SlideShare une entreprise Scribd logo
1  sur  3
Télécharger pour lire hors ligne
Transcript
15364159-1 1 Francis Ho –April 2013
INTRODUCTION TO THE CIOB COMPLEX PROJECTS CONTRACT 2013
PROJECT SUITABILITY AND PROCUREMENT STRATEGY
The following is a loose transcript of a talk given in London on 25 April 2013 at the launch of the
Chartered Institute of Building’s Complex Projects Contract 2013 by one of its authors.
BACKGROUND
· “Guide to Good Practice in the Management of Time in Complex Projects”published by
CIOB in 2010 following detailed 2007 research into complex projects.
· The Complex Projects Contract 2013 (CPC) is designed for complex projects and built
upon foundations of 2010 Guide. Not suited to simple projects.
· A “simple project”typically has all of following characteristics:
o Repetitive work;
o Fewer than 5 storeys;
o One completion date, no phasing;
o Straightforward utilities;
o Single contractor;
o Less than 9 month build period;
o Fewer than 10 sub-contracts.
· A complex project typically has any or more of the following characteristics:
o Incomplete design;
o More than 5 storeys;
o Below ground accommodation;
o Multiple sections and possessions;
o Civil engineering;
o Multiple contractors and sub-contractors.
· Simple projects can be managed intuitively; have high chance of finishing on time using
such traditional management techniques (finding of the 2007 research).
· Examples of complex projects: airports, O&G projects, railway stations, high-rise buildings,
engineering, power stations. Extremely likely to be late using traditional time management
techniques.
15364159-1 2 Francis Ho –April 2013
· Added expense in using a contract written and intended for complex projects, which mean
that the benefits will not be so evident on a simpler, low value project. Investment time
needed for participants to understand the contract (e.g. understanding the 2010 Guide),
workshops for the project team and upskilling main participants and advisers, completing
the CPC’s Appendices and client involvement.
· Since CPC envisages that it is sensible the client be actively involved throughout the
project, it is not for novice employers.
TO MANAGE COMPLEX PROJECTS, NEED TO CHANGE WAY OF THINKING
· Need regularly updated contractual programme with quality controls so the information is
useful at the time given.
· Need “Project Time Manager”to advise independently on time management procedures
and compliance.
· Need a programme which is a dynamic management tool in three different levels of detail
so programme not simply tool in disputes.
· Need a 21
st
century contract specifically written for complex projects.
WHAT DOES CPC DO DIFFERENTLY?
· A single contract form does it all.
· Turnkey (EPC), traditional, design and build. With amendment CPC can even be used for
EPCM, with Contract Administrator as EPCM Manager and CPC used as basis of trade
contracts.
· The Contractor’s Pricing Document allows for cost reimbursable or lump sum pricing.
· As well as use in England and Wales (and the rest of the UK), it is suitable to be used
internationally (with provisions catering for mandatory local law and governing law being
specified by CPC’s Contract Agreement).
· Provisions for bonds, parent company guarantees and collateral warranties/direct
agreements.
· Risk register.
· Professional skill and care in design.
· Either party may assign contractual rights and benefits by way of security.
· Special Conditions recognise and cater for the fact that all complex projects have different
requirements.
15364159-1 3 Francis Ho –April 2013
· Bespoke testing and commissioning provisions can be included seamlessly.
WHAT IS UNIQUE TO CPC?
· Time management procedures, detailed progress records, role of Project Time Manager.
· Provisions for Common Data Environment, Building Information Modelling (UK Level 2,
with suggested Levels of Development).
· Defines the key terms of “Concurrency”, “Free Float”and “Total Float”so these are clearly
understood.
· Confidentiality obligations on Employer for Contactor’s rates and prices (if marked as
confidential).
· By default, if the Employer provides information on site conditions to Contractor,
Contractor may rely on it.
· Termination for convenience by Employer.
· Employer has to provide evidence if reasonably required that it has the means to pay the
Predicted Cost, otherwise Contractor can suspend carrying out of the works.
INTERNATIONAL USAGE, NOT JUST FOR THE UNITED KINGDOM
· Adjudication applies where mandatory under the governing law, optional otherwise.
Compliant with England’s Scheme for Construction Contracts. Arbitration is the final,
binding dispute resolution procedure.
· Can be used with English law as governing law, with mandatory provisions of local law
being taken into account. References to local legislation or trade union recommended
minimum wages, visas and work permits.
· Can also be used under a different governing law.
· Minimum standards of site safety and welfare, e.g. Contractor’s safety manager, minimum
medical and first facilities on site – which may be beneficial when contracting in particular
territories.
· Provisions for paying in different currencies.
· Anti-corruption provisions apply to both parties.
· Special Conditions act as modifiers to the General Conditions.
Francis Ho, Olswang LLP
francis.ho@olswang.com

Contenu connexe

En vedette

State of the Cloud Computing Marketplace
State of the Cloud Computing MarketplaceState of the Cloud Computing Marketplace
State of the Cloud Computing MarketplaceFlexera
 
