SlideShare une entreprise Scribd logo
1  sur  46
+ From Needed Capabilities to
Project Deliverables ‒ On Time, On
Budget, On Specification
A step by step guide to increasing the Probability of Program success
start with the WBS, developing the Integrated Master Plan and
Integrated Master Schedule, risk adjusting the IMS, and measuring
progress to plan in units of measure meaningful to the decision
makers.
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016 1
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016
Research shows 70-80% of a project manager’s time is spent in communicating
inside and outside the project.
We need processes and tools that radiate project information as the foundation
for communication to increase project success 2
+ The Best Communication Inside and Outside
the Project is a Big Visible Chart
3
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016
1. What Does DONE Look
Like?
2. How Do We Get to
DONE?
3. Is There Enough Time,
Money, and Resources,
To Get to DONE?
4. What Impediments Will
Be Encountered Along
The Way to DONE?
5. What Are The Units Of
Measures For Progress
All Successful Projects Must Provide
Credible Answers To These 5
Questions …
4 Performance–Based Project Management®, Copyright © Glen B. Alleman, 2012, 2013, 2014, 2015
5 Principles of
Project
Success
5 Practices of Performance‒Based Project Management®
Identify
Needed
Capabilities
Define
Requirements
from Capabilities
Establish
Performance
Measurement
Baseline (PMB)
Execute the
PMB as planned
Perform
Continuous Risk
Management
(CRM)
What does Done
Look like in
Meaningful Units of
Measures?
ConOps,
SOO, SOW
Technical And
Operational
Delivery Plan
Incremental
Maturity
Assessment
(MOE, MOP,
TPM, KPP)
Assess Physical
Percent
Complete
Risk
Identification
How are we going
to get there? Integrated
Master Plan
(IMP)
Work
Breakdown
Structure (WBS) Integrated
Master Schedule
(IMS)
Iterative and
Incremental
Delivery
Risk Analysis
What Resources
do we need along
the way?
Resource
Management
Plan (RMP)
Future
Performance
Forecasting
Risk Planning
What Impediments
will we encounter
along the way?
4 Levels Of
Uncertainty
Planning
Technical And
Programmatic
Risks Assigned
To All WBS
Deliverables
Risk Adjustment
To Cost And
Schedule
Measures
Risk Adjusted
Performance
Measurement
Baseline
Risk Tracking
How do we
Measure Progress
to plan?
Measures Of
Effectiveness
(MOE)
Measures Of
Performance
(MOP)
Technical
Performance
Measures (TPM)
Earned Value
Management
(EVM)
Risk Control
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016 5
+ Increasing Probability of Program
Success through Information Radiators
 WBS – it shows what is being delivered and what work processes are
used for this delivery (MIL-STD-881-C).
 Integrated Master Plan (IMP) – shows how the deliverables increase in
their maturity toward the final product.
 Integrated Master Schedule (IMS) – shows the sequence of work to
increases the maturity of the deliverables.
 Programmatic and Technical Risk Management – shows what
reducible and irreducible risks are present on the project and what
mitigation activities are needed increase the probability of project
success.
 Performance Measurement and Reporting – shows how Physical
Percent Complete to date, Estimate to Complete, and Estimate At
Complete are compared to plan.
 Root Cause Analysis ‒ most efforts are project corrective actions are
addressing symptoms not the Cause. Without identify the Root Cause the
symptoms are not removed.
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016
6
+
Capabilities Based
Planning
 Define operational concepts
as capabilities.
 Define Capabilities through
Scenarios or Use Cases.
 Asses Needs, Cost, and Risks
of the Capability
simultaneously.
 Define explicit, balanced, and
feasible alternatives.
Planning, under uncertainty, to provide
capabilities suitable for a wide range of
modern–day challenges and
circumstances while working within an
economic framework that necessitates
choice.”
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016
7
+
Identify Needed Capabilities
8
What Should We Do?
Where Are We Now?
Abstracted from:
“Capabilities‒Based Planning – How It Is Intended
To Work And Challenges To Its Successful
Implementation,” Col. Stephen K. Walker, United
States Army, U. S. Army War College, March 2005
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016
+
Measures of Effectiveness (MOE)
9
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016
Measures of Effectiveness …
 Are stated in units meaningful to the buyer,
 Focus on capabilities independent of any technical
implementation,
 Are connected to the mission success.
Operational measures of success that are closely related to
the achievements of the mission or operational objectives
evaluated in the operational environment, under a specific set
of conditions.
MoE’s Belong to the End User
“Technical Measurement,” INCOSE–TP–2003–020–01
+
Measures of Performance (MOP)
10
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016
Measures of Performance are …
 Attributes that assure the system has the capability
and capacity to perform,
 Assessment of the system to assure it meets design
requirements to satisfy the MoE.
Measures that characterize physical or functional attributes
relating to the system operation, measured or estimated
under specific conditions.
“Technical Measurement,” INCOSE–TP–2003–020–01
MoP’s belong to the Program – Developed by the Systems
Engineer, Measured By CAMs, and Analyzed by PP&C
+ Technical Performance Measures
(TPM)
11
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016
Technical Performance Measures …
 Assess design progress,
 Define compliance to performance requirements,
 Identify technical risk,
 Are limited to critical thresholds,
 Include projected performance.
Attributes that determine how well a system or system
element is satisfying or expected to satisfy a technical
requirement or goal
“Technical Measurement,” INCOSE–TP–2003–020–01
+
Key Performance Parameters (KPP)
12
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016
Key Performance Parameters …
 Have a threshold or objective value,
 Characterize the major drivers of performance,
 Are considered Critical to Customer (CTC).
Measures that Represent the capabilities and characteristics
so significant that failure to meet them can be cause for
reevaluation, reassessing, or termination of the program
The acquirer defines the KPPs during the operational concept
development – KPPs say what DONE looks like
“Technical Measurement,” INCOSE–TP–2003–020–01
+ Capabilities Map from Strategy to
Project Execution
13
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016
Performance Goal Key Performance
Indicator (KPI)
Critical Success Factor
(CSF)
Strategic Objective
Be The Preferred
Supplier Of Business
Applications Traceable
to Increased Customer
Revenue
Provide on-time, on-
budget, on-
specification for our
enterprise applications
Budget Variance
Schedule Variance
% Requirements
Variance
BPI ≥ 0.95
CPI ≥ 0.97
Function Points
Delivered ≥ 90%
Target
Provide scalable
platform for acquisition
and growth of our
customer base
Cost of Delivery
Impact
Performance Impact
Global Operational
Baseline
Declining Cost per
Customer
SLA Compliance ≥ 0.98
24/7/365 Non-Stop
Operations
What How Measures
Vision
Positively Impact
Financial Performance
Why
Top Down
Making the effect-and-cause connection between Strategy
and Key Performance Indicators is the role of an Balanced
Scorecard automation system
Flow Down from Strategy to KPIs
Making the effect-and-cause connection between Strategy
and Key Performance Indicators is the role of an Balanced
Scorecard automation system
+
WBS is Paramount
 The WBS describes the product and
services needed to produce the products
 The Work Breakdown Structure
development starts with NWS Policy
Directive 70-3, from DOC Scalable
Project Management Methodology,
§7.2.4 in accordance with PMI® Practice
Standard for Work Breakdown Structure
 A starting point for developing the WBS
is MIL-STD-881-C.
 Each Federal Agency may have their
own instance of the 881-C guide.
Without a WBS, we don’t know what is
being delivered by the project.
We don’t know what End Item
Deliverables are related to other items
– parents of the final deliverables.
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016
14
+
The WBS …
 … is a product-oriented family tree composed of hardware, software, services,
data, and facilities. The family tree results from systems engineering efforts during
the acquisition of a defense materiel item.
