SlideShare une entreprise Scribd logo
1  sur  36
Télécharger pour lire hors ligne
 Dredging Program and Project Background
 Project Benefits
 Royal Lake Conditions
 Phased Approach
 Dredging Methods and Alternatives
 Park Access and Community Coordination
 Next Steps
Royal Lake: Meeting Agenda
 History
– Lakes previously dredged by DPWES Stormwater
– Limited to small quantities
– Dewatered on site
 Lake Barton completed in 2011
 Currently working on:
– Huntsman Lake, Woodglen Lake, Royal Lake
Dredging and Lake Restoration Program
 Completed Data Collection
 Developing Lake Dredging and Management Plan
 Community coordination at design and construction
phases
– Preliminary Design (65%)
– Final Design (95%)
– Preconstruction: Pardon Our Dust meeting
 December 2013: Final Design
 Construction in Fiscal Year 2015 (July 2014)
Royal Lake Dredging and Restoration
Project Timeline and Coordination
 Restore sediment pool capacity
– Downstream water quality benefits
– Lake water quality
– Aesthetics
 Improve lake water quality and habitat
 Provide long term maintenance improvements
Project Goals and Benefit
Lake Barton Dredging and Restoration
Area Treated
(acres)
Phosphorous Removal Nitrogen Removal Sediment Removal
544 77,000 lbs dredged 115,500 lbs dredged 38,500 tons dredged
Annual benefit from
increased trapping
efficiency
130 lbs/year 200 lbs/year 65 tons/year
Royal Lake Facts
 Drainage area =
2,477 acres (3.67 square miles)
 Lake surface area =
37.5 acres
 Sediment pool capacity =
416,000 cubic yards (CY)
 Current sediment in lake =
100,400 CY
 Estimated annual sediment load =
4,400 CY
50 feet
100,400 CY
Royal Lake
Royal Lake: Sediment Thickness
Royal Lake: Water Depth
Royal Lake: Dredging Areas
 Phase 1: Base Dredge = 40,000 CY
 Phase 2: Up to an additional 60,000 CY
Zone D
12,400 CY
Royal Lake: Partial Drawdown
Dredging Methods and Alternatives
1. Mechanically dredge
deposited sediment and
haul wet
2. Drain lake and dry
deposited sediment in
place before hauling
PRE-DREDGING:
An estimated
35,000 cubic yards
of sediment had
accumulated in
the lake, forming
islands and
reducing water
levels to less than
three feet in most
areas.
Lake Barton Example
Lake Barton Example: Pre-Dredging
LakeBartonExample: DredginginProgress
Dredging:
Dredging took
place without
draining the lake.
LakeBartonExample: DredginginProgress
Lake Barton Example: Disposal Site
North Park Lake Example Allegheny County, Pennsylvania
Dredging:
The lake was drained
and the sediment was
dried in-place.
North Park Lake Example Allegheny County, Pennsylvania
Temporary Diversion
Channels
Equipment Working
on Next Slide
North Park Lake: Dredging Allegheny County, Pennsylvania
Truck Wash
Temporary
Diversion Channel
Low Pressure
Excavator
Bulldozer
Bulldozer
Excavator
and DozerTruck Access
Staging
 General Sequence
– Establish access and staging areas
– Conduct dredging utilizing barges
– Haul wet sediment to disposal site
for drying
 Benefits
– Less weather dependent
– Quicker initial start to dredging
– Less potential for schedule
extensions or delay
 Concerns
– Increased sediment handling effort
at disposal area
– Potentially higher cost
Dredge Alternative – In the Wet
 General Sequence
– Initiate drawdown of lake
– Establish access and staging areas
– Establish diversion channels within lake
– Conduct dredging
 Benefits
– Higher daily sediment removal rates
– Minimal sediment handling effort at disposal
area
– Potentially lower cost
 Concerns
– Very weather dependent
– Higher potential for delays due to weather
– Typically more odor from sediment exposed
– Need to relocate/salvage fish
Dredge Alternative – In the Dry
 In-lake forebay
 Wetland planting
 Shoreline stabilization
 Fish habitat
 Fish stocking
Lake Restoration
Fish habitat created
from salvaged trees
Lake Barton:
Fish stocking by Virginia Game and Inland Fisheries
Royal Lake: Shoreline Restoration
Royal Lake: Shoreline Restoration
Royal Lake
Existing
Conditions
Shoreline Protection Options
Fish Habitat Structures
Royal Lake: Site Access and Staging
Optional?
Royal Lake: Site Access and Staging
Staging Area 1 Potential Expansion
Berm/Cofferdam
to be built
Area to be dewatered and
backfilled to expand staging
area after berm/cofferdam
is built
Royal Lake: Dewatering Basin
Inactive
Dewatering Basin
Access During Construction
Public Access:
The park will remain
open and existing
parking lot will be
available.
Access During Construction
Public Access:
Pedestrian gates will be
provided. Access
through work areas and
trails around the lake
after work hours.
 Community coordination at design and construction phases
– Preliminary Design (65%)
– Final Design (95%)
– Preconstruction: “Pardon Our Dust” meeting
 December 2013: Final Design
 Construction in Fiscal Year 2015 (Starts July 2014)
 Project Duration:
– Phase 1, Base Dredge: Dredge 40,000 CY = 5 to 6 Months
– Phase 2, Full Dredge: 9 to 12 Months
Royal Lake Dredging and Restoration
Project Timeline and Coordination
Contacts:
 Martin Chang, Project Manager
703-324-5825 | Martin.Chang@fairfaxcounty.gov
 Dipmani Kumar, Section Chief
703-324-4612 | Dipmani.Kumar@fairfaxcounty.gov
 http://www.fairfaxcounty.gov/dpwes/stormwater/
Royal Lake DredgingandRestoration
http://www.fairfaxcounty.gov/NVSWCD/ http://www.fairfaxcounty.gov/parks/

