CmmIi Assignment Vish 04 Nov 2003
- 1. SM
CMMI
Pittsburgh, PA 15213-3890
Pre-Class Assignment
Submitted by N Visweswara
Satyam Computer Services Ltd.,
Intermediate Concepts of CMMI
Sponsored by the U.S. Department of Defense
© 2002 by Carnegie Mellon University
This material is approved for public release. Distribution is limited by the Software Engineering Institute to
attendees.
Intermediate CMMI V 1.1 PMC 053102 - Page 1
- 2. SM
CMMI
Pittsburgh, PA 15213-3890
Measurement and Analysis
Intermediate Concepts of CMMI
Sponsored by the U.S. Department of Defense
© 2002 by Carnegie Mellon University
This material is approved for public release. Distribution is limited by the Software Engineering Institute to
attendees.
Intermediate CMMI V 1.1 PMC 053102 - Page 2
- 3. SM
CMMI
Pittsburgh, PA 15213-3890
Importance of Measurement and Analysis
b) Monitor and Measure progress towards Strategic Process
Improvement Goals
c) Improve communication of development status and product
quality by providing a standard set of metrics for use on
projects
d) Allow PMs and Project Review Authorities (PRA) better
visibility into project and process performance
e) To provide organizational measurement data base thus
facilitating acquisition and bidding proposals
Sponsored by the U.S. Department of Defense
© 2002 by Carnegie Mellon University
This material is approved for public release. Distribution is limited by the Software Engineering Institute to
attendees.
Intermediate CMMI V 1.1 PMC 053102 - Page 3
- 4. SM
CMMI
Pittsburgh, PA 15213-3890
Benefits of M and A
c) Quantitative Management of Projects through Project
Performance Metrics
d) Determination of Project Process Capability
e) PRA Metrics helps in providing objective, quantitative,
information for senior management
f) Organizational metrics helps in measuring organizational
process capability
Sponsored by the U.S. Department of Defense
© 2002 by Carnegie Mellon University
This material is approved for public release. Distribution is limited by the Software Engineering Institute to
attendees.
Intermediate CMMI V 1.1 PMC 053102 - Page 4
- 5. SM
CMMI
Pittsburgh, PA 15213-3890
M and A depends on
c) Project Planning Process area
d) Project Monitoring & Control Process area
e) Config Management Process area
f) Requirements Development Process area
g) Requirements Management Process area
h) Organizational Process Definition Process area
i) Quantitative Project Management Process area
Sponsored by the U.S. Department of Defense
© 2002 by Carnegie Mellon University
This material is approved for public release. Distribution is limited by the Software Engineering Institute to
attendees.
Intermediate CMMI V 1.1 PMC 053102 - Page 5
- 6. SM
CMMI
Pittsburgh, PA 15213-3890
PAs that depend on M & A
c) Project Monitoring & Control Process area
d) Config Management Process area
e) Requirements Management Process area
f) Quantitative Project Management Process area
Sponsored by the U.S. Department of Defense
© 2002 by Carnegie Mellon University
This material is approved for public release. Distribution is limited by the Software Engineering Institute to
attendees.
Intermediate CMMI V 1.1 PMC 053102 - Page 6
- 7. SM
CMMI
Pittsburgh, PA 15213-3890
Ordering of SPs in M & A
• SG 1 Align Measurement and Analysis Activities [PA154.IG101]
• SP 1.1 Establish Measurement Objectives
• SP 1.2 Specify Measures
• SP 1.3 Specify Data Collection and Storage Procedures
• SP 1.4 Specify Analysis Procedures
• SG 2 Provide Measurement Results [PA154.IG102]
• SP 2.1 Collect Measurement Data
• SP 2.2 Analyze Measurement Data
• SP 2.3 Store Data and Results
• SP 2.4 Communicate Results
Sponsored by the U.S. Department of Defense
© 2002 by Carnegie Mellon University
This material is approved for public release. Distribution is limited by the Software Engineering Institute to
attendees.