 … a WBS displays and defines the product, or products, to be developed
and/or produced. It relates the elements of work to be accomplished to each
other and to the end product. In other words, the WBS is an organized method to
breakdown a product into sub-products at lower levels of detail.
 … can be expressed to any level of detail. While the top three levels are the
minimum required for reporting purposes on any program or contract, effective
management of complex programs requires WBS definition at considerably lower
levels.
 This is particularly true of items identified as high-cost, high-risk, or high technical interest.
 Under these circumstances, it is critical to define the product at a lower level of WBS detail.
 In this case, managers should distinguish between WBS definition and WBS reporting.
 The WBS should be defined at the level necessary to identify work progress and enable
effective management, regardless of the WBS level reported to program oversight.
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016
15
+
Integrated Master
Plan (IMP)
 The IMP is a hierarchy of program
events, in which each event is supported
by specific accomplishments, and each
accomplishment is based on satisfying
specific criteria to be considered
complete.
 The IMP consists of three elements
 Program Events
 Significant Accomplishments
 Accomplishment Criteria
The Integrated Master Plan is a
hierarchical description of what Done
looks like in the form of increasing
maturity of the program’s deliverables
and the capabilities they provide
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016
16
+
IMP / IMS Structure
17
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016
IMS
IMP
Describes how program
capabilities will be
delivered and
how these
capabilities will
be recognized
as ready for
delivery
Supplemental Schedules (CAM Notebook)
Work Packages and Tasks
Criteria
Accomplishment
Events
or
Milestones
+
Maturity Process Flow
18
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016
+
The Integrated Master Plan
 Program planning involves developing and maintaining plans for all
program processes, including those required for effective program
office-contractor interaction.
 Once the contract is signed and schedule, costs, and resources from
the contractor are established, the program plan takes into account, at
an appropriate level of detail, the contractor's estimations for the
program.
 The IMP should provide sufficient definition to track the step-by-step
completion of the required accomplishments for each event, and to
demonstrate satisfaction of the completion criteria for each
accomplishment.
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016
19
+
The Integrated Master Plan …
 Provides flexibility in performing detailed program execution planning,
organization, and scheduling within any existing Request for Proposal
(RFP) constraints.
 Serve as the basis for detailed Execution IMS.
 Provides basis of integrated product development and systems
integration approaches
 Serve as the basis for ensuring mutual understanding of Government
expectations and agreement on the program content, program plan,
schedule, and risk.
 Provide detailed integrated execution plan and supporting schedule,
clearly identifying what has to be done and when it must be done.
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016
20
+ The IMP enables Program
Management to…
 Identify and assess actual progress versus the planned progress
 Monitor the program critical path and help develop workarounds to
problem areas
 Assess program maturity
 Assess the status of risk management activities based on the inclusion
of the program risk mitigation activities in the IMP and IMS
 Assess the progress on selected Key Performance Parameters
(KPPs) and Technical Performance Measures (TPMs)
 Provide an objective, quantitative basis for the contractor’s
performance assessment
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016
21
+
IMP for Cloud Deployment
22
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016
+
Integrated Master
Schedule (IMS)
 Packages of Work and their Tasks,
implement the deliverables from the
Work Breakdown Structure.
 These Work Packages should have a
singular outcome matched to a
deliverable or service in the WBS
 The assessment of the maturity of these
outcomes is done in the IMP using the
Accomplishment Criteria that show the
increasing maturity of the Significant
Accomplishments.
 Each Work Package has some measure
of Performance or Technical
Performance Measure for the
deliverable.
The IMS is an integrated, networked
schedule containing all the detailed
discrete work packages and planning
packages (or lower level tasks of
activities) necessary to support the
events, accomplishments, and criteria
of the IMP.
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016
23
+ Vertical and Horizontal Traceability
between IMP and IMS
24
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016
Program Events
Define the maturity
of a Capability at a point in time.
Significant Accomplishments
Represent requirements
that enable Capabilities.
Accomplishment Criteria
Exit Criteria for the Work
Packages that fulfill Requirements.
Work
Package
Work
Package
Work
Package
Work
Package
Work
Package
Work
Package
Work
package
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016 25
+
Managing Technical
and Programmatic
Risk
 Risk Management is how adults manage
projects ‒ Tim Lister
 All risk comes from uncertainty
 The integrated master schedule must be
risk adjusted for these uncertainties
 Specific work must be in the IMS for
reducible uncertainties
 Schedule, cost, and technical margin
must be in the IMS for irreducible
uncertainties
All risk comes from uncertainty.
Uncertainty comes in two forms
Reducible uncertainty (Epistemic)
Irreducible uncertainty (Aleatory)
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016
26
+
All Risk Comes from Uncertainty
Uncertainty
Irreducible
(Aleatory)
Reducible
(Epistemic)
Natural Variability
Ambiguity
Ontological
Uncertainty
Probabilistic Events
Probabilistic
Impacts
Periods of Exposure
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2016
27
Technical Risk Management
Track and Control
Performance Deviations
Deliberate and recommend a
decision alternative
Risk analysis of decision
alternatives, performing
trade studies and ranking
Propose and/or identify
decision alternatives
Formulate objectives
Hierarchy and Technical
Performance Measures
Stakeholder
expectations,
requirements
definition and
management
Design solutions,
technical planning
Design solution,
technical planning,
and decision
analysis
Technical planning
and decision
analysis
Decision analysis,
lessons learned,
knowledge
management
Identify
Analyze
Plan
Track
Control
Decide and
implement
decision
alternatives
Communicate
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2016
28
+
Performance
Measurement and
Reporting
 Physical Percent Complete is defined as
tangible evidence of progress to plan.
 Define this Physical Percent Complete
before the work starts in units of
measure meaningful to the decision
makers
 Effectiveness
 Performance
 Key Performance Parameters
Performance measurement is always
based on tangible evidence of
progress to plan.
The passage of time and consumption
of resources is not the basis of
performance measurement.
Physical Percent Complete of some
predefined measure of Effectiveness,
Performance, or Key Parameter is.
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016
30
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016 31
You Know you're applying the 5 Principals of Project
Success if you …
1
… have a defined Mission, Vision, Capabilities, and
Requirements ‒ by which to create …
2
… the Plan for fulling these capabilities and connected
Requirements and Schedule for producing the needed
outcomes to meet this Plan ‒ and have …
3
… allocated enough Time, Money, and Resources to
increase the probability of the project’s success ‒ and you
can …
4
… know what Risks are in front of you and their retirement or
handling plans ‒ and you can …
5
… confirm progress as Physical Percent Complete for each
planned Deliverables in the Plan “on or before the planned
time and “at or below” the planned cost.
+
Monthly Business Rhythm
 Each participate in the Business Rhythm, the data produced and
consumed, interconnections
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016
32
+
Root Cause Analysis
1. Define the Problem.
2. Determine the Causal Relationships.
3. Provide a Graphical Representation of
Cause and Effect that is not linear