台灣海岸之美
台灣海岸之美台灣海岸之美
台灣海岸之美Josephine C
 
License Position Snapshot Service
License Position Snapshot ServiceLicense Position Snapshot Service
License Position Snapshot ServiceFlexera
 
Psychosociale problemen Chris Verhaak
Psychosociale problemen   Chris VerhaakPsychosociale problemen   Chris Verhaak
Psychosociale problemen Chris VerhaakMijnZorgnet
 
Master key system part 09
Master key system   part 09Master key system   part 09
Master key system part 09canei2day
 
前端Mvc探讨及实践
前端Mvc探讨及实践前端Mvc探讨及实践
前端Mvc探讨及实践taobao.com
 
台灣也有桃花源~一段期然而遇的歇心之旅
台灣也有桃花源~一段期然而遇的歇心之旅台灣也有桃花源~一段期然而遇的歇心之旅
台灣也有桃花源~一段期然而遇的歇心之旅Josephine C
 
Vũ trụ & các học thuyết
Vũ trụ & các học thuyếtVũ trụ & các học thuyết
Vũ trụ & các học thuyếtMai Trong
 

En vedette (14)

State of the Cloud Computing Marketplace
State of the Cloud Computing MarketplaceState of the Cloud Computing Marketplace
State of the Cloud Computing Marketplace
 
My Presentation to Teradata_13 Jan 2014
My Presentation to Teradata_13 Jan 2014My Presentation to Teradata_13 Jan 2014
My Presentation to Teradata_13 Jan 2014
 
台灣海岸之美
台灣海岸之美台灣海岸之美
台灣海岸之美
 
License Position Snapshot Service
License Position Snapshot ServiceLicense Position Snapshot Service
License Position Snapshot Service
 
Psychosociale problemen Chris Verhaak
Psychosociale problemen   Chris VerhaakPsychosociale problemen   Chris Verhaak
Psychosociale problemen Chris Verhaak
 
Ranking analysis-12-20-2011-3
Ranking analysis-12-20-2011-3Ranking analysis-12-20-2011-3
Ranking analysis-12-20-2011-3
 
What todo
What todoWhat todo
What todo
 
台灣行腳
台灣行腳台灣行腳
台灣行腳
 
Master key system part 09
Master key system   part 09Master key system   part 09
Master key system part 09
 
Splinternet January2011
Splinternet January2011Splinternet January2011
Splinternet January2011
 
前端Mvc探讨及实践
前端Mvc探讨及实践前端Mvc探讨及实践
前端Mvc探讨及实践
 
Jamia Ikhwan
Jamia Ikhwan Jamia Ikhwan
Jamia Ikhwan
 
台灣也有桃花源~一段期然而遇的歇心之旅
台灣也有桃花源~一段期然而遇的歇心之旅台灣也有桃花源~一段期然而遇的歇心之旅
台灣也有桃花源~一段期然而遇的歇心之旅
 
Vũ trụ & các học thuyết
Vũ trụ & các học thuyếtVũ trụ & các học thuyết
Vũ trụ & các học thuyết
 

Similaire à CIOB Complex Projects Contract 2013 - 25 April 2013 - Transcript of Talk

05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITIONByishimoBTCChef
 
Construction project delivery methods
Construction project delivery methodsConstruction project delivery methods
Construction project delivery methodsNitin Kumar
 
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...Praveen Premkumar
 
Construction Futures Wales - NEC Contracts Overview Workshop
Construction Futures Wales  - NEC Contracts Overview WorkshopConstruction Futures Wales  - NEC Contracts Overview Workshop
Construction Futures Wales - NEC Contracts Overview WorkshopRae Davies
 
What is NEC 3?, by Dr Jon Broome, 31st March 2015 copyright leadingedgeprojec...
What is NEC 3?, by Dr Jon Broome, 31st March 2015 copyright leadingedgeprojec...What is NEC 3?, by Dr Jon Broome, 31st March 2015 copyright leadingedgeprojec...
What is NEC 3?, by Dr Jon Broome, 31st March 2015 copyright leadingedgeprojec...Association for Project Management
 
What is NEC3? by Dr Jon Broome, with industry examples by John Rayner, 21st A...
What is NEC3? by Dr Jon Broome, with industry examples by John Rayner, 21st A...What is NEC3? by Dr Jon Broome, with industry examples by John Rayner, 21st A...
What is NEC3? by Dr Jon Broome, with industry examples by John Rayner, 21st A...Association for Project Management
 
Introductory Note on International Construction Contracts
Introductory Note on International Construction ContractsIntroductory Note on International Construction Contracts
Introductory Note on International Construction ContractsFrancis Ho
 
Building Contracts and CDM regulations
Building Contracts and CDM regulationsBuilding Contracts and CDM regulations
Building Contracts and CDM regulationsJulian Swindell
 
NEC Interview with Wai-Chi Sing of the HK Development Bureau
NEC Interview with Wai-Chi Sing of the HK Development BureauNEC Interview with Wai-Chi Sing of the HK Development Bureau
NEC Interview with Wai-Chi Sing of the HK Development BureauNEC Contracts
 
