This Slideshare presentation is a partial preview of the full business document. To view and download the full document, please go here:
http://flevy.com/browse/business-document/master-production-scheduling-1115
DESCRIPTION
This documents shares you insights about the key operations management techniques such as master scheduling and master production scheduling . Manufacturing?s portion of the Master Schedule. It is the anticipated build schedule, stated in specific product configurations.
2. Master Production Schedule
•Manufacturing‘s portion of the Master Schedule. It is the
anticipated build schedule, stated in specific product
configurations.
•1) Links ‘Production Planning’ to what will be built. 2)
Calculates capacity and resources needed. 3) Drives
the materials requirements plan. 4) Drives priorities
for manufacturing.
•May be stated in terms of modules constituting the end
products (rather than the end products themselves).
•Arises from a ‘Top-down’ process.
5
This document is a partial preview. Full document download can be found on Flevy:
http://flevy.com/browse/document/master-production-scheduling-1115
3. 2. An Example
Master Production Schedule
8
This document is a partial preview. Full document download can be found on Flevy:
http://flevy.com/browse/document/master-production-scheduling-1115
4. 3. About
Master Production Scheduling
(as a process)
11
This document is a partial preview. Full document download can be found on Flevy:
http://flevy.com/browse/document/master-production-scheduling-1115
5. MPS and Time Fences
(as applied to product A)
FROZEN
0 2 Weeks 26 Weeks
SLUSHY LIQUID
Due Date
Demand
Time Fence
Planning
Time FenceA
B C D
E
(LT=2)
(LT=8)
(LT=6) (LT=5)
(LT=16)
14
This document is a partial preview. Full document download can be found on Flevy:
http://flevy.com/browse/document/master-production-scheduling-1115
6. 4. Developing MPS
from Aggregate Plans
– An Example
17
This document is a partial preview. Full document download can be found on Flevy:
http://flevy.com/browse/document/master-production-scheduling-1115
7. MPS from Disaggregation of Aggregate
plans – An Example
(Continued)
Individual Product Inventory profiles associated
with the Master Production Schedule
1 2 3 4 5 6 7 8 9 10 11 12
Product - 1 280 210 140 70 0 125 250 320 240 160 80 0
Product - 2 266 432 598 559 465 345 215 140 215 260 130 0
Product - 3 0 -50 -100 55 210 160 120 80 40 30 195 360
Total
inventory 546 642 738 684 675 630 585 540 495 450 405 360
Aggregate
Plan Capacity 546 592 638 684 675 630 585 540 495 450 405 360
Deviation 0 50 100 0 0 0 0 0 0 0 0 0
Deviation
Week
Inventory
= Total inventory-inventory from the aggregate plan
20
This document is a partial preview. Full document download can be found on Flevy:
http://flevy.com/browse/document/master-production-scheduling-1115
8. Product Load Profiles :
1 2 3 4 5 6
5
10
15
20
25
5
10
15
20
25
1 2 3 4 5
Product-Lot
Due Date
Product – 1
Resource - X
Product – 2,
Resource - X
Product-Lot
Due Date
Rough-cut Capacity Planning :
Calculation Of Resource Requirement Profile – An Example
(Continued)
23
This document is a partial preview. Full document download can be found on Flevy:
http://flevy.com/browse/document/master-production-scheduling-1115
9. The MPS Hourglass
End Items
MPS
Options
Components
26
Rule: Do
Master
Scheduling
where the
smallest
number of
product
options
exists.
This document is a partial preview. Full document download can be found on Flevy:
http://flevy.com/browse/document/master-production-scheduling-1115
10. The Production Planning Process
Leading To Final Assembly Schedule
Summary of typical production planning schedule, for JIT Production
Planning
Stage
Purpose Planning
Horizon
Planning
Cycle
Format Developed
From
1. Long-
range plan
Plan new products and
models
Plan facilities
Plan systems changes
3-5 yrs. 6 mths to
1 year
Indefinite Corporate
forecasts and
policies
2.Production
Plan
Plan tools and materials
Supplier planning
Total manpower
1 yr. 1 month Summari
zed by
model or
family in
monthly
buckets
Long range
plan and more
detailed
forecasts
3.Master
production
schedule
Develop data over time to
evolve into final
assembly schedule.
Make major manpower
allocations
3-6
months*
1
month*
Summary
of
expected
final
assembly
schedule
in daily
buckets
Production
plan and more
detailed
forecasts and
actual orders.
Sometimes
from finished
goods system
* There may be shorter times and horizons for mix change plans for those companies which have them.
29
This document is a partial preview. Full document download can be found on Flevy:
http://flevy.com/browse/document/master-production-scheduling-1115
11. Mixed Model Scheduling (under JIT)
Tennant Company
Model / Week # 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Total
A 21 21 42
B 17 18 35
C 49 49 98
D 21 21
42
E 11 10 21
Total # Units Kitted per
week 21 17 49 - - 21 11 21 18 49 - - 21 10 238
EOQ-Based Master Scheduling: Assembly Line Starts / Kitting
32
This document is a partial preview. Full document download can be found on Flevy:
http://flevy.com/browse/document/master-production-scheduling-1115
12. 1
Flevy (www.flevy.com) is the marketplace
for premium documents. These
documents can range from Business
Frameworks to Financial Models to
PowerPoint Templates.
Flevy was founded under the principle that
companies waste a lot of time and money
recreating the same foundational business
documents. Our vision is for Flevy to
become a comprehensive knowledge base
of business documents. All organizations,
from startups to large enterprises, can use
Flevy— whether it's to jumpstart projects, to
find reference or comparison materials, or
just to learn.
Contact Us
Please contact us with any questions you may have
about our company.
• General Inquiries
support@flevy.com
• Media/PR
press@flevy.com
• Billing
billing@flevy.com