Cost and Schedule Integration:              
                      g
      An Industry Update
      2nd Annual Acumen Summit
        September 18‐19, 2012
              Hotel ZaZa
              Hotel ZaZa
             Houston, TX
Outline
•   Speaker Introductions
•   Government  Contracting Perspective
    Government Contracting Perspective
•   Commercial Contracting Update
•   Conclusion 




                                          2
Introductions
• Michael R. Nosbisch, CCC, PSP
   – PT&C Vice President and EVMS Practice Lead
      • Personally brokered partnership with Acumen in 2011
   – 2011‐2012 AACE International President
• Glen B. Alleman
   – PT&C, Program Performance Management
   –M b
     Member of NDIA Risk and Opportunity Board  
              f NDIA Ri k d O     t it B d




                                                              3
DI‐MGMT‐81861 states clearly that …




1.2.1 Integrate cost and schedule performance data with
       objective technical measures of performance.
                                                          4
Government Contracting Perspective




                                     5
Start with the end in mind …


              Risk         Cost


    IMP/IMS          PMB          SOW


              WBS          TPM


                                        6
The 100,000 foot view of what is new …




                    OSD EVM Data Requirements Integrated Program Management
                    Report (IPMR) Data Item Description (DID) & Work Breakdown
                    Structures (WBS) NDIA, PMSC meeting, August 15, 2012

                                                                                 7
How can we measure performance?




                                  8
Integrated CPR, IMS, CSFR
Format 1 – WBS
Format 2 –
Format 2 OBS
Format 3 – Baseline
Format 4 –
Format 4 Staffing
Format 5 – Explanations 
and Problem Analysis
and Problem Analysis
Format 6 – IMS
Format 7 – Hi t
F     t 7 History and 
                     d
Forecast
                            9
One Big Hitter – Variance Analysis
• Formal variances are limited to a total of 15 WBS Elements.
• Two methods allowed for determining which variances are 
  addressed
       – Top 15 WBS Elements approach
       – Allows for Government selection approach or a defined 
         contractor process that covers all aspects (current, cumulative 
                    p                         p     (       ,
         and at‐complete)
• Allows contractor or government to temporarily increase the 
  number of reported variances to cover emerging tread(s)
               p                             g g       ()
• Linked Formats 1–4 and 6 discussions to Format 5
       – Significant Format 6 changes.  Require SRA, Health Assessment 
         and drivers as applicable
         and drivers as applicable
• Reconcile Best/Worst/Most Likely EAC
Integrated Program Management Report (IPMR) DID Training, 31 July 2012, Robert Loop, NAVY CEVM.
                                                                                                  10
The IMS has one new format …
• The Integrated Master Schedule (IMS) had been a 
  separate deliverable with its own DID
       – Now merged with the CPR as Format 6 in the IPMR
       – IMS analysis requirements will be submitted as part of Format 5
• Added significant language to eliminate most needs for 
  statement of work clarification
       – Defined minimum level of subcontractor integration
       – Reached agreement on the definition of Schedule Margin and 
         Schedule Visibility Tasks (SVTs)
       – Required disclosing of justification for Leads Lags and most
         Required disclosing of justification for Leads, Lags and most 
         Constraints
       – Defined minimum fields
       – Expanded when SRA is required and how it is reported
           p                        q                      p


Integrated Program Management Report (IPMR) DID Training, 31 July 2012, Robert Loop, NAVY CEVM.
                                                                                                  11
Format 6
• Consistency with Format 1 Addressed
       – Included “The WBS numbering system in the IMS must be 
         consistent with the Format 1 structure.”
• Schedule Margin 
       – Allowed before program events. §3.7.2.4.
• Critical & Driving Paths
  Critical & Driving Paths 
       – Included  definition that tasks with “0” or negative total 
         float are not by default the critical path §3.7.1.3.5.9.
       – Driving path and interim milestones defined (not in 2005
         Driving path and interim milestones defined (not in 2005 
         IMS DID) §3.7.1.3.5.8.
       – Excessive constraints and incomplete, incorrect, or overly 
                                              §
         constrained logic shall be avoided.§3.7.1.3.5.9.
                        g