Pai 3-03
Pai 3-03Pai 3-03
Pai 3-03ypinada
 
PP1 presentation slide.
PP1 presentation slide.PP1 presentation slide.
PP1 presentation slide.lucaschinsheng
 
Toronto Pearson Airport - Terminal Expansion Project Presentation
Toronto Pearson Airport - Terminal Expansion Project PresentationToronto Pearson Airport - Terminal Expansion Project Presentation
Toronto Pearson Airport - Terminal Expansion Project PresentationAhmed Mahmoud
 
Mr Bolaji Johnson Paper.pptx
Mr Bolaji Johnson Paper.pptxMr Bolaji Johnson Paper.pptx
Mr Bolaji Johnson Paper.pptxssusercdf134
 
Infrastructure Projects and Construction contracts in ppp
Infrastructure Projects and Construction contracts in pppInfrastructure Projects and Construction contracts in ppp
Infrastructure Projects and Construction contracts in pppChhabiYadav2
 
Fidic contract
Fidic contract Fidic contract
Fidic contract Yash Patel
 
FIDIC Presentation-2016.pdf
FIDIC Presentation-2016.pdfFIDIC Presentation-2016.pdf
FIDIC Presentation-2016.pdfPachyCarmona1
 
Turnkey project
Turnkey projectTurnkey project
Turnkey projectzairanieto
 

Similaire à CIOB Complex Projects Contract 2013 - 25 April 2013 - Transcript of Talk (20)

05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION
 
Construction project delivery methods
Construction project delivery methodsConstruction project delivery methods
Construction project delivery methods
 
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
 
Construction Futures Wales - NEC Contracts Overview Workshop
Construction Futures Wales  - NEC Contracts Overview WorkshopConstruction Futures Wales  - NEC Contracts Overview Workshop
Construction Futures Wales - NEC Contracts Overview Workshop
 
What is NEC 3?, by Dr Jon Broome, 31st March 2015 copyright leadingedgeprojec...
What is NEC 3?, by Dr Jon Broome, 31st March 2015 copyright leadingedgeprojec...What is NEC 3?, by Dr Jon Broome, 31st March 2015 copyright leadingedgeprojec...
What is NEC 3?, by Dr Jon Broome, 31st March 2015 copyright leadingedgeprojec...
 
Muckle LLP - Which contract should I be using?
Muckle LLP - Which contract should I be using?Muckle LLP - Which contract should I be using?
Muckle LLP - Which contract should I be using?
 
17 10 16
17 10 1617 10 16
17 10 16
 
What is NEC3? by Dr Jon Broome, with industry examples by John Rayner, 21st A...
What is NEC3? by Dr Jon Broome, with industry examples by John Rayner, 21st A...What is NEC3? by Dr Jon Broome, with industry examples by John Rayner, 21st A...
What is NEC3? by Dr Jon Broome, with industry examples by John Rayner, 21st A...
 
Introductory Note on International Construction Contracts
Introductory Note on International Construction ContractsIntroductory Note on International Construction Contracts
Introductory Note on International Construction Contracts
 
Building Contracts and CDM regulations
Building Contracts and CDM regulationsBuilding Contracts and CDM regulations
Building Contracts and CDM regulations
 
NEC Interview with Wai-Chi Sing of the HK Development Bureau
NEC Interview with Wai-Chi Sing of the HK Development BureauNEC Interview with Wai-Chi Sing of the HK Development Bureau
NEC Interview with Wai-Chi Sing of the HK Development Bureau
 
Pai 3-03
Pai 3-03Pai 3-03
Pai 3-03
 
PP1 presentation slide.
PP1 presentation slide.PP1 presentation slide.
PP1 presentation slide.
 
Toronto Pearson Airport - Terminal Expansion Project Presentation
Toronto Pearson Airport - Terminal Expansion Project PresentationToronto Pearson Airport - Terminal Expansion Project Presentation
Toronto Pearson Airport - Terminal Expansion Project Presentation
 
Mr Bolaji Johnson Paper.pptx
Mr Bolaji Johnson Paper.pptxMr Bolaji Johnson Paper.pptx
Mr Bolaji Johnson Paper.pptx
 
Practitioner class 3: Contract strategy
Practitioner class 3: Contract strategyPractitioner class 3: Contract strategy
Practitioner class 3: Contract strategy
 
Infrastructure Projects and Construction contracts in ppp
Infrastructure Projects and Construction contracts in pppInfrastructure Projects and Construction contracts in ppp
Infrastructure Projects and Construction contracts in ppp
 
Fidic contract
Fidic contract Fidic contract
Fidic contract
 
FIDIC Presentation-2016.pdf
FIDIC Presentation-2016.pdfFIDIC Presentation-2016.pdf
FIDIC Presentation-2016.pdf
 
Turnkey project
Turnkey projectTurnkey project
Turnkey project
 

Plus de Francis Ho

COP26: Eating for the Planet
COP26: Eating for the PlanetCOP26: Eating for the Planet
COP26: Eating for the PlanetFrancis Ho
 
