SlideShare une entreprise Scribd logo
1  sur  30
Télécharger pour lire hors ligne
1
1 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
EOSC 547:
Tunnelling &
Underground Design
Topic 5:
Hard & Weak Rock
Tunnelling
2 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
Tunnel Excavation in Rock
It is instructive to consider the fundamental objective of the excavation
process – which is to remove rock material (either to create an opening or
to obtain material for its inherent value). In order to remove part of a
rock mass, it is necessary to induce additional fracturing and
fragmentation of the rock.
The peak strength of the
rock must be exceeded.
This introduces three critical aspects of excavation:
The in situ block size
distribution must be changed
to the required fragment size
distribution.
By what means should the
required energy be introduced
into the rock?
2
3 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
Tunnel Excavation in Rock
Strength
The tensile strength of rock is
about 1/10th the compressive
strength and the energy beneath
the stress-strain curve is roughly
its square. Therefore, breaking
the rock in tension requires only
1/100th of the energy as that in
compression.
Block Size
Hudson & Harrison (1997)
The fracturing of rock during
excavation changes the natural
block size distribution to the
fragment size distribution. The goal
therefore is to consider how best
to move from one curve to the
other in the excavation process.
4 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
Energy and Excavation Process
One objective in the excavation process may be to optimize the
use of energy, i.e. the amount of energy required to remove a
unit volume of rock (specific energy = J/m3). There are two
fundamental ways of inputting energy into the rock for excavation:
Blasting: Energy is input in
large quantities over very short
durations (cyclical – drill then
blast, drill then blast, etc.).
Machine Excavation: Energy is
input in smaller quantities
continuously.
3
5 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
Drill & Blast
The technique of rock breakage using
explosives involves drilling blastholes by
percussion or rotary-percussive means, loading
the boreholes with explosives and then
detonating the explosive in each hole in
sequence according to the blast design.
The explosion generates a
stress wave and significant
gas pressure. Following the
local fracturing at the
blasthole wall and the
spalling of the free face,
the subsequent gas
pressure then provides the
necessary energy to
disaggregate the broken
rock.
Hudson & Harrison (1997)
6 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
Conventional Drill & Blast Cycle
4
7 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
Conventional Drill & Blast Cycle
Drill Load
Blast
Ventilate
Scoop
Scale
Bolt
Survey
8 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
Drill & Blast – Drilling Rates
0
1
2
3
4
5
0 20 40 60 80 100 120 140
Uniaxial Compressive Strength (MPa)
DrillingRate(m/min)
0
1
2
3
4
5
0 100 200 300 400 500
Specific Energy (kJ/m3)
DrillingRate(m/min)
Thuro&Plinninger(2003)
5
9 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
Drill & Blast – Drilling Rates
UNIT-NTH(1995)
10 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
Blasting Rounds – Burn Cut
The correct design of a blast starts with the first hole to be detonated.
In the case of a tunnel blast, the first requirement is to create a void into
which rock broken by the blast can expand. This is generally achieved by a
wedge or burn cut which is designed to create a clean void and to eject the
rock originally contained in this void clear of the tunnel face.
Burn cut designs using
millisecond delays.
6
11 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
Blasting Rounds – Blast Pattern Design
12 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
Specialized Blasting Techniques
During blasting, the explosive damage may not only occur according
to the blasting round design, but there may also be extra rock
damage behind the excavation boundary. To minimize damage to the
rock, a smooth-wall blast may be used to create the final
excavation surface.
Hudson&Harrison(1997)
The smooth-wall blast begins by creating a rough opening using a large bulk
blast. This is followed by a smooth-wall blast along a series of closely
spaced and lightly charged parallel holes, designed to create a fracture
plane connecting the holes through by means of coalescing fractures.
7
13 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
Blasting Rounds – Fragmentation
How efficiently muck from a working tunnel or surface excavation can be
removed is a function of the blast fragmentation. Broken rock by volume
is usually 50% greater than the in situ material. In mining, both the ore
and waste has to be moved to surface for milling or disposal. Some waste
material can be used underground to backfill mined voids. In tunnelling,
everything has to be removed and dumped in fills – or if the material is
right, may be removed and used for road ballast or concrete aggregate
(which can sometimes then be re-used in the tunnel itself).
14 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
Blasting – Summary NTNU(1995)
8
15 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
Machine Excavation in Rock
Tunnel Boring Machine (TBM)
16 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
Machine Excavation in Rock
There are two basic types of machine for underground rock excavation:
Partial-face machines: use a
cutting head on the end of a
movable boom (that itself may
be track mounted).
Full-face machines: use a rotating
head armed with cutters, which fills
the tunnel cross-section completely,
and thus almost always excavates
circular tunnels.
9
17 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
Machine Excavation in Rock
Partial-face machines
are cheaper, smaller
and much more flexible
in operation.
cut
scoop
muck
out
18 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
Machine Excavation in Rock
Full-face machines – when used for relatively
straight and long tunnels (>2 km) – permit high
rates of advance in a smooth, automated
construction operation.
muck
out
cut
scoop
10
19 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
Machine Excavation in Rock
20 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
Machine Excavation
The advance rate at which the excavation proceeds is a function of the
