EFFICIENT PLANT LAYOUT DESIGN PROJECT FOR A
SMALL SCALE GARMENT WORKSHOP
Haileyesus Wondwossen
B LE
MANUFACTURING COLLAGE
Agenda Section
In this section we will understand and implement industrial
layout. Then analyzing available resources.
Garment Layout
01
In this section we will demonstrate and analyze different layouts
with relative to our area
Design Layout
02
In this section we will describe different biro layout. This is
because the organization need to change some adjustments.
Organizational Layout
03
Finally we will demonstrate our research factor and errors made
before this document.
Challenge
04
Section Break
Garment Layout
2m
Introduction to Plant Layout
Plant layout refers a systematic and efficient functional
arrangement of various machines, equipment, tools.
Layout identically involves the allocation of space
and the arrangement of equipment
Layout decisions are one of the key facts
determining the long-run efficiency of operations.
Layouts have numerous strategic implications because
they establish an organization´s competitive priorities in
regard to capacity, processes, flexibility, and cost.
Experimental Layout
Visualization
Principle of Layout
Workers and materials must pass through the shortest distance
between the processes to avoid wastage of labor and time.
Principle of minimum travel
Machineries and processes should be arranged in a sequential
order which is achieved in the product layout.
Principle of sequence
Every foot of existing space should be effectively utilized. It
includes the proper usage of space both horizontally and vertically.
Principle of usage
There should be harmonious fusion of all the related factors so that
the final layout looks well integrated and compact.
Principle of compactness
workers to ensure they are safeguarded from the occurrence of fire
and must be protected from excessive heat, dust from the raw
materials such as fabrics and the trimmings of the threads in
sewing, glare and fumes.
Principle of safety and satisfaction
Principle of Layout
The layout must allow modifications with minimum complications
and at minimum cost.
Principle of flexibility
A good layout is one that makes the materials move only in the
forward direction, towards the completion stage.
Principle of Uni-direction flow
Duplicated movements consume unnecessary materials handling,
add to costs and lead to inefficiency.
Effective use of available space
A good layout is one that makes men, machines and materials
ready and observable at all times
Maximum Visibility
A good layout is one that makes all servicing and maintenance
points readily accessible
Maximum Accessibility
Influencing Factors
START
These decide the size and type of the
machinery to be installed which, in turn,
influences the plant layout.
Machinery
Whether the product is light or heavy,
small or big, its arrangement related to
the plant location affects the plant layout.
Product
2
any industry there is a need to offer a
proper storage and movement of raw
materials, which are necessary for the
production of a product, until they are
transformed into finished products.
Materials
Worker facilities is needed like wellbeing
and related services, locker rooms and
public facilities
Worker
1 1
2
The volume of production and provision
for expansion
The extent of automation
Making or buying a particular component
Management policies
Desire of rapid delivery of goods to the
customers
Purchase policy
Personnel policies
Management policies
3 3
Benefits of Plant Layout
Secure a smooth flow of work over the shortest routes
of production
IN TERMS OF PRODUCTION
Good plant layout facilitates accurate planning and
control of production
IN TERMS OF PLANNING
Efficient utilization of machinery, material and men
IN TERMS OF 3MS
Ideal plant layout secures better utilization of available
floor space.
Well-designed plant layout economizes the space
required for production and reduces the unit cost
IN TERMS OF SPACE
GOOD PLANT LAYOUT BRINGS
ABOUT
• Economies in materials and product handling;
• Reduction in number of accidents, loss of man-hours and wastage of
equipment;
• Better utilization of available floor space;
• Cut-back in idle capacity, superfluous work and delay in operations;
• Better provision for maintenance and inspection of the production
capacity, work in process and the work completed;
• Reduction in cost of supervision; and
• improvement in personnel morale and response.
• The distance between the departments must be as small
as possible to minimize the material movement.
• The machines that are similar are grouped in one section/
department.
• It must be convenient for supervision and inspection.
Requirement
01
• There is greater flexibility in the production.
• Better supervision is achievable through
specialization.
• This layout provides better use of men and
machines.
Advantage
02
• Movement of materials is difficult.
• Requires more floor space.
• The WIP accumulates at different
places.
Disadvantage
03
Process layout
The process arrangement is meant by the grouping together of similar machines
based upon their uniqueness.
The process starts at one side of the line and the
assembled product is delivered at another side of the line.
In between, partly finished goods move automatically or
manually from one machine to another
Definition
01
• Reduction in materials handling cost
• Better production control
• Less floor space per unit of production
Advantage
02
• Expensive and inflexible layout.
• Supervision is difficult.
• Expansion is difficult
Disadvantage
03
Product layout
The machines are generally arranged in a series based on the process sequence
required for manufacturing the garment.
men and machine have to move toward it which is desirable
as the cost of moving them is lower than the cost of moving
the product.
Definition
01
• Men and machines can be utilized for
numerous kinds of operations
manufacturing different products.
• The investment on layout is less.
• The costs of transportation for a bulky
product are avoided.
Advantage
02
Fixed position layout
The product remains stationary in a fixed location
Every cell in this design is shaped to produce single parts,
all with common attributes, which typically means they
necessitate the same machines and have similar machine
settings.
Definition
01
• Reduced material handling costs.
• Flow time of materials is less in production
planning.
• Improved visual control of process which
enables quicker set ups.
Advantage
02
• Manufacturing flexibility.
• Reduced machine stoppage time.
Disadvantage
03
Cellular
Manufacturing layout
The machines are generally assembled into cells which function fairly like a
product layout within a process layout.
Combined and service layout
Combined layout
It is a mixture of the product and process
layouts, which could be observed in many of
the apparel units.
Service facility layout
The major distinction between the service
facility and manufacturing facility layouts is
that many service facilities exist to bring
collectively customers and services together.
Each process is situated as a single unit and a number of such
units is arranged in a product layout. It is feasible to have both
types of layout in a capably combined form if the products
manufactured are fairly similar and not complex.
Some of the requirements of service facility layouts are
large, well organized and amply lighted parking areas
and well-designed walkways to and from parking areas.
Garment production process
Laying of paper pattern helps one to plan the
placement of the pattern pieces in a tentative
manner.
Laying
Relaxing refers to the process that allows the
material to relax and contract prior to being
manufactured.
Fabric Relaxing
Spreading, Form Layout, and Cutting
allow operators to identify fabric defects;
control the tension and slack of the fabric during
cutting; and
ensure each ply is accurately aligned on top of
the others.
Receiving Fabrics
Garment factories receive fabric from overseas
textile manufacturers in large bolts with cardboard
or plastic center tubes or in piles or bags.
Preparation
Process
Marking
Cutting
Embroidery
and Screen
Printing
Sewing
Checking
marker planner uses
full-size patterns and
arranges them in an
economical manner
on marker paper.
Of all the operations in
the cutting room, this
is the most decisive,
because once the
fabric has been cut,
very little can be done
to rectify serious
defects.
These processes are
commonly
subcontracted to off-
site facilities
Garments are sewn in
an assembly line, with
the garment becoming