City of London Law Society - Submittal to BEIS on Statutory Retention Deposit...
City of London Law Society - Submittal to BEIS on Statutory Retention Deposit...City of London Law Society - Submittal to BEIS on Statutory Retention Deposit...
City of London Law Society - Submittal to BEIS on Statutory Retention Deposit...Francis Ho
 
City of London Law Society - Construction Law Committee - Response to Retenti...
City of London Law Society - Construction Law Committee - Response to Retenti...City of London Law Society - Construction Law Committee - Response to Retenti...
City of London Law Society - Construction Law Committee - Response to Retenti...Francis Ho
 
How will Brexit impact on Construction?
How will Brexit impact on Construction?How will Brexit impact on Construction?
How will Brexit impact on Construction?Francis Ho
 
Variations and their Consequences - Olswang Construction Law Masterclass - 5 ...
Variations and their Consequences - Olswang Construction Law Masterclass - 5 ...Variations and their Consequences - Olswang Construction Law Masterclass - 5 ...
Variations and their Consequences - Olswang Construction Law Masterclass - 5 ...Francis Ho
 
Construction Insolvency
Construction InsolvencyConstruction Insolvency
Construction InsolvencyFrancis Ho
 
The Management of Complex Contracts
The Management of Complex ContractsThe Management of Complex Contracts
The Management of Complex ContractsFrancis Ho
 
Key Developments in Emerging Markets
Key Developments in Emerging MarketsKey Developments in Emerging Markets
Key Developments in Emerging MarketsFrancis Ho
 
Using Two-Stage Tendering Effectively
Using Two-Stage Tendering EffectivelyUsing Two-Stage Tendering Effectively
Using Two-Stage Tendering EffectivelyFrancis Ho
 
Managing the Risks of Delay in Construction Projects
Managing the Risks of Delay in Construction ProjectsManaging the Risks of Delay in Construction Projects
Managing the Risks of Delay in Construction ProjectsFrancis Ho
 
It Pays to Be Right: Payment in Construction Contracts
It Pays to Be Right: Payment in Construction ContractsIt Pays to Be Right: Payment in Construction Contracts
It Pays to Be Right: Payment in Construction ContractsFrancis Ho
 
Adjudication: Tips, Traps and Tactics
Adjudication: Tips, Traps and TacticsAdjudication: Tips, Traps and Tactics
Adjudication: Tips, Traps and TacticsFrancis Ho
 
Contractual Options for Procuring Major Projects in the UK
Contractual Options for Procuring Major Projects in the UKContractual Options for Procuring Major Projects in the UK
Contractual Options for Procuring Major Projects in the UKFrancis Ho
 
Works Insurance and Latent Defects Insurance
Works Insurance and Latent Defects InsuranceWorks Insurance and Latent Defects Insurance
Works Insurance and Latent Defects InsuranceFrancis Ho
 
Third Party Rights and Why They Matter
Third Party Rights and Why They MatterThird Party Rights and Why They Matter
Third Party Rights and Why They MatterFrancis Ho
 
A Practical Guide to the Construction (Design and Management) Regulations 2015
A Practical Guide to the Construction (Design and Management) Regulations 2015A Practical Guide to the Construction (Design and Management) Regulations 2015
A Practical Guide to the Construction (Design and Management) Regulations 2015Francis Ho
 
Construction Dispute Resolution and Avoidance in a Boom Market
Construction Dispute Resolution and Avoidance in a Boom MarketConstruction Dispute Resolution and Avoidance in a Boom Market
Construction Dispute Resolution and Avoidance in a Boom MarketFrancis Ho
 
Letters of Intent
Letters of IntentLetters of Intent
Letters of IntentFrancis Ho
 
Collateral Warranties and Third Party Rights
Collateral Warranties and Third Party RightsCollateral Warranties and Third Party Rights
Collateral Warranties and Third Party RightsFrancis Ho
 
Early Dispute Resolution in the Construction Industry
Early Dispute Resolution in the Construction IndustryEarly Dispute Resolution in the Construction Industry
Early Dispute Resolution in the Construction IndustryFrancis Ho
 

Plus de Francis Ho (20)

COP26: Eating for the Planet
COP26: Eating for the PlanetCOP26: Eating for the Planet
COP26: Eating for the Planet
 
City of London Law Society - Submittal to BEIS on Statutory Retention Deposit...
City of London Law Society - Submittal to BEIS on Statutory Retention Deposit...City of London Law Society - Submittal to BEIS on Statutory Retention Deposit...
City of London Law Society - Submittal to BEIS on Statutory Retention Deposit...
 
City of London Law Society - Construction Law Committee - Response to Retenti...
City of London Law Society - Construction Law Committee - Response to Retenti...City of London Law Society - Construction Law Committee - Response to Retenti...
City of London Law Society - Construction Law Committee - Response to Retenti...
 
How will Brexit impact on Construction?
How will Brexit impact on Construction?How will Brexit impact on Construction?
How will Brexit impact on Construction?
 