Integrated Program Management Report (IPMR) DID Training, 31 July 2012, Robert Loop, NAVY CEVM.
                                                                                                  12
Format 6 (cont’d)
• Relationships & Float 
       – All non‐constrained discrete tasks/activities/milestones 
         shall have at least one predecessor and successor, except 
                                 p                               p
         the start and end of the program or interim delivery
• Subcontractor Integration
       – Subcontractor discrete work shall be incorporated as tasks 
                                                    p
         within the prime IMS at a level necessary for a realistic 
         critical path
• Calendars
       – The IMS shall contain all calendars that define working and 
         nonworking time periods or other information that may 
         impact the schedule


Integrated Program Management Report (IPMR) DID Training, 31 July 2012, Robert Loop, NAVY CEVM.
                                                                                                  13
New Format 7
• New requirement not in CPR DID, but similar 
  information was previously required by the EVM 
  Central Repository (called historical file)
  Central Repository (called historical file)
• Time phased BCWS, BCWP, ACWP, ETC from contract 
  award to completion as applicable
• Must reconcile with Format 1 BAC and EAC for the 
  month submitted
• Due as a minimum annually at the same time as
  Due as a minimum annually, at the same time as 
  other Formats.  Recommend quarterly according to 
  the government fiscal calendar.  
• Purpose to support Government planning cycle 
Integrated Program Management Report (IPMR) DID Training, 31 July 2012, Robert Loop, NAVY CEVM.
                                                                                                  14
Commercial Contracting Perspective




                                     15
Commercial Contracting Perspective
•   General Observations
•   The Contractors Side
    The Contractors’ Side
•   The Owners’ Side 
•   Recommended Practice(s) 




                                     16
General Observations
• Commercial contracting environment much more 
  reliant on FFP/FUP contract types for large projects
   – Cost and performance risk “transferred” from owners to 
     contractors
   – Nuances will exist between different project delivery 
                                          p j            y
     methods 
• Schedules usually integrated with cost only when 
  contractually required as basis for pay applications 
            ll      i d b i f                li i
   – Formalizes requirement to perform monthly updates
   – Often times leads to secondary “field schedule”
     Often times leads to secondary  field schedule


                                                               17
The Contractors’ Side
• Parsons Corporation
  – A current Acumen customer
  –BBegan as engineering‐specific, now full scope design‐
                 i    i      ifi       f ll       d i
    build/EPC contractor
     • Specializes in first of a kind, one of a kind projects
  – Three primary business units
     • Parsons Government Services (formerly PI&T)
     • Parsons Environment & Infrastructure
       Parsons Environment & Infrastructure
         – Commercial Technology
         – Water & Infrastructure
     • Transportation Group
       Transportation Group 


                                                                18
The Contractors’ Side
• Summary of Parsons Requirements
  1. Hierarchical Work Breakdown Structure (WBS) and 
     WBS Dictionary
     • Unique WBS numbers assigned to the lowest level elements 
       of the WBS
     • One responsible individual for each WBS element (one 
       person can manage multiple WBS elements)
  2. Metrics identified for consistently establishing 
  2 Metrics identified for consistently establishing
     physical progress
     • Budgets match the structure and detail of the metrics used 
       for physical progress
       f    h i l


                                                                     19
The Contractors’ Side
• Summary of Parsons Requirements (cont’d)
   3. Logic‐based schedules that identify the sequence of work 
      and significant task relationships
        d i ifi t t k l ti hi
      • WBS reflected within schedule so that activities can be 
        associated with specific control accounts
   4. Time‐phased budget baselines (i.e. overlay or budget‐load 
      the schedule)
      • Both cost and revenue required to generate cash flow curve 
                                    q         g
        for large projects during proposal review
      • Level‐of‐effort activities are identified and isolated in a 
        separate control account


                                                                       20
The Contractors’ Side
• Summary of Parsons Requirements (cont’d)
  5. Baseline plan is controlled 
     • Prevent unauthorized changes
     • Ensure that authorized changes are immediately 
       incorporated
            p
  6. Monthly or more frequent comparison of progress 
     and costs to the baselines  
     • C l l i
       Calculation of cost and schedule variances and indexes, with 
                    f        d h d l       i         di d       ih
       explanations provided for significant variances  
     • Corrective actions implemented as appropriate



                                                                       21
The Owners’ Side
• Orange County Sanitation District
   – Responsible for safely collecting, treating and disposing the 
     wastewater generated by 2.5 million people living in a 479‐
     wastewater generated by 2 5 million people living in a 479
     square‐mile area of central and northwest Orange County (CA)
   – Ongoing Capital Improvements Program comprised of multiple 
     rehabilitation and expansion projects totaling app. $3 billion
     rehabilitation and expansion projects totaling app $3 billion
       • Most projects are FFP, design‐bid‐build
• OCSD Scheduling Specification Review
   – Submittal/acceptance of baseline schedule 
      • Required for full payment of mobilization line item 
      • $300K or 10% of line item
        $


