResume2015
KJGResume2015KJGResume2015
KJGResume2015
 
CPTC Site Plan Review module 8.23.2015
CPTC Site Plan Review module 8.23.2015CPTC Site Plan Review module 8.23.2015
CPTC Site Plan Review module 8.23.2015
 
Blake Lapthorn's Rural Breakfast Slides 2014
Blake Lapthorn's Rural Breakfast Slides 2014Blake Lapthorn's Rural Breakfast Slides 2014
Blake Lapthorn's Rural Breakfast Slides 2014
 
Project Management Services
Project Management ServicesProject Management Services
Project Management Services
 
EWSO
EWSOEWSO
EWSO
 
Helping practitioners understand changes to Exempt and Complying Development
Helping practitioners understand changes to Exempt and Complying DevelopmentHelping practitioners understand changes to Exempt and Complying Development
Helping practitioners understand changes to Exempt and Complying Development
 
Attachement 3 61T01411 - Construction Execution Plan
Attachement 3 61T01411 - Construction Execution PlanAttachement 3 61T01411 - Construction Execution Plan
Attachement 3 61T01411 - Construction Execution Plan
 
Item # 13 - PPT Plan Review Process Revisions
Item # 13 - PPT Plan Review Process RevisionsItem # 13 - PPT Plan Review Process Revisions
Item # 13 - PPT Plan Review Process Revisions
 

Plus de Fairfax County

Plus de Fairfax County (20)

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer Replacement
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction Progress
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IV
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick Offpptx
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing Council
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap Up
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction Project
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual Arts
 

Dernier

{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
hyt3577
 
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost LoverPowerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
PsychicRuben LoveSpells
 

Dernier (20)

Kishan Reddy Report To People (2019-24).pdf
Kishan Reddy Report To People (2019-24).pdfKishan Reddy Report To People (2019-24).pdf
Kishan Reddy Report To People (2019-24).pdf
 
BDSM⚡Call Girls in Sector 135 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 135 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 135 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 135 Noida Escorts >༒8448380779 Escort Service
 
BDSM⚡Call Girls in Sector 143 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 143 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 143 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 143 Noida Escorts >༒8448380779 Escort Service
 
Embed-2 (1).pdfb[k[k[[k[kkkpkdpokkdpkopko
Embed-2 (1).pdfb[k[k[[k[kkkpkdpokkdpkopkoEmbed-2 (1).pdfb[k[k[[k[kkkpkdpokkdpkopko
Embed-2 (1).pdfb[k[k[[k[kkkpkdpokkdpkopko
 
Verified Love Spells in Little Rock, AR (310) 882-6330 Get My Ex-Lover Back
Verified Love Spells in Little Rock, AR (310) 882-6330 Get My Ex-Lover BackVerified Love Spells in Little Rock, AR (310) 882-6330 Get My Ex-Lover Back
Verified Love Spells in Little Rock, AR (310) 882-6330 Get My Ex-Lover Back
 
AI as Research Assistant: Upscaling Content Analysis to Identify Patterns of ...
AI as Research Assistant: Upscaling Content Analysis to Identify Patterns of ...AI as Research Assistant: Upscaling Content Analysis to Identify Patterns of ...
AI as Research Assistant: Upscaling Content Analysis to Identify Patterns of ...
 
China's soft power in 21st century .pptx
China's soft power in 21st century   .pptxChina's soft power in 21st century   .pptx
China's soft power in 21st century .pptx
 
BDSM⚡Call Girls in Greater Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Greater Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Greater Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Greater Noida Escorts >༒8448380779 Escort Service
 
05052024_First India Newspaper Jaipur.pdf
05052024_First India Newspaper Jaipur.pdf05052024_First India Newspaper Jaipur.pdf
05052024_First India Newspaper Jaipur.pdf
 