cutting rate and utilization factor (which is the amount of time that the
machine is cutting rock). Factors contributing to low utilization rates are
difficulties with ground support and steering, the need to frequently
replace cutters, blocked scoops, broken conveyors, etc.
The cutters may damage
if the TBM is pushed
forwards with too much
force, or large blocks
fall and strike them.
Broken conveyor
11
21 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
TBM Operation
Factors that may control
TBM performance include:
• TBM Penetration Rate
(meters/machine hour)
• TBM Downtime (minutes)
• TBM Utilization (machine
hours/shift hours)
• Tool Wear (tool changes per
shift)
22 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
Mechanics of Rock Cutting
In tunnelling terms, a TBM applies both thrust (Fn) and torque (Ft) during
the cutting process. In selecting the proper cutting tool, the engineer
wishes to know how the tools should be configured on a machine cutting
head, how to minimize the need to replace cutters, how to avoid
damaging the cutter mounts, and how to minimize vibration.
Hudson&Harrison(1997)
12
23 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
Mechanics of Rock Cutting
NTNU-Anleggsdrift(1998)
Cutting involves a complex mixture of tensile,
shear and compressive modes of failure. With
thrust, the cutting disc penetrates the rock and
generates extensive crack propagation to the
free surface. Further strain relief occurs as the
disc edge rolls out of its cut, inducing further
tensile cracking and slabbing at the rock surface.
24 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
Mechanics of Rock Cutting – Cutter Wear
new
uneven
wear
normal
wear
heavy
wear
The primary impact of disc wear on costs can be so severe that cutter
costs are often considered as a separate item in bid preparation. In
general, 1.5 hours are required for a single cutter change, and if several
cutters are changed at one time, each may require 30-40 minutes. Even
higher downtimes can be expected with large water inflows, which make
cutter change activities more difficult and time-consuming.
13
25 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
Mechanical Excavation – Cutter Heads
Delays: When the tunnel boring machine is inside the tunnel, the cutters
must be changed from the inside the cutting head.
26 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
Mechanical Excavation – Cutter Heads
14
27 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
Mechanical Excavation – Cutter Heads
28 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
Mechanical Excavation – Cutter Heads
15
29 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
Mechanical Excavation – Cutter Heads
30 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
TBM Excavation & Design
The two main factors that will stop
tunnel boring machines are either
the rock is too hard to cut or that
the rock is too soft to sustain the
reactionary force necessary to
push the machine forward. TBM’s
will operate within certain ranges
of rock deformability and strength,
where the machine can be tailored
to a specific range to achieve
maximum efficiency (the risk being
if rock conditions diverge from
those the TBM is designed for) .
Instability problems at the tunnel
face, encountered during
excavation of the 12.9km long
Pinglin tunnel in Taiwan.
Barla&Pelizza(2000)
16
31 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
TBM Excavation & Design
32 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
TBM Excavation & Design
Single & Double Shield TBM’s – Single-shield TBM’s are cheaper
and are the preferred machine for hard rock tunnelling. Double
shielded TBMs are normally used in unstable geology (as they
offer more worker protection), or where a high rate of
advancement is required.
“Single”
shield TBM
“Double”
shield TBM
17
33 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
TBM Excavation & Design
U.S. Army Corps of Engineers (1997)
34 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
TBM Excavation & Design
U.S. Army Corps of Engineers (1997)
18
35 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
TBM Excavation & Design
TBM insertion through
vertical shaft.
TBM gripper used to provide
reactionary force for forward thrust
by gripping onto sidewalls of tunnel.
TBM working platform for
installing support (e.g. rock
bolts, meshing, shotcrete).
36 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
TBM Operation
19
37 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
Tunnelling Breakthroughs
38 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
TBM Selection & Weak Rock
The Yacambú-Quibor Tunnel is a prime example of
tunnelling blind – the geology was largely unfamiliar
and unpredictable. With little previous experience,
it was unknown how the rock would react, especially
under the high stresses of the Andes.
1975: Excavation begins on the 24 km tunnel, for which the
use of a full-face TBM is specified (for rapid excavation).
1977: The weak phyllites fail to provide the TBM grippers
with enough of a foundation to push off of. Supporting
squeezing ground was another defeating problem.
Geology: Weak, tectonically sheared graphitic phyllites were
encountered giving rise to serious squeezing problems, which without
adequate support would result in complete closure of the tunnel.
Hoek(2001)
Mining out the remains of
the trapped TBM.
1979: During a holiday shutdown, squeezing rock conditions
were left unchecked, resulting in the converging ground
effectively “swallowing” one of the TBMs.
1980’s: A decision is made to permit the tunnel to be
excavated by drill & blast. Recently completed, it took
more than 33 years to tunnel the full 24 km.
20
39 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
Sequential Excavation & Design - Benches
Benched excavations are used for large
diameter tunnels in weak rock. The benefits
are that the weak rock will be easier to
control for a small opening and reinforcement
can be progressively installed along the
heading before benching downward. Variations
may involve sequences in which the inverts, top
heading and bench are excavated in different
order.
40 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
Ground Reaction - Convergence
A key principle in underground construction involving weak rock is the
recognition that the main component of tunnel support is the