                                                                      22
The Owners’ Side
• OCSD Scheduling Specification Review (cont’d)
   – Cost loading of activities
      • Required on all discrete work activities
        Required on all discrete work activities
            – Not procurement and submittal preparation/review (except for 
              baseline schedule) 
       • Cost loading should be equal to value of contract price (revenue)
         Cost loading should be equal to value of contract price (revenue)
            – Not required to be integrated with resource loading (crew‐
              based) 
            – Overhead/profit prorated and added to each activity
              Overhead/profit prorated and added to each activity
            – Cost (revenue) curve required as separate submittal
            – Schedule updates used as basis for progress payments, but not 
                        y
              exclusively



                                                                               23
Recommended Practice(s)
• Contractors’ Side
   – If internal decision is made to cost load schedule, should be 
     performed at summary (control account) level only
     performed at summary (control account) level only
       • Should not be integrated with resource loading to allow for more 
         flexibility
   – In addition to initial cash flow curve generated by cost loaded
     In addition to initial cash flow curve generated by cost loaded 
     schedule, “earned value” curves should be developed
       • Based on what has been approved (“earned revenue”) for monthly 
         progress payment
         progress payment
       • Facilitates trend for how much work is required on monthly basis to 
         complete in accordance with forecasted date in CPM schedule   




                                                                                24
Recommended Practice(s)
• Owners’ Side
  – Specifying cost (revenue) loading  as basis of progress 
    payments helps to ensure timely schedule updates
     • Should also specify that each discrete activity be subdivided 
       into “substantial completion” and “final completion” to 
                             p                       p
       prevent widespread out‐of‐sequence progress
     • Should allow for overhead/profit to be loaded outside of 
       discrete activities
         – Also, should be loaded in activity with fixed duration equal to 
           contractual PoP (not hammocked over entire schedule)
         – Will allow contractor to recover overhead/profit as originally 
           planned, lessening cash flow impact of delays/claims   


                                                                              25
Conclusion and Questions

• mike.nosbisch@ptcinc.com
• glen.alleman@niwotridge.com
   l    ll    @ i    id




                                26

Contenu connexe

Tendances

Thomas.coonce
Thomas.coonceThomas.coonce
Thomas.coonceNASAPMC
 
Woods.edwards.pm challenge bpr presentation 2012 v1
Woods.edwards.pm challenge bpr presentation 2012 v1Woods.edwards.pm challenge bpr presentation 2012 v1
Woods.edwards.pm challenge bpr presentation 2012 v1NASAPMC
 
Gary.humphreys
Gary.humphreysGary.humphreys
Gary.humphreysNASAPMC
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeffNASAPMC
 
Vanessa.jeff
Vanessa.jeffVanessa.jeff
Vanessa.jeffNASAPMC
 
William.miller.pmc2010
William.miller.pmc2010William.miller.pmc2010
William.miller.pmc2010NASAPMC
 
Thomas.a.greathouse.r
Thomas.a.greathouse.rThomas.a.greathouse.r
Thomas.a.greathouse.rNASAPMC
 
Vladi Fin09 Expert Guide How To Migrate From Bi Ip To Bpc
Vladi Fin09 Expert Guide How To Migrate From Bi Ip To BpcVladi Fin09 Expert Guide How To Migrate From Bi Ip To Bpc
Vladi Fin09 Expert Guide How To Migrate From Bi Ip To BpcLAZAR Consultants LLC
 
2012 04-19 governance valuation
2012 04-19 governance valuation2012 04-19 governance valuation
2012 04-19 governance valuationFreeBalance
 
Ed mangopanelpm challengefinal
Ed mangopanelpm challengefinalEd mangopanelpm challengefinal
Ed mangopanelpm challengefinalNASAPMC
 
Glenn.counts
Glenn.countsGlenn.counts
Glenn.countsNASAPMC
 
Weaver.ed
Weaver.edWeaver.ed
Weaver.edNASAPMC
 
Mahmood porter
Mahmood porterMahmood porter
Mahmood porterNASAPMC
 
Randall.taylor
Randall.taylorRandall.taylor
Randall.taylorNASAPMC
 
Sandra smalley
Sandra smalleySandra smalley
Sandra smalleyNASAPMC
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski johnNASAPMC
 