Contenu connexe

Tendances

approaches to curriculum
approaches to curriculumapproaches to curriculum
approaches to curriculumjeniferdivya
 
10. self instructional module.pptx
10. self instructional module.pptx10. self instructional module.pptx
10. self instructional module.pptxpurvipatel517209
 
Curriculum implementation moosa assignment
Curriculum implementation moosa assignmentCurriculum implementation moosa assignment
Curriculum implementation moosa assignmentMohammad Moosa
 
Teacher educators competencies
Teacher educators competenciesTeacher educators competencies
Teacher educators competenciesQurratulainMUST
 
Methods of teaching
Methods of teaching Methods of teaching
Methods of teaching REMYAcommerce
 
Knowledge base of teacher Education from view point of T.S. Schulman
Knowledge base of teacher Education from view point of T.S. SchulmanKnowledge base of teacher Education from view point of T.S. Schulman
Knowledge base of teacher Education from view point of T.S. SchulmanRavi Mishra
 
Stuti microteaching
Stuti microteachingStuti microteaching
Stuti microteachingStutiSingh49
 
Continuous Assessment
Continuous AssessmentContinuous Assessment
Continuous AssessmentManuel Reyes
 
Innovative teaching - learning practices at school level
Innovative teaching - learning practices at school levelInnovative teaching - learning practices at school level
Innovative teaching - learning practices at school levelMadhu Singh
 
Assessment and learning
Assessment and learningAssessment and learning
Assessment and learningSarat Rout
 
Ict integration in science
Ict integration in scienceIct integration in science
Ict integration in sciencesuchetanapawar
 
Science education for students with special education needs
Science education for students with special education needsScience education for students with special education needs
Science education for students with special education needsThomasantony93
 
Instructional strategies
Instructional strategiesInstructional strategies
Instructional strategiesAntwuan Stinson
 
Notes on evaluation part iii
Notes on evaluation part   iiiNotes on evaluation part   iii
Notes on evaluation part iiiBabitha Devu
 
Obstacles in curriculum development, different barriers in curriculum develop...
Obstacles in curriculum development, different barriers in curriculum develop...Obstacles in curriculum development, different barriers in curriculum develop...
Obstacles in curriculum development, different barriers in curriculum develop...Bhaskar Reddy
 
Week 9 instructional objectives
Week 9 instructional objectivesWeek 9 instructional objectives
Week 9 instructional objectivesNoor Syamila
 
Management , maintenance and inspection of science laboratory
Management , maintenance and inspection of science laboratoryManagement , maintenance and inspection of science laboratory
Management , maintenance and inspection of science laboratoryZahoor Ahmad
 

Tendances (20)

approaches to curriculum
approaches to curriculumapproaches to curriculum
approaches to curriculum
 
10. self instructional module.pptx
10. self instructional module.pptx10. self instructional module.pptx
10. self instructional module.pptx
 