strength of the rock mass and that it can be mobilized by minimizing
deformations and preventing rock mass “loosening”.
Whittaker&Frith(1990)
During construction of a tunnel, some
relaxation of the rock mass will occur
above and along the sides of the tunnel.
21
41 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
Terzaghi’s Rock Load
Terzaghi (1946) formulated the first rational method of evaluating
rock loads appropriate to the design of steel sets.
The movement of the loosened area of
rock (acdb) will be resisted by friction
forces along its lateral boundaries and
these friction forces help to transfer
the major portion of the overburden
weight onto the material on either side
of the tunnel.
As such, the roof and sides of the tunnel
are required only to support the balance
which is equivalent to a height Hp.
Terzaghi related this parameter to the
tunnel dimensions and characteristics of
the rock mass to define a series of steel
arch support guidelines.
42 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
Terzaghi’s Rock Load
Terzaghi(1946)
Deere et al. (1970)
22
43 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
Tunnelling in Weak Rock
Terzaghi’s ”Rock Load” implicitly relates the
benefits gained through the grounds natural
tendency to arch. The essence of tunnelling in many
respects is to disturb the natural arch as little as
possible while excavating the material.
In weak rock, ground loosening breaches the integrity
of this natural arch. The consequence is that without
supporting the excavation soon after it is completed –
the walls may squeeze together and the roof collapse.
Besides the strength of the rock mass, a second key factor controlling the
extent of loosening is the size of the excavation. Several difficulties
relating to the size of the face include:
• increased volume of ground disturbed
• decreased accessibility to all parts of the face
• increasing difficulty in supporting and controlling face stability
44 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
Building on Past Experiences – Ground Control
23
45 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
Early Tunnel Experiences in Weak Rock
Through much trial and error, the lesson commonly learned was that with
a small tunnel face, the volume of ground moving and relaxing is also
smaller and can often be tolerated or kept within acceptable limits by
relatively simple timbering or other temporary support.
Belgium method
46 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
Early Tunnel Experiences in Weak Rock
Belgium method The method was first employed in building the
Chaleroy tunnel (in Belgium) in 1828. The great
advantage claimed for the system by Belgian and
French engineers was the speed whereby the roof of
the tunnel could be secured, a desirable advantage in
poor rock.
The method fell out of favour as a result of
catastrophic experiences encountered during
the construction of the Gotthard Tunnel
(1872-1882). The key problem was that the
sequencing following Stage 3 required the
arch to be underpinned. However, this
proved difficult in the yielding ground
conditions encountered, leading to the
timbers giving way, followed by the cracking
or total collapse of the masonry arch.
Beaver(1972)
24
47 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
Early Tunnel Experiences in Weak Rock
German system
The “German System” introduced the principle of
leaving a central bench of ground to be excavated last
and to use it to support roof and wall timbering.
This allowed the arching to be
built in one operation, unlike the
Belgium method which had the
disadvantage of building the
arch and walls separately.
The German system proved disastrous when applied to
the Cžernitz tunnel in Austria (1866), where the
timbers supporting the heading either pushed into the
core, whereupon they became loose, or were crushed
by swelling pressures that developed in the core.
48 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
Early Tunnel Experiences in Weak Rock
Austrian methodThe “Old” Austrian Tunnelling Method was first
used for the Oberau tunnel in 1837, which was
constructed through marls, gneiss and granite.
The method differed from others in that it
required the full section to be excavated before
the masonry was added, with the excavation
being carried out in small sections.
A centre-bottom heading was first driven for a
distance of about 5 m. This ‘pilot tunnel’ served
to ventilate the workings, drain the surrounding
area, and establish the tunnel alignment.
Sandström(1963)
A centre-top heading then followed (driven
for the same distance). Section 3 was
then removed by men working from the top
heading, enabling the top structures to
rest on the undisturbed timbers below.
25
49 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
Early Tunnel Experiences in Weak Rock
Austrian methodSandström(1963)
Once the excavation was
fully opened, the
masonry lining was built
up from the foundations
to the crown of the arch
in consecutive 5 m long
sections.
Breaking out of the tunnel to full width then
began at the shoulders, working down.
50 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
Sequential Excavation Methods (SEM)
Although the use of these early systems eventually died out due to the
huge quantity and high cost of timber required, and the replacement of
masonry linings with concrete, their underlying principles still live on. That
is the benefits of driving one or more small headings that are later
enlarged, enabling for ground deformations to be controlled better.
26
51 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
The Observational Method in Design
“In geotechnical engineering, vast goes towards securing approximate values
for required parameter inputs. Many additional variables are not considered
or remain unknown. Thus, the results of computations are no more than
working hypotheses, subject to confirmation or modification during
construction.”
In the 1940’s, Karl Terzaghi introduced a systematic means to manage
geological uncertainty in geotechnical design:
“These uncertainties require either the adoption of an excessive factor of
safety, or else assumptions based on general experience. The first of
these is wasteful; the second is dangerous as most failures occur due to
unanticipated ground conditions.”
“As an alternative, the observational method provides a ‘learn as you go’
