The scope of this project included the construction of approximately 1,500 linear feet of six-foot wide concrete sidewalk, curb and gutter, pedestrian curb ramp, pavement mill and overlay, pavement markings and signage, storm drainage improvements and pedestrian signal installations.
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
Route 50 Sidewalk from Annandale Road to Cherry Street
1. A Fairfax County, VA, publication
Department of Public Works and Environmental Services
Working for You!
Route 50 Sidewalk from Annandale Road to Cherry
Street
Project No. 1400059-2012
Contract No. CN17102044
VDOT UPC No. 108501
Providence District
July 30, 2019
2. Route 50 from Annandale Road to Cherry Street
Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
3. Project Details
Route 50 Sidewalk from Annandale Road to Cherry Street
Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
Description:
The Route 50 sidewalk from Annandale Road to Cherry Street project was substantially completed
on June 13, 2019. The scope of this project was the construction of approximately 1500 LF of 6-foot
wide concrete sidewalk, curb & gutter, pedestrian curb ramp, pavement mill and overlay, pavement
markings and signage, storm drainage improvements and pedestrian signal installations.
Project Team:
Project Manager, FCDOT – Mohammod El Kaissi
Project Engineer, UDCD – Fasika Metafria
Project Inspector, RK&K – Rick L. Richardson and Abdallah Saad
Land Survey Branch, UDCD – Christopher J. Jensen
4. Route 50 Sidewalk from Annandale Road to Cherry Street
Providence District , Tax Map 50-4
Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
Project Location
ANNANDALE ROAD TO CHERRY STREET
PROJECT SITE
5. Route 50 Sidewalk from Annandale Road to Cherry Street
Installation of Storm Drainage Improvements
Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
6. Route 50 Sidewalk from Annandale Road to Cherry Street
Installation of the Concrete Sidewalk
Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
7. Route 50 Sidewalk from Annandale Road to Cherry Street
Installation of Concrete Curb Ramp and Sidewalk
Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
8. Route 50 Sidewalk from Annandale Road to Cherry Street
Installation of Pedestrian Signal Improvement
Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
9. Route 50 Sidewalk from Annandale Road to Cherry Street
Installation of Pedestrian Crosswalk
Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
10. Before After
Route 50 Sidewalk from Annandale Road to Cherry Street
Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
11. Additional Information
For additional Information, please call
www.fairfaxcounty.gov/publicworks
Route 50 Sidewalk from Annandale Road to Cherry Street
Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
Matthew Kaiser, Public Information Officer
703-324-8455, TTY 711
Matthew.kaiser@fairfaxcounty.gov