thinking.
4. Provide Evidence for each Cause and
Effect.
5. Determine if each Cause is Sufficient
and Necessary.
6. Identify Effective Solutions
 Finding the cause is needed.
 Preventing the effect is needed.
 But installing an effective solution is
the desired business outcome.
7. Implement And Track the Effective
Solutions.
When the project goes bad.
Root Cause Analysis is the method of
problem solving that identifies the root
causes of failures or problems. A root
cause is the source of a problem and
its resulting symptom, that once
removed, corrects or prevents an
undesirable outcome from recurring.
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016
33
+
The Notion of Root Cause Analysis
Symptom: The result or outcome of the problem.
An observation
 We have late additions to the release that break the software
 We have “core” defects that should been caught long before
production release
 We make changes to software, stored procedures, or the
database only to discover it was a mistake.
 We make promises to the customer before assessing the
impact on our resources or the technical difficulty
Problem:
 Test coverage insufficient the detect latent bugs in software
 We commit before understanding the consequences
Root Cause:
 No software structure to determine test coverage or change
impacts on baseline.
 No detailed understanding of our capacity for work and
productivity of our technical staff
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2018
34
+
 Causes are never part of a Linear Chain found in standard Fishbone
diagram or narrative approach.
 Look for causes to create the effect. Two causes are needed for each
Effect.
 Conditions – may exist prior to the Effect. Or conditions may be in motion or
active during the Effect. Conditions are the causes often ignored or beyond our
knowledge.
 Actions – momentary causes that bring conditions together to cause an effect.
Actions are causes most easily recognized.
 Connect all causes (Actions and Conditions) with a Caused By phrase to
either an action or a condition.
 Support each Cause with evidence or an answered question.
For each Primary Effect we need ask why that Effect
occurred.
Principles of the Cause and Effect
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2016
35
+ Cause and Effect are Part of a
Continuum of Causes
 Causes are never linear.
 Causes branch into at
least two other causes,
each time we ask why of
an effect and if we ask
why of each of those
causes we find an
expanding set of causes
like those to the right.
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2016
36
+ Four Root Causes for Program Cost
and Schedule Overruns
37
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2018
Unrealistic Performance Expectations,
missing Measures of Effectiveness (MOE)
and Measures of Performance (MOP).
Unrealistic Cost and Schedule estimates
based on inadequate risk adjusted growth
models.
Inadequate assessment of risk and
unmitigated exposure to these risks without
proper handling plans.
Unanticipated technical issues without
alternative plans and solutions to maintain
effectiveness.
Unanticipated
Cost and
Schedule
Growth
TheLensofPerformance
Assessment “Borrowed” with permission from Mr. Gary Bliss,
Director, Performance Assessment and Root
Cause Analysis (PARCA), Office of Assistant
Secretary of Defense for Acquisition,
Technology and Logistics.
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2018 38
Root Causes Have Root Causes
It’s not a matter of asking 5 Whys
You must keep asking until you reach the end of the chain or action and condition
+
Resources (1)
 MIL-STD-881-C defines how to build a Work Breakdown Structure ‒
http://quicksearch.dla.mil/Transient/38A8B775A4BF4CEF8871CEF7E
EA34156.pdf
 Guestimate ‒ a spread sheet for making estimating
https://www.getguesstimate.com/
 Reality Charting, using the Apollo Method,
http://www.apollorootcause.com/media/32309/realitycharting_-
_seven_steps_to_effective_problem-solving_and_strategie....pdf
 XMIND – low cost Mind Mapping Tool ‒ www.xmind.com
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016
39
+
Resources (2)
 “Guide to Capabilities Based Planning: The Technical Cooperation
Program Joint Systems and Analysis Group Technical Panel 3,”
www.acq.osd.mil/ttcp/reference/docs/JSA-TP-3-CBP-Paper-Final.doc
 “Naval Analytical Capabilities: Improving Capabilities-Based Planning,”
Committee on Naval Analytical Capabilities and Improving
Capabilities-Based Planning,” Naval Studies Board, Division on
Engineering and Physical Sciences, National Research Council,
https://www.nap.edu/download/11455
 RiskyProject ‒ Monte Carlo Simulation tool starting with a Risk
Register and modeling tools for the Reducible and Irreducible risks ‒
www.riskyproject.com
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016
40
+
Resources (2)
 Risk Management Toolkit, Mitre Systems Engineering Process Office,
http://www2.mitre.org/work/sepo/toolkits/risk/index.html
 Risk Matrix tool is free Excel tool downloaded from here ‒
http://www2.mitre.org/work/sepo/toolkits/risk/ToolsTechniques/RiskMatrix.ht
ml
 Risk Radar tool is a Access Database to downloaded from here ‒
http://www2.mitre.org/work/sepo/toolkits/risk/ToolsTechniques/RiskRadar.ht
ml
 Software Engineering Institute Continuous Risk Management,
http://www.sei.cmu.edu/risk/
 “What’s Wrong With Risk Matrices,” Tony Cox,
https://www.researchgate.net/profile/Louis_Cox/publication/5432360_
What's_Wrong_with_Risk_Matrices/links/55582a5408ae980ca60e2e8
e.pdf
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016
41
+
Resources (3)
 Design Structure Matrix
 http://www.dsmweb.org/
 Design Structure Matrix Methods and Applications
https://mitpress.mit.edu/books/design-structure-matrix-methods-and-
applications
 International Cost Estimating and Analysis Association,
http://www.iceaaonline.com/
 College of Performance Management, www.mycpm.org
 “Opportunity Management: Be Careful What You Ask For,” Edmund
Conrow, https://acc.dau.mil/adl/en-
US/193752/attachment/32944/conr_ma08_1.pdf
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016
42
+
Resources (4)
 Society for Effective Lessons Learned Sharing (SELLS),
http://www.au.af.mil/au/awc/awcgate/lessons/sells/llsite.pdf
 Software Engineering Institute, Continuous Risk Management,
https://resources.sei.cmu.edu/library/asset-view.cfm?assetid=30856
 Risk Informed Decision Making, NASA/SP-2010-576,
https://ntrs.nasa.gov/archive/nasa/casi.ntrs.nasa.gov/20100021361.pd
f
 “An Implementation of the Lurie-Goldberg Algorithm Scheduling Risk
Analysis,” http://www.slideserve.com/tahir/an-implementation-of-the-
lurie-goldberg-algorithm-in-schedule-risk-analysis
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016
43
+
Resources (5)
 ACQuipedia, https://dap.dau.mil/acquipedia/Pages/Default.aspx
 Defense Acquisition University tools and resources,
https://www.dau.mil/tools#All|All||recent
 Mitre Systems Engineering Handbook,
http://www.mitre.org/sites/default/files/publications/se-guide-book-
interactive.pdf
 Implementing the Program Management Improvement and
Accountability Act of 2015, https://www.pmi.org/-
/media/pmi/documents/public/pdf/business-solutions/program-
management-accountability-act.pdf
 Making the Impossible Possible: Leading Extraordinary Performance ‒
The Rocky Flats Story, Kim Cameron and Marc Lavine, Berrett-
Koehler, 2006.
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016
44
+
Resources (6)
 Beyond Bullet Points, Cliff Atkinson, Microsoft Press, 2011.
 Effective Risk Management: Some Keys to Success, Edmund Conrow,
AIAA Press, 2003.
 Integrated Master Plan and Integrated Master Schedule Preparation
and Use Guide,
https://www.acq.osd.mil/se/docs/IMP_IMS_Guide_v9.pdf
 Defense Agile Acquisition Guide: Tailoring DoD IT Acquisition Program
Structures and Processes to Rapidly Deliver Capabilities,
https://www.mitre.org/publications/technical-papers/defense-agile-
acquisition-guide-tailoring-dod-it-acquisition-program
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016
45
+
Resources (7)
 How to Lie with Statistics, Darrell Huff, W. W. Norton, 1993. Orginal
published 1953
 “Society for Effective Lessons Learned Sharing (SELLS),”
http://www.au.af.mil/au/awc/awcgate/lessons/sells/llsite.pdf
 NASA’s Management of the Orion Multi-Purpose Crew Vehicle
Program, https://oig.nasa.gov/audits/reports/FY16/IG-16-029.pdf
 Integrated Master and Integrated Master Schedule Preparation and
Use Guide, https://www.acq.osd.mil/se/docs/IMP_IMS_Guide_v9.pdf
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016
46