approach. First, base the design on whatever information can be secured,
making note of all possible differences between reality and the
assumptions (i.e. worst case scenarios), and computing for the assumed
conditions, various quantities that can be measured in the field. Then,
based on these measurements, gradually close the gaps in knowledge and,
if necessary, modify the design during construction.”
Terzaghi&Peck(1948)
52 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
The Observation Method in Design
a) Sufficient exploration to establish the general nature, pattern and
properties of the soil deposits or rock mass;
b) Assessment of the most probable conditions and the most unfavourable
conceivable deviations from these conditions;
c) Establishment of the design based on a working hypothesis of behaviour
anticipated under the most probable conditions;
d) Selection of quantities to be observed during construction and calculation
of their anticipated values on the basis of the working hypothesis;
In brief, the method embodies the following components:
e) Calculation of values of the same quantities under the most unfavourable
conditions compatible with the available subsurface data;
f) Selection in advance of a course of action or modification of design for
every foreseeable significant deviation of the observational findings from
those predicted on the basis of the working hypothesis;
g) Measurement of quantities to be observed and evaluation of actual
conditions;
h) Modification of design to suit actual conditions.
27
53 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
Observation Method Example – Jubilee Extension
The Jubilee Line Extension to the London Underground, started in 1994
and called for twin tunnels 11 km long, crossing the river in four places,
with eleven new stations to be built, eight of which were to be
underground. One of the more problematic of these was a station placed
right opposite Big Ben.
54 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
Observation Method Example – Jubilee Extension
The technical implications were immense. Built in 1858, Big Ben
is known to be on a shallow foundation. It started to lean
towards the North shortly after completion. Any ground
movement in the vicinity would exaggerate this lean, and
threaten the stability of the structure.
28
55 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
Observation Method Example – Jubilee Extension
To deal with excavation-induced settlements that may irreversibly
damage historic buildings in the area, the design called for the use of
compensation grouting during tunnelling. In this process, a network of
horizontal tubes between the tunnels and the ground surface is
introduced, from which a series of grout holes are drilled. From these,
liquid cement can be injected into the ground from multiple points to
control/prevent movement during excavation of the main tunnels.
56 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
Observation Method Example – Jubilee Extension
Instrumentation was attached to Big Ben and to the buildings in the vicinity
to measure movement (with some 7000 monitoring points), and computers
were used to analyze the data to calculate where and when the grout has
to be injected.
For Big Ben, a movement of
15 mm at a height of 55m
(approximately the height of
the clock face above ground
level) was taken to be the
point at which movement had
to be controlled. Throughout
the 28 month construction
period, experience had to be
gained as to which tube to
use for grouting, the volume
of grout to be injected and
at what rate.
29
57 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
Observation Method Example – Jubilee Extension
It was calculated that without the
grouting, the movement of Big Ben
would have gone well over 100 mm,
which would have caused
unacceptable damage.
Following construction, the grouting pipes were
left in place and monitoring continued. Thus,
compensation grouting can be restarted if
required. However, instrumentation is showing
that no further grouting is necessary.
58 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
Lecture References
Barla, G & Pelizza, S (2000). TBM Tunneling in difficult conditions. In GeoEng2000, Melbourne.
Technomic Publishing Company: Lancaster, pp. 329-354.
Beaver, P. (1972). “A History of Tunnels”. Peter Davies: London. 155 pp.
Burland JB, Standing JR & Jardine FM (2001). Building Response to Tunnelling - Case Studies
from Construction of the Jubilee Line Extension, London. Thomas Telford: London.
Deere, DU, Peck, RB, Parker, H, Monsees, JE & Schmidt, B (1970). Design of tunnel support
systems. Highway Research Record, 339: 26-33.
Harding, H (1981). “Tunnelling History and My Own Involvement”. Golder Associates: Toronto,
258pp.
Hoek, E & Guevara, R (1999). Overcoming squeezing in the Yacambu´-Quibor Tunnel, Venezuela.
Rock Mechanics Rock Engineering, 42: 389–418.
Hudson, JA & Harrison, JP (1997). “Engineering Rock Mechanics – An Introduction to the
Principles ”. Elsevier Science: Oxford, 444pp.
Maidl, B, Herrenknecht, M & Anheuser, L (1996). “Mechanised Shield Tunnelling”. Ernst & Sohn:
Berlin, 428pp.
NTNU (1995). “Tunnel: Blast Design”. Department of Building and Construction Engineering,
Norwegian University of Science and Technology (NTNU), Trondheim, Project Report 2A-95.
30
59 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt
Lecture References
NTNU-Anleggsdrift (1998). “Hard Rock Tunnel Boring: The Boring Process”. Norwegian University
of Science and Technology (NTNU), Trondheim, Project Report 1F-98.
Sandström, G.E. (1963). “The History of Tunnelling”. Barrie and Rockliff: London. 427pp.
Terzagi, K (1946). Rock defects and loads on tunnel support. In Proctor & White (eds.), Rock
Tunneling with Steel Supports, pp. 15-99.
Terzaghi, K & Peck, RB (1948). “Soil mechanics in engineering practice”. Wiley: New York. 566pp.
Thuro, K & Plinninger, RJ (2003). Hard rock tunnel boring, cutting, drilling and blasting: rock
parameters for excavatability. In: Proc., 10th ISRM Congress, Johannesburg. SAIMM:
Johannesburg, pp. 1227-1234.
UNIT-NTH (1995). “Tunnel: Prognosis for Drill and Blast”. Department of Building and
Construction Engineering, Norwegian University of Science and Technology (NTNU), Trondheim,
Project Report 2B-95.
Whittaker, BN & Frith, RC (1990). “Tunnelling: Design, Stability and Construction”. Institution of
Mining and Metallurgy: London, 460pp.