Variations and their Consequences - Olswang Construction Law Masterclass - 5 ...
Variations and their Consequences - Olswang Construction Law Masterclass - 5 ...Variations and their Consequences - Olswang Construction Law Masterclass - 5 ...
Variations and their Consequences - Olswang Construction Law Masterclass - 5 ...
 
Construction Insolvency
Construction InsolvencyConstruction Insolvency
Construction Insolvency
 
The Management of Complex Contracts
The Management of Complex ContractsThe Management of Complex Contracts
The Management of Complex Contracts
 
Key Developments in Emerging Markets
Key Developments in Emerging MarketsKey Developments in Emerging Markets
Key Developments in Emerging Markets
 
Using Two-Stage Tendering Effectively
Using Two-Stage Tendering EffectivelyUsing Two-Stage Tendering Effectively
Using Two-Stage Tendering Effectively
 
Managing the Risks of Delay in Construction Projects
Managing the Risks of Delay in Construction ProjectsManaging the Risks of Delay in Construction Projects
Managing the Risks of Delay in Construction Projects
 
It Pays to Be Right: Payment in Construction Contracts
It Pays to Be Right: Payment in Construction ContractsIt Pays to Be Right: Payment in Construction Contracts
It Pays to Be Right: Payment in Construction Contracts
 
Adjudication: Tips, Traps and Tactics
Adjudication: Tips, Traps and TacticsAdjudication: Tips, Traps and Tactics
Adjudication: Tips, Traps and Tactics
 
Contractual Options for Procuring Major Projects in the UK
Contractual Options for Procuring Major Projects in the UKContractual Options for Procuring Major Projects in the UK
Contractual Options for Procuring Major Projects in the UK
 
Works Insurance and Latent Defects Insurance
Works Insurance and Latent Defects InsuranceWorks Insurance and Latent Defects Insurance
Works Insurance and Latent Defects Insurance
 
Third Party Rights and Why They Matter
Third Party Rights and Why They MatterThird Party Rights and Why They Matter
Third Party Rights and Why They Matter
 
A Practical Guide to the Construction (Design and Management) Regulations 2015
A Practical Guide to the Construction (Design and Management) Regulations 2015A Practical Guide to the Construction (Design and Management) Regulations 2015
A Practical Guide to the Construction (Design and Management) Regulations 2015
 
Construction Dispute Resolution and Avoidance in a Boom Market
Construction Dispute Resolution and Avoidance in a Boom MarketConstruction Dispute Resolution and Avoidance in a Boom Market
Construction Dispute Resolution and Avoidance in a Boom Market
 
Letters of Intent
Letters of IntentLetters of Intent
Letters of Intent
 
Collateral Warranties and Third Party Rights
Collateral Warranties and Third Party RightsCollateral Warranties and Third Party Rights
Collateral Warranties and Third Party Rights
 
Early Dispute Resolution in the Construction Industry
Early Dispute Resolution in the Construction IndustryEarly Dispute Resolution in the Construction Industry
Early Dispute Resolution in the Construction Industry
 

Dernier

Kohinoor Hinjewadi Phase 2 Pune E-Brochure.pdf
Kohinoor Hinjewadi Phase 2 Pune  E-Brochure.pdfKohinoor Hinjewadi Phase 2 Pune  E-Brochure.pdf
Kohinoor Hinjewadi Phase 2 Pune E-Brochure.pdfManishSaxena95
 
SVN Live 5.6.24 Weekly Property Broadcast
SVN Live 5.6.24 Weekly Property BroadcastSVN Live 5.6.24 Weekly Property Broadcast
SVN Live 5.6.24 Weekly Property BroadcastSVN International Corp.
 
Yedi Mavi TOBB Zeytinburnu - Listing Turkey
Yedi Mavi TOBB Zeytinburnu - Listing TurkeyYedi Mavi TOBB Zeytinburnu - Listing Turkey
Yedi Mavi TOBB Zeytinburnu - Listing TurkeyListing Turkey
 
Shapoorji Pallonji Joyville Vista Pune | Spend Your Family Time Together
Shapoorji Pallonji Joyville Vista Pune | Spend Your Family Time TogetherShapoorji Pallonji Joyville Vista Pune | Spend Your Family Time Together
Shapoorji Pallonji Joyville Vista Pune | Spend Your Family Time Togetheraidasheikh47
 
Enjoy Night ≽ 8448380779 ≼ Call Girls In Huda City Centre (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Huda City Centre (Gurgaon)Enjoy Night ≽ 8448380779 ≼ Call Girls In Huda City Centre (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Huda City Centre (Gurgaon)Delhi Call girls
 
BPTP THE AMAARIO For The Royals Of Tomorrow in Sector 37D Gurgaon Dwarka Expr...
BPTP THE AMAARIO For The Royals Of Tomorrow in Sector 37D Gurgaon Dwarka Expr...BPTP THE AMAARIO For The Royals Of Tomorrow in Sector 37D Gurgaon Dwarka Expr...
BPTP THE AMAARIO For The Royals Of Tomorrow in Sector 37D Gurgaon Dwarka Expr...ApartmentWala1
 