Contenu connexe

Tendances

Improving Project Performance in the DOE
Improving Project Performance in the DOEImproving Project Performance in the DOE
Improving Project Performance in the DOEGlen Alleman
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan DevelopmentGlen Alleman
 
The integrated master plan and integrated master schedule
The integrated master plan and integrated master scheduleThe integrated master plan and integrated master schedule
The integrated master plan and integrated master scheduleGlen Alleman
 
Project Management Theory
Project Management TheoryProject Management Theory
Project Management TheoryGlen Alleman
 
Building a Credible Performance Measurement Baseling
Building a Credible Performance Measurement BaselingBuilding a Credible Performance Measurement Baseling
Building a Credible Performance Measurement BaselingGlen Alleman
 
Integrated Master Schedule
Integrated Master ScheduleIntegrated Master Schedule
Integrated Master Scheduleellefsonj
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement BaselineGlen Alleman
 
How primavera can help you in managing risks in project intensive industry ppt
How primavera can help you in managing risks in project intensive industry pptHow primavera can help you in managing risks in project intensive industry ppt
How primavera can help you in managing risks in project intensive industry pptp6academy
 
Establishing the Performance Measurement Baseline
Establishing the Performance Measurement BaselineEstablishing the Performance Measurement Baseline
Establishing the Performance Measurement BaselineGlen Alleman
 
SOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERP
SOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERPSOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERP
SOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERPKevin West
 
Scrum Lifecycle At Enterprise Levels
Scrum Lifecycle At Enterprise LevelsScrum Lifecycle At Enterprise Levels
Scrum Lifecycle At Enterprise LevelsGlen Alleman
 
Deliverables based planning handbook
Deliverables based planning handbookDeliverables based planning handbook
Deliverables based planning handbookGlen Alleman
 
Integrated Program Performance Management
Integrated Program Performance ManagementIntegrated Program Performance Management
Integrated Program Performance ManagementGlen Alleman
 
The simple problem of schedule performance indices
The simple problem of schedule performance indicesThe simple problem of schedule performance indices
The simple problem of schedule performance indicesGlen Alleman
 
EVM+Agile the darkside
EVM+Agile the darksideEVM+Agile the darkside
EVM+Agile the darksideGlen Alleman
 
Six ½ Day Sessions on the Road To Becoming a CAM
Six ½ Day Sessions on the Road To Becoming a CAMSix ½ Day Sessions on the Road To Becoming a CAM
Six ½ Day Sessions on the Road To Becoming a CAMGlen Alleman
 
Measures of Effectiveness, Measures of Performance, Technical Performance Mea...
Measures of Effectiveness, Measures of Performance, Technical Performance Mea...Measures of Effectiveness, Measures of Performance, Technical Performance Mea...
Measures of Effectiveness, Measures of Performance, Technical Performance Mea...Glen Alleman
 
Assessing Project Performance Beyond CPI/SPI
Assessing Project Performance Beyond CPI/SPIAssessing Project Performance Beyond CPI/SPI
Assessing Project Performance Beyond CPI/SPIGlen Alleman
 
Integrating cost schedule and technical performance
Integrating cost schedule and technical performanceIntegrating cost schedule and technical performance
Integrating cost schedule and technical performanceGlen Alleman
 
Earned Value Management Meets Big Data
Earned Value Management Meets Big DataEarned Value Management Meets Big Data
Earned Value Management Meets Big DataGlen Alleman
 

Tendances (20)

Improving Project Performance in the DOE
Improving Project Performance in the DOEImproving Project Performance in the DOE
Improving Project Performance in the DOE
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan Development
 
The integrated master plan and integrated master schedule
The integrated master plan and integrated master scheduleThe integrated master plan and integrated master schedule
The integrated master plan and integrated master schedule
 
Project Management Theory
Project Management TheoryProject Management Theory
Project Management Theory
 
Building a Credible Performance Measurement Baseling
Building a Credible Performance Measurement BaselingBuilding a Credible Performance Measurement Baseling
Building a Credible Performance Measurement Baseling
 
Integrated Master Schedule
Integrated Master ScheduleIntegrated Master Schedule
Integrated Master Schedule
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement Baseline
 
How primavera can help you in managing risks in project intensive industry ppt
How primavera can help you in managing risks in project intensive industry pptHow primavera can help you in managing risks in project intensive industry ppt
How primavera can help you in managing risks in project intensive industry ppt
 
Establishing the Performance Measurement Baseline
Establishing the Performance Measurement BaselineEstablishing the Performance Measurement Baseline
Establishing the Performance Measurement Baseline
 
SOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERP
SOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERPSOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERP
SOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERP
 
Scrum Lifecycle At Enterprise Levels
Scrum Lifecycle At Enterprise LevelsScrum Lifecycle At Enterprise Levels
Scrum Lifecycle At Enterprise Levels
 
Deliverables based planning handbook
Deliverables based planning handbookDeliverables based planning handbook
Deliverables based planning handbook
 
Integrated Program Performance Management
Integrated Program Performance ManagementIntegrated Program Performance Management
Integrated Program Performance Management
 
The simple problem of schedule performance indices
The simple problem of schedule performance indicesThe simple problem of schedule performance indices
The simple problem of schedule performance indices
 
EVM+Agile the darkside
EVM+Agile the darksideEVM+Agile the darkside
EVM+Agile the darkside
 
Six ½ Day Sessions on the Road To Becoming a CAM
Six ½ Day Sessions on the Road To Becoming a CAMSix ½ Day Sessions on the Road To Becoming a CAM
Six ½ Day Sessions on the Road To Becoming a CAM
 
Measures of Effectiveness, Measures of Performance, Technical Performance Mea...
Measures of Effectiveness, Measures of Performance, Technical Performance Mea...Measures of Effectiveness, Measures of Performance, Technical Performance Mea...
Measures of Effectiveness, Measures of Performance, Technical Performance Mea...
 
Assessing Project Performance Beyond CPI/SPI
Assessing Project Performance Beyond CPI/SPIAssessing Project Performance Beyond CPI/SPI
Assessing Project Performance Beyond CPI/SPI
 
Integrating cost schedule and technical performance
Integrating cost schedule and technical performanceIntegrating cost schedule and technical performance
Integrating cost schedule and technical performance
 
Earned Value Management Meets Big Data
Earned Value Management Meets Big DataEarned Value Management Meets Big Data
Earned Value Management Meets Big Data
 

Similaire à From Needed Capabilities to Project Deliverables - On Time, On Budget, On Specification

From WBS to Integrated Master Schedule
From WBS to Integrated Master ScheduleFrom WBS to Integrated Master Schedule
From WBS to Integrated Master ScheduleGlen Alleman
 
Deliverables based planning
Deliverables based planning Deliverables based planning
Deliverables based planning Glen Alleman
 
Chapter 0 of Performance Based Project Management (sm)
Chapter 0 of Performance Based Project Management (sm)Chapter 0 of Performance Based Project Management (sm)
Chapter 0 of Performance Based Project Management (sm)Glen Alleman
 
Performance based management in a nut shell (v5)
Performance based management in a nut shell (v5)Performance based management in a nut shell (v5)
Performance based management in a nut shell (v5)Glen Alleman
 
Performance based planning in a nut shell (V5)
Performance based planning in a nut shell (V5)Performance based planning in a nut shell (V5)
Performance based planning in a nut shell (V5)Glen Alleman
 
