The project included approximate 325 linear feet of concrete sidewalk, pedestrian ramp, curb and gutter, reconstructed entrances, pavement markings and signing, drainage structures, and water service adjustments.
Top Rated Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...
Route 50 Sidewalk Project in Fairfax County
1. A Fairfax County, VA, publication
Department of Public Works and Environmental Services
Working for You!
ROUTE 50 SIDEWALK FROM PATRICK HENRY
DRIVE TO OLIN DRIVE
Contract No. CN17102047
Project No. AA1400062-2012
Mason District
November 16, 2018
2. Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
Route 50 Sidewalk from Patrick Henry Drive to
Olin Drive
3. N
Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
Route 50 Sidewalk from Patrick Henry Drive to Olin Drive
Mason District, Tax Map 51-4
4. Project Details
Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
Description:
The Route 50 Sidewalk from Patrick Henry Drive to Olin Drive project was substantially complete on
October 10, 2018. The project included approximate 325 LF of Concrete sidewalk, pedestrian ramp, curb &
gutter, reconstructed entrances, pavement markings & signing, drainage structures, and water service
adjustments.
Project Overview:
• Project Delivery: Design-Bid-Build
• Contract: Unit Price Contract
Project Team:
• Contractor : Arthur Construction Co. Inc
• Fairfax County
• Department of Transportation – Seyed Navabi
• Utilities Design and Construction Division - Sanjala Bajracharya
• Maintenance & Stormwater Management Division - Karlee H. Copeland
• Land Survey Branch, UDCD – Bryan Wilson
Route 50 Sidewalk from Patrick Henry Drive to Olin Drive
5. Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
Installation of Storm Drainage
Route 50 Sidewalk from Patrick Henry Drive to Olin Drive
6. Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
Route 50 Sidewalk from Patrick Henry Drive to Olin Drive
Installation of Concrete Sidewalk
7. Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
Installation of Concrete Entrance Apron
Route 50 Sidewalk from Patrick Henry Drive to Olin Drive
8. Installation of Pavement Markings
Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
Route 50 Sidewalk from Patrick Henry Drive to Olin Drive
9. Before After
Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
Route 50 Sidewalk from Patrick Henry Drive to
Olin Drive
10. Before After
Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
Route 50 Sidewalk from Patrick Henry Drive to
Olin Drive
11. Additional Information
For additional Information, please call
www.fairfaxcounty.gov/publicworks
Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
Matthew Kaiser, Public Information Officer
703-324-8455, TTY 711
Matthew.kaiser@fairfaxcounty.gov
Route 50 Sidewalk from Patrick Henry Drive to Olin Drive