Simon.dekker.vance kotrla
Simon.dekker.vance kotrlaSimon.dekker.vance kotrla
Simon.dekker.vance kotrlaNASAPMC
 
Ken poole
Ken pooleKen poole
Ken pooleNASAPMC
 
Murphy.dar jean.jean
Murphy.dar jean.jeanMurphy.dar jean.jean
Murphy.dar jean.jeanNASAPMC
 
Chambers.calvin
Chambers.calvinChambers.calvin
Chambers.calvinNASAPMC
 

Tendances (20)

Thomas.coonce
Thomas.coonceThomas.coonce
Thomas.coonce
 
Woods.edwards.pm challenge bpr presentation 2012 v1
Woods.edwards.pm challenge bpr presentation 2012 v1Woods.edwards.pm challenge bpr presentation 2012 v1
Woods.edwards.pm challenge bpr presentation 2012 v1
 
Gary.humphreys
Gary.humphreysGary.humphreys
Gary.humphreys
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeff
 
Vanessa.jeff
Vanessa.jeffVanessa.jeff
Vanessa.jeff
 
William.miller.pmc2010
William.miller.pmc2010William.miller.pmc2010
William.miller.pmc2010
 
Thomas.a.greathouse.r
Thomas.a.greathouse.rThomas.a.greathouse.r
Thomas.a.greathouse.r
 
Vladi Fin09 Expert Guide How To Migrate From Bi Ip To Bpc
Vladi Fin09 Expert Guide How To Migrate From Bi Ip To BpcVladi Fin09 Expert Guide How To Migrate From Bi Ip To Bpc
Vladi Fin09 Expert Guide How To Migrate From Bi Ip To Bpc
 
2012 04-19 governance valuation
2012 04-19 governance valuation2012 04-19 governance valuation
2012 04-19 governance valuation
 
Ed mangopanelpm challengefinal
Ed mangopanelpm challengefinalEd mangopanelpm challengefinal
Ed mangopanelpm challengefinal
 
Glenn.counts
Glenn.countsGlenn.counts
Glenn.counts
 
Weaver.ed
Weaver.edWeaver.ed
Weaver.ed
 
Mahmood porter
Mahmood porterMahmood porter
Mahmood porter
 
Randall.taylor
Randall.taylorRandall.taylor
Randall.taylor
 
Sandra smalley
Sandra smalleySandra smalley
Sandra smalley
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski john
 
Simon.dekker.vance kotrla
Simon.dekker.vance kotrlaSimon.dekker.vance kotrla
Simon.dekker.vance kotrla
 
Ken poole
Ken pooleKen poole
Ken poole
 
Murphy.dar jean.jean
Murphy.dar jean.jeanMurphy.dar jean.jean
Murphy.dar jean.jean
 
Chambers.calvin
Chambers.calvinChambers.calvin
Chambers.calvin
 

Similaire à Acumen presentation (final)

Implementation review eppm p6 8.2 at a major utility - Oracle Primavera P6 Co...
Implementation review eppm p6 8.2 at a major utility - Oracle Primavera P6 Co...Implementation review eppm p6 8.2 at a major utility - Oracle Primavera P6 Co...
Implementation review eppm p6 8.2 at a major utility - Oracle Primavera P6 Co...p6academy
 
Best Practices: Implement Massive SCM Projects
Best Practices: Implement Massive SCM ProjectsBest Practices: Implement Massive SCM Projects
Best Practices: Implement Massive SCM ProjectsARC Advisory Group
 
Pollitt.julie
Pollitt.juliePollitt.julie
Pollitt.julieNASAPMC
 
Essential program management views
Essential program management viewsEssential program management views
Essential program management viewsGlen Alleman
 
Key Career Primary Responsiblities
Key Career Primary ResponsiblitiesKey Career Primary Responsiblities
Key Career Primary Responsiblitiesmsrslide
 
Mitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueMitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueChris Carson
 
Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueChris Carson
 
Integrated Agile Software Development with Earned Value Management
Integrated Agile Software Development with Earned Value ManagementIntegrated Agile Software Development with Earned Value Management
Integrated Agile Software Development with Earned Value ManagementGlen Alleman
 