complete as it
progresses down the
sewing line.
Spot Cleaning and
Laundry
Fusing and Pressing
Packaging and
Shipping
MACHINES IN GARMENT WORKSHOP
This area is used to define
the work area on a computer,
each individual can make his
own storage area. A storage
area is used to group related
work, such as pattern pieces
and a marker for a particular
style.
CAD SOFTWARE
DIGITIZING BOARD
PLOTTER MACHINE
MACHINES IN GARMENT WORKSHOP
Modern embroidery
machines are mostly
computer controlled and
exclusively designed for
embroidery.
DIGITAL EMBROIDERY
MACHINE
MACHINES IN GARMENT WORKSHOP
It has a drive motor and end
switches that allow the
machine to automatically
drive itself from beginning to
the end of the table and back.
FABRIC SPREADER
MACHINE
MACHINES IN GARMENT WORKSHOP
It may have rails fixed on the
top of a spreading table to
guide and control the
spreader as it moves along
the length of the table.
CUTTING TABLE
MACHINES IN GARMENT WORKSHOP
Creating patterns for clothing
production is a skilled
practice. The detail and
technique behind each
pattern ensure that garments
are made to specification
with a minimal margin of
error.
PATTERN MAKING
TABLE
MACHINES IN GARMENT WORKSHOP
is an often-articulated doll
used by artists, tailors,
dressmakers, window
dressers and others specially
to display or fit clothing
MANNEQUIN
MACHINES IN GARMENT WORKSHOP
It is the most useful cutting
instrument in apparel cutting
STRAIGHT KNIFE
CUTTER
MACHINES IN GARMENT WORKSHOP
This machine is small in size,
flexible & used for small
production. It is also a
popular cutting machine.
ROUND KNIFE
CUTTING MACHINE
MACHINES IN GARMENT WORKSHOP
a hot drill is used which will
slightly scorch or fuse the
edges of the hole. A
hypodermic drill may be used
which leaves a small deposit
of paint on each ply of fabric.
If it is important that no mark
remains on the fabric
DRILLING MACHINE
MACHINES IN GARMENT WORKSHOP
While layering fabric on the
cutting table, cutting
allowance is taken at both
ends of the ply. The
allowance of fabric in length
is called end loss. End loss
can be also defined as length
of fabric of a lay that doesn’t
get covered by a marker.
END CUTTER
MACHINES IN GARMENT WORKSHOP
Iron which is known
commonly as iron box has
been in existence for a very
long time with the traditional
one being used with heat
generated using charcoal.
IRONING MACHINE
MACHINES IN GARMENT WORKSHOP
high-speed lockstitch sewing
machine is the best common
mechanical system stitch
made by the sewing machine.
The term of single needle
stitching often found on dress
shirt labels, referring to
lockstitch machine.
HIGH SPEED LOCKSTITCH
SEWING MACHINE
MACHINES IN GARMENT WORKSHOP
Single needle lock stitch
machines are used for joining
two or multiple fabric plies
together. The machine is
used to sew lightweight,
medium weight and heavy
materials.
HIGH SPEED
COMPUTERIZED
LOCKSTITCH SEWING
MACHINE
MACHINES IN GARMENT WORKSHOP
A double needle lockstitch
machine works on the same
principle as the single needle
machine by using two
needles and two bobbins
thus resulting in two parallel
rows of lockstitch.
HIGH SPEED DOUBLE
NEEDLE LOCKSTITCH
SEWING MACHINE
MACHINES IN GARMENT WORKSHOP
Industrial zig-zag sewing
machine stitch moves from
side to side instead of
creating a straight stitch.
HIGH SPEED ZIG ZAG
LOCKSTITCH SEWING
MACHINE
MACHINES IN GARMENT WORKSHOP
Overlock machine also
known as serge, over edge
sewing machine and
interlock sewing machine.
HIGH SPEED 4 THREAD
OVER LOCK LOCKSTITCH
SEWING MACHINE
MACHINES IN GARMENT WORKSHOP
Overlock machine also
known as serge, over edge
sewing machine and
interlock sewing machine.
HIGH SPEED 5 THREAD
OVER LOCK LOCKSTITCH
SEWING MACHINE
MACHINES IN GARMENT WORKSHOP
these machines resemble
traditional sewing machines
in that the arm and needle
extend over the flat base of
the machine.
HIGH SPEED FLATBED
INTERLOCK SEWING
MACHINE
MACHINES IN GARMENT WORKSHOP
Chain stitch is formed by two
or more sets of threads
named needle thread and
looper thread.
HIGH SPEED
CYLINDERBED
INTERLOCK CHAIN STICH
SEWING MACHINE
MACHINES IN GARMENT WORKSHOP
It is a very expensive
machine and is used for
mainly sewing Jeans,
Grabidding goods & Double
stitching pants.
FEED OFF THE ARM
INTERLOCK SEWING
MACHINE
MACHINES IN GARMENT WORKSHOP
These cylinders bed shape
multi needle machine ensure,
with speed and ease, firm
and beautiful inserting
(attaching) of elastic tape.
MULTI NEEDLE CHAIN
STICH INTERLOCK
SEWING MACHINE
MACHINES IN GARMENT WORKSHOP
during pressing switch after
sewing one complete button
hole the machine will stop.
HIGH SPEED LOCKSTITCH
BUTTON HOLE SEWING
MACHINE
MACHINES IN GARMENT WORKSHOP
button sewing machine is
used to sew the button in the
garment without damaging it.
HIGH SPEED CHAIN
STITCH BUTTON SEWING
MACHINE
MACHINES IN GARMENT WORKSHOP
The bar tack machine is used
for sewing dense tack around
the open end of the
buttonhole.
HIGH SPEED ELECTRONIC
LOCK STITCH BAR
TRACKING SEWING
MACHINE
MACHINES IN GARMENT WORKSHOP
Button and buttonhole play
an important role in any kind
of apparel for easiness in
wearing and final
presentation.
BUTTON MACHINE
MACHINES IN GARMENT WORKSHOP
movable whiteboard is
double sided and magnetic to
be a versatile fixture for your
office or classroom.
MOVABLE WHITE BORD
• Congestion reduction
• Elimination of unnecessary occupied areas
• Reduction of administrative and indirect work
• Improvement on control and supervision
• Better adjustment of changing directions
• Better utilization of the workforce, equipment and services
• Reduction of material handling activities and stock in
process
• Reduction on parts and quality risks
• Reduction on health risks and increase on workers safety
• Ensuring that workers satisfaction is increased
• Reduction on delays and manufacturing time as well as
production capacity
Contents Title
SPECIFIC OBJECTIVE
The principal objective of a proper plant layout is to maximize the
production at the minimum of the costs. This objective should keep in
mind while designing a layout for a new plant as well as while making
the necessary changes in the existing layout in response to changes in
management policies and processes and techniques of teaching with
analyzing and providing a good working environment on specified
space for Garment workshop.
OBJECTIVE OF THE STUDY
Procedures and Principles of plant
layout
85%
Objectives
70%
Information gathering
65%
Production and flow analysis
40%
Support services
Implementation and evaluation.
55%
Compilation of overall plan
Integration
Content A
Minimum distance
Content B
Maximum space utilization
Content C
Maximum flexibility
Content D
Minimum material handling
Content E
Model One
First design
Rough potation
MODEL ONE
Machine Area
(m2)
Working Area
(m2)
Walking Area
(m2)
Sewing Machine 226.8
316.4
685.13
Chair 61.6
Pattern Table 111.84 ------------
Spreading
Machine
98.82 79.47
Cutting Table 41.94 28
Total 541 423.87 1650
Model Two
Regular design
MODEL TWO
Machine Area
(m2)
Working Area
(m2)
Walking Area
(m2)
Sewing Machine 103.68
144.64
1013.45
Chair 28.16
Pattern Table 111.84 ------------
Spreading
Machine
98.82 79.47
Cutting Table 41.94 28
Total 384.44 252.11 1650
Model Three
Regular design
MODEL THREE
Machine Area
(m2)
Working Area
(m2)
Walking Area
(m2)
Sewing Machine 127.008
177.184
909.302
Chair 34.496
Pattern Table 153.78 ------------
Spreading Machine 98.82 79.47
Cutting Table 41.94 28
Total 456.004 284.654 1650
Model Four
Regular design
MODEL FOUR
Machine Area
(m2)
Working Area
(m2)
Walking Area
(m2)
Sewing Machine 127.008
177.184
945.65
Chair 34.496
Pattern Table 117.432 ------------
Spreading
Machine
98.82 79.47
Cutting Table 41.94 28
Total 419.696 284.654 1650
Model Five
Regular design
MODEL FIVE
Machine Area
(m2)
Working Area
(m2)
Walking Area
(m2)
Sewing Machine 127.008
177.184
962.426
Chair 34.496
Pattern Table 100.656 ------------
Spreading
Machine
98.82 79.47
Cutting Table 41.94 28
Total 402.92 284.654 1650
Model Six
Regular design
MODEL SIX
Machine Area
(m2)
Working Area
(m2)
Walking Area
(m2)
Sewing Machine 127.008
177.184
962.426
Chair 34.496
Pattern Table 100.656 ------------
Spreading
Machine
98.82 79.47
Cutting Table 41.94 28
Total 402.92 284.654 1650
Final
Result
This action need to done
Maximizing efficiency with available resource
No Trial activity
Sewing
Qty
Pattern
Qty
Spreader
Qty
Cutting
Qty
Machine
Area
Working
Area
Walking
Area
1 Model one 350 40 0 0 541 424 685
2 Model two 160 40 9 3 385 252 1013
3 Model three 196 55 9 3 456 285 910
4 Model four 196 42 9 3 420 285 945
