31. Tysons
31
TMSAMS Major Projects (continued)
• Ashgrove Trail Phase II, est. $1,300,000
• FCPA to implement; working on agreement.
• Scotts Run Walkway from Magarity Road to Colshire Meadow
Drive, est. $2,550,000
• Expect FCPA to construct. Concept/alignment alternative
analysis complete. FCPA proceeding with intermediate design.
• Route 7 Walkway from Dulles Toll Road to Beulah Road, est.
$5,375,000
• This project has been recommended to be “deleted” and to be
constructed as part of VDOT’s Route 7 Widening project from
Jarrett Valley to Reston Parkway.