Thomas.coonce
Thomas.coonceThomas.coonce
Thomas.coonceNASAPMC
 
Building a Credible Performance Measurement Baseline in Two Days
Building a Credible Performance Measurement Baseline in Two DaysBuilding a Credible Performance Measurement Baseline in Two Days
Building a Credible Performance Measurement Baseline in Two DaysGlen Alleman
 
Guidelines for field development plan
Guidelines for field development planGuidelines for field development plan
Guidelines for field development planGiuseppe Moricca
 
WBS Compliance Challenges for Agile ERP Projects
WBS Compliance Challenges for Agile ERP ProjectsWBS Compliance Challenges for Agile ERP Projects
WBS Compliance Challenges for Agile ERP ProjectsGlen Alleman
 
Day1 sp3 icgfm may 2014-phil_sinnett_en
Day1 sp3 icgfm may 2014-phil_sinnett_enDay1 sp3 icgfm may 2014-phil_sinnett_en
Day1 sp3 icgfm may 2014-phil_sinnett_enicgfmconference
 
Professional Profile - Robyn Varley 2016 Feb v1 0
Professional Profile - Robyn Varley 2016 Feb v1 0Professional Profile - Robyn Varley 2016 Feb v1 0
Professional Profile - Robyn Varley 2016 Feb v1 0Robyn Varley
 
FINGRC2015_Enaganti_Arunachalam_Casestudyinsightsinto
FINGRC2015_Enaganti_Arunachalam_CasestudyinsightsintoFINGRC2015_Enaganti_Arunachalam_Casestudyinsightsinto
FINGRC2015_Enaganti_Arunachalam_CasestudyinsightsintoVish Arunachalam
 
NRB Sap Day 03/10/2019 - Wbfin What An Exciting Challenge - Sophie Algoet - C...
NRB Sap Day 03/10/2019 - Wbfin What An Exciting Challenge - Sophie Algoet - C...NRB Sap Day 03/10/2019 - Wbfin What An Exciting Challenge - Sophie Algoet - C...
NRB Sap Day 03/10/2019 - Wbfin What An Exciting Challenge - Sophie Algoet - C...NRB
 

Similaire à Acumen presentation (final) (20)

Implementation review eppm p6 8.2 at a major utility - Oracle Primavera P6 Co...
Implementation review eppm p6 8.2 at a major utility - Oracle Primavera P6 Co...Implementation review eppm p6 8.2 at a major utility - Oracle Primavera P6 Co...
Implementation review eppm p6 8.2 at a major utility - Oracle Primavera P6 Co...
 
Best Practices: Implement Massive SCM Projects
Best Practices: Implement Massive SCM ProjectsBest Practices: Implement Massive SCM Projects
Best Practices: Implement Massive SCM Projects
 
Pollitt.julie
Pollitt.juliePollitt.julie
Pollitt.julie
 
Essential program management views
Essential program management viewsEssential program management views
Essential program management views
 
Key Career Primary Responsiblities
Key Career Primary ResponsiblitiesKey Career Primary Responsiblities
Key Career Primary Responsiblities
 
Mitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueMitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned Value
 
Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned Value
 
Integrated Agile Software Development with Earned Value Management
Integrated Agile Software Development with Earned Value ManagementIntegrated Agile Software Development with Earned Value Management
Integrated Agile Software Development with Earned Value Management
 
Thomas.coonce
Thomas.coonceThomas.coonce
Thomas.coonce
 
Contracting Best Practices - MESC 2014
Contracting Best Practices - MESC 2014Contracting Best Practices - MESC 2014
Contracting Best Practices - MESC 2014
 
Building a Credible Performance Measurement Baseline in Two Days
Building a Credible Performance Measurement Baseline in Two DaysBuilding a Credible Performance Measurement Baseline in Two Days
Building a Credible Performance Measurement Baseline in Two Days
 
Guidelines for field development plan
Guidelines for field development planGuidelines for field development plan
Guidelines for field development plan
 
Managing Project Success
Managing Project SuccessManaging Project Success
Managing Project Success
 
WBS Compliance Challenges for Agile ERP Projects
WBS Compliance Challenges for Agile ERP ProjectsWBS Compliance Challenges for Agile ERP Projects
WBS Compliance Challenges for Agile ERP Projects
 
Day1 sp3 icgfm may 2014-phil_sinnett_en
Day1 sp3 icgfm may 2014-phil_sinnett_enDay1 sp3 icgfm may 2014-phil_sinnett_en
Day1 sp3 icgfm may 2014-phil_sinnett_en
 