Intermediate CMMI V 1.1 PMC 053102 - Page 7
- 8. SM
CMMI
Pittsburgh, PA 15213-3890
Generic Practices and M & A
• GG 2 Institutionalize a Managed Process [CL103.GL101]
• GP 2.1 (CO 1) Establish an Organizational Policy
• GP 2.2 (AB 1) Plan the Process
• GP 2.3 (AB 2) Provide Resources
• GP 2.4 (AB 3) Assign Responsibility
• GP 2.5 (AB 4) Train People
• GP 2.6 (DI 1) Manage Configurations
• GP 2.7 (DI 2) Identify and Involve Relevant Stakeholders
• GP 2.8 (DI 3) Monitor and Control the Process
• GP 2.9 (VE 1) Objectively Evaluate Adherence
• GP 2.10 (VE 2) Review Status with Higher Level Management
Sponsored by the U.S. Department of Defense
© 2002 by Carnegie Mellon University
This material is approved for public release. Distribution is limited by the Software Engineering Institute to
attendees.
Intermediate CMMI V 1.1 PMC 053102 - Page 8
- 9. SM
CMMI
Pittsburgh, PA 15213-3890
“Critical” SPs in M & A
SG 1 Align Measurement and Analysis Activities [PA154.IG101]
• SP 1.1 Establish Measurement Objectives
• Sub practice1 Document information needs and objectives
• Sub practice 2 Prioritize information needs and objectives
• Sub practice 3 Document, review, and update measurement
objectives
• Sub practice 4 Provide feedback for refining and clarifying
information needs and objectives as necessary
• Sub practice 5 Maintain trace ability of the measurement
objectives to the identified information needs and objectives
Sponsored by the U.S. Department of Defense
© 2002 by Carnegie Mellon University
This material is approved for public release. Distribution is limited by the Software Engineering Institute to
attendees.
Intermediate CMMI V 1.1 PMC 053102 - Page 9
- 10. SM
CMMI
Pittsburgh, PA 15213-3890
“Critical” SPs in M & A
SG 1 Align Measurement and Analysis Activities [PA154.IG101]
• SP 1.1 Establish Measurement Objectives
• Sub practice1 Document information needs and objectives
Refer next slide
Sponsored by the U.S. Department of Defense
© 2002 by Carnegie Mellon University
This material is approved for public release. Distribution is limited by the Software Engineering Institute to
attendees.
Intermediate CMMI V 1.1 PMC 053102 - Page 10
- 11. SM
CMMI
Pittsburgh, PA 15213-3890
Project
Organizational Goals Performance Goals
*
Project Performance
Organizational Process • Project Management
Performance
• Project Process Capability
• Support Cost Estimation for
Proposals and Program • Emphasis on Predictive
Rebaselining Capability
• Support Determination of
Organizational Process Capability
Senior Management Evaluation
• Top Level Project Performance
• Organizational Health
• Emphasis on Early Warning
* Organizational Goals flowed down
Sponsored by the U.S. Department of Defense
to project and proposal
© 2002 by Carnegie Mellon University
performance evaluation
This material is approved for public release. Distribution is limited by the Software Engineering Institute to
attendees.
Intermediate CMMI V 1.1 PMC 053102 - Page 11
- 12. SM
CMMI
Pittsburgh, PA 15213-3890
“Critical” SPs in M & A
SG 1 Align Measurement and Analysis Activities [PA154.IG101]
• SP 1.1 Establish Measurement Objectives
• Sub practice 3 Document, review, and update measurement objectives
• a Strategic plans
• b.Established management objectives
• c.Interviews with managers and others who have information needs
• d.External industry benchmarks
• e.Process improvement plans
• f.Formal requirements or contractual obligations
• gProject plans
• hMonitoring of project performance
• i.Recurring or other troublesome management or technical problems
• j.Experiences of other projects or organizational entities
Sponsored by the U.S. Department of Defense
© 2002 by Carnegie Mellon University
This material is approved for public release. Distribution is limited by the Software Engineering Institute to
attendees.
Intermediate CMMI V 1.1 PMC 053102 - Page 12
- 13. SM
CMMI
Pittsburgh, PA 15213-3890
“Critical” SPs in M & A
SG 1 Align Measurement and Analysis Activities [PA154.IG101]
• SP 1.1 Establish Measurement Objectives
• Sub practice 5 Maintain trace ability of the measurement
objectives to the identified information needs and objectives
Microsoft Word
Document
Sponsored by the U.S. Department of Defense
© 2002 by Carnegie Mellon University
This material is approved for public release. Distribution is limited by the Software Engineering Institute to
attendees.