Curriculum implementation moosa assignment
Curriculum implementation moosa assignmentCurriculum implementation moosa assignment
Curriculum implementation moosa assignment
 
Teacher educators competencies
Teacher educators competenciesTeacher educators competencies
Teacher educators competencies
 
Methods of teaching
Methods of teaching Methods of teaching
Methods of teaching
 
Knowledge base of teacher Education from view point of T.S. Schulman
Knowledge base of teacher Education from view point of T.S. SchulmanKnowledge base of teacher Education from view point of T.S. Schulman
Knowledge base of teacher Education from view point of T.S. Schulman
 
Stuti microteaching
Stuti microteachingStuti microteaching
Stuti microteaching
 
Action research
Action researchAction research
Action research
 
Principles of teaching
Principles of teachingPrinciples of teaching
Principles of teaching
 
Continuous Assessment
Continuous AssessmentContinuous Assessment
Continuous Assessment
 
Innovative teaching - learning practices at school level
Innovative teaching - learning practices at school levelInnovative teaching - learning practices at school level
Innovative teaching - learning practices at school level
 
Assessment and learning
Assessment and learningAssessment and learning
Assessment and learning
 
Teaching skills
Teaching skillsTeaching skills
Teaching skills
 
Ict integration in science
Ict integration in scienceIct integration in science
Ict integration in science
 
Science education for students with special education needs
Science education for students with special education needsScience education for students with special education needs
Science education for students with special education needs
 
Instructional strategies
Instructional strategiesInstructional strategies
Instructional strategies
 
Notes on evaluation part iii
Notes on evaluation part   iiiNotes on evaluation part   iii
Notes on evaluation part iii
 
Obstacles in curriculum development, different barriers in curriculum develop...
Obstacles in curriculum development, different barriers in curriculum develop...Obstacles in curriculum development, different barriers in curriculum develop...
Obstacles in curriculum development, different barriers in curriculum develop...
 
Week 9 instructional objectives
Week 9 instructional objectivesWeek 9 instructional objectives
Week 9 instructional objectives
 
Management , maintenance and inspection of science laboratory
Management , maintenance and inspection of science laboratoryManagement , maintenance and inspection of science laboratory
Management , maintenance and inspection of science laboratory
 

Similaire à Royal Lake Dredging and Restoration

Royal Lake Dredging and Restoration Project Update-June 2014
Royal Lake Dredging and Restoration Project Update-June 2014Royal Lake Dredging and Restoration Project Update-June 2014
Royal Lake Dredging and Restoration Project Update-June 2014Fairfax County
 
Woodglen Lake Dredging and Restoration
Woodglen Lake Dredging and RestorationWoodglen Lake Dredging and Restoration
Woodglen Lake Dredging and RestorationFairfax County
 
Woodglen Lake Dredging and Restoration
Woodglen Lake Dredging and Restoration Woodglen Lake Dredging and Restoration
Woodglen Lake Dredging and Restoration Fairfax County
 
Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016
Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016
Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016Fairfax County
 
Huntsman Lake Dam Rehabilitation Project
Huntsman Lake Dam Rehabilitation ProjectHuntsman Lake Dam Rehabilitation Project
Huntsman Lake Dam Rehabilitation ProjectFairfax County
 
Flood and drought mitigation - Matt Machielse
Flood and drought mitigation - Matt MachielseFlood and drought mitigation - Matt Machielse
Flood and drought mitigation - Matt MachielseYourAlberta
 
Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration
Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake RestorationPohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration
Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake RestorationFairfax County
 
Huntsman Lake Dredging January 2015
Huntsman Lake Dredging January 2015Huntsman Lake Dredging January 2015
Huntsman Lake Dredging January 2015Fairfax County
 
Feb 11 2014 public meeting
Feb 11 2014 public meetingFeb 11 2014 public meeting
Feb 11 2014 public meetingMCDEP
 
Huntsman Lake “Pardon Our Dust”
Huntsman Lake “Pardon Our Dust” Huntsman Lake “Pardon Our Dust”
Huntsman Lake “Pardon Our Dust” Fairfax County
 
Woodglen Lake Dredging and Restoration
Woodglen Lake Dredging and RestorationWoodglen Lake Dredging and Restoration
Woodglen Lake Dredging and RestorationFairfax County
 