The Gale at Godrej Park World Hinjewadi Pune Brochure.pdf
The Gale at Godrej Park World Hinjewadi Pune Brochure.pdfThe Gale at Godrej Park World Hinjewadi Pune Brochure.pdf
The Gale at Godrej Park World Hinjewadi Pune Brochure.pdfPrachiRudram
 
Call Girls in Karkardooma Delhi +91 84487779280}Woman Seeking Man in Delhi NCR
Call Girls in Karkardooma Delhi +91 84487779280}Woman Seeking Man in Delhi NCRCall Girls in Karkardooma Delhi +91 84487779280}Woman Seeking Man in Delhi NCR
Call Girls in Karkardooma Delhi +91 84487779280}Woman Seeking Man in Delhi NCRasmaqueen5
 
9990771857 Call Girls in Dwarka Sector 6 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 6 Delhi (Call Girls) Delhi9990771857 Call Girls in Dwarka Sector 6 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 6 Delhi (Call Girls) Delhidelhimodel235
 
Kolte Patil Kharadi Pune E Brochure.pdf
Kolte Patil Kharadi Pune E  Brochure.pdfKolte Patil Kharadi Pune E  Brochure.pdf
Kolte Patil Kharadi Pune E Brochure.pdfabbu831446
 
Greater Vancouver Realtors Statistics Package April 2024
Greater Vancouver Realtors Statistics Package April 2024Greater Vancouver Realtors Statistics Package April 2024
Greater Vancouver Realtors Statistics Package April 2024VickyAulakh1
 
9990771857 Call Girls in Dwarka Sector 1 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 1 Delhi (Call Girls) Delhi9990771857 Call Girls in Dwarka Sector 1 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 1 Delhi (Call Girls) Delhidelhimodel235
 
Premium Villa Projects in Sarjapur Road Bengaluru
Premium Villa Projects in Sarjapur Road BengaluruPremium Villa Projects in Sarjapur Road Bengaluru
Premium Villa Projects in Sarjapur Road BengaluruShivaSeo3
 
9990771857 Call Girls Dwarka Sector 8 Delhi (Call Girls ) Delhi
9990771857 Call Girls  Dwarka Sector 8 Delhi (Call Girls ) Delhi9990771857 Call Girls  Dwarka Sector 8 Delhi (Call Girls ) Delhi
9990771857 Call Girls Dwarka Sector 8 Delhi (Call Girls ) Delhidelhimodel235
 
9990771857 Call Girls Dwarka Sector 9 Delhi (Call Girls ) Delhi
9990771857 Call Girls Dwarka Sector 9 Delhi (Call Girls ) Delhi9990771857 Call Girls Dwarka Sector 9 Delhi (Call Girls ) Delhi
9990771857 Call Girls Dwarka Sector 9 Delhi (Call Girls ) Delhidelhimodel235
 
Kohinoor Teiko Hinjewadi Phase 2 Pune E-Brochure.pdf
Kohinoor Teiko Hinjewadi Phase 2 Pune  E-Brochure.pdfKohinoor Teiko Hinjewadi Phase 2 Pune  E-Brochure.pdf
Kohinoor Teiko Hinjewadi Phase 2 Pune E-Brochure.pdfManishSaxena95
 
Acibadem Konaklari Uskudar - Listin Turkey
Acibadem Konaklari Uskudar - Listin TurkeyAcibadem Konaklari Uskudar - Listin Turkey
Acibadem Konaklari Uskudar - Listin TurkeyListing Turkey
 
Bptp The Amaario Launch Luxury Project Sector 37D Gurgaon Dwarka Expressway...
Bptp The Amaario Launch  Luxury Project  Sector 37D Gurgaon Dwarka Expressway...Bptp The Amaario Launch  Luxury Project  Sector 37D Gurgaon Dwarka Expressway...
Bptp The Amaario Launch Luxury Project Sector 37D Gurgaon Dwarka Expressway...ApartmentWala1
 
Prestige Sancoale Goa Residneces Brochure.pdf
Prestige Sancoale Goa Residneces Brochure.pdfPrestige Sancoale Goa Residneces Brochure.pdf
Prestige Sancoale Goa Residneces Brochure.pdfkishor21012022
 

Dernier (20)

Kohinoor Hinjewadi Phase 2 Pune E-Brochure.pdf
Kohinoor Hinjewadi Phase 2 Pune  E-Brochure.pdfKohinoor Hinjewadi Phase 2 Pune  E-Brochure.pdf
Kohinoor Hinjewadi Phase 2 Pune E-Brochure.pdf
 
SVN Live 5.6.24 Weekly Property Broadcast
SVN Live 5.6.24 Weekly Property BroadcastSVN Live 5.6.24 Weekly Property Broadcast
SVN Live 5.6.24 Weekly Property Broadcast
 
Yedi Mavi TOBB Zeytinburnu - Listing Turkey
Yedi Mavi TOBB Zeytinburnu - Listing TurkeyYedi Mavi TOBB Zeytinburnu - Listing Turkey
Yedi Mavi TOBB Zeytinburnu - Listing Turkey
 
