Elvira Huizeling, responsible for Special Projects in the Capture team of the ROAD project, lead a Global CCS Institute webinar on the ROAD CO2 Capture Plant FEED Study report. ROAD stands for ‘Rotterdam Opslag en Afvang Demonstratieproject’ (Rotterdam Capture and Storage Demonstration Project) and is one of the largest integrated demonstration projects in the world for the capture and storage of CO2.
ROAD had just completed the front-end engineering design (FEED) study for the capture plant as performed by Fluor. The main results from the FEED study were presented in this webinar, including topics such as technology selection, process flow diagrams, heat and mass balances, layout designs, cooling studies, capital and O&M cost estimates and project schedules.
A recording of the webinar can be seen at http://www.globalccsinstitute.com/community/events/2011/10/27/webinar-road-project-co2-capture-plant-feed-study
5. Co-operating Partners ROAD
• Maasvlakte CCS Project C.V. is a joint venture of:
• E.ON Benelux
• Electrabel Nederland (GDF SUEZ Group)
• In co-operation with intended partners:
• TAQA Energy
• GDF SUEZ E&P
• With financial support of:
• European Commission (EU)
• Government of the Netherlands
• Global CCS Institute
Page 5
6. Objectives ROAD
• Demonstrate feasibility (technical, economic) of large-scale, integrated
CCS chain
• Capture and storage of ca. 1.1 Mton CO2 per year in (nearly) depleted gas
reservoirs in period of 2015 – 2020
• Acquire knowledge and experience with deployment of large-scale,
integrated CCS chain:
• Technical
• Legal
• Economic
• Organizational
• Social
Page 6
7. Power plant
(Maasvlakte)
ROAD CO2 Capture, Transport and Storage Chain
CO2
capture
Platform
compression P-18A
pipeline 20 meters
5 km onshore
(Maasvlakte)
pipeline 20 km over seabed (North Sea)
3,5 km
CO2 storage in
depleted gasreservoirs
Not on scale
Page 7
14. Boundary of this work
• In this report you can find a short inventarisation on all topics relevant
for taking a Final Investment Decision, based on GCCSI know-how
• Work reported here is about Capture Front End Engineering and Design
(FEED), not about complete project
• Integration with power plant is included
Page 14
16. Base installation
• E.ON Maasvlakte Power Plant 3 (Rotterdam, The Netherlands)
• Output : 1.070 MWe
• Efficiency : 46% (LHV)
• Operational : End 2012
• Capture ready (conform TÜV NORD requirements)
Page 16
17. CCS@MPP3 – Overview Interfaces
MPP3
Treated Flue gas Carbon Capture
Flue gas
Flue gas condensate CO2 to storage
LP-steam
(steam) condensate
CW to outletpond
CW supply
Electric power
Cold Condensate
Heated condensate
Demin water
Solvent Reclaimer waste
Caustic Soda
Instrument air
Nitrogen
17
Page 17
25. Requested permit values
EIA: Tabel 3.5: Emission in stack (MPP3 and CC-Plant)
Operational situation: Operational situation:
100% flue gas through CC-Plant ca. ¼ flue gas through CC-Plant
1) NO2
Component Yearly value Mass flow Yearly value Mass flow based on
5% of NOx
(6% O2) [tonnes per (6% O2) [tonnes per
[mg/Nm3] year] [mg/Nm3] year]
MEA 11 6.2 2.0 6.2
NH3 1 5.0 2.8 1.0 3.1
NOx as NO2 77.6 44.0 70.0 215.0
SO2 0 0 31 95.0
HCl 3.7 2.1 2.9 9.0
HF 0.5 0.3 0.4 1.3
CxHy 23 13 10 31
Fly ash 2 1.1 3.3 10
CO2 - 18,000 - 687,000
Page 25
26. Other streams to consider for permit
• Water
• Process water
• Cooling water
• Demineralized water
• Waste
• Other chemicals
• Sodium hydroxide
• Solvent
• Hydrogen
• Nitrogen
• Activated Coal
• Noise
Page 26
27. HAZID
• Hazid was performed in June 2010 and three actions still remained for
EPC phase
• First item is already picked up in discussions with authorities
No: Description: By: Due: Response: By: Date:
Discussions with authorities need to be opened
to discuss impact of capture plant on operating
7 permit, with respect to emissions. JV Project EPC
Capture plant and MPP3 operators to be trained
10 regarding emergency response planning. JV operations EPC
Ensure all power lines are identified prior to any
20 excavation or piling work. Construction EPC
Page 27
29. CO2 stream specification
• The boundaries of the CO2 specification have been defined
• Purity of CO2 99.9%
• From all elements produced in post combustion capture plant only H2O
and O2 are of any relevance.
• Details like the trip values still have to be determined (at which amount
of for example H2O and O2 the plant must be stopped?)
• Most important is the temperature and pressure of the stream to
determine the phase of the stream
Page 29
30. Compressor will operate in supercritical area
Assumed operating conditions
for ROAD:
Pressure max 129 bar (a)
T between 40 and 80 °C
Page 30
32. CAPEX for Capture plant of 250 MWe excl. integration
The capital cost estimate breakdown for the capture plant is as follows:
• Equipment: 60 – 70 MM Euro
• Materials and Labor: 65 – 75 MM Euro
• Engineering: 15 – 20 MM Euro
• Indirect Field Costs: 5 – 10 MM Euro
• Owner’s costs (Operator training & first fills): 1 – 2 MM Euro
• Financial and other costs: 25 – 35 MM Euro
• Total: 170 – 210 MM Euro
Page 32
35. Time Path and Milestones
14 July 2009 : EU project proposal submission
September 2009 : Project selection by EU
May 2010 : Grant decision by Government of the Netherlands
September 2010 : Publication starting note Environmental Impact Assessment
Q4 2011 : EIA and permit procedures
2013 : Power plant (MPP3) operational
2015 : Integrated CCS chain operational
2015-2020 : Demonstration phase CCS chain
Page 35