Update on Tysons Development and Transportation Projects: Oct. 28, 2013
1. Tyso
ns
1
Update on Tysons Development
and Transportation Projects
Tysons Transportation Service District Advisory Board
October 28, 2013
2. Tyso
ns
2
Today’s Presentation
• Recap of FY 2014 service district tax rate recommendation
• Modified Bell Curve
• Development
• Construction
• Growth
• Project Status
• Funding Plan Recap
• Tysons-wide Roadway Projects (17)
• Tysons Comprehensive Plan Amendment
• Grid of Streets
• Tysons Circulator Study/Service
• Neighborhood Intersection Improvements Study and the Tysons
Metrorail System Access Management projects (postponed until
next meeting)
3. Tyso
ns
3
Recap of FY 2014 ServiceDistrict Tax Rate
Recommendation
• The advisory board endorsed the “modified bell curve”.
• Recommended a tax rate of $0.04/$100 of assessed value for
FY 2014.
• Subsequently, the Board approved a service district tax rate of
$0.04 with the adoption of the FY 2014 budget.
• Tax rate started on July 1, 2013, mid-year of tax collection cycle
making the effective rate for CY 2013 $0.02.
• It is anticipated that the service district tax rate would be
reviewed and reevaluated annually.
4. Tyso
ns
4
Recap of “Modified Bell Curve”
Model Results
• Payoff period finishes in 2048
• Reduces tax rates in last years
• Most years at $0.06 tax rate
• Increases gross tax revenue contributions
• When combined with Dulles Rail Phase I, does not exceed
$0.29 planning cap
• Bell curve proposes an increase in tax rate from $0.04 to $0.05
in FY 2015.
• Board action is required to set a rate for FY 2015.
8. Tyso
ns
8
Construction Since 2010
Limited amount of approved redevelopment has been
constructed between 2010 - 2013
• Avalon Park Crest six-story residential building (354 units)
• Urban-style WalMart and fitness center in Tysons West
• Removal of older retail and office development (80,000 sq.ft.)
2013 Annual Report: Page 18
9. Tyso
ns
9
Existing Development Levels
Land Use 2011 2013 Change
Office 26,862,000 26,758,000 -
Retail 5,096,000 4,945,000 -3%
Car Dealership 730,000 730,000 -
Hotel 2,578,000 2,578,000 -
Industrial 986,000 986,000 -
Gvmt/Inst 80,000 80,000 -
Resd (sq. ft.) 10,844,000 11,210,000 +3%
Resd (units) 8,943 9,297 +4%
Total All Uses 47,176,000 47,287,000 -
2013 Annual Report: Table 1, page 8
10. Tyso
ns
10
Current Major Construction Activity
Currently eight buildings are under construction, totaling 2.7M
square feet;
Office - 1,183,000, Retail – 36,000, Hotel – 252,000
Residential 1,262,000 (1,099 units)
Projects currently under construction include;
• Spring Hill Station; 26-story high-rise residential
• Tysons Corner Center; four structures in Phase I, including a
22-story office, 28-story residential, hotel and retail structure
• Scotts Run South; MITRE 4 office building (340,000 sq.ft.)
• Park Crest; 19-story residential building
• Tysons Overlook; 11-story LMI Headquarters office building
2013 Annual Report: Tables 3 & 4, pages 11-14
11. Tyso
ns
11
Approved Development
• Sixteen major rezoning applications approved in Tysons (six
prior to plan approval)
• Seven rezoning applications were approved in past year.
• 100 acres, 17 million SF of commercial and residential
development.
• Estimated to accommodate 13,000 new residents and 21,000
new jobs.
2013 Annual Report: Tables 3 & 4, pages 10-14
12. Tyso
ns
12
Pending Development Applications
• Eight rezoning applications currently under review.
• 90 acres, 7 million SF each of commercial and residential
development.
• Estimated to add 12,500 new residents and 17,000 new jobs.
• Four applications placed on indefinite deferral.
2013 Annual Report: Tables 7 & 8, pages 14, 17
13. Tyso
ns
13
Summary of Development
2013 Annual Report: Tables 7 & 8, pages 14, 17
Existing
Under
Construction
Approved
Development
Proposed
Development Total
Residential
Population
17,000 1,925 23,870 12,260 55,055
Residential
Units
9,297 1,099 13,640 7,006 31,040
Employment
Population
105,000 4,225 44,150 16,470 169,845
Conclusion – Meeting the goals set forth in the Tysons
development plan.
18. Tyso
ns
18
Overall Funding Approach
• Diverse plan to fund transportation improvements
• 10 Funding Sources Identified
• 36% from redevelopment commitments
• 33% from County sources
• 19% from State and Federal sources
• 12% from special funding/financing sources
• Service District is part of the 12%.