5 Model five 196 36 9 3 403 285 962
6 Model six 196 36 9 3 403 285 962
Section Break
Design Layout
2m
r e c e n t
P l a n t l a y o u t
Some modifications must be done for the sake of
collage efficiency
Bole Manufacturing collage Three
identical shop layouts with Error
Designer
Unknown
Sewing Machine = 180
Pattern Table = 84
Spreader Machine = 9
Cutting Table = 3
Total Number of Machineries and Equipment's
Total Area = 1560
Utilized Space (all measurement in m2)
Over utilized space and remaining machineries
Sound problem and merged space
Complicated to implement for 4 levels education
Electrical installation and Room Partitioning is needed
There is group pattern area
Layout Challenge
Store available
2 CAD, 2 class, 2 dressing, 2 toilet room available
7 biros available
Improvement
Sewing Machine = 14
Pattern Table = 12
Spreader Machine = 0
Cutting Table = 0
Remaining Number of Equipment's
Sewing Machine = 60
Pattern Table = 28
Spreader Machine = 3
Cutting Table = 1
Total Number of Machineries and Equipment's
Machine Area = 175
Working Area + Walking Area = 1385
Utilized Space (all measurement in m2)
Over utilized space and remaining machineries
Sound problem and merged space
Complicated to implement for 4 levels education
Electrical installation is needed
Room Partitioning is needed
Layout Challenge
Store available
1 CAD, 2 class, 2 dressing, 2 toilet room available
7 biros available
Improvement
Sewing Machine = 134
Pattern Table = 56
Spreader Machine = 6
Cutting Table = 2
Remaining Number of Equipment's
Sewing Machine = 350
Pattern Table = 40
Spreader Machine = 0
Cutting Table = 0
Total Number of Machineries and Equipment's
Machine Area = 541
Working Area = 424
Walking Area = 685
Utilized Space (all measurement in m2)
Over utilized space and remaining machineries
Sound problem and merged space
Complicated to implement for 4 levels education
Electrical installation is needed
Room Partitioning is needed
Layout Challenge
Store available
2 CAD, 2 class, 2 dressing, 2 toilet room available
7 biros available
Improvement
Sewing Machine = -156
Pattern Table = 44
Spreader Machine = 9
Cutting Table = 3
Remaining Number of Equipment's
Sewing Machine = 160
Pattern Table = 40
Spreader Machine = 9
Cutting Table = 3
Total Number of Machineries and Equipment's
Machine Area = 385
Working Area = 252
Walking Area = 1013
Utilized Space (all measurement in m2)
Over utilized space and remaining machineries
Sound problem and merged space
Complicated to implement for 4 levels education
Electrical installation and Room Partitioning is needed
There is no group pattern area
Layout Challenge
Store available
2 CAD, 2 class, 2 dressing, 2 toilet room available
7 biros available
Improvement
Sewing Machine = 34
Pattern Table = 44
Spreader Machine = 0
Cutting Table = 0
Remaining Number of Equipment's
Sewing Machine = 196
Pattern Table = 55
Spreader Machine = 9
Cutting Table = 3
Total Number of Machineries and Equipment's
Machine Area = 456
Working Area = 285
Walking Area = 910
Utilized Space (all measurement in m2)
Over utilized space and remaining machineries
Sound problem and merged space
Complicated to implement for 4 levels education
Electrical installation and Room Partitioning is needed
Layout Challenge
Store available
2 CAD, 2 class, 2 dressing, 2 toilet room available
7 biros available
There is group pattern area
Improvement
Sewing Machine = -2
Pattern Table = 29
Spreader Machine = 0
Cutting Table = 0
Remaining Number of Equipment's
Sewing Machine = 196
Pattern Table = 42
Spreader Machine = 9
Cutting Table = 3
Total Number of Machineries and Equipment's
Machine Area = 420
Working Area = 285
Walking Area = 945
Utilized Space (all measurement in m2)
Over utilized space and remaining machineries
Sound problem and merged space
Complicated to implement for 4 levels education
Electrical installation and Room Partitioning is needed
Layout Challenge
Store available
2 CAD, 2 class, 2 dressing, 2 toilet room available
7 biros available
There is group pattern area
Improvement
Sewing Machine = -2
Pattern Table = 42
Spreader Machine = 0
Cutting Table = 0
Remaining Number of Equipment's
Sewing Machine = 196
Pattern Table = 36
Spreader Machine = 9
Cutting Table = 3
Total Number of Machineries and Equipment's
Machine Area = 403
Working Area = 285
Walking Area = 962
Utilized Space (all measurement in m2)
Over utilized space and remaining machineries
Sound problem and merged space
Complicated to implement for 4 levels education
Electrical installation and Room Partitioning is needed
There is group pattern area
Layout Challenge
Store available
2 CAD, 2 class, 2 dressing, 2 toilet room available
7 biros available
Improvement
Sewing Machine = -2
Pattern Table = 48
Spreader Machine = 0
Cutting Table = 0
Remaining Number of Equipment's
Sewing Machine = 196
Pattern Table = 36
Spreader Machine = 9
Cutting Table = 3
Total Number of Machineries and Equipment's
Machine Area = 403
Working Area = 285
Walking Area = 962
Utilized Space (all measurement in m2)
Over utilized space and remaining machineries
Sound problem and merged space
Complicated to implement for 4 levels education
Electrical installation and Room Partitioning is needed
There is group pattern area
Layout Challenge
Store available
2 CAD, 2 class, 2 dressing, 2 toilet room available
7 biros available
Improvement
Sewing Machine = -2
Pattern Table = 48
Spreader Machine = 0
Cutting Table = 0
Remaining Number of Equipment's
Section Break
Organizational Layout
2m
BMC
BMC
BMC
Adjustments
New Room
Adjustments
Efficient work
Old building organizational layout adjustments
Section Break
Challenge
2m
Mrs. Beza Assefa
Main building
challenge
Garment challenge
Solution
Organizational
challenge
Every challenge
EXECUTIVE SUMMERY
One of the most common industrial problem is proper use of man, material and machines
properly.
So, I begin to solve this illusion by
reduction of three garment workshop
into two workshop and free the
remaining workshop. In methodology
part there is a calculation based on
every machinery manuals and ISO
standard specification, some of the data
also count from literatures. But finally
using the requirements I found that the
plant need to place one workshop for
garment only so other departments can
use remaining. This is a great
opportunity for the collage to increase its
efficiency. Also, from my sample point
yearly graduating class is very minimum
like 24.6% only in garment this telling us
the collage must change its policy by
adding more department depending on
customer needs. Finally, I will
recommend to deeply analyze every
system for future better work and to fulfill
the components or materials need to
build the facility
Contents B
Contents A
Some organization are thriving to solve
this problem even educational institutes.
The key idea of this project is proper use
or efficient use of resources with
available area. So this project begin with
analyzing the total area used by a
collage and I have found that the collage
have 31,719.685 m2 area, from this
much amount of space building 8562 m2,
road 5149 m2, green area 5900 m2 is
used, so by roughly calculation the
collage will have 12,108.685m2 space
but the collage need much more space
than this because students need a
playground for football, there is no
entertainment center even tv room,
there is no lab workshop building area
for maximizing collage aim finally there
is 2 building this to be planted with this
area. This calculation will give us the
collage must maximizing its efficiency
with minimum requirements and
available resources.
ACKNOWLE
DGMENT
I wish to express my deep gratitude to Ms. Beza, Mr. Yared, Mr. Sisay, Mr.
Eyob, Mr. Endale and Mr. Negese for support and some of them help me
for the field measurement process. I also appreciate their consideration
and understanding towards my effort. Next, I would like to thank garment
workshop assistances for their encouragement, sharing materials and
ideas with interview, and those who share materials like Mr. wendu with me
for what I am going to do,
academically support and guidance revealed and offered from the initiation to the very last time
at which our design has come true.
Finally, I wish to be thankful for all the people who aren’t mentioned by their
name for their support presented in a straight line, in some way
academically. Lastly, I wish to appreciate the encouragement and
sympathetic by my families for the duration of every part of my enjoyable
and dreadful moment.
Thank you
THANK YOU
With a great power comes a great responsibility!
Question ?
B LE
MANUFACTURING COLLAGE