Contenu connexe

Tendances

Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine
mohammadsalikali
 

Tendances (20)

Development and depillaring with continuous miner
Development and depillaring with continuous minerDevelopment and depillaring with continuous miner
Development and depillaring with continuous miner
 
Tunnels concepts
Tunnels conceptsTunnels concepts
Tunnels concepts
 
Drilling and blasting
Drilling and blastingDrilling and blasting
Drilling and blasting
 
GI For Tunnel Projects
GI For Tunnel ProjectsGI For Tunnel Projects
GI For Tunnel Projects
 
Blast hole drill
Blast hole drillBlast hole drill
Blast hole drill
 
Tunnel boring machines123
Tunnel boring machines123Tunnel boring machines123
Tunnel boring machines123
 
NATM (New Austrian Tunneling Method ) in Tunneling
NATM (New Austrian Tunneling Method ) in TunnelingNATM (New Austrian Tunneling Method ) in Tunneling
NATM (New Austrian Tunneling Method ) in Tunneling
 
Pillar design
Pillar designPillar design
Pillar design
 
Ug mechanical excavation
Ug mechanical excavationUg mechanical excavation
Ug mechanical excavation
 
Tunneling by tunnel boring machine
Tunneling by tunnel boring machineTunneling by tunnel boring machine
Tunneling by tunnel boring machine
 
Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine
 
Tunnel boring machine
Tunnel boring machineTunnel boring machine
Tunnel boring machine
 
Theories of interaction of rock cutting tools
Theories of interaction of rock cutting toolsTheories of interaction of rock cutting tools
Theories of interaction of rock cutting tools
 
Blasting and rock fragmentation
Blasting and rock fragmentationBlasting and rock fragmentation
Blasting and rock fragmentation
 
Tunnel boring machine ppt
Tunnel boring machine pptTunnel boring machine ppt
Tunnel boring machine ppt
 
NATM-Time cycle presentation (2)
NATM-Time cycle presentation (2)NATM-Time cycle presentation (2)
NATM-Time cycle presentation (2)
 
In pit crushing and conveying in surface mines
In pit crushing and conveying  in surface minesIn pit crushing and conveying  in surface mines
In pit crushing and conveying in surface mines
 
Drilling and blasting
Drilling and blastingDrilling and blasting
Drilling and blasting
 
Oc mechanical excavation
Oc mechanical excavationOc mechanical excavation
Oc mechanical excavation
 
Blasting
BlastingBlasting
Blasting
 

En vedette

segmental construction of bridges
segmental construction of bridgessegmental construction of bridges
segmental construction of bridges
Sravan Kumar
 
Shield Tail Deformations - Experiences, Mechanics and Lessons
Shield Tail Deformations - Experiences, Mechanics and LessonsShield Tail Deformations - Experiences, Mechanics and Lessons
Shield Tail Deformations - Experiences, Mechanics and Lessons
coen_van_der_vliet
 
Segmental Lining Design Presentation
Segmental Lining Design PresentationSegmental Lining Design Presentation
Segmental Lining Design Presentation
Keith Kong
 

En vedette (20)

segmental construction of bridges
segmental construction of bridgessegmental construction of bridges
segmental construction of bridges
 
Top down construction
Top down constructionTop down construction
Top down construction
 
Tunnelling methods
Tunnelling methodsTunnelling methods
Tunnelling methods
 
Shield Tail Deformations - Experiences, Mechanics and Lessons
Shield Tail Deformations - Experiences, Mechanics and LessonsShield Tail Deformations - Experiences, Mechanics and Lessons
Shield Tail Deformations - Experiences, Mechanics and Lessons
 
New Austrian Tunnelling Method (NATM)
New Austrian Tunnelling Method (NATM)New Austrian Tunnelling Method (NATM)
New Austrian Tunnelling Method (NATM)
 