Showing how to Increase the Probability of Project Success by applying the ...
Showing how to Increase the Probability of Project Success by applying the ...Showing how to Increase the Probability of Project Success by applying the ...
Showing how to Increase the Probability of Project Success by applying the ...Glen Alleman
 
Agile in an ANSI-748-C environment
Agile in an ANSI-748-C environmentAgile in an ANSI-748-C environment
Agile in an ANSI-748-C environmentGlen Alleman
 
Agile in the government
Agile in the government Agile in the government
Agile in the government Glen Alleman
 
Making Agile Development work in Government Contracting
Making Agile Development work in Government ContractingMaking Agile Development work in Government Contracting
Making Agile Development work in Government ContractingGlen Alleman
 
Connecting PMB® with PMBOK®
Connecting PMB® with PMBOK®Connecting PMB® with PMBOK®
Connecting PMB® with PMBOK®Glen Alleman
 
Breaking the Project Failure Cycle
Breaking the Project Failure CycleBreaking the Project Failure Cycle
Breaking the Project Failure CycleGlen Alleman
 
Measurement News Webinar
Measurement News WebinarMeasurement News Webinar
Measurement News WebinarGlen Alleman
 
Performance Based Management Handbook
Performance Based Management HandbookPerformance Based Management Handbook
Performance Based Management HandbookGlen Alleman
 
Evm+agile (8.8).chapter 9
Evm+agile (8.8).chapter 9Evm+agile (8.8).chapter 9
Evm+agile (8.8).chapter 9Glen Alleman
 
Niwot Ridge LLC Capabilities
Niwot Ridge LLC CapabilitiesNiwot Ridge LLC Capabilities
Niwot Ridge LLC CapabilitiesGlen Alleman
 
Five Immutable Principles of Project of Digital Transformation Success
Five Immutable Principles of Project of Digital Transformation SuccessFive Immutable Principles of Project of Digital Transformation Success
Five Immutable Principles of Project of Digital Transformation SuccessGlen Alleman
 
Integrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master ScheduleIntegrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master ScheduleGlen Alleman
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by StepGlen Alleman
 
Cpm500 d _alleman__tpm jun 2010 lesson 3 (v2)
Cpm500 d _alleman__tpm jun 2010 lesson 3 (v2)Cpm500 d _alleman__tpm jun 2010 lesson 3 (v2)
Cpm500 d _alleman__tpm jun 2010 lesson 3 (v2)Glen Alleman
 

Similaire à From Needed Capabilities to Project Deliverables - On Time, On Budget, On Specification (20)

From WBS to Integrated Master Schedule
From WBS to Integrated Master ScheduleFrom WBS to Integrated Master Schedule
From WBS to Integrated Master Schedule
 
Deliverables based planning
Deliverables based planning Deliverables based planning
Deliverables based planning
 
Chapter 0 of Performance Based Project Management (sm)
Chapter 0 of Performance Based Project Management (sm)Chapter 0 of Performance Based Project Management (sm)
Chapter 0 of Performance Based Project Management (sm)
 
Performance based management in a nut shell (v5)
Performance based management in a nut shell (v5)Performance based management in a nut shell (v5)
Performance based management in a nut shell (v5)
 
Performance based planning in a nut shell (V5)
Performance based planning in a nut shell (V5)Performance based planning in a nut shell (V5)
Performance based planning in a nut shell (V5)
 
Showing how to Increase the Probability of Project Success by applying the ...
Showing how to Increase the Probability of Project Success by applying the ...Showing how to Increase the Probability of Project Success by applying the ...
Showing how to Increase the Probability of Project Success by applying the ...
 
Agile in an ANSI-748-C environment
Agile in an ANSI-748-C environmentAgile in an ANSI-748-C environment
Agile in an ANSI-748-C environment
 
Agile in the government
Agile in the government Agile in the government
Agile in the government
 
Making Agile Development work in Government Contracting
Making Agile Development work in Government ContractingMaking Agile Development work in Government Contracting
Making Agile Development work in Government Contracting
 
Connecting PMB® with PMBOK®
Connecting PMB® with PMBOK®Connecting PMB® with PMBOK®
Connecting PMB® with PMBOK®
 
Breaking the Project Failure Cycle
Breaking the Project Failure CycleBreaking the Project Failure Cycle
Breaking the Project Failure Cycle
 
Measurement News Webinar
Measurement News WebinarMeasurement News Webinar
Measurement News Webinar
 
Performance Based Management Handbook
Performance Based Management HandbookPerformance Based Management Handbook
Performance Based Management Handbook
 
Evm+agile (8.8).chapter 9
Evm+agile (8.8).chapter 9Evm+agile (8.8).chapter 9
Evm+agile (8.8).chapter 9
 
Niwot Ridge LLC Capabilities
Niwot Ridge LLC CapabilitiesNiwot Ridge LLC Capabilities
Niwot Ridge LLC Capabilities
 
Five Immutable Principles of Project of Digital Transformation Success
Five Immutable Principles of Project of Digital Transformation SuccessFive Immutable Principles of Project of Digital Transformation Success
Five Immutable Principles of Project of Digital Transformation Success
 
Integrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master ScheduleIntegrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master Schedule
 
Ev+agile=success
Ev+agile=successEv+agile=success
Ev+agile=success
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by Step
 
Cpm500 d _alleman__tpm jun 2010 lesson 3 (v2)
Cpm500 d _alleman__tpm jun 2010 lesson 3 (v2)Cpm500 d _alleman__tpm jun 2010 lesson 3 (v2)
Cpm500 d _alleman__tpm jun 2010 lesson 3 (v2)
 

Plus de Glen Alleman

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planningGlen Alleman
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSGlen Alleman
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project SuccessGlen Alleman
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMGlen Alleman
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk managementGlen Alleman
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk ManagementGlen Alleman
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Glen Alleman
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringGlen Alleman
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideGlen Alleman
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineGlen Alleman
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Glen Alleman
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)Glen Alleman
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possibleGlen Alleman
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic AbundanceGlen Alleman
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planningGlen Alleman
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for AgileGlen Alleman
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaGlen Alleman
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure RolloutGlen Alleman
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan DevelopmentGlen Alleman
 
Increasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesIncreasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesGlen Alleman
 

Plus de Glen Alleman (20)

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planning
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMS
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project Success
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPM
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk management
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk Management
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems Engineering
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guide
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possible
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic Abundance
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planning
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for Agile
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six Sigma
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure Rollout
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan Development
 
Increasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesIncreasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and Practices
 

Dernier

08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking MenDelhi Call girls
 
Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Allon Mureinik
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking MenDelhi Call girls
 
SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024Scott Keck-Warren
 
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024BookNet Canada
 
Maximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxMaximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxOnBoard
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdfhans926745
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024Rafal Los
 
Key Features Of Token Development (1).pptx
Key  Features Of Token  Development (1).pptxKey  Features Of Token  Development (1).pptx
Key Features Of Token Development (1).pptxLBM Solutions
 
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersEnhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersThousandEyes
 
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationMichael W. Hawkins
 
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...HostedbyConfluent
 
Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slidespraypatel2
 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxMalak Abu Hammad
 
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...shyamraj55
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationRadu Cotescu
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsEnterprise Knowledge
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreternaman860154
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptxHampshireHUG
 

Dernier (20)

08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
 
Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men
 
SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024
 
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
 
Maximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxMaximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptx
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024
 
Key Features Of Token Development (1).pptx
Key  Features Of Token  Development (1).pptxKey  Features Of Token  Development (1).pptx
Key Features Of Token Development (1).pptx
 