3.3 project fiche
3.3 project fiche3.3 project fiche
3.3 project fiche
 
Professional Profile - Robyn Varley 2016 Feb v1 0
Professional Profile - Robyn Varley 2016 Feb v1 0Professional Profile - Robyn Varley 2016 Feb v1 0
Professional Profile - Robyn Varley 2016 Feb v1 0
 
FINGRC2015_Enaganti_Arunachalam_Casestudyinsightsinto
FINGRC2015_Enaganti_Arunachalam_CasestudyinsightsintoFINGRC2015_Enaganti_Arunachalam_Casestudyinsightsinto
FINGRC2015_Enaganti_Arunachalam_Casestudyinsightsinto
 
NRB Sap Day 03/10/2019 - Wbfin What An Exciting Challenge - Sophie Algoet - C...
NRB Sap Day 03/10/2019 - Wbfin What An Exciting Challenge - Sophie Algoet - C...NRB Sap Day 03/10/2019 - Wbfin What An Exciting Challenge - Sophie Algoet - C...
NRB Sap Day 03/10/2019 - Wbfin What An Exciting Challenge - Sophie Algoet - C...
 
ATCO-BaasKaar Roadmap to SAP Quality Award 2014
ATCO-BaasKaar Roadmap to SAP Quality Award 2014ATCO-BaasKaar Roadmap to SAP Quality Award 2014
ATCO-BaasKaar Roadmap to SAP Quality Award 2014
 

Plus de Glen Alleman

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planningGlen Alleman
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSGlen Alleman
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project SuccessGlen Alleman
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMGlen Alleman
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk managementGlen Alleman
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk ManagementGlen Alleman
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Glen Alleman
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringGlen Alleman
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideGlen Alleman
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineGlen Alleman
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Glen Alleman
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by StepGlen Alleman
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)Glen Alleman
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possibleGlen Alleman
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic AbundanceGlen Alleman
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planningGlen Alleman
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for AgileGlen Alleman
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement BaselineGlen Alleman
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaGlen Alleman
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure RolloutGlen Alleman
 

Plus de Glen Alleman (20)

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planning
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMS
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project Success
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPM
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk management
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk Management
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems Engineering
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guide
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by Step
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possible
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic Abundance
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planning
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for Agile
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement Baseline
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six Sigma
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure Rollout
 

Dernier

Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)wesley chun
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking MenDelhi Call girls
 
Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsJoaquim Jorge
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...Neo4j
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘RTylerCroy
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfEnterprise Knowledge
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreternaman860154
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking MenDelhi Call girls
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)Gabriella Davis
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsMaria Levchenko
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Igalia
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking MenDelhi Call girls
 
Evaluating the top large language models.pdf
Evaluating the top large language models.pdfEvaluating the top large language models.pdf
Evaluating the top large language models.pdfChristopherTHyatt
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationMichael W. Hawkins
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Miguel Araújo
 
Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Enterprise Knowledge
 
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemkeProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemkeProduct Anonymous
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationRadu Cotescu
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slidevu2urc
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking MenDelhi Call girls
 

Dernier (20)

Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
 
Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and Myths
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreter
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed texts
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
 
Evaluating the top large language models.pdf
Evaluating the top large language models.pdfEvaluating the top large language models.pdf
Evaluating the top large language models.pdf
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day Presentation
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
 
Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...
 
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemkeProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organization
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slide
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men
 

Acumen presentation (final)