Bridge 91 Design
Bridge 91 DesignBridge 91 Design
Bridge 91 Design
 
Tunneling
Tunneling Tunneling
Tunneling
 
World Tunnel Conference 2014
World Tunnel Conference 2014World Tunnel Conference 2014
World Tunnel Conference 2014
 
Directional Drilling
Directional DrillingDirectional Drilling
Directional Drilling
 
Casting yard
Casting yardCasting yard
Casting yard
 
Tunnels ppt
Tunnels pptTunnels ppt
Tunnels ppt
 
Dam PPT
Dam PPTDam PPT
Dam PPT
 
PreCast Construction
PreCast ConstructionPreCast Construction
PreCast Construction
 
Precast concrete construction
Precast concrete constructionPrecast concrete construction
Precast concrete construction
 
Bridge facts
Bridge factsBridge facts
Bridge facts
 
Segmental bridge construction
Segmental bridge constructionSegmental bridge construction
Segmental bridge construction
 
Challenges of Tunneling-- A Peep Into The Exciting World of Tunnelling
Challenges of Tunneling-- A Peep Into The Exciting World of TunnellingChallenges of Tunneling-- A Peep Into The Exciting World of Tunnelling
Challenges of Tunneling-- A Peep Into The Exciting World of Tunnelling
 
Tunnel Liners, Relines and Rehabilitation
Tunnel Liners, Relines and RehabilitationTunnel Liners, Relines and Rehabilitation
Tunnel Liners, Relines and Rehabilitation
 
Segmental Lining Design Presentation
Segmental Lining Design PresentationSegmental Lining Design Presentation
Segmental Lining Design Presentation
 
tunneling & its effects
tunneling & its effectstunneling & its effects
tunneling & its effects
 

Similaire à Tunnelling & underground design (Topic5-hard & weak rock tunnelling)

Wall control blasting practices at ksladag gold mine
Wall control blasting practices at ksladag gold mineWall control blasting practices at ksladag gold mine
Wall control blasting practices at ksladag gold mine
Alan Monzon
 
Buffer blasting presentation for Coal 2016.rev1
Buffer blasting presentation for Coal 2016.rev1Buffer blasting presentation for Coal 2016.rev1
Buffer blasting presentation for Coal 2016.rev1
John Latilla
 
Principles of-rock-drilling
Principles of-rock-drillingPrinciples of-rock-drilling
Principles of-rock-drilling
Saurabh Jain
 
Q922+de1+l08 v1
Q922+de1+l08 v1Q922+de1+l08 v1
Q922+de1+l08 v1
AFATous
 

Similaire à Tunnelling & underground design (Topic5-hard & weak rock tunnelling) (20)

Tunnelling & underground design (Topic4-soft ground tunnelling methods)
Tunnelling & underground design (Topic4-soft ground tunnelling methods)Tunnelling & underground design (Topic4-soft ground tunnelling methods)
Tunnelling & underground design (Topic4-soft ground tunnelling methods)
 
New burn cut blast design in drives enhances drilling blasting efficiency wit...
New burn cut blast design in drives enhances drilling blasting efficiency wit...New burn cut blast design in drives enhances drilling blasting efficiency wit...
New burn cut blast design in drives enhances drilling blasting efficiency wit...
 
Performance review of TBM
Performance review of TBMPerformance review of TBM
Performance review of TBM
 
Presentation on Piling Machine & TMB
Presentation on Piling Machine & TMBPresentation on Piling Machine & TMB
Presentation on Piling Machine & TMB
 
Tunnel boring machine
Tunnel boring machineTunnel boring machine
Tunnel boring machine
 
Wall control blasting practices at ksladag gold mine
Wall control blasting practices at ksladag gold mineWall control blasting practices at ksladag gold mine
Wall control blasting practices at ksladag gold mine
 
A Review Study on Methods of Tunneling in Hard Rocks
A Review Study on Methods of Tunneling in Hard RocksA Review Study on Methods of Tunneling in Hard Rocks
A Review Study on Methods of Tunneling in Hard Rocks
 
Drilling equipments
Drilling equipmentsDrilling equipments
Drilling equipments
 
Types of Drilling
Types of Drilling Types of Drilling
Types of Drilling
 
Buffer blasting presentation for Coal 2016.rev1
Buffer blasting presentation for Coal 2016.rev1Buffer blasting presentation for Coal 2016.rev1
Buffer blasting presentation for Coal 2016.rev1
 
IRJET - Enhancing Productivity in Opencast Mines – A Quantified Approach
IRJET -  	  Enhancing Productivity in Opencast Mines – A Quantified ApproachIRJET -  	  Enhancing Productivity in Opencast Mines – A Quantified Approach
IRJET - Enhancing Productivity in Opencast Mines – A Quantified Approach
 
Shaft sinking 1
Shaft sinking 1Shaft sinking 1
Shaft sinking 1
 
Principles of-rock-drilling
Principles of-rock-drillingPrinciples of-rock-drilling
Principles of-rock-drilling
 
Rocas de perforacion
Rocas de perforacionRocas de perforacion
Rocas de perforacion
 