Shapoorji Pallonji Joyville Vista Pune | Spend Your Family Time Together
Shapoorji Pallonji Joyville Vista Pune | Spend Your Family Time TogetherShapoorji Pallonji Joyville Vista Pune | Spend Your Family Time Together
Shapoorji Pallonji Joyville Vista Pune | Spend Your Family Time Together
 
Retail Center For Sale - 1019 River St., Belleville, WI
Retail Center For Sale - 1019 River St., Belleville, WIRetail Center For Sale - 1019 River St., Belleville, WI
Retail Center For Sale - 1019 River St., Belleville, WI
 
Enjoy Night ≽ 8448380779 ≼ Call Girls In Huda City Centre (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Huda City Centre (Gurgaon)Enjoy Night ≽ 8448380779 ≼ Call Girls In Huda City Centre (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Huda City Centre (Gurgaon)
 
BPTP THE AMAARIO For The Royals Of Tomorrow in Sector 37D Gurgaon Dwarka Expr...
BPTP THE AMAARIO For The Royals Of Tomorrow in Sector 37D Gurgaon Dwarka Expr...BPTP THE AMAARIO For The Royals Of Tomorrow in Sector 37D Gurgaon Dwarka Expr...
BPTP THE AMAARIO For The Royals Of Tomorrow in Sector 37D Gurgaon Dwarka Expr...
 
The Gale at Godrej Park World Hinjewadi Pune Brochure.pdf
The Gale at Godrej Park World Hinjewadi Pune Brochure.pdfThe Gale at Godrej Park World Hinjewadi Pune Brochure.pdf
The Gale at Godrej Park World Hinjewadi Pune Brochure.pdf
 
Call Girls in Karkardooma Delhi +91 84487779280}Woman Seeking Man in Delhi NCR
Call Girls in Karkardooma Delhi +91 84487779280}Woman Seeking Man in Delhi NCRCall Girls in Karkardooma Delhi +91 84487779280}Woman Seeking Man in Delhi NCR
Call Girls in Karkardooma Delhi +91 84487779280}Woman Seeking Man in Delhi NCR
 
9990771857 Call Girls in Dwarka Sector 6 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 6 Delhi (Call Girls) Delhi9990771857 Call Girls in Dwarka Sector 6 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 6 Delhi (Call Girls) Delhi
 
Kolte Patil Kharadi Pune E Brochure.pdf
Kolte Patil Kharadi Pune E  Brochure.pdfKolte Patil Kharadi Pune E  Brochure.pdf
Kolte Patil Kharadi Pune E Brochure.pdf
 
Greater Vancouver Realtors Statistics Package April 2024
Greater Vancouver Realtors Statistics Package April 2024Greater Vancouver Realtors Statistics Package April 2024
Greater Vancouver Realtors Statistics Package April 2024
 
9990771857 Call Girls in Dwarka Sector 1 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 1 Delhi (Call Girls) Delhi9990771857 Call Girls in Dwarka Sector 1 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 1 Delhi (Call Girls) Delhi
 
Premium Villa Projects in Sarjapur Road Bengaluru
Premium Villa Projects in Sarjapur Road BengaluruPremium Villa Projects in Sarjapur Road Bengaluru
Premium Villa Projects in Sarjapur Road Bengaluru
 
9990771857 Call Girls Dwarka Sector 8 Delhi (Call Girls ) Delhi
9990771857 Call Girls  Dwarka Sector 8 Delhi (Call Girls ) Delhi9990771857 Call Girls  Dwarka Sector 8 Delhi (Call Girls ) Delhi
9990771857 Call Girls Dwarka Sector 8 Delhi (Call Girls ) Delhi
 
9990771857 Call Girls Dwarka Sector 9 Delhi (Call Girls ) Delhi
9990771857 Call Girls Dwarka Sector 9 Delhi (Call Girls ) Delhi9990771857 Call Girls Dwarka Sector 9 Delhi (Call Girls ) Delhi
9990771857 Call Girls Dwarka Sector 9 Delhi (Call Girls ) Delhi
 
Kohinoor Teiko Hinjewadi Phase 2 Pune E-Brochure.pdf
Kohinoor Teiko Hinjewadi Phase 2 Pune  E-Brochure.pdfKohinoor Teiko Hinjewadi Phase 2 Pune  E-Brochure.pdf
Kohinoor Teiko Hinjewadi Phase 2 Pune E-Brochure.pdf
 
Acibadem Konaklari Uskudar - Listin Turkey
Acibadem Konaklari Uskudar - Listin TurkeyAcibadem Konaklari Uskudar - Listin Turkey
Acibadem Konaklari Uskudar - Listin Turkey
 
Bptp The Amaario Launch Luxury Project Sector 37D Gurgaon Dwarka Expressway...
Bptp The Amaario Launch  Luxury Project  Sector 37D Gurgaon Dwarka Expressway...Bptp The Amaario Launch  Luxury Project  Sector 37D Gurgaon Dwarka Expressway...
Bptp The Amaario Launch Luxury Project Sector 37D Gurgaon Dwarka Expressway...
 