  • 1. Cost and Schedule Integration:               g An Industry Update 2nd Annual Acumen Summit September 18‐19, 2012 Hotel ZaZa Hotel ZaZa Houston, TX
  • 2. Outline • Speaker Introductions • Government  Contracting Perspective Government Contracting Perspective • Commercial Contracting Update • Conclusion  2
  • 3. Introductions • Michael R. Nosbisch, CCC, PSP – PT&C Vice President and EVMS Practice Lead • Personally brokered partnership with Acumen in 2011 – 2011‐2012 AACE International President • Glen B. Alleman – PT&C, Program Performance Management –M b Member of NDIA Risk and Opportunity Board   f NDIA Ri k d O t it B d 3
  • 4. DI‐MGMT‐81861 states clearly that … 1.2.1 Integrate cost and schedule performance data with objective technical measures of performance. 4
  • 6. Start with the end in mind … Risk Cost IMP/IMS PMB SOW WBS TPM 6
  • 7. The 100,000 foot view of what is new … OSD EVM Data Requirements Integrated Program Management Report (IPMR) Data Item Description (DID) & Work Breakdown Structures (WBS) NDIA, PMSC meeting, August 15, 2012 7
  • 9. Integrated CPR, IMS, CSFR Format 1 – WBS Format 2 – Format 2 OBS Format 3 – Baseline Format 4 – Format 4 Staffing Format 5 – Explanations  and Problem Analysis and Problem Analysis Format 6 – IMS Format 7 – Hi t F t 7 History and  d Forecast 9
  • 10. One Big Hitter – Variance Analysis • Formal variances are limited to a total of 15 WBS Elements. • Two methods allowed for determining which variances are  addressed – Top 15 WBS Elements approach – Allows for Government selection approach or a defined  contractor process that covers all aspects (current, cumulative  p p ( , and at‐complete) • Allows contractor or government to temporarily increase the  number of reported variances to cover emerging tread(s) p g g () • Linked Formats 1–4 and 6 discussions to Format 5 – Significant Format 6 changes.  Require SRA, Health Assessment  and drivers as applicable and drivers as applicable • Reconcile Best/Worst/Most Likely EAC Integrated Program Management Report (IPMR) DID Training, 31 July 2012, Robert Loop, NAVY CEVM. 10
  • 11. The IMS has one new format … • The Integrated Master Schedule (IMS) had been a  separate deliverable with its own DID – Now merged with the CPR as Format 6 in the IPMR – IMS analysis requirements will be submitted as part of Format 5 • Added significant language to eliminate most needs for  statement of work clarification – Defined minimum level of subcontractor integration – Reached agreement on the definition of Schedule Margin and  Schedule Visibility Tasks (SVTs) – Required disclosing of justification for Leads Lags and most Required disclosing of justification for Leads, Lags and most  Constraints – Defined minimum fields – Expanded when SRA is required and how it is reported p q p Integrated Program Management Report (IPMR) DID Training, 31 July 2012, Robert Loop, NAVY CEVM. 11
  • 12. Format 6 • Consistency with Format 1 Addressed – Included “The WBS numbering system in the IMS must be  consistent with the Format 1 structure.” • Schedule Margin  – Allowed before program events. §3.7.2.4. • Critical & Driving Paths Critical & Driving Paths  – Included  definition that tasks with “0” or negative total  float are not by default the critical path §3.7.1.3.5.9. – Driving path and interim milestones defined (not in 2005 Driving path and interim milestones defined (not in 2005  IMS DID) §3.7.1.3.5.8. – Excessive constraints and incomplete, incorrect, or overly  § constrained logic shall be avoided.§3.7.1.3.5.9. g Integrated Program Management Report (IPMR) DID Training, 31 July 2012, Robert Loop, NAVY CEVM. 12
  • 13. Format 6 (cont’d) • Relationships & Float  – All non‐constrained discrete tasks/activities/milestones  shall have at least one predecessor and successor, except  p p the start and end of the program or interim delivery • Subcontractor Integration – Subcontractor discrete work shall be incorporated as tasks  p within the prime IMS at a level necessary for a realistic  critical path • Calendars – The IMS shall contain all calendars that define working and  nonworking time periods or other information that may  impact the schedule Integrated Program Management Report (IPMR) DID Training, 31 July 2012, Robert Loop, NAVY CEVM. 13
  • 14. New Format 7 • New requirement not in CPR DID, but similar  information was previously required by the EVM  Central Repository (called historical file) Central Repository (called historical file) • Time phased BCWS, BCWP, ACWP, ETC from contract  award to completion as applicable • Must reconcile with Format 1 BAC and EAC for the  month submitted • Due as a minimum annually at the same time as Due as a minimum annually, at the same time as  other Formats.  Recommend quarterly according to  the government fiscal calendar.   • Purpose to support Government planning cycle  Integrated Program Management Report (IPMR) DID Training, 31 July 2012, Robert Loop, NAVY CEVM. 14
  • 16. Commercial Contracting Perspective • General Observations • The Contractors Side The Contractors’ Side • The Owners’ Side  • Recommended Practice(s)  16