Steelhead Haven
Steelhead HavenSteelhead Haven
Steelhead HavenSWCNabi
 
Rury 206PM Room B_Integr Hab Restor & Stormwater Treat
Rury 206PM Room B_Integr Hab Restor & Stormwater TreatRury 206PM Room B_Integr Hab Restor & Stormwater Treat
Rury 206PM Room B_Integr Hab Restor & Stormwater TreatPhillip Rury
 

Similaire à Royal Lake Dredging and Restoration (20)

Royal Lake Dredging and Restoration Project Update-June 2014
Royal Lake Dredging and Restoration Project Update-June 2014Royal Lake Dredging and Restoration Project Update-June 2014
Royal Lake Dredging and Restoration Project Update-June 2014
 
Woodglen Lake Dredging and Restoration
Woodglen Lake Dredging and RestorationWoodglen Lake Dredging and Restoration
Woodglen Lake Dredging and Restoration
 
Woodglen Lake Dredging and Restoration
Woodglen Lake Dredging and Restoration Woodglen Lake Dredging and Restoration
Woodglen Lake Dredging and Restoration
 
Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016
Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016
Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016
 
Huntsman Lake Dam Rehabilitation Project
Huntsman Lake Dam Rehabilitation ProjectHuntsman Lake Dam Rehabilitation Project
Huntsman Lake Dam Rehabilitation Project
 
Flood and drought mitigation - Matt Machielse
Flood and drought mitigation - Matt MachielseFlood and drought mitigation - Matt Machielse
Flood and drought mitigation - Matt Machielse
 
Truckee River Restoration
Truckee River RestorationTruckee River Restoration
Truckee River Restoration
 
Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration
Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake RestorationPohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration
Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration
 
Muskegon Lake Restoration: A Success Story
Muskegon Lake Restoration: A Success StoryMuskegon Lake Restoration: A Success Story
Muskegon Lake Restoration: A Success Story
 
Huntsman Lake Dredging January 2015
Huntsman Lake Dredging January 2015Huntsman Lake Dredging January 2015
Huntsman Lake Dredging January 2015
 
Feb 11 2014 public meeting
Feb 11 2014 public meetingFeb 11 2014 public meeting
Feb 11 2014 public meeting
 
Tim randle dam removal in the united states
Tim randle   dam removal in the united statesTim randle   dam removal in the united states
Tim randle dam removal in the united states
 
Tim randle dam removal in the united states
Tim randle   dam removal in the united statesTim randle   dam removal in the united states
Tim randle dam removal in the united states
 
Huntsman Lake “Pardon Our Dust”
Huntsman Lake “Pardon Our Dust” Huntsman Lake “Pardon Our Dust”
Huntsman Lake “Pardon Our Dust”
 
10. Restoring the River Camac - Mary-Liz Walshe, DCC
10. Restoring the River Camac - Mary-Liz Walshe, DCC10. Restoring the River Camac - Mary-Liz Walshe, DCC
10. Restoring the River Camac - Mary-Liz Walshe, DCC
 
Woodglen Lake Dredging and Restoration
Woodglen Lake Dredging and RestorationWoodglen Lake Dredging and Restoration
Woodglen Lake Dredging and Restoration
 
Steelhead Haven
Steelhead HavenSteelhead Haven
Steelhead Haven
 
Rury 206PM Room B_Integr Hab Restor & Stormwater Treat
Rury 206PM Room B_Integr Hab Restor & Stormwater TreatRury 206PM Room B_Integr Hab Restor & Stormwater Treat
Rury 206PM Room B_Integr Hab Restor & Stormwater Treat
 
Deschutes Estuary Restoration Team presentation 4-28-11
Deschutes Estuary Restoration Team presentation 4-28-11Deschutes Estuary Restoration Team presentation 4-28-11
Deschutes Estuary Restoration Team presentation 4-28-11
 
Lake shady plans
Lake shady plansLake shady plans
Lake shady plans
 

Plus de Fairfax County

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementFairfax County
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS Fairfax County
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22Fairfax County
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxFairfax County
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19 Fairfax County
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationFairfax County
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction ProgressFairfax County
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxFairfax County
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IVFairfax County
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Fairfax County
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxFairfax County
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilFairfax County
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptxFairfax County
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT Fairfax County
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap UpFairfax County
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Fairfax County
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Fairfax County
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectFairfax County
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Fairfax County
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual ArtsFairfax County
 

Plus de Fairfax County (20)

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer Replacement
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction Progress
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IV
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick Offpptx
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing Council
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap Up
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction Project
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual Arts
 