Contenu connexe

Similaire à Addis Ababa City Administration Technical, Vocational, Education And Training Agency Bole Manufacturing Collage Efficient Plant Layout Design Project For A Small Scale Garment Workshop.pdf

plant layout ( Operation Research )
plant layout ( Operation Research ) plant layout ( Operation Research )
plant layout ( Operation Research )
Arpit gupta
 

Similaire à Addis Ababa City Administration Technical, Vocational, Education And Training Agency Bole Manufacturing Collage Efficient Plant Layout Design Project For A Small Scale Garment Workshop.pdf (20)

Production and Operations Management
Production and Operations ManagementProduction and Operations Management
Production and Operations Management
 
Operation management - Importance & Type of layout
Operation management - Importance & Type of layoutOperation management - Importance & Type of layout
Operation management - Importance & Type of layout
 
Production mgmt
Production mgmtProduction mgmt
Production mgmt
 
Group Layout (Manufacturing Management)
Group Layout (Manufacturing Management)Group Layout (Manufacturing Management)
Group Layout (Manufacturing Management)
 
Facility layout
Facility layoutFacility layout
Facility layout
 
plant layout ( Operation Research )
plant layout ( Operation Research ) plant layout ( Operation Research )
plant layout ( Operation Research )
 
PLANT LAYOUT AND TYPES OF LAYOUTS
PLANT LAYOUT AND TYPES OF LAYOUTSPLANT LAYOUT AND TYPES OF LAYOUTS
PLANT LAYOUT AND TYPES OF LAYOUTS
 
IARE_PLMH_PPT.pdf
IARE_PLMH_PPT.pdfIARE_PLMH_PPT.pdf
IARE_PLMH_PPT.pdf
 
3.0 Plant Layout Types.pptx
3.0 Plant Layout Types.pptx3.0 Plant Layout Types.pptx
3.0 Plant Layout Types.pptx
 
Plant location and Layout
Plant location and LayoutPlant location and Layout
Plant location and Layout
 
Facility layout.pdf
Facility layout.pdfFacility layout.pdf
Facility layout.pdf
 
Pl and material
Pl and materialPl and material
Pl and material
 
Plant layout
Plant layoutPlant layout
Plant layout
 
INTRODUCTION TO OPERATIONS MANAGEMENT
INTRODUCTION TO OPERATIONS MANAGEMENTINTRODUCTION TO OPERATIONS MANAGEMENT
INTRODUCTION TO OPERATIONS MANAGEMENT
 
chapter 5.pdf
chapter 5.pdfchapter 5.pdf
chapter 5.pdf
 
Plant layout
Plant layoutPlant layout
Plant layout
 
Lead Time.pptx
Lead Time.pptxLead Time.pptx
Lead Time.pptx
 
plant layout
plant layoutplant layout
plant layout
 
Planning for high volume standardised product
Planning for high volume standardised productPlanning for high volume standardised product
Planning for high volume standardised product
 
INDUSTRIAL ENGINEERING - PLANT LAYOUT
INDUSTRIAL ENGINEERING -  PLANT LAYOUTINDUSTRIAL ENGINEERING -  PLANT LAYOUT
INDUSTRIAL ENGINEERING - PLANT LAYOUT
 

Dernier

Call Girls in Chandni Chowk (delhi) call me [9953056974] escort service 24X7
Call Girls in Chandni Chowk (delhi) call me [9953056974] escort service 24X7Call Girls in Chandni Chowk (delhi) call me [9953056974] escort service 24X7
Call Girls in Chandni Chowk (delhi) call me [9953056974] escort service 24X7
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 

Dernier (20)

Night 7k to 12k Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...
Night 7k to 12k  Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...Night 7k to 12k  Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...
Night 7k to 12k Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...
 
celebrity 💋 Agra Escorts Just Dail 8250092165 service available anytime 24 hour
celebrity 💋 Agra Escorts Just Dail 8250092165 service available anytime 24 hourcelebrity 💋 Agra Escorts Just Dail 8250092165 service available anytime 24 hour
celebrity 💋 Agra Escorts Just Dail 8250092165 service available anytime 24 hour
 
VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...
VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...
VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...
 