  • 17. General Observations • Commercial contracting environment much more  reliant on FFP/FUP contract types for large projects – Cost and performance risk “transferred” from owners to  contractors – Nuances will exist between different project delivery  p j y methods  • Schedules usually integrated with cost only when  contractually required as basis for pay applications  ll i d b i f li i – Formalizes requirement to perform monthly updates – Often times leads to secondary “field schedule” Often times leads to secondary  field schedule 17
  • 18. The Contractors’ Side • Parsons Corporation – A current Acumen customer –BBegan as engineering‐specific, now full scope design‐ i i ifi f ll d i build/EPC contractor • Specializes in first of a kind, one of a kind projects – Three primary business units • Parsons Government Services (formerly PI&T) • Parsons Environment & Infrastructure Parsons Environment & Infrastructure – Commercial Technology – Water & Infrastructure • Transportation Group Transportation Group  18
  • 19. The Contractors’ Side • Summary of Parsons Requirements 1. Hierarchical Work Breakdown Structure (WBS) and  WBS Dictionary • Unique WBS numbers assigned to the lowest level elements  of the WBS • One responsible individual for each WBS element (one  person can manage multiple WBS elements) 2. Metrics identified for consistently establishing  2 Metrics identified for consistently establishing physical progress • Budgets match the structure and detail of the metrics used  for physical progress f h i l 19
  • 20. The Contractors’ Side • Summary of Parsons Requirements (cont’d) 3. Logic‐based schedules that identify the sequence of work  and significant task relationships d i ifi t t k l ti hi • WBS reflected within schedule so that activities can be  associated with specific control accounts 4. Time‐phased budget baselines (i.e. overlay or budget‐load  the schedule) • Both cost and revenue required to generate cash flow curve  q g for large projects during proposal review • Level‐of‐effort activities are identified and isolated in a  separate control account 20
  • 21. The Contractors’ Side • Summary of Parsons Requirements (cont’d) 5. Baseline plan is controlled  • Prevent unauthorized changes • Ensure that authorized changes are immediately  incorporated p 6. Monthly or more frequent comparison of progress  and costs to the baselines   • C l l i Calculation of cost and schedule variances and indexes, with  f d h d l i di d ih explanations provided for significant variances   • Corrective actions implemented as appropriate 21
  • 22. The Owners’ Side • Orange County Sanitation District – Responsible for safely collecting, treating and disposing the  wastewater generated by 2.5 million people living in a 479‐ wastewater generated by 2 5 million people living in a 479 square‐mile area of central and northwest Orange County (CA) – Ongoing Capital Improvements Program comprised of multiple  rehabilitation and expansion projects totaling app. $3 billion rehabilitation and expansion projects totaling app $3 billion • Most projects are FFP, design‐bid‐build • OCSD Scheduling Specification Review – Submittal/acceptance of baseline schedule  • Required for full payment of mobilization line item  • $300K or 10% of line item $ 22
  • 23. The Owners’ Side • OCSD Scheduling Specification Review (cont’d) – Cost loading of activities • Required on all discrete work activities Required on all discrete work activities – Not procurement and submittal preparation/review (except for  baseline schedule)  • Cost loading should be equal to value of contract price (revenue) Cost loading should be equal to value of contract price (revenue) – Not required to be integrated with resource loading (crew‐ based)  – Overhead/profit prorated and added to each activity Overhead/profit prorated and added to each activity – Cost (revenue) curve required as separate submittal – Schedule updates used as basis for progress payments, but not  y exclusively 23
  • 24. Recommended Practice(s) • Contractors’ Side – If internal decision is made to cost load schedule, should be  performed at summary (control account) level only performed at summary (control account) level only • Should not be integrated with resource loading to allow for more  flexibility – In addition to initial cash flow curve generated by cost loaded In addition to initial cash flow curve generated by cost loaded  schedule, “earned value” curves should be developed • Based on what has been approved (“earned revenue”) for monthly  progress payment progress payment • Facilitates trend for how much work is required on monthly basis to  complete in accordance with forecasted date in CPM schedule    24
  • 25. Recommended Practice(s) • Owners’ Side – Specifying cost (revenue) loading  as basis of progress  payments helps to ensure timely schedule updates • Should also specify that each discrete activity be subdivided  into “substantial completion” and “final completion” to  p p prevent widespread out‐of‐sequence progress • Should allow for overhead/profit to be loaded outside of  discrete activities – Also, should be loaded in activity with fixed duration equal to  contractual PoP (not hammocked over entire schedule) – Will allow contractor to recover overhead/profit as originally  planned, lessening cash flow impact of delays/claims    25