Dernier

Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...
Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...
Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...srinuseo15
 
02052024_First India Newspaper Jaipur.pdf
02052024_First India Newspaper Jaipur.pdf02052024_First India Newspaper Jaipur.pdf
02052024_First India Newspaper Jaipur.pdfFIRST INDIA
 
05052024_First India Newspaper Jaipur.pdf
05052024_First India Newspaper Jaipur.pdf05052024_First India Newspaper Jaipur.pdf
05052024_First India Newspaper Jaipur.pdfFIRST INDIA
 
04052024_First India Newspaper Jaipur.pdf
04052024_First India Newspaper Jaipur.pdf04052024_First India Newspaper Jaipur.pdf
04052024_First India Newspaper Jaipur.pdfFIRST INDIA
 
Busty Desi⚡Call Girls in Vasundhara Ghaziabad >༒8448380779 Escort Service
Busty Desi⚡Call Girls in Vasundhara Ghaziabad >༒8448380779 Escort ServiceBusty Desi⚡Call Girls in Vasundhara Ghaziabad >༒8448380779 Escort Service
Busty Desi⚡Call Girls in Vasundhara Ghaziabad >༒8448380779 Escort ServiceDelhi Call girls
 
declarationleaders_sd_re_greens_theleft_5.pdf
declarationleaders_sd_re_greens_theleft_5.pdfdeclarationleaders_sd_re_greens_theleft_5.pdf
declarationleaders_sd_re_greens_theleft_5.pdfssuser5750e1
 
BDSM⚡Call Girls in Sector 143 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 143 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 143 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 143 Noida Escorts >༒8448380779 Escort ServiceDelhi Call girls
 
Kishan Reddy Report To People (2019-24).pdf
Kishan Reddy Report To People (2019-24).pdfKishan Reddy Report To People (2019-24).pdf
Kishan Reddy Report To People (2019-24).pdfKISHAN REDDY OFFICE
 
BDSM⚡Call Girls in Greater Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Greater Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Greater Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Greater Noida Escorts >༒8448380779 Escort ServiceDelhi Call girls
 
Julius Randle's Injury Status: Surgery Not Off the Table
Julius Randle's Injury Status: Surgery Not Off the TableJulius Randle's Injury Status: Surgery Not Off the Table
Julius Randle's Injury Status: Surgery Not Off the Tableget joys
 
Nara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's Development
Nara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's DevelopmentNara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's Development
Nara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's Developmentnarsireddynannuri1
 
America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...
America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...
America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...Andy (Avraham) Blumenthal
 
Embed-4.pdf lkdiinlajeklhndklheduhuekjdh
Embed-4.pdf lkdiinlajeklhndklheduhuekjdhEmbed-4.pdf lkdiinlajeklhndklheduhuekjdh
Embed-4.pdf lkdiinlajeklhndklheduhuekjdhbhavenpr
 
China's soft power in 21st century .pptx
China's soft power in 21st century   .pptxChina's soft power in 21st century   .pptx
China's soft power in 21st century .pptxYasinAhmad20
 
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 46 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 46 (Gurgaon)Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 46 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 46 (Gurgaon)Delhi Call girls
 
Enjoy Night ≽ 8448380779 ≼ Call Girls In Palam Vihar (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Palam Vihar (Gurgaon)Enjoy Night ≽ 8448380779 ≼ Call Girls In Palam Vihar (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Palam Vihar (Gurgaon)Delhi Call girls
 
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 48 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 48 (Gurgaon)Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 48 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 48 (Gurgaon)Delhi Call girls
 
Embed-2 (1).pdfb[k[k[[k[kkkpkdpokkdpkopko
Embed-2 (1).pdfb[k[k[[k[kkkpkdpokkdpkopkoEmbed-2 (1).pdfb[k[k[[k[kkkpkdpokkdpkopko
Embed-2 (1).pdfb[k[k[[k[kkkpkdpokkdpkopkobhavenpr
 
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...Faga1939
 
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 47 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 47 (Gurgaon)Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 47 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 47 (Gurgaon)Delhi Call girls
 

Dernier (20)

Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...
Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...
Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...
 