2024: The FAR, Federal Acquisition Regulations - Part 29
2024: The FAR, Federal Acquisition Regulations - Part 292024: The FAR, Federal Acquisition Regulations - Part 29
2024: The FAR, Federal Acquisition Regulations - Part 29
 
Call Girls in Chandni Chowk (delhi) call me [9953056974] escort service 24X7
Call Girls in Chandni Chowk (delhi) call me [9953056974] escort service 24X7Call Girls in Chandni Chowk (delhi) call me [9953056974] escort service 24X7
Call Girls in Chandni Chowk (delhi) call me [9953056974] escort service 24X7
 
Top Rated Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...
Top Rated  Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...Top Rated  Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...
Top Rated Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...
 
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
 
Junnar ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
Junnar ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...Junnar ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...
Junnar ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
 
Top Rated Pune Call Girls Dapodi ⟟ 6297143586 ⟟ Call Me For Genuine Sex Serv...
Top Rated  Pune Call Girls Dapodi ⟟ 6297143586 ⟟ Call Me For Genuine Sex Serv...Top Rated  Pune Call Girls Dapodi ⟟ 6297143586 ⟟ Call Me For Genuine Sex Serv...
Top Rated Pune Call Girls Dapodi ⟟ 6297143586 ⟟ Call Me For Genuine Sex Serv...
 
PPT BIJNOR COUNTING Counting of Votes on ETPBs (FOR SERVICE ELECTORS
PPT BIJNOR COUNTING Counting of Votes on ETPBs (FOR SERVICE ELECTORSPPT BIJNOR COUNTING Counting of Votes on ETPBs (FOR SERVICE ELECTORS
PPT BIJNOR COUNTING Counting of Votes on ETPBs (FOR SERVICE ELECTORS
 
World Press Freedom Day 2024; May 3rd - Poster
World Press Freedom Day 2024; May 3rd - PosterWorld Press Freedom Day 2024; May 3rd - Poster
World Press Freedom Day 2024; May 3rd - Poster
 
Postal Ballots-For home voting step by step process 2024.pptx
Postal Ballots-For home voting step by step process 2024.pptxPostal Ballots-For home voting step by step process 2024.pptx
Postal Ballots-For home voting step by step process 2024.pptx
 
The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)
 
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
 
Regional Snapshot Atlanta Aging Trends 2024
Regional Snapshot Atlanta Aging Trends 2024Regional Snapshot Atlanta Aging Trends 2024
Regional Snapshot Atlanta Aging Trends 2024
 
A Press for the Planet: Journalism in the face of the Environmental Crisis
A Press for the Planet: Journalism in the face of the Environmental CrisisA Press for the Planet: Journalism in the face of the Environmental Crisis
A Press for the Planet: Journalism in the face of the Environmental Crisis
 
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'IsraëlAntisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
 
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
 
Sustainability by Design: Assessment Tool for Just Energy Transition Plans
Sustainability by Design: Assessment Tool for Just Energy Transition PlansSustainability by Design: Assessment Tool for Just Energy Transition Plans
Sustainability by Design: Assessment Tool for Just Energy Transition Plans
 
Government e Marketplace GeM Presentation
Government e Marketplace GeM PresentationGovernment e Marketplace GeM Presentation
Government e Marketplace GeM Presentation
 

Addis Ababa City Administration Technical, Vocational, Education And Training Agency Bole Manufacturing Collage Efficient Plant Layout Design Project For A Small Scale Garment Workshop.pdf