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersEnhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
 
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day Presentation
 
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
 
Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slides
 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptx
 
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organization
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreter
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
 

From Needed Capabilities to Project Deliverables - On Time, On Budget, On Specification

  • 1. + From Needed Capabilities to Project Deliverables ‒ On Time, On Budget, On Specification A step by step guide to increasing the Probability of Program success start with the WBS, developing the Integrated Master Plan and Integrated Master Schedule, risk adjusting the IMS, and measuring progress to plan in units of measure meaningful to the decision makers. Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016 1
  • 2. Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016 Research shows 70-80% of a project manager’s time is spent in communicating inside and outside the project. We need processes and tools that radiate project information as the foundation for communication to increase project success 2
  • 3. + The Best Communication Inside and Outside the Project is a Big Visible Chart 3 Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016
  • 4. 1. What Does DONE Look Like? 2. How Do We Get to DONE? 3. Is There Enough Time, Money, and Resources, To Get to DONE? 4. What Impediments Will Be Encountered Along The Way to DONE? 5. What Are The Units Of Measures For Progress All Successful Projects Must Provide Credible Answers To These 5 Questions … 4 Performance–Based Project Management®, Copyright © Glen B. Alleman, 2012, 2013, 2014, 2015
  • 5. 5 Principles of Project Success 5 Practices of Performance‒Based Project Management® Identify Needed Capabilities Define Requirements from Capabilities Establish Performance Measurement Baseline (PMB) Execute the PMB as planned Perform Continuous Risk Management (CRM) What does Done Look like in Meaningful Units of Measures? ConOps, SOO, SOW Technical And Operational Delivery Plan Incremental Maturity Assessment (MOE, MOP, TPM, KPP) Assess Physical Percent Complete Risk Identification How are we going to get there? Integrated Master Plan (IMP) Work Breakdown Structure (WBS) Integrated Master Schedule (IMS) Iterative and Incremental Delivery Risk Analysis What Resources do we need along the way? Resource Management Plan (RMP) Future Performance Forecasting Risk Planning What Impediments will we encounter along the way? 4 Levels Of Uncertainty Planning Technical And Programmatic Risks Assigned To All WBS Deliverables Risk Adjustment To Cost And Schedule Measures Risk Adjusted Performance Measurement Baseline Risk Tracking How do we Measure Progress to plan? Measures Of Effectiveness (MOE) Measures Of Performance (MOP) Technical Performance Measures (TPM) Earned Value Management (EVM) Risk Control Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016 5
  • 6. + Increasing Probability of Program Success through Information Radiators  WBS – it shows what is being delivered and what work processes are used for this delivery (MIL-STD-881-C).  Integrated Master Plan (IMP) – shows how the deliverables increase in their maturity toward the final product.  Integrated Master Schedule (IMS) – shows the sequence of work to increases the maturity of the deliverables.  Programmatic and Technical Risk Management – shows what reducible and irreducible risks are present on the project and what mitigation activities are needed increase the probability of project success.  Performance Measurement and Reporting – shows how Physical Percent Complete to date, Estimate to Complete, and Estimate At Complete are compared to plan.  Root Cause Analysis ‒ most efforts are project corrective actions are addressing symptoms not the Cause. Without identify the Root Cause the symptoms are not removed. Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016 6
  • 7. + Capabilities Based Planning  Define operational concepts as capabilities.  Define Capabilities through Scenarios or Use Cases.  Asses Needs, Cost, and Risks of the Capability simultaneously.  Define explicit, balanced, and feasible alternatives. Planning, under uncertainty, to provide capabilities suitable for a wide range of modern–day challenges and circumstances while working within an economic framework that necessitates choice.” Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016 7
  • 8. + Identify Needed Capabilities 8 What Should We Do? Where Are We Now? Abstracted from: “Capabilities‒Based Planning – How It Is Intended To Work And Challenges To Its Successful Implementation,” Col. Stephen K. Walker, United States Army, U. S. Army War College, March 2005 Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016
  • 9. + Measures of Effectiveness (MOE) 9 Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016 Measures of Effectiveness …  Are stated in units meaningful to the buyer,  Focus on capabilities independent of any technical implementation,  Are connected to the mission success. Operational measures of success that are closely related to the achievements of the mission or operational objectives evaluated in the operational environment, under a specific set of conditions. MoE’s Belong to the End User “Technical Measurement,” INCOSE–TP–2003–020–01
  • 10. + Measures of Performance (MOP) 10 Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016 Measures of Performance are …  Attributes that assure the system has the capability and capacity to perform,  Assessment of the system to assure it meets design requirements to satisfy the MoE. Measures that characterize physical or functional attributes relating to the system operation, measured or estimated under specific conditions. “Technical Measurement,” INCOSE–TP–2003–020–01 MoP’s belong to the Program – Developed by the Systems Engineer, Measured By CAMs, and Analyzed by PP&C
  • 11. + Technical Performance Measures (TPM) 11 Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016 Technical Performance Measures …  Assess design progress,  Define compliance to performance requirements,  Identify technical risk,  Are limited to critical thresholds,  Include projected performance. Attributes that determine how well a system or system element is satisfying or expected to satisfy a technical requirement or goal “Technical Measurement,” INCOSE–TP–2003–020–01
  • 12. + Key Performance Parameters (KPP) 12 Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016 Key Performance Parameters …  Have a threshold or objective value,  Characterize the major drivers of performance,  Are considered Critical to Customer (CTC). Measures that Represent the capabilities and characteristics so significant that failure to meet them can be cause for reevaluation, reassessing, or termination of the program The acquirer defines the KPPs during the operational concept development – KPPs say what DONE looks like “Technical Measurement,” INCOSE–TP–2003–020–01
  • 13. + Capabilities Map from Strategy to Project Execution 13 Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016 Performance Goal Key Performance Indicator (KPI) Critical Success Factor (CSF) Strategic Objective Be The Preferred Supplier Of Business Applications Traceable to Increased Customer Revenue Provide on-time, on- budget, on- specification for our enterprise applications Budget Variance Schedule Variance % Requirements Variance BPI ≥ 0.95 CPI ≥ 0.97 Function Points Delivered ≥ 90% Target Provide scalable platform for acquisition and growth of our customer base Cost of Delivery Impact Performance Impact Global Operational Baseline Declining Cost per Customer SLA Compliance ≥ 0.98 24/7/365 Non-Stop Operations What How Measures Vision Positively Impact Financial Performance Why Top Down Making the effect-and-cause connection between Strategy and Key Performance Indicators is the role of an Balanced Scorecard automation system Flow Down from Strategy to KPIs Making the effect-and-cause connection between Strategy and Key Performance Indicators is the role of an Balanced Scorecard automation system
  • 14. + WBS is Paramount  The WBS describes the product and services needed to produce the products  The Work Breakdown Structure development starts with NWS Policy Directive 70-3, from DOC Scalable Project Management Methodology, §7.2.4 in accordance with PMI® Practice Standard for Work Breakdown Structure  A starting point for developing the WBS is MIL-STD-881-C.  Each Federal Agency may have their own instance of the 881-C guide. Without a WBS, we don’t know what is being delivered by the project. We don’t know what End Item Deliverables are related to other items – parents of the final deliverables. Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016 14