Q922+de1+l08 v1
Q922+de1+l08 v1Q922+de1+l08 v1
Q922+de1+l08 v1
 
Design and Preparation of Aluminium Nozzle Using Metal Spinning Process
Design and Preparation of Aluminium Nozzle Using Metal Spinning ProcessDesign and Preparation of Aluminium Nozzle Using Metal Spinning Process
Design and Preparation of Aluminium Nozzle Using Metal Spinning Process
 
P-39 Yang Qiu
P-39 Yang QiuP-39 Yang Qiu
P-39 Yang Qiu
 
IRJET- Computer Aided Design and Finite Element Analysis of Swing Jaw Plate o...
IRJET- Computer Aided Design and Finite Element Analysis of Swing Jaw Plate o...IRJET- Computer Aided Design and Finite Element Analysis of Swing Jaw Plate o...
IRJET- Computer Aided Design and Finite Element Analysis of Swing Jaw Plate o...
 
Ijebea14 262
Ijebea14 262Ijebea14 262
Ijebea14 262
 
Jack hammer drill
Jack hammer drillJack hammer drill
Jack hammer drill
 

Plus de Hamed Zarei

دانلود مجموعه مقالات دومین کنفرانس ملی خاک و مهندسی پی
دانلود مجموعه مقالات دومین کنفرانس ملی خاک و مهندسی پیدانلود مجموعه مقالات دومین کنفرانس ملی خاک و مهندسی پی
دانلود مجموعه مقالات دومین کنفرانس ملی خاک و مهندسی پی
Hamed Zarei
 
(جلد دوم) SPSS 19 راهنمای آموزش
(جلد دوم) SPSS 19 راهنمای آموزش(جلد دوم) SPSS 19 راهنمای آموزش
(جلد دوم) SPSS 19 راهنمای آموزش
Hamed Zarei
 

Plus de Hamed Zarei (20)

دانلود مجموعه مقالات دومین کنفرانس ملی خاک و مهندسی پی
دانلود مجموعه مقالات دومین کنفرانس ملی خاک و مهندسی پیدانلود مجموعه مقالات دومین کنفرانس ملی خاک و مهندسی پی
دانلود مجموعه مقالات دومین کنفرانس ملی خاک و مهندسی پی
 
Blasting rock
Blasting rockBlasting rock
Blasting rock
 
جزوه درس اصول مهندسي سد
جزوه درس اصول مهندسي سدجزوه درس اصول مهندسي سد
جزوه درس اصول مهندسي سد
 
سدهای لاستیکی
سدهای لاستیکی سدهای لاستیکی
سدهای لاستیکی
 
ظرفیت عرضی و محوری تک شمع برای توربین های بادی ساحلی
ظرفیت عرضی و محوری تک شمع برای توربین های بادی ساحلیظرفیت عرضی و محوری تک شمع برای توربین های بادی ساحلی
ظرفیت عرضی و محوری تک شمع برای توربین های بادی ساحلی
 
numerical study and analytical solution of P-wave attenuation insensitive und...
numerical study and analytical solution of P-wave attenuation insensitive und...numerical study and analytical solution of P-wave attenuation insensitive und...
numerical study and analytical solution of P-wave attenuation insensitive und...
 
Intelligent back analysis using data from the instrument (poster)
Intelligent back analysis using data from the instrument (poster)Intelligent back analysis using data from the instrument (poster)
Intelligent back analysis using data from the instrument (poster)
 
(جلد دوم) SPSS 19 راهنمای آموزش
(جلد دوم) SPSS 19 راهنمای آموزش(جلد دوم) SPSS 19 راهنمای آموزش
(جلد دوم) SPSS 19 راهنمای آموزش
 
(جلد اول) SPSS 19 راهنمای آموزش
(جلد اول) SPSS 19 راهنمای آموزش(جلد اول) SPSS 19 راهنمای آموزش
(جلد اول) SPSS 19 راهنمای آموزش
 
3DEC برآورد میزان همگرایی تونل انتقال آب چهل‌چای با استفاده از شبکه عصبی مصنو...
3DEC برآورد میزان همگرایی تونل انتقال آب چهل‌چای با استفاده از شبکه عصبی مصنو...3DEC برآورد میزان همگرایی تونل انتقال آب چهل‌چای با استفاده از شبکه عصبی مصنو...
3DEC برآورد میزان همگرایی تونل انتقال آب چهل‌چای با استفاده از شبکه عصبی مصنو...
 