Embed-4.pdf lkdiinlajeklhndklheduhuekjdh
Embed-4.pdf lkdiinlajeklhndklheduhuekjdhEmbed-4.pdf lkdiinlajeklhndklheduhuekjdh
Embed-4.pdf lkdiinlajeklhndklheduhuekjdh
 
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 48 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 48 (Gurgaon)Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 48 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 48 (Gurgaon)
 
Group_5_US-China Trade War to understand the trade
Group_5_US-China Trade War to understand the tradeGroup_5_US-China Trade War to understand the trade
Group_5_US-China Trade War to understand the trade
 
declarationleaders_sd_re_greens_theleft_5.pdf
declarationleaders_sd_re_greens_theleft_5.pdfdeclarationleaders_sd_re_greens_theleft_5.pdf
declarationleaders_sd_re_greens_theleft_5.pdf
 
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 47 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 47 (Gurgaon)Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 47 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 47 (Gurgaon)
 
Nara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's Development
Nara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's DevelopmentNara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's Development
Nara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's Development
 
Julius Randle's Injury Status: Surgery Not Off the Table
Julius Randle's Injury Status: Surgery Not Off the TableJulius Randle's Injury Status: Surgery Not Off the Table
Julius Randle's Injury Status: Surgery Not Off the Table
 
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
 
Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...
Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...
Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...
 
WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)
WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)
WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)
 
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost LoverPowerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
 