• Service District represents 8% of Total Tysons Transportation Cost
Estimate of $3.1B
All revenue and costs are displayed as 2012 Dollar
20. Tyso
ns
20
Tysons-wide Roadway Projects
• Road projects to improve traffic flow into and within Tysons
(included in Table in Comp Plan).
• Improvements include: new ramps, new roads, and widening
existing roads.
• Estimated cost of $1.2 billion
• Public sector funding of $701 million
• Tysons-wide Road Fund - $253 million
• Tysons Transportation Service District - $253 million
All revenue and costs are displayed as 2012 Dollar
23. Tyso
ns
23
Tysons-wide Roadway Projects
Phase I Update
Jones Branch Connector
• Preliminary design (30% level) developed and distributed to
VDOT and FCDOT for comment.
• The Interchange Modification Report (IMR) and National
Environmental Policy Act (NEPA) reevaluation preparations are
underway.
• Approval anticipated April 2014.
• FCDOT will administer the Preliminary Engineering (PE) and
Right‐of‐Way (ROW) phases. VDOT will administer
Construction (CN).
• Current Activity: survey, hired designer, utility designation
• Scheduled completion of construction – 2018.
25. Tyso
ns
25
Tysons-wide Roadway Projects
Phase I Update
Rte 7 Widening (Rt. 123 to I-495)
• Study currently underway.
• Evaluating concepts to accommodate projected traffic
demands that conforms with the grid of streets and the
Consolidated Traffic Impact Analyses (CTIAs).
• The widening study is being conducted in conjunction with the
Route 7/123 Interchange/Intersection Study
• Study expected to be completed by Spring 2014.
26. Tyso
ns
26
Tysons-wide Roadway Projects
Phase I Update
Rte 7 Widening (Dulles Toll Road to Reston Ave)
• Working Group Meeting was scheduled on September 25,
2013.
• A Public Information Meeting (PIM) scheduled for 11/6/2013
at the Colvin Run Elementary School.
• VDOT is currently performing traffic engineering study of
reversible HOV/Transit lanes along corridor; anticipated
completion October 2013.
• Met with Fairfax County Public Schools, Fire and Rescue,
Police, McLean Bible Church to brief them on the project so
far.
• Project briefings are scheduled with Supervisor Foust and
McLean Bible Church adjacent homeowners.
27. Tyso
ns
27
Tysons-wide Roadway Projects
Phase I Update
Rte 123 Widening (Old Courthouse to Rte 7)
• Anticipated to begin preliminary engineering in 2014.
Rte 123 Widening (Rte 7 to I-495)
• Anticipated to begin preliminary engineering in 2014.
28. Tyso
ns
28
Tysons-wide Roadway Projects
Phase II Update
Dulles Toll Road Ramps to Greensboro Dr, Jones Branch Dr, and
Boone Blvd Extensions; Eastbound/Westbound
Collector/Distributors
• Conceptual plans developed for ramps at Boone Blvd,
Greensboro Dr, and Jones Branch Dr.
• Portion included in approved rezoning; Greensboro Dr
• Report on conceptual design submitted to VDOT; comments
received for Jones Branch Dr.
• Community meetings conducted.
• Anticipate Board approval in early 2014.
• Study complete after Board approval.
29. Tyso
ns
29
Amendments to Tysons ComprehensivePlan
• The Comprehensive Plan for Tysons, adopted in 2010,
recommends additional work and studies that should be
undertaken to implement the long-term vision for Tysons
• Examples of additional work and studies include detailed
street grid and ramp studies, urban design guidelines, and a
transportation funding plan
• Most of the recommended studies and implementation plans
have been completed so Tysons Plan is proposed to be
amended to reflect this additional work.
30. Tyso
ns
30
Amendments to Tysons ComprehensivePlan
(continued)
• The amendment to the Tysons Plan will be addressed in three
separate sections:
• Implementation, Land Use, Urban Design - Target completion
fall 2013
• Transportation - Target completion winter 2013-14
• Parks, Public Facilities, and Other - Target completion 2014
• The three sections will be combined into one plan
amendment with target Planning Commission and Board
hearing dates late 2014 /early 2015
31. Tyso
ns
31
Grid of Streets
• Improvements to transform current superblock street network
to a more urban model.
• Estimated cost of $865 million
• In-kind construction - $560 million
• Tysons Grid of Street Fund - $305 million
• 2013 rates: $1,000/residential unit and $6.44/non-residential
sq. ft.