  • 15. + The WBS …  … is a product-oriented family tree composed of hardware, software, services, data, and facilities. The family tree results from systems engineering efforts during the acquisition of a defense materiel item.  … a WBS displays and defines the product, or products, to be developed and/or produced. It relates the elements of work to be accomplished to each other and to the end product. In other words, the WBS is an organized method to breakdown a product into sub-products at lower levels of detail.  … can be expressed to any level of detail. While the top three levels are the minimum required for reporting purposes on any program or contract, effective management of complex programs requires WBS definition at considerably lower levels.  This is particularly true of items identified as high-cost, high-risk, or high technical interest.  Under these circumstances, it is critical to define the product at a lower level of WBS detail.  In this case, managers should distinguish between WBS definition and WBS reporting.  The WBS should be defined at the level necessary to identify work progress and enable effective management, regardless of the WBS level reported to program oversight. Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016 15
  • 16. + Integrated Master Plan (IMP)  The IMP is a hierarchy of program events, in which each event is supported by specific accomplishments, and each accomplishment is based on satisfying specific criteria to be considered complete.  The IMP consists of three elements  Program Events  Significant Accomplishments  Accomplishment Criteria The Integrated Master Plan is a hierarchical description of what Done looks like in the form of increasing maturity of the program’s deliverables and the capabilities they provide Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016 16
  • 17. + IMP / IMS Structure 17 Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016 IMS IMP Describes how program capabilities will be delivered and how these capabilities will be recognized as ready for delivery Supplemental Schedules (CAM Notebook) Work Packages and Tasks Criteria Accomplishment Events or Milestones
  • 18. + Maturity Process Flow 18 Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016
  • 19. + The Integrated Master Plan  Program planning involves developing and maintaining plans for all program processes, including those required for effective program office-contractor interaction.  Once the contract is signed and schedule, costs, and resources from the contractor are established, the program plan takes into account, at an appropriate level of detail, the contractor's estimations for the program.  The IMP should provide sufficient definition to track the step-by-step completion of the required accomplishments for each event, and to demonstrate satisfaction of the completion criteria for each accomplishment. Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016 19
  • 20. + The Integrated Master Plan …  Provides flexibility in performing detailed program execution planning, organization, and scheduling within any existing Request for Proposal (RFP) constraints.  Serve as the basis for detailed Execution IMS.  Provides basis of integrated product development and systems integration approaches  Serve as the basis for ensuring mutual understanding of Government expectations and agreement on the program content, program plan, schedule, and risk.  Provide detailed integrated execution plan and supporting schedule, clearly identifying what has to be done and when it must be done. Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016 20
  • 21. + The IMP enables Program Management to…  Identify and assess actual progress versus the planned progress  Monitor the program critical path and help develop workarounds to problem areas  Assess program maturity  Assess the status of risk management activities based on the inclusion of the program risk mitigation activities in the IMP and IMS  Assess the progress on selected Key Performance Parameters (KPPs) and Technical Performance Measures (TPMs)  Provide an objective, quantitative basis for the contractor’s performance assessment Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016 21
  • 22. + IMP for Cloud Deployment 22 Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016
  • 23. + Integrated Master Schedule (IMS)  Packages of Work and their Tasks, implement the deliverables from the Work Breakdown Structure.  These Work Packages should have a singular outcome matched to a deliverable or service in the WBS  The assessment of the maturity of these outcomes is done in the IMP using the Accomplishment Criteria that show the increasing maturity of the Significant Accomplishments.  Each Work Package has some measure of Performance or Technical Performance Measure for the deliverable. The IMS is an integrated, networked schedule containing all the detailed discrete work packages and planning packages (or lower level tasks of activities) necessary to support the events, accomplishments, and criteria of the IMP. Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016 23
  • 24. + Vertical and Horizontal Traceability between IMP and IMS 24 Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016 Program Events Define the maturity of a Capability at a point in time. Significant Accomplishments Represent requirements that enable Capabilities. Accomplishment Criteria Exit Criteria for the Work Packages that fulfill Requirements. Work Package Work Package Work Package Work Package Work Package Work Package Work package
  • 25. Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016 25
  • 26. + Managing Technical and Programmatic Risk  Risk Management is how adults manage projects ‒ Tim Lister  All risk comes from uncertainty  The integrated master schedule must be risk adjusted for these uncertainties  Specific work must be in the IMS for reducible uncertainties  Schedule, cost, and technical margin must be in the IMS for irreducible uncertainties All risk comes from uncertainty. Uncertainty comes in two forms Reducible uncertainty (Epistemic) Irreducible uncertainty (Aleatory) Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016 26
  • 27. + All Risk Comes from Uncertainty Uncertainty Irreducible (Aleatory) Reducible (Epistemic) Natural Variability Ambiguity Ontological Uncertainty Probabilistic Events Probabilistic Impacts Periods of Exposure Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2016 27
  • 28. Technical Risk Management Track and Control Performance Deviations Deliberate and recommend a decision alternative Risk analysis of decision alternatives, performing trade studies and ranking Propose and/or identify decision alternatives Formulate objectives Hierarchy and Technical Performance Measures Stakeholder expectations, requirements definition and management Design solutions, technical planning Design solution, technical planning, and decision analysis Technical planning and decision analysis Decision analysis, lessons learned, knowledge management Identify Analyze Plan Track Control Decide and implement decision alternatives Communicate Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2016 28
  • 29.
  • 30. + Performance Measurement and Reporting  Physical Percent Complete is defined as tangible evidence of progress to plan.  Define this Physical Percent Complete before the work starts in units of measure meaningful to the decision makers  Effectiveness  Performance  Key Performance Parameters Performance measurement is always based on tangible evidence of progress to plan. The passage of time and consumption of resources is not the basis of performance measurement. Physical Percent Complete of some predefined measure of Effectiveness, Performance, or Key Parameter is. Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016 30
  • 31. Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016 31 You Know you're applying the 5 Principals of Project Success if you … 1 … have a defined Mission, Vision, Capabilities, and Requirements ‒ by which to create … 2 … the Plan for fulling these capabilities and connected Requirements and Schedule for producing the needed outcomes to meet this Plan ‒ and have … 3 … allocated enough Time, Money, and Resources to increase the probability of the project’s success ‒ and you can … 4 … know what Risks are in front of you and their retirement or handling plans ‒ and you can … 5 … confirm progress as Physical Percent Complete for each planned Deliverables in the Plan “on or before the planned time and “at or below” the planned cost.
  • 32. + Monthly Business Rhythm  Each participate in the Business Rhythm, the data produced and consumed, interconnections Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016 32
  • 33. + Root Cause Analysis 1. Define the Problem. 2. Determine the Causal Relationships. 3. Provide a Graphical Representation of Cause and Effect that is not linear thinking. 4. Provide Evidence for each Cause and Effect. 5. Determine if each Cause is Sufficient and Necessary. 6. Identify Effective Solutions  Finding the cause is needed.  Preventing the effect is needed.  But installing an effective solution is the desired business outcome. 7. Implement And Track the Effective Solutions. When the project goes bad. Root Cause Analysis is the method of problem solving that identifies the root causes of failures or problems. A root cause is the source of a problem and its resulting symptom, that once removed, corrects or prevents an undesirable outcome from recurring. Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016 33