  • 2. EFFICIENT PLANT LAYOUT DESIGN PROJECT FOR A SMALL SCALE GARMENT WORKSHOP Haileyesus Wondwossen B LE MANUFACTURING COLLAGE
  • 3. Agenda Section In this section we will understand and implement industrial layout. Then analyzing available resources. Garment Layout 01 In this section we will demonstrate and analyze different layouts with relative to our area Design Layout 02 In this section we will describe different biro layout. This is because the organization need to change some adjustments. Organizational Layout 03 Finally we will demonstrate our research factor and errors made before this document. Challenge 04
  • 5.
  • 6. Introduction to Plant Layout Plant layout refers a systematic and efficient functional arrangement of various machines, equipment, tools. Layout identically involves the allocation of space and the arrangement of equipment Layout decisions are one of the key facts determining the long-run efficiency of operations. Layouts have numerous strategic implications because they establish an organization´s competitive priorities in regard to capacity, processes, flexibility, and cost.
  • 8. Principle of Layout Workers and materials must pass through the shortest distance between the processes to avoid wastage of labor and time. Principle of minimum travel Machineries and processes should be arranged in a sequential order which is achieved in the product layout. Principle of sequence Every foot of existing space should be effectively utilized. It includes the proper usage of space both horizontally and vertically. Principle of usage There should be harmonious fusion of all the related factors so that the final layout looks well integrated and compact. Principle of compactness workers to ensure they are safeguarded from the occurrence of fire and must be protected from excessive heat, dust from the raw materials such as fabrics and the trimmings of the threads in sewing, glare and fumes. Principle of safety and satisfaction
  • 9. Principle of Layout The layout must allow modifications with minimum complications and at minimum cost. Principle of flexibility A good layout is one that makes the materials move only in the forward direction, towards the completion stage. Principle of Uni-direction flow Duplicated movements consume unnecessary materials handling, add to costs and lead to inefficiency. Effective use of available space A good layout is one that makes men, machines and materials ready and observable at all times Maximum Visibility A good layout is one that makes all servicing and maintenance points readily accessible Maximum Accessibility
  • 10. Influencing Factors START These decide the size and type of the machinery to be installed which, in turn, influences the plant layout. Machinery Whether the product is light or heavy, small or big, its arrangement related to the plant location affects the plant layout. Product 2 any industry there is a need to offer a proper storage and movement of raw materials, which are necessary for the production of a product, until they are transformed into finished products. Materials Worker facilities is needed like wellbeing and related services, locker rooms and public facilities Worker 1 1 2 The volume of production and provision for expansion The extent of automation Making or buying a particular component Management policies Desire of rapid delivery of goods to the customers Purchase policy Personnel policies Management policies 3 3
  • 11. Benefits of Plant Layout Secure a smooth flow of work over the shortest routes of production IN TERMS OF PRODUCTION Good plant layout facilitates accurate planning and control of production IN TERMS OF PLANNING Efficient utilization of machinery, material and men IN TERMS OF 3MS Ideal plant layout secures better utilization of available floor space. Well-designed plant layout economizes the space required for production and reduces the unit cost IN TERMS OF SPACE GOOD PLANT LAYOUT BRINGS ABOUT • Economies in materials and product handling; • Reduction in number of accidents, loss of man-hours and wastage of equipment; • Better utilization of available floor space; • Cut-back in idle capacity, superfluous work and delay in operations; • Better provision for maintenance and inspection of the production capacity, work in process and the work completed; • Reduction in cost of supervision; and • improvement in personnel morale and response.
  • 12. • The distance between the departments must be as small as possible to minimize the material movement. • The machines that are similar are grouped in one section/ department. • It must be convenient for supervision and inspection. Requirement 01 • There is greater flexibility in the production. • Better supervision is achievable through specialization. • This layout provides better use of men and machines. Advantage 02 • Movement of materials is difficult. • Requires more floor space. • The WIP accumulates at different places. Disadvantage 03 Process layout The process arrangement is meant by the grouping together of similar machines based upon their uniqueness.
  • 13. The process starts at one side of the line and the assembled product is delivered at another side of the line. In between, partly finished goods move automatically or manually from one machine to another Definition 01 • Reduction in materials handling cost • Better production control • Less floor space per unit of production Advantage 02 • Expensive and inflexible layout. • Supervision is difficult. • Expansion is difficult Disadvantage 03 Product layout The machines are generally arranged in a series based on the process sequence required for manufacturing the garment.
  • 14. men and machine have to move toward it which is desirable as the cost of moving them is lower than the cost of moving the product. Definition 01 • Men and machines can be utilized for numerous kinds of operations manufacturing different products. • The investment on layout is less. • The costs of transportation for a bulky product are avoided. Advantage 02 Fixed position layout The product remains stationary in a fixed location
  • 15. Every cell in this design is shaped to produce single parts, all with common attributes, which typically means they necessitate the same machines and have similar machine settings. Definition 01 • Reduced material handling costs. • Flow time of materials is less in production planning. • Improved visual control of process which enables quicker set ups. Advantage 02 • Manufacturing flexibility. • Reduced machine stoppage time. Disadvantage 03 Cellular Manufacturing layout The machines are generally assembled into cells which function fairly like a product layout within a process layout.
  • 16. Combined and service layout Combined layout It is a mixture of the product and process layouts, which could be observed in many of the apparel units. Service facility layout The major distinction between the service facility and manufacturing facility layouts is that many service facilities exist to bring collectively customers and services together. Each process is situated as a single unit and a number of such units is arranged in a product layout. It is feasible to have both types of layout in a capably combined form if the products manufactured are fairly similar and not complex. Some of the requirements of service facility layouts are large, well organized and amply lighted parking areas and well-designed walkways to and from parking areas.
  • 17. Garment production process Laying of paper pattern helps one to plan the placement of the pattern pieces in a tentative manner. Laying Relaxing refers to the process that allows the material to relax and contract prior to being manufactured. Fabric Relaxing Spreading, Form Layout, and Cutting allow operators to identify fabric defects; control the tension and slack of the fabric during cutting; and ensure each ply is accurately aligned on top of the others. Receiving Fabrics Garment factories receive fabric from overseas textile manufacturers in large bolts with cardboard or plastic center tubes or in piles or bags. Preparation
  • 18. Process Marking Cutting Embroidery and Screen Printing Sewing Checking marker planner uses full-size patterns and arranges them in an economical manner on marker paper. Of all the operations in the cutting room, this is the most decisive, because once the fabric has been cut, very little can be done to rectify serious defects. These processes are commonly subcontracted to off- site facilities Garments are sewn in an assembly line, with the garment becoming complete as it progresses down the sewing line. Spot Cleaning and Laundry Fusing and Pressing Packaging and Shipping