Intermediate CMMI V 1.1 PMC 053102 - Page 13
- 14. SM
CMMI
Pittsburgh, PA 15213-3890
“Critical” SPs in M & A
SG 1 Align Measurement and Analysis Activities [PA154.IG101]
• SP 1.4 Specify Analysis Procedures
• Sub practice1 Specify and prioritize the analysis that will be
conducted and the reports that will be prepared
• Sub practice 2 Select appropriate data analysis methods and
tools
• Sub practice 3 Specify administrative procedures for analyzing the
data and communicating the results
• Sub practice 4 Review and update the proposed content and
format of the specified analysis and reports
• Sub practice 5 Update measures and measurement objectives as
necessary
• Sub practice 6 Specify criteria for evaluating the utility of the
analysis results, and of the conduct of the M&A activities
Sponsored by the U.S. Department of Defense
© 2002 by Carnegie Mellon University
This material is approved for public release. Distribution is limited by the Software Engineering Institute to
attendees.
Intermediate CMMI V 1.1 PMC 053102 - Page 14
- 15. SM
CMMI
Pittsburgh, PA 15213-3890
“Critical” SPs in M & A
SG 1 Align Measurement and Analysis Activities [PA154.IG101]
• SP 1.4 Specify Analysis Procedures
• Sub practice 2 Select appropriate data analysis methods and
tools
Microsoft Word
Document
Sponsored by the U.S. Department of Defense
© 2002 by Carnegie Mellon University
This material is approved for public release. Distribution is limited by the Software Engineering Institute to
attendees.
Intermediate CMMI V 1.1 PMC 053102 - Page 15
- 16. SM
CMMI
Pittsburgh, PA 15213-3890
“Critical” SPs in M & A
SG 1 Align Measurement and Analysis Activities [PA154.IG101]
• SP 1.4 Specify Analysis Procedures
• Sub practice 4 Review and update the proposed content and
format of the specified analysis and reports
The measurements may also be derived using the Goal Question
Metric (GQM) method. The GQM method includes:
• a. Identifying the information goal
• b. Identifying questions that determine whether the goal is being
met
• c. Identifying the specific parameters that must be measured to
answer the questions
• d.Applying the measures selected and evaluating their usefulness
Sponsored by the U.S. Department of Defense
© 2002 by Carnegie Mellon University
This material is approved for public release. Distribution is limited by the Software Engineering Institute to
attendees.
Intermediate CMMI V 1.1 PMC 053102 - Page 16
- 17. SM
CMMI
Pittsburgh, PA 15213-3890
“Critical” SPs in M & A
SG 1 Align Measurement and Analysis Activities [PA154.IG101]
• SP 1.4 Specify Analysis Procedures
• Sub practice 6 Specify criteria for evaluating the utility of the
analysis results, and of the conduct of the M&A activities
• a) Divisions shall establish and maintain measurement objectives
derived from identified organizational needs and objectives.
• b) Divisions shall derive organizational measurements based on
organizational measurement objectives.
• c) Projects shall establish and maintain measurement objectives
derived from organizational objectives and project needs and
objectives.
• d) Projects shall derive project measurements based on project
measurement objectives.
Sponsored by the U.S. Department of Defense
© 2002 by Carnegie Mellon University
This material is approved for public release. Distribution is limited by the Software Engineering Institute to
attendees.
Intermediate CMMI V 1.1 PMC 053102 - Page 17
- 18. SM
CMMI
Pittsburgh, PA 15213-3890
“Critical” SPs in M & A
• SG 2 Provide Measurement Results [PA154.IG102]
• SP 2.1 Collect Measurement Data
• SP 2.2 Analyze Measurement Data
• SP 2.3 Store Data and Results
• SP 2.4 Communicate Results
Sponsored by the U.S. Department of Defense
© 2002 by Carnegie Mellon University
This material is approved for public release. Distribution is limited by the Software Engineering Institute to
attendees.