02052024_First India Newspaper Jaipur.pdf
02052024_First India Newspaper Jaipur.pdf02052024_First India Newspaper Jaipur.pdf
02052024_First India Newspaper Jaipur.pdf
 
05052024_First India Newspaper Jaipur.pdf
05052024_First India Newspaper Jaipur.pdf05052024_First India Newspaper Jaipur.pdf
05052024_First India Newspaper Jaipur.pdf
 
04052024_First India Newspaper Jaipur.pdf
04052024_First India Newspaper Jaipur.pdf04052024_First India Newspaper Jaipur.pdf
04052024_First India Newspaper Jaipur.pdf
 
Busty Desi⚡Call Girls in Vasundhara Ghaziabad >༒8448380779 Escort Service
Busty Desi⚡Call Girls in Vasundhara Ghaziabad >༒8448380779 Escort ServiceBusty Desi⚡Call Girls in Vasundhara Ghaziabad >༒8448380779 Escort Service
Busty Desi⚡Call Girls in Vasundhara Ghaziabad >༒8448380779 Escort Service
 
declarationleaders_sd_re_greens_theleft_5.pdf
declarationleaders_sd_re_greens_theleft_5.pdfdeclarationleaders_sd_re_greens_theleft_5.pdf
declarationleaders_sd_re_greens_theleft_5.pdf
 
BDSM⚡Call Girls in Sector 143 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 143 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 143 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 143 Noida Escorts >༒8448380779 Escort Service
 
Kishan Reddy Report To People (2019-24).pdf
Kishan Reddy Report To People (2019-24).pdfKishan Reddy Report To People (2019-24).pdf
Kishan Reddy Report To People (2019-24).pdf
 
BDSM⚡Call Girls in Greater Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Greater Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Greater Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Greater Noida Escorts >༒8448380779 Escort Service
 
Julius Randle's Injury Status: Surgery Not Off the Table
Julius Randle's Injury Status: Surgery Not Off the TableJulius Randle's Injury Status: Surgery Not Off the Table
Julius Randle's Injury Status: Surgery Not Off the Table
 
Nara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's Development
Nara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's DevelopmentNara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's Development
Nara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's Development
 
America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...
America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...
America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...
 
Embed-4.pdf lkdiinlajeklhndklheduhuekjdh
Embed-4.pdf lkdiinlajeklhndklheduhuekjdhEmbed-4.pdf lkdiinlajeklhndklheduhuekjdh
Embed-4.pdf lkdiinlajeklhndklheduhuekjdh
 
China's soft power in 21st century .pptx
China's soft power in 21st century   .pptxChina's soft power in 21st century   .pptx
China's soft power in 21st century .pptx
 
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 46 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 46 (Gurgaon)Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 46 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 46 (Gurgaon)
 
Enjoy Night ≽ 8448380779 ≼ Call Girls In Palam Vihar (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Palam Vihar (Gurgaon)Enjoy Night ≽ 8448380779 ≼ Call Girls In Palam Vihar (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Palam Vihar (Gurgaon)
 
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 48 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 48 (Gurgaon)Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 48 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 48 (Gurgaon)
 
Embed-2 (1).pdfb[k[k[[k[kkkpkdpokkdpkopko
Embed-2 (1).pdfb[k[k[[k[kkkpkdpokkdpkopkoEmbed-2 (1).pdfb[k[k[[k[kkkpkdpokkdpkopko
Embed-2 (1).pdfb[k[k[[k[kkkpkdpokkdpkopko
 
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
 
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 47 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 47 (Gurgaon)Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 47 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 47 (Gurgaon)
 