  • 19. MACHINES IN GARMENT WORKSHOP This area is used to define the work area on a computer, each individual can make his own storage area. A storage area is used to group related work, such as pattern pieces and a marker for a particular style. CAD SOFTWARE DIGITIZING BOARD PLOTTER MACHINE
  • 20. MACHINES IN GARMENT WORKSHOP Modern embroidery machines are mostly computer controlled and exclusively designed for embroidery. DIGITAL EMBROIDERY MACHINE
  • 21. MACHINES IN GARMENT WORKSHOP It has a drive motor and end switches that allow the machine to automatically drive itself from beginning to the end of the table and back. FABRIC SPREADER MACHINE
  • 22. MACHINES IN GARMENT WORKSHOP It may have rails fixed on the top of a spreading table to guide and control the spreader as it moves along the length of the table. CUTTING TABLE
  • 23. MACHINES IN GARMENT WORKSHOP Creating patterns for clothing production is a skilled practice. The detail and technique behind each pattern ensure that garments are made to specification with a minimal margin of error. PATTERN MAKING TABLE
  • 24. MACHINES IN GARMENT WORKSHOP is an often-articulated doll used by artists, tailors, dressmakers, window dressers and others specially to display or fit clothing MANNEQUIN
  • 25. MACHINES IN GARMENT WORKSHOP It is the most useful cutting instrument in apparel cutting STRAIGHT KNIFE CUTTER
  • 26. MACHINES IN GARMENT WORKSHOP This machine is small in size, flexible & used for small production. It is also a popular cutting machine. ROUND KNIFE CUTTING MACHINE
  • 27. MACHINES IN GARMENT WORKSHOP a hot drill is used which will slightly scorch or fuse the edges of the hole. A hypodermic drill may be used which leaves a small deposit of paint on each ply of fabric. If it is important that no mark remains on the fabric DRILLING MACHINE
  • 28. MACHINES IN GARMENT WORKSHOP While layering fabric on the cutting table, cutting allowance is taken at both ends of the ply. The allowance of fabric in length is called end loss. End loss can be also defined as length of fabric of a lay that doesn’t get covered by a marker. END CUTTER
  • 29. MACHINES IN GARMENT WORKSHOP Iron which is known commonly as iron box has been in existence for a very long time with the traditional one being used with heat generated using charcoal. IRONING MACHINE
  • 30. MACHINES IN GARMENT WORKSHOP high-speed lockstitch sewing machine is the best common mechanical system stitch made by the sewing machine. The term of single needle stitching often found on dress shirt labels, referring to lockstitch machine. HIGH SPEED LOCKSTITCH SEWING MACHINE
  • 31. MACHINES IN GARMENT WORKSHOP Single needle lock stitch machines are used for joining two or multiple fabric plies together. The machine is used to sew lightweight, medium weight and heavy materials. HIGH SPEED COMPUTERIZED LOCKSTITCH SEWING MACHINE
  • 32. MACHINES IN GARMENT WORKSHOP A double needle lockstitch machine works on the same principle as the single needle machine by using two needles and two bobbins thus resulting in two parallel rows of lockstitch. HIGH SPEED DOUBLE NEEDLE LOCKSTITCH SEWING MACHINE
  • 33. MACHINES IN GARMENT WORKSHOP Industrial zig-zag sewing machine stitch moves from side to side instead of creating a straight stitch. HIGH SPEED ZIG ZAG LOCKSTITCH SEWING MACHINE
  • 34. MACHINES IN GARMENT WORKSHOP Overlock machine also known as serge, over edge sewing machine and interlock sewing machine. HIGH SPEED 4 THREAD OVER LOCK LOCKSTITCH SEWING MACHINE
  • 35. MACHINES IN GARMENT WORKSHOP Overlock machine also known as serge, over edge sewing machine and interlock sewing machine. HIGH SPEED 5 THREAD OVER LOCK LOCKSTITCH SEWING MACHINE
  • 36. MACHINES IN GARMENT WORKSHOP these machines resemble traditional sewing machines in that the arm and needle extend over the flat base of the machine. HIGH SPEED FLATBED INTERLOCK SEWING MACHINE
  • 37. MACHINES IN GARMENT WORKSHOP Chain stitch is formed by two or more sets of threads named needle thread and looper thread. HIGH SPEED CYLINDERBED INTERLOCK CHAIN STICH SEWING MACHINE
  • 38. MACHINES IN GARMENT WORKSHOP It is a very expensive machine and is used for mainly sewing Jeans, Grabidding goods & Double stitching pants. FEED OFF THE ARM INTERLOCK SEWING MACHINE
  • 39. MACHINES IN GARMENT WORKSHOP These cylinders bed shape multi needle machine ensure, with speed and ease, firm and beautiful inserting (attaching) of elastic tape. MULTI NEEDLE CHAIN STICH INTERLOCK SEWING MACHINE
  • 40. MACHINES IN GARMENT WORKSHOP during pressing switch after sewing one complete button hole the machine will stop. HIGH SPEED LOCKSTITCH BUTTON HOLE SEWING MACHINE
  • 41. MACHINES IN GARMENT WORKSHOP button sewing machine is used to sew the button in the garment without damaging it. HIGH SPEED CHAIN STITCH BUTTON SEWING MACHINE
  • 42. MACHINES IN GARMENT WORKSHOP The bar tack machine is used for sewing dense tack around the open end of the buttonhole. HIGH SPEED ELECTRONIC LOCK STITCH BAR TRACKING SEWING MACHINE
  • 43. MACHINES IN GARMENT WORKSHOP Button and buttonhole play an important role in any kind of apparel for easiness in wearing and final presentation. BUTTON MACHINE
  • 44. MACHINES IN GARMENT WORKSHOP movable whiteboard is double sided and magnetic to be a versatile fixture for your office or classroom. MOVABLE WHITE BORD
  • 45. • Congestion reduction • Elimination of unnecessary occupied areas • Reduction of administrative and indirect work • Improvement on control and supervision • Better adjustment of changing directions • Better utilization of the workforce, equipment and services • Reduction of material handling activities and stock in process • Reduction on parts and quality risks • Reduction on health risks and increase on workers safety • Ensuring that workers satisfaction is increased • Reduction on delays and manufacturing time as well as production capacity Contents Title SPECIFIC OBJECTIVE The principal objective of a proper plant layout is to maximize the production at the minimum of the costs. This objective should keep in mind while designing a layout for a new plant as well as while making the necessary changes in the existing layout in response to changes in management policies and processes and techniques of teaching with analyzing and providing a good working environment on specified space for Garment workshop. OBJECTIVE OF THE STUDY
  • 46. Procedures and Principles of plant layout 85% Objectives 70% Information gathering 65% Production and flow analysis 40% Support services Implementation and evaluation. 55% Compilation of overall plan Integration Content A Minimum distance Content B Maximum space utilization Content C Maximum flexibility Content D Minimum material handling Content E
  • 47. Model One First design Rough potation MODEL ONE Machine Area (m2) Working Area (m2) Walking Area (m2) Sewing Machine 226.8 316.4 685.13 Chair 61.6 Pattern Table 111.84 ------------ Spreading Machine 98.82 79.47 Cutting Table 41.94 28 Total 541 423.87 1650
  • 48. Model Two Regular design MODEL TWO Machine Area (m2) Working Area (m2) Walking Area (m2) Sewing Machine 103.68 144.64 1013.45 Chair 28.16 Pattern Table 111.84 ------------ Spreading Machine 98.82 79.47 Cutting Table 41.94 28 Total 384.44 252.11 1650
  • 49. Model Three Regular design MODEL THREE Machine Area (m2) Working Area (m2) Walking Area (m2) Sewing Machine 127.008 177.184 909.302 Chair 34.496 Pattern Table 153.78 ------------ Spreading Machine 98.82 79.47 Cutting Table 41.94 28 Total 456.004 284.654 1650
  • 50. Model Four Regular design MODEL FOUR Machine Area (m2) Working Area (m2) Walking Area (m2) Sewing Machine 127.008 177.184 945.65 Chair 34.496 Pattern Table 117.432 ------------ Spreading Machine 98.82 79.47 Cutting Table 41.94 28 Total 419.696 284.654 1650
  • 51. Model Five Regular design MODEL FIVE Machine Area (m2) Working Area (m2) Walking Area (m2) Sewing Machine 127.008 177.184 962.426 Chair 34.496 Pattern Table 100.656 ------------ Spreading Machine 98.82 79.47 Cutting Table 41.94 28 Total 402.92 284.654 1650
  • 52. Model Six Regular design MODEL SIX Machine Area (m2) Working Area (m2) Walking Area (m2) Sewing Machine 127.008 177.184 962.426 Chair 34.496 Pattern Table 100.656 ------------ Spreading Machine 98.82 79.47 Cutting Table 41.94 28 Total 402.92 284.654 1650
  • 53. Final Result This action need to done Maximizing efficiency with available resource No Trial activity Sewing Qty Pattern Qty Spreader Qty Cutting Qty Machine Area Working Area Walking Area 1 Model one 350 40 0 0 541 424 685 2 Model two 160 40 9 3 385 252 1013 3 Model three 196 55 9 3 456 285 910 4 Model four 196 42 9 3 420 285 945 5 Model five 196 36 9 3 403 285 962 6 Model six 196 36 9 3 403 285 962