Intermediate CMMI V 1.1 PMC 053102 - Page 18
- 19. SM
CMMI
Pittsburgh, PA 15213-3890
“Critical” SPs in M & A
• SG 2 Provide Measurement Results [PA154.IG102]
• SP 2.2 Analyze Measurement Data
• Sub practice 1 Conduct initial analysis, interpret the
results, and draw preliminary conclusions
• Sub practice 2 Conduct additional M&A as necessary and
prepare results for presentation
• Sub practice 3 Review the initial results with relevant
stakeholders
• Sub practice 4 Refine criteria for future analysis
Sponsored by the U.S. Department of Defense
© 2002 by Carnegie Mellon University
This material is approved for public release. Distribution is limited by the Software Engineering Institute to
attendees.
Intermediate CMMI V 1.1 PMC 053102 - Page 19
- 20. SM
CMMI
Pittsburgh, PA 15213-3890
“Critical” SPs in M & A
• SG 2 Provide Measurement Results [PA154.IG102]
• SP 2.2 Analyze Measurement Data
• Sub practice 1 Conduct initial analysis, interpret the
results, and draw preliminary conclusions
Refer next two slides
Sponsored by the U.S. Department of Defense
© 2002 by Carnegie Mellon University
This material is approved for public release. Distribution is limited by the Software Engineering Institute to
attendees.
Intermediate CMMI V 1.1 PMC 053102 - Page 20
- 21. SM
CMMI
Pittsburgh, PA 15213-3890
Metrics can be generally classified into two types:
· trend-based
· limit-based
Trend-based Metrics: – these are used when expected or planned value
changes regularly over time. Typical examples of this type of metric
are growth of code size, no. of units completed etc.
Limit-based Metric: – These are used when expected or planned value
remains relatively constant over time. Typical examples of this type of
metric are effort estimation variance, schedule estimation variance,
productivity etc.
Sponsored by the U.S. Department of Defense
© 2002 by Carnegie Mellon University
This material is approved for public release. Distribution is limited by the Software Engineering Institute to
attendees.
Intermediate CMMI V 1.1 PMC 053102 - Page 21
- 22. SM
CMMI
Pittsburgh, PA 15213-3890
In simplest form metric is analysed in following steps
· Compute the metric using the collected data
· Compare the computed value for the metric with defined goal and
allowable range as per the metric plan
· If the computed metric value is outside the range, then a cause
analysis is performed to identify the cause for this exception /
deviation.
Once the cause(s) has been established, identify the corrective
actions that need to be taken
Sponsored by the U.S. Department of Defense
© 2002 by Carnegie Mellon University
This material is approved for public release. Distribution is limited by the Software Engineering Institute to
attendees.
Intermediate CMMI V 1.1 PMC 053102 - Page 22
- 23. SM
CMMI
Pittsburgh, PA 15213-3890
“Critical” SPs in M & A
• SG 2 Provide Measurement Results [PA154.IG102]
• SP 2.2 Analyze Measurement Data
• Sub practice 3 Review the initial results with relevant
stakeholders
Refer next two slides
Sponsored by the U.S. Department of Defense
© 2002 by Carnegie Mellon University
This material is approved for public release. Distribution is limited by the Software Engineering Institute to
attendees.
Intermediate CMMI V 1.1 PMC 053102 - Page 23
- 24. SM
CMMI
Pittsburgh, PA 15213-3890
“Critical” SPs in M & A
Taking corrective actions based on Metric Analysis
• Probable causes for exception may include one or more of the
following
• Complexity of Project - New technology
• Lack of experience and skills - Attrition
• Frequent Changes - Unclear requirements
• Resources not available - Under estimation
• Lack of process compliance
Sponsored by the U.S. Department of Defense
© 2002 by Carnegie Mellon University
This material is approved for public release. Distribution is limited by the Software Engineering Institute to
attendees.
Intermediate CMMI V 1.1 PMC 053102 - Page 24
- 25. SM
CMMI
Pittsburgh, PA 15213-3890
“Critical” SPs in M & A
• Corrective actions may include one or more of the following
• Replanning the project schedules, estimates, risk etc
• Improving process compliance in the project
• Giving project specific training to the project teams
• Proper change control
• Close monitoring and tracking
Sponsored by the U.S. Department of Defense
© 2002 by Carnegie Mellon University
This material is approved for public release. Distribution is limited by the Software Engineering Institute to
attendees.