P7: Define and Implement Future Service Delivery Model - Update to NVBIA/NAIOP

  • 1. P7 : Define and implement future service delivery model Update to NVBIA/NAIOP William Marsh, Land Development Services November 8, 2018
  • 2. 1. Describe P7’s background 2. Summarize P7 work so far 3. Brief audience on future processes to review and review methods 2
  • 3. P7 background includes: • A mandate to collaborate with industry to improve permitting processes, begun in 2017; • A process of group interactions that select which processes get reviewed when: there are over 45 processes that are classified; 3
  • 4. P7 background includes: • An expectation that the pace of this process review is thorough yet timely; and • All permitting processes develop continuous improvement mechanisms. 4
  • 5. Completed process reviews include: • Commercial building plans and permits; • Rezoning and Proffered condition amendments; • Residential Use Permits (RUP); • Site plan and bond approval. 5
  • 6. Process changes include the following: • Commercial building plans and permits: Created web page for fast track process and display for fast track review time metrics • Residential Use Permits (RUP): Extended cut-off time for calling in RUPs, developing SOP for building and site inspectors’ roles. • Site plan and bond approval: Letter to Industry in development for submitting bond estimate with first site plan submittal, regular check-ins with ESI. 6
  • 7. 7 Processes Commercial Building Plan/Permits (Inclusive of Trade Permits) Studies (Noise, ESA, EA, etc.) Parking Reduction New Tenant Layout (Tenant Fit-Out or Improvement) Interpretation (Development, Proffers, Conditions) Special Permit/Amendment (BZA) Rezoning/PCA Easement Plats/Record Plats Parking Studies (Change in Use) Major Site Plan Comprehensive Sign Plan/Amendment Final Development Plan/Amendment Tenant Occupancy (Non-RUP) Waivers (RPA, PFM, Art 17, 101, Ches Bay, etc.) Temporary Special Permit Concurrent Processing (Zoning/Site) Public Facility Review- 6409 Variance (BZA)/Amendment Public Facility Review- 2232 Process Traffic Impact Analysis Infill Grading Plan Bond Approval (inclusive of extension and reduction) Residential Building Plan/Permits (Inclusive of Trades Permits) As-Built Separation Permits Rough Grading Plan Use Determination Tenant Occupancy (RUP) Modified Processing (Footing and Foundation) Simple Subdivision- Minor Lot Line Adjustment- Final Subdivision Board Authorized Plan Amendment Concurrent with a Rezoning Phased Occupancy (Core and Shell) Pre-Application Process Site Specific Plan Amendment (SSPA) Minor Site Plan Setback Certification Special Exception/SEA Preliminary Subdivision Plat Lot Validation Application Acceptance Process (Zoning) Bond Release (Letter 18) Conservation Plan Zoning Ordinance Amendment Subdivision Plan Height Certification Home Occupation
  • 8. 8 Processes Commercial Building Plan/Permits (Inclusive of Trade Permits) Studies (Noise, ESA, EA, etc.) Parking Reduction New Tenant Layout (Tenant Fit-Out or Improvement) Interpretation (Development, Proffers, Conditions) Special Permit/Amendment (BZA) Rezoning/PCA Easement Plats/Record Plats Parking Studies (Change in Use) Major Site Plan Comprehensive Sign Plan/Amendment Final Development Plan/Amendment Tenant Occupancy (Non-RUP) Waivers (RPA, PFM, Art 17, 101, Ches Bay, etc.) Temporary Special Permit Concurrent Processing (Zoning/Site) Public Facility Review- 6409 Variance (BZA)/Amendment Public Facility Review- 2232 Process Traffic Impact Analysis Infill Grading Plan Bond Approval (inclusive of extension and reduction) Residential Building Plan/Permits (Inclusive of Trades Permits) As-Built Separation Permits Rough Grading Plan Use Determination Tenant Occupancy (RUP) Modified Processing (Footing and Foundation) Simple Subdivision- Minor Lot Line Adjustment- Final Subdivision Board Authorized Plan Amendment Concurrent with a Rezoning Phased Occupancy (Core and Shell) Pre-Application Process Site Specific Plan Amendment (SSPA) Minor Site Plan Setback Certification Special Exception/SEA Preliminary Subdivision Plat Lot Validation Application Acceptance Process (Zoning) Bond Release (Letter 18) Conservation Plan Zoning Ordinance Amendment Subdivision Plan Height Certification Home Occupation
  • 9. 9 Processes Commercial Building Plan/Permits (Inclusive of Trade Permits) Studies (Noise, ESA, EA, etc.) Parking Reduction New Tenant Layout (Tenant Fit-Out or Improvement) Interpretation (Development, Proffers, Conditions) Special Permit/Amendment (BZA) Rezoning/PCA Easement Plats/Record Plats Parking Studies (Change in Use) Major Site Plan Comprehensive Sign Plan/Amendment Final Development Plan/Amendment Tenant Occupancy (Non-RUP) Waivers (RPA, PFM, Art 17, 101, Ches Bay, etc.) Temporary Special Permit Concurrent Processing (Zoning/Site) Public Facility Review- 6409 Variance (BZA)/Amendment Public Facility Review- 2232 Process Traffic Impact Analysis Infill Grading Plan Bond Approval (inclusive of extension and reduction) Residential Building Plan/Permits (Inclusive of Trades Permits) As-Built Separation Permits Rough Grading Plan Use Determination Tenant Occupancy (RUP) Modified Processing (Footing and Foundation) Simple Subdivision- Minor Lot Line Adjustment- Final Subdivision Board Authorized Plan Amendment Concurrent with a Rezoning Phased Occupancy (Core and Shell) Pre-Application Process Site Specific Plan Amendment (SSPA) Minor Site Plan Setback Certification Special Exception/SEA Preliminary Subdivision Plat Lot Validation Application Acceptance Process (Zoning) Bond Release (Letter 18) Conservation Plan Zoning Ordinance Amendment Subdivision Plan Height Certification Home Occupation
  • 10. Next steps include: • Report out to Large stakeholder group about process changes, November 2018; • Gain Large group’s endorsement of next processes to review; • Develop a more streamlined review process with Large group’s blessing. 10

Notes de l'éditeur

  1. Relevant web page for fast track is https://www.fairfaxcounty.gov/landdevelopment/fast-track-plan-review Web page for performance metrics that includes fast track is: https://www.fairfaxcounty.gov/landdevelopment/development-review-metrics