  • 55. r e c e n t P l a n t l a y o u t Some modifications must be done for the sake of collage efficiency Bole Manufacturing collage Three identical shop layouts with Error Designer Unknown
  • 56. Sewing Machine = 180 Pattern Table = 84 Spreader Machine = 9 Cutting Table = 3 Total Number of Machineries and Equipment's Total Area = 1560 Utilized Space (all measurement in m2) Over utilized space and remaining machineries Sound problem and merged space Complicated to implement for 4 levels education Electrical installation and Room Partitioning is needed There is group pattern area Layout Challenge Store available 2 CAD, 2 class, 2 dressing, 2 toilet room available 7 biros available Improvement Sewing Machine = 14 Pattern Table = 12 Spreader Machine = 0 Cutting Table = 0 Remaining Number of Equipment's
  • 57. Sewing Machine = 60 Pattern Table = 28 Spreader Machine = 3 Cutting Table = 1 Total Number of Machineries and Equipment's Machine Area = 175 Working Area + Walking Area = 1385 Utilized Space (all measurement in m2) Over utilized space and remaining machineries Sound problem and merged space Complicated to implement for 4 levels education Electrical installation is needed Room Partitioning is needed Layout Challenge Store available 1 CAD, 2 class, 2 dressing, 2 toilet room available 7 biros available Improvement Sewing Machine = 134 Pattern Table = 56 Spreader Machine = 6 Cutting Table = 2 Remaining Number of Equipment's
  • 58. Sewing Machine = 350 Pattern Table = 40 Spreader Machine = 0 Cutting Table = 0 Total Number of Machineries and Equipment's Machine Area = 541 Working Area = 424 Walking Area = 685 Utilized Space (all measurement in m2) Over utilized space and remaining machineries Sound problem and merged space Complicated to implement for 4 levels education Electrical installation is needed Room Partitioning is needed Layout Challenge Store available 2 CAD, 2 class, 2 dressing, 2 toilet room available 7 biros available Improvement Sewing Machine = -156 Pattern Table = 44 Spreader Machine = 9 Cutting Table = 3 Remaining Number of Equipment's
  • 59. Sewing Machine = 160 Pattern Table = 40 Spreader Machine = 9 Cutting Table = 3 Total Number of Machineries and Equipment's Machine Area = 385 Working Area = 252 Walking Area = 1013 Utilized Space (all measurement in m2) Over utilized space and remaining machineries Sound problem and merged space Complicated to implement for 4 levels education Electrical installation and Room Partitioning is needed There is no group pattern area Layout Challenge Store available 2 CAD, 2 class, 2 dressing, 2 toilet room available 7 biros available Improvement Sewing Machine = 34 Pattern Table = 44 Spreader Machine = 0 Cutting Table = 0 Remaining Number of Equipment's
  • 60. Sewing Machine = 196 Pattern Table = 55 Spreader Machine = 9 Cutting Table = 3 Total Number of Machineries and Equipment's Machine Area = 456 Working Area = 285 Walking Area = 910 Utilized Space (all measurement in m2) Over utilized space and remaining machineries Sound problem and merged space Complicated to implement for 4 levels education Electrical installation and Room Partitioning is needed Layout Challenge Store available 2 CAD, 2 class, 2 dressing, 2 toilet room available 7 biros available There is group pattern area Improvement Sewing Machine = -2 Pattern Table = 29 Spreader Machine = 0 Cutting Table = 0 Remaining Number of Equipment's
  • 61. Sewing Machine = 196 Pattern Table = 42 Spreader Machine = 9 Cutting Table = 3 Total Number of Machineries and Equipment's Machine Area = 420 Working Area = 285 Walking Area = 945 Utilized Space (all measurement in m2) Over utilized space and remaining machineries Sound problem and merged space Complicated to implement for 4 levels education Electrical installation and Room Partitioning is needed Layout Challenge Store available 2 CAD, 2 class, 2 dressing, 2 toilet room available 7 biros available There is group pattern area Improvement Sewing Machine = -2 Pattern Table = 42 Spreader Machine = 0 Cutting Table = 0 Remaining Number of Equipment's
  • 62. Sewing Machine = 196 Pattern Table = 36 Spreader Machine = 9 Cutting Table = 3 Total Number of Machineries and Equipment's Machine Area = 403 Working Area = 285 Walking Area = 962 Utilized Space (all measurement in m2) Over utilized space and remaining machineries Sound problem and merged space Complicated to implement for 4 levels education Electrical installation and Room Partitioning is needed There is group pattern area Layout Challenge Store available 2 CAD, 2 class, 2 dressing, 2 toilet room available 7 biros available Improvement Sewing Machine = -2 Pattern Table = 48 Spreader Machine = 0 Cutting Table = 0 Remaining Number of Equipment's
  • 63. Sewing Machine = 196 Pattern Table = 36 Spreader Machine = 9 Cutting Table = 3 Total Number of Machineries and Equipment's Machine Area = 403 Working Area = 285 Walking Area = 962 Utilized Space (all measurement in m2) Over utilized space and remaining machineries Sound problem and merged space Complicated to implement for 4 levels education Electrical installation and Room Partitioning is needed There is group pattern area Layout Challenge Store available 2 CAD, 2 class, 2 dressing, 2 toilet room available 7 biros available Improvement Sewing Machine = -2 Pattern Table = 48 Spreader Machine = 0 Cutting Table = 0 Remaining Number of Equipment's
  • 65. BMC
  • 66. BMC
  • 67. BMC
  • 68. Adjustments New Room Adjustments Efficient work Old building organizational layout adjustments
  • 70. Mrs. Beza Assefa Main building challenge Garment challenge Solution Organizational challenge Every challenge
  • 71. EXECUTIVE SUMMERY One of the most common industrial problem is proper use of man, material and machines properly. So, I begin to solve this illusion by reduction of three garment workshop into two workshop and free the remaining workshop. In methodology part there is a calculation based on every machinery manuals and ISO standard specification, some of the data also count from literatures. But finally using the requirements I found that the plant need to place one workshop for garment only so other departments can use remaining. This is a great opportunity for the collage to increase its efficiency. Also, from my sample point yearly graduating class is very minimum like 24.6% only in garment this telling us the collage must change its policy by adding more department depending on customer needs. Finally, I will recommend to deeply analyze every system for future better work and to fulfill the components or materials need to build the facility Contents B Contents A Some organization are thriving to solve this problem even educational institutes. The key idea of this project is proper use or efficient use of resources with available area. So this project begin with analyzing the total area used by a collage and I have found that the collage have 31,719.685 m2 area, from this much amount of space building 8562 m2, road 5149 m2, green area 5900 m2 is used, so by roughly calculation the collage will have 12,108.685m2 space but the collage need much more space than this because students need a playground for football, there is no entertainment center even tv room, there is no lab workshop building area for maximizing collage aim finally there is 2 building this to be planted with this area. This calculation will give us the collage must maximizing its efficiency with minimum requirements and available resources.
  • 72. ACKNOWLE DGMENT I wish to express my deep gratitude to Ms. Beza, Mr. Yared, Mr. Sisay, Mr. Eyob, Mr. Endale and Mr. Negese for support and some of them help me for the field measurement process. I also appreciate their consideration and understanding towards my effort. Next, I would like to thank garment workshop assistances for their encouragement, sharing materials and ideas with interview, and those who share materials like Mr. wendu with me for what I am going to do, academically support and guidance revealed and offered from the initiation to the very last time at which our design has come true. Finally, I wish to be thankful for all the people who aren’t mentioned by their name for their support presented in a straight line, in some way academically. Lastly, I wish to appreciate the encouragement and sympathetic by my families for the duration of every part of my enjoyable and dreadful moment. Thank you
  • 73. THANK YOU With a great power comes a great responsibility!