  • 34. + The Notion of Root Cause Analysis Symptom: The result or outcome of the problem. An observation  We have late additions to the release that break the software  We have “core” defects that should been caught long before production release  We make changes to software, stored procedures, or the database only to discover it was a mistake.  We make promises to the customer before assessing the impact on our resources or the technical difficulty Problem:  Test coverage insufficient the detect latent bugs in software  We commit before understanding the consequences Root Cause:  No software structure to determine test coverage or change impacts on baseline.  No detailed understanding of our capacity for work and productivity of our technical staff Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2018 34
  • 35. +  Causes are never part of a Linear Chain found in standard Fishbone diagram or narrative approach.  Look for causes to create the effect. Two causes are needed for each Effect.  Conditions – may exist prior to the Effect. Or conditions may be in motion or active during the Effect. Conditions are the causes often ignored or beyond our knowledge.  Actions – momentary causes that bring conditions together to cause an effect. Actions are causes most easily recognized.  Connect all causes (Actions and Conditions) with a Caused By phrase to either an action or a condition.  Support each Cause with evidence or an answered question. For each Primary Effect we need ask why that Effect occurred. Principles of the Cause and Effect Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2016 35
  • 36. + Cause and Effect are Part of a Continuum of Causes  Causes are never linear.  Causes branch into at least two other causes, each time we ask why of an effect and if we ask why of each of those causes we find an expanding set of causes like those to the right. Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2016 36
  • 37. + Four Root Causes for Program Cost and Schedule Overruns 37 Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2018 Unrealistic Performance Expectations, missing Measures of Effectiveness (MOE) and Measures of Performance (MOP). Unrealistic Cost and Schedule estimates based on inadequate risk adjusted growth models. Inadequate assessment of risk and unmitigated exposure to these risks without proper handling plans. Unanticipated technical issues without alternative plans and solutions to maintain effectiveness. Unanticipated Cost and Schedule Growth TheLensofPerformance Assessment “Borrowed” with permission from Mr. Gary Bliss, Director, Performance Assessment and Root Cause Analysis (PARCA), Office of Assistant Secretary of Defense for Acquisition, Technology and Logistics.
  • 38. Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 ― 2018 38 Root Causes Have Root Causes It’s not a matter of asking 5 Whys You must keep asking until you reach the end of the chain or action and condition
  • 39. + Resources (1)  MIL-STD-881-C defines how to build a Work Breakdown Structure ‒ http://quicksearch.dla.mil/Transient/38A8B775A4BF4CEF8871CEF7E EA34156.pdf  Guestimate ‒ a spread sheet for making estimating https://www.getguesstimate.com/  Reality Charting, using the Apollo Method, http://www.apollorootcause.com/media/32309/realitycharting_- _seven_steps_to_effective_problem-solving_and_strategie....pdf  XMIND – low cost Mind Mapping Tool ‒ www.xmind.com Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016 39
  • 40. + Resources (2)  “Guide to Capabilities Based Planning: The Technical Cooperation Program Joint Systems and Analysis Group Technical Panel 3,” www.acq.osd.mil/ttcp/reference/docs/JSA-TP-3-CBP-Paper-Final.doc  “Naval Analytical Capabilities: Improving Capabilities-Based Planning,” Committee on Naval Analytical Capabilities and Improving Capabilities-Based Planning,” Naval Studies Board, Division on Engineering and Physical Sciences, National Research Council, https://www.nap.edu/download/11455  RiskyProject ‒ Monte Carlo Simulation tool starting with a Risk Register and modeling tools for the Reducible and Irreducible risks ‒ www.riskyproject.com Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016 40
  • 41. + Resources (2)  Risk Management Toolkit, Mitre Systems Engineering Process Office, http://www2.mitre.org/work/sepo/toolkits/risk/index.html  Risk Matrix tool is free Excel tool downloaded from here ‒ http://www2.mitre.org/work/sepo/toolkits/risk/ToolsTechniques/RiskMatrix.ht ml  Risk Radar tool is a Access Database to downloaded from here ‒ http://www2.mitre.org/work/sepo/toolkits/risk/ToolsTechniques/RiskRadar.ht ml  Software Engineering Institute Continuous Risk Management, http://www.sei.cmu.edu/risk/  “What’s Wrong With Risk Matrices,” Tony Cox, https://www.researchgate.net/profile/Louis_Cox/publication/5432360_ What's_Wrong_with_Risk_Matrices/links/55582a5408ae980ca60e2e8 e.pdf Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016 41
  • 42. + Resources (3)  Design Structure Matrix  http://www.dsmweb.org/  Design Structure Matrix Methods and Applications https://mitpress.mit.edu/books/design-structure-matrix-methods-and- applications  International Cost Estimating and Analysis Association, http://www.iceaaonline.com/  College of Performance Management, www.mycpm.org  “Opportunity Management: Be Careful What You Ask For,” Edmund Conrow, https://acc.dau.mil/adl/en- US/193752/attachment/32944/conr_ma08_1.pdf Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016 42
  • 43. + Resources (4)  Society for Effective Lessons Learned Sharing (SELLS), http://www.au.af.mil/au/awc/awcgate/lessons/sells/llsite.pdf  Software Engineering Institute, Continuous Risk Management, https://resources.sei.cmu.edu/library/asset-view.cfm?assetid=30856  Risk Informed Decision Making, NASA/SP-2010-576, https://ntrs.nasa.gov/archive/nasa/casi.ntrs.nasa.gov/20100021361.pd f  “An Implementation of the Lurie-Goldberg Algorithm Scheduling Risk Analysis,” http://www.slideserve.com/tahir/an-implementation-of-the- lurie-goldberg-algorithm-in-schedule-risk-analysis Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016 43
  • 44. + Resources (5)  ACQuipedia, https://dap.dau.mil/acquipedia/Pages/Default.aspx  Defense Acquisition University tools and resources, https://www.dau.mil/tools#All|All||recent  Mitre Systems Engineering Handbook, http://www.mitre.org/sites/default/files/publications/se-guide-book- interactive.pdf  Implementing the Program Management Improvement and Accountability Act of 2015, https://www.pmi.org/- /media/pmi/documents/public/pdf/business-solutions/program- management-accountability-act.pdf  Making the Impossible Possible: Leading Extraordinary Performance ‒ The Rocky Flats Story, Kim Cameron and Marc Lavine, Berrett- Koehler, 2006. Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016 44
  • 45. + Resources (6)  Beyond Bullet Points, Cliff Atkinson, Microsoft Press, 2011.  Effective Risk Management: Some Keys to Success, Edmund Conrow, AIAA Press, 2003.  Integrated Master Plan and Integrated Master Schedule Preparation and Use Guide, https://www.acq.osd.mil/se/docs/IMP_IMS_Guide_v9.pdf  Defense Agile Acquisition Guide: Tailoring DoD IT Acquisition Program Structures and Processes to Rapidly Deliver Capabilities, https://www.mitre.org/publications/technical-papers/defense-agile- acquisition-guide-tailoring-dod-it-acquisition-program Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016 45
  • 46. + Resources (7)  How to Lie with Statistics, Darrell Huff, W. W. Norton, 1993. Orginal published 1953  “Society for Effective Lessons Learned Sharing (SELLS),” http://www.au.af.mil/au/awc/awcgate/lessons/sells/llsite.pdf  NASA’s Management of the Orion Multi-Purpose Crew Vehicle Program, https://oig.nasa.gov/audits/reports/FY16/IG-16-029.pdf  Integrated Master and Integrated Master Schedule Preparation and Use Guide, https://www.acq.osd.mil/se/docs/IMP_IMS_Guide_v9.pdf Performance–Based Project Management®, Copyright © Glen B. Alleman, 2002 - 2016 46

Notes de l'éditeur

  1. The five immutable principles of project management are: Know where you are going by defining “done” at some point in the future. This point may be far in the future – months or years from now. Or closer in the future days or weeks from now. Have some kind of plan to get to where you are going. This plan can be simple or it can be complex. The fidelity of the plan depends on the tolerance for risk by the users of the plan. Understand the resources needed to execute the plan. How much time and money is needed to reach the destination. This can be fixed or it can be variable. Identify the impediments to progress along the way to the destination. Have some means of removing, avoiding, or ignoring these impediments. Have some way to measure your planned progress, not just your progress. Progress to Plan must be measured in units of physical percent complete.