Intermediate CMMI V 1.1 PMC 053102 - Page 25
- 26. SM
CMMI
Pittsburgh, PA 15213-3890
“Critical” SPs in M & A
• SG 2 Provide Measurement Results [PA154.IG102]
• SP 2.4 Communicate Results
• Sub practice 1 Keep relevant stakeholders apprised of
measurement results on a timely basis
• Sub practice 2 Assist relevant stakeholders in
understanding the results
Sponsored by the U.S. Department of Defense
© 2002 by Carnegie Mellon University
This material is approved for public release. Distribution is limited by the Software Engineering Institute to
attendees.
Intermediate CMMI V 1.1 PMC 053102 - Page 26
- 27. SM
CMMI
Pittsburgh, PA 15213-3890
“Critical” SPs in M & A
• SG 2 Provide Measurement Results [PA154.IG102]
• SP 2.4 Communicate Results
• Sub practice 2 Assist relevant stakeholders in
understanding the results
• Conduct training sessions on quality tools like Pareto Analysis, cause
and Effect diagram
Sponsored by the U.S. Department of Defense
© 2002 by Carnegie Mellon University
This material is approved for public release. Distribution is limited by the Software Engineering Institute to
attendees.
Intermediate CMMI V 1.1 PMC 053102 - Page 27
- 28. SM
CMMI
Pittsburgh, PA 15213-3890
Generic Practices and M & A
• GG 2 Institutionalize a Managed Process [CL103.GL101]
• GP 2.5 (AB 4) Train People
Train M&A stake holders on
• Statistical techniques
• Data collection, analysis and reporting processes
• Goal Question Metrics
Microsoft Word
Document
Sponsored by the U.S. Department of Defense
© 2002 by Carnegie Mellon University
This material is approved for public release. Distribution is limited by the Software Engineering Institute to
attendees.
Intermediate CMMI V 1.1 PMC 053102 - Page 28
- 29. SM
CMMI
Pittsburgh, PA 15213-3890
Generic Practices and M & A
• GG 2 Institutionalize a Managed Process [CL103.GL101]
• GP 2.7 (DI 2) Identify and Involve Relevant Stakeholders
• This is achieved by setting up standards for flowing down of
organizational quality goals through a set of questionnaire
passed on to relevant stakeholders and compiling the same
on regular intervals.
Microsoft Word
Document
Sponsored by the U.S. Department of Defense
© 2002 by Carnegie Mellon University
This material is approved for public release. Distribution is limited by the Software Engineering Institute to
attendees.
Intermediate CMMI V 1.1 PMC 053102 - Page 29
- 30. SM
CMMI
Pittsburgh, PA 15213-3890
Generic Practices and M & A
• GG 2 Institutionalize a Managed Process [CL103.GL101]
• GP 2.8 (DI 3) Monitor and Control the Process
As discussed in Slide # 15, SG1
Sponsored by the U.S. Department of Defense
© 2002 by Carnegie Mellon University
This material is approved for public release. Distribution is limited by the Software Engineering Institute to
attendees.
Intermediate CMMI V 1.1 PMC 053102 - Page 30
- 31. SM
CMMI
Pittsburgh, PA 15213-3890
Generic Practices and M & A
• GG 2 Institutionalize a Managed Process [CL103.GL101]
• GP 2.10 (VE 2) Review Status with Higher Level Management
• Presentations could be in the form of “Stop Light” charts,
indicating the Red/Yellow/Green status of each major area.
The determination of Red, Yellow or Green status shall be
based on pre-established threshold values.
• Areas with Red or Yellow status on the Stop Light Charts
shall have backup metrics trend data and an action plan to
improve the status.
Microsoft Word
Document
Sponsored by the U.S. Department of Defense
© 2002 by Carnegie Mellon University
This material is approved for public release. Distribution is limited by the Software Engineering Institute to
attendees.
Intermediate CMMI V 1.1 PMC 053102 - Page 31
- 32. SM
CMMI
Pittsburgh, PA 15213-3890
Thank You
Sponsored by the U.S. Department of Defense
© 2002 by Carnegie Mellon University
This material is approved for public release. Distribution is limited by the Software Engineering Institute to
attendees.
Intermediate CMMI V 1.1 PMC 053102 - Page 32