Royal Lake Dredging and Restoration

  • 1.
  • 2.  Dredging Program and Project Background  Project Benefits  Royal Lake Conditions  Phased Approach  Dredging Methods and Alternatives  Park Access and Community Coordination  Next Steps Royal Lake: Meeting Agenda
  • 3.  History – Lakes previously dredged by DPWES Stormwater – Limited to small quantities – Dewatered on site  Lake Barton completed in 2011  Currently working on: – Huntsman Lake, Woodglen Lake, Royal Lake Dredging and Lake Restoration Program
  • 4.  Completed Data Collection  Developing Lake Dredging and Management Plan  Community coordination at design and construction phases – Preliminary Design (65%) – Final Design (95%) – Preconstruction: Pardon Our Dust meeting  December 2013: Final Design  Construction in Fiscal Year 2015 (July 2014) Royal Lake Dredging and Restoration Project Timeline and Coordination
  • 5.  Restore sediment pool capacity – Downstream water quality benefits – Lake water quality – Aesthetics  Improve lake water quality and habitat  Provide long term maintenance improvements Project Goals and Benefit
  • 6. Lake Barton Dredging and Restoration Area Treated (acres) Phosphorous Removal Nitrogen Removal Sediment Removal 544 77,000 lbs dredged 115,500 lbs dredged 38,500 tons dredged Annual benefit from increased trapping efficiency 130 lbs/year 200 lbs/year 65 tons/year
  • 7. Royal Lake Facts  Drainage area = 2,477 acres (3.67 square miles)  Lake surface area = 37.5 acres  Sediment pool capacity = 416,000 cubic yards (CY)  Current sediment in lake = 100,400 CY  Estimated annual sediment load = 4,400 CY 50 feet 100,400 CY
  • 11. Royal Lake: Dredging Areas  Phase 1: Base Dredge = 40,000 CY  Phase 2: Up to an additional 60,000 CY Zone D 12,400 CY
  • 13. Dredging Methods and Alternatives 1. Mechanically dredge deposited sediment and haul wet 2. Drain lake and dry deposited sediment in place before hauling
  • 14. PRE-DREDGING: An estimated 35,000 cubic yards of sediment had accumulated in the lake, forming islands and reducing water levels to less than three feet in most areas. Lake Barton Example
  • 15. Lake Barton Example: Pre-Dredging
  • 18. Lake Barton Example: Disposal Site
  • 19. North Park Lake Example Allegheny County, Pennsylvania Dredging: The lake was drained and the sediment was dried in-place.
  • 20. North Park Lake Example Allegheny County, Pennsylvania Temporary Diversion Channels Equipment Working on Next Slide
  • 21. North Park Lake: Dredging Allegheny County, Pennsylvania Truck Wash Temporary Diversion Channel Low Pressure Excavator Bulldozer Bulldozer Excavator and DozerTruck Access Staging
  • 22.  General Sequence – Establish access and staging areas – Conduct dredging utilizing barges – Haul wet sediment to disposal site for drying  Benefits – Less weather dependent – Quicker initial start to dredging – Less potential for schedule extensions or delay  Concerns – Increased sediment handling effort at disposal area – Potentially higher cost Dredge Alternative – In the Wet
  • 23.  General Sequence – Initiate drawdown of lake – Establish access and staging areas – Establish diversion channels within lake – Conduct dredging  Benefits – Higher daily sediment removal rates – Minimal sediment handling effort at disposal area – Potentially lower cost  Concerns – Very weather dependent – Higher potential for delays due to weather – Typically more odor from sediment exposed – Need to relocate/salvage fish Dredge Alternative – In the Dry
  • 24.  In-lake forebay  Wetland planting  Shoreline stabilization  Fish habitat  Fish stocking Lake Restoration Fish habitat created from salvaged trees Lake Barton: Fish stocking by Virginia Game and Inland Fisheries
  • 25. Royal Lake: Shoreline Restoration
  • 26. Royal Lake: Shoreline Restoration Royal Lake Existing Conditions
  • 29. Royal Lake: Site Access and Staging Optional?
  • 30. Royal Lake: Site Access and Staging
  • 31. Staging Area 1 Potential Expansion Berm/Cofferdam to be built Area to be dewatered and backfilled to expand staging area after berm/cofferdam is built
  • 32. Royal Lake: Dewatering Basin Inactive Dewatering Basin
  • 33. Access During Construction Public Access: The park will remain open and existing parking lot will be available.
  • 34. Access During Construction Public Access: Pedestrian gates will be provided. Access through work areas and trails around the lake after work hours.
  • 35.  Community coordination at design and construction phases – Preliminary Design (65%) – Final Design (95%) – Preconstruction: “Pardon Our Dust” meeting  December 2013: Final Design  Construction in Fiscal Year 2015 (Starts July 2014)  Project Duration: – Phase 1, Base Dredge: Dredge 40,000 CY = 5 to 6 Months – Phase 2, Full Dredge: 9 to 12 Months Royal Lake Dredging and Restoration Project Timeline and Coordination
  • 36. Contacts:  Martin Chang, Project Manager 703-324-5825 | Martin.Chang@fairfaxcounty.gov  Dipmani Kumar, Section Chief 703-324-4612 | Dipmani.Kumar@fairfaxcounty.gov  http://www.fairfaxcounty.gov/dpwes/stormwater/ Royal Lake DredgingandRestoration http://www.fairfaxcounty.gov/NVSWCD/ http://www.fairfaxcounty.gov/parks/