All revenue and costs are displayed as 2012 Dollar
34. Tyso
ns
34
Grid of Streets Update
• Consolidated Traffic Impact Analyses (CTIAs), three conducted
(Tysons East, Central, and West) to:
• Determine current and future traffic conditions,
• Evaluate and optimize the grid of streets, and
• Determine right-of-way needs.
• Examines best possible traffic flow with minimal impact to
environment and property.
• Examines how Tysons can be transformed into a walkable
urban center through redevelopment of land and
corresponding grid of streets.
35. Tyso
ns
35
Grid of Streets Update (continued)
• Tysons East and West CTIAs complete, and approval received
from VDOT. Tysons Central in final review, VDOT approval
expected November 2013.
• Currently working with stakeholders on the alignment of State
Street
• 7-8 options being considered.
36. Tyso
ns
36
Transit ServiceEnhancements
• Enhanced transit service to capitalize on Metrorail investment
and support transit oriented development.
• Improvements include:
• Neighborhood bus routes
• Circulator routes serving Metrorail
• Express Routes
• Bus Rapid Transit routes
• Estimated cost of $953 million
• Capital expenses - $155 million
• Operating - $798 million
• Various public sector revenue sources
All revenue and costs are displayed as 2012 Dollar
37. Tyso
ns
37
Transit ServiceEnhancements
Tysons Circulator Study (Long Term)
• Planning study to support the redevelopment of Tysons over
the next 40 years.
• Focused on the development of a long term Circulator System
intended to support the Tysons Area by 2050.
• Key recommendations from the study:
• Provision of a three route network; use of buses, which can
provide sufficient capacity for future demand;
• Provision of strategically placed exclusive lanes and queue jumps
with shared right‐of‐way travel for the remainder of the routes.
• http://www.fairfaxcounty.gov/tysons/transportation/downloa
d/tysons_circulator_study_final_report.pdf
39. Tyso
ns
39
Transit ServiceEnhancements
Tysons Circulator Upcoming Service(Short Term)
• The first phase of the Circulator System, serving the Metrorail
stations in Tysons immediately after Dulles Rail service begins.
• Three routes starting service with Dulles Rail Phase I:
• 422 – West Tysons – Greensboro
• 423 – Central Tysons – Tysons Corner
• 424 – North Tysons – Springhill
• Serving Tysons weekdays, Saturdays, and Sundays
• Approximately 32,000 revenue hours of service annually.
• On June 4, 2012, the Board approved the Fairfax Connector ‘s
Dulles Rail Phase I service plan.
• Includes Tysons Circulator routes.
• http://www.fairfaxcounty.gov/connector/routes/silverline/tys
ons.htm
Proposed DRPI tax rates based on current assumptions; largely projected assessed value.
Cost estimates and scheduled completion dates could possibly be revised in time for the second AB meeting.
Approved through rezoning applications.
See Jeff’s email.
See Jeff’s email.
Final Recommended Network – Three Route Network
the Circulator, which will be focused on providing circulation within Tysons, will be part of much denser transit network that will include WMATA Metrobus service, Fairfax County Connector service, and long distance bus service from other parts of Northern Virginia
mode option analysis indicated that buses can provide sufficient capacity to meet ridership demand under all scenarios evaluated, at a lower cost than streetcar.
Route Details - 422
Summary: New route
Metro Stations served: Greensboro (Silver)
Route serves: Boone Boulevard, Ring Road, Tysons Galleria, Tysons Corner Center, Route 7
Route operates: Weekdays
Hours operated:
Weekdays: 5:30 a.m. - 11 p.m.
Frequency of service:
Weekdays: Every 10 minutes during rush hour; every 20 minutes during the rest of the day
Direction: Clockwise
Route Details - 423
Summary: New route
Metro Stations served: Tysons Corner (Silver), Spring Hill (Silver)
Route serves: Greensboro Drive, Jones Branch Drive, Tysons Blvd, International Drive, Westpark Drive, Spring Hill Road
Route operates: Weekdays, Saturdays, Sundays
Hours operated:
Weekdays: 5:30 a.m. - 11:30 p.m.
Saturdays: 6 a.m. - 10 p.m.
Sundays: 6 a.m. - 8 p.m.
Frequency of service:
Weekdays: Every 10 minutes during rush hour; every 20 minutes during the rest of the day
Saturdays: Every 30 minutes
Sundays: Every 30 minutes
Direction: Clockwise
Route Details - 424
Summary: New route
Metro Stations served: Spring Hill (Silver)
Route serves: Westpark Drive, Jones Branch Drive, International Drive, Tyco Road
Route operates: Weekdays
Hours operated:
Weekdays: 5:30 a.m. - 11:30 p.m.
Frequency of service:
Weekdays: Every 10 minutes during rush hour; every 20 minutes during the rest of the day
Direction: Clockwise