Prestige Sancoale Goa Residneces Brochure.pdf
Prestige Sancoale Goa Residneces Brochure.pdfPrestige Sancoale Goa Residneces Brochure.pdf
Prestige Sancoale Goa Residneces Brochure.pdf
 

CIOB Complex Projects Contract 2013 - 25 April 2013 - Transcript of Talk

  • 1. Transcript 15364159-1 1 Francis Ho –April 2013 INTRODUCTION TO THE CIOB COMPLEX PROJECTS CONTRACT 2013 PROJECT SUITABILITY AND PROCUREMENT STRATEGY The following is a loose transcript of a talk given in London on 25 April 2013 at the launch of the Chartered Institute of Building’s Complex Projects Contract 2013 by one of its authors. BACKGROUND · “Guide to Good Practice in the Management of Time in Complex Projects”published by CIOB in 2010 following detailed 2007 research into complex projects. · The Complex Projects Contract 2013 (CPC) is designed for complex projects and built upon foundations of 2010 Guide. Not suited to simple projects. · A “simple project”typically has all of following characteristics: o Repetitive work; o Fewer than 5 storeys; o One completion date, no phasing; o Straightforward utilities; o Single contractor; o Less than 9 month build period; o Fewer than 10 sub-contracts. · A complex project typically has any or more of the following characteristics: o Incomplete design; o More than 5 storeys; o Below ground accommodation; o Multiple sections and possessions; o Civil engineering; o Multiple contractors and sub-contractors. · Simple projects can be managed intuitively; have high chance of finishing on time using such traditional management techniques (finding of the 2007 research). · Examples of complex projects: airports, O&G projects, railway stations, high-rise buildings, engineering, power stations. Extremely likely to be late using traditional time management techniques.
  • 2. 15364159-1 2 Francis Ho –April 2013 · Added expense in using a contract written and intended for complex projects, which mean that the benefits will not be so evident on a simpler, low value project. Investment time needed for participants to understand the contract (e.g. understanding the 2010 Guide), workshops for the project team and upskilling main participants and advisers, completing the CPC’s Appendices and client involvement. · Since CPC envisages that it is sensible the client be actively involved throughout the project, it is not for novice employers. TO MANAGE COMPLEX PROJECTS, NEED TO CHANGE WAY OF THINKING · Need regularly updated contractual programme with quality controls so the information is useful at the time given. · Need “Project Time Manager”to advise independently on time management procedures and compliance. · Need a programme which is a dynamic management tool in three different levels of detail so programme not simply tool in disputes. · Need a 21 st century contract specifically written for complex projects. WHAT DOES CPC DO DIFFERENTLY? · A single contract form does it all. · Turnkey (EPC), traditional, design and build. With amendment CPC can even be used for EPCM, with Contract Administrator as EPCM Manager and CPC used as basis of trade contracts. · The Contractor’s Pricing Document allows for cost reimbursable or lump sum pricing. · As well as use in England and Wales (and the rest of the UK), it is suitable to be used internationally (with provisions catering for mandatory local law and governing law being specified by CPC’s Contract Agreement). · Provisions for bonds, parent company guarantees and collateral warranties/direct agreements. · Risk register. · Professional skill and care in design. · Either party may assign contractual rights and benefits by way of security. · Special Conditions recognise and cater for the fact that all complex projects have different requirements.
  • 3. 15364159-1 3 Francis Ho –April 2013 · Bespoke testing and commissioning provisions can be included seamlessly. WHAT IS UNIQUE TO CPC? · Time management procedures, detailed progress records, role of Project Time Manager. · Provisions for Common Data Environment, Building Information Modelling (UK Level 2, with suggested Levels of Development). · Defines the key terms of “Concurrency”, “Free Float”and “Total Float”so these are clearly understood. · Confidentiality obligations on Employer for Contactor’s rates and prices (if marked as confidential). · By default, if the Employer provides information on site conditions to Contractor, Contractor may rely on it. · Termination for convenience by Employer. · Employer has to provide evidence if reasonably required that it has the means to pay the Predicted Cost, otherwise Contractor can suspend carrying out of the works. INTERNATIONAL USAGE, NOT JUST FOR THE UNITED KINGDOM · Adjudication applies where mandatory under the governing law, optional otherwise. Compliant with England’s Scheme for Construction Contracts. Arbitration is the final, binding dispute resolution procedure. · Can be used with English law as governing law, with mandatory provisions of local law being taken into account. References to local legislation or trade union recommended minimum wages, visas and work permits. · Can also be used under a different governing law. · Minimum standards of site safety and welfare, e.g. Contractor’s safety manager, minimum medical and first facilities on site – which may be beneficial when contracting in particular territories. · Provisions for paying in different currencies. · Anti-corruption provisions apply to both parties. · Special Conditions act as modifiers to the General Conditions. Francis Ho, Olswang LLP francis.ho@olswang.com