(روش های بهبود کیفیت بستر طبیعی زمین (راه آهن
(روش های بهبود کیفیت بستر طبیعی زمین (راه آهن (روش های بهبود کیفیت بستر طبیعی زمین (راه آهن
(روش های بهبود کیفیت بستر طبیعی زمین (راه آهن
 
(MATLAB) شبکه‌های عصبی و استفاده از جعبه ابزار آن در محيط متلب
(MATLAB) شبکه‌های عصبی و استفاده از جعبه ابزار آن در محيط متلب(MATLAB) شبکه‌های عصبی و استفاده از جعبه ابزار آن در محيط متلب
(MATLAB) شبکه‌های عصبی و استفاده از جعبه ابزار آن در محيط متلب
 
Tunnelling & underground design (Topic7-brittle failure)
Tunnelling & underground design (Topic7-brittle failure)Tunnelling & underground design (Topic7-brittle failure)
Tunnelling & underground design (Topic7-brittle failure)
 
Tunnelling & underground design (Topic3-geotechnical data baseline reports)
Tunnelling & underground design (Topic3-geotechnical data baseline reports)Tunnelling & underground design (Topic3-geotechnical data baseline reports)
Tunnelling & underground design (Topic3-geotechnical data baseline reports)
 
Tunnelling & underground design (Topic2-geological uncertainty)
Tunnelling & underground design (Topic2-geological uncertainty)Tunnelling & underground design (Topic2-geological uncertainty)
Tunnelling & underground design (Topic2-geological uncertainty)
 
Tunnelling & underground design (Topic1-introduction to the tunnelling industry)
Tunnelling & underground design (Topic1-introduction to the tunnelling industry)Tunnelling & underground design (Topic1-introduction to the tunnelling industry)
Tunnelling & underground design (Topic1-introduction to the tunnelling industry)
 
کنترل نشست های سطحی با روش قوس چتری در حفاری مرحله ی دوم متروی استانبول
کنترل نشست های سطحی با روش قوس چتری در حفاری مرحله ی دوم متروی استانبولکنترل نشست های سطحی با روش قوس چتری در حفاری مرحله ی دوم متروی استانبول
کنترل نشست های سطحی با روش قوس چتری در حفاری مرحله ی دوم متروی استانبول
 
Modeling of twain Tunnel water conveyance
Modeling of twain Tunnel water conveyanceModeling of twain Tunnel water conveyance
Modeling of twain Tunnel water conveyance
 
ابزاربندی و رفتارسنجی در تونل ها
ابزاربندی و رفتارسنجی در تونل هاابزاربندی و رفتارسنجی در تونل ها
ابزاربندی و رفتارسنجی در تونل ها
 
PLAXIS و SNAILمقایسه و تحلیل عددی دیوار میخکوبی شده با دو نرم افزار
 PLAXIS و SNAILمقایسه و تحلیل عددی دیوار میخکوبی شده با دو نرم افزار  PLAXIS و SNAILمقایسه و تحلیل عددی دیوار میخکوبی شده با دو نرم افزار
PLAXIS و SNAILمقایسه و تحلیل عددی دیوار میخکوبی شده با دو نرم افزار
 

Dernier

UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
rknatarajan
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Dr.Costas Sachpazis
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
dharasingh5698
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Christo Ananth
 

Dernier (20)

UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 
NFPA 5000 2024 standard .
NFPA 5000 2024 standard                                  .NFPA 5000 2024 standard                                  .
NFPA 5000 2024 standard .
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLPVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
Vivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design SpainVivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design Spain
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 

Tunnelling & underground design (Topic5-hard & weak rock tunnelling)

  • 1. 1 1 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt EOSC 547: Tunnelling & Underground Design Topic 5: Hard & Weak Rock Tunnelling 2 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt Tunnel Excavation in Rock It is instructive to consider the fundamental objective of the excavation process – which is to remove rock material (either to create an opening or to obtain material for its inherent value). In order to remove part of a rock mass, it is necessary to induce additional fracturing and fragmentation of the rock. The peak strength of the rock must be exceeded. This introduces three critical aspects of excavation: The in situ block size distribution must be changed to the required fragment size distribution. By what means should the required energy be introduced into the rock?
  • 2. 2 3 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt Tunnel Excavation in Rock Strength The tensile strength of rock is about 1/10th the compressive strength and the energy beneath the stress-strain curve is roughly its square. Therefore, breaking the rock in tension requires only 1/100th of the energy as that in compression. Block Size Hudson & Harrison (1997) The fracturing of rock during excavation changes the natural block size distribution to the fragment size distribution. The goal therefore is to consider how best to move from one curve to the other in the excavation process. 4 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt Energy and Excavation Process One objective in the excavation process may be to optimize the use of energy, i.e. the amount of energy required to remove a unit volume of rock (specific energy = J/m3). There are two fundamental ways of inputting energy into the rock for excavation: Blasting: Energy is input in large quantities over very short durations (cyclical – drill then blast, drill then blast, etc.). Machine Excavation: Energy is input in smaller quantities continuously.
  • 3. 3 5 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt Drill & Blast The technique of rock breakage using explosives involves drilling blastholes by percussion or rotary-percussive means, loading the boreholes with explosives and then detonating the explosive in each hole in sequence according to the blast design. The explosion generates a stress wave and significant gas pressure. Following the local fracturing at the blasthole wall and the spalling of the free face, the subsequent gas pressure then provides the necessary energy to disaggregate the broken rock. Hudson & Harrison (1997) 6 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt Conventional Drill & Blast Cycle
  • 4. 4 7 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt Conventional Drill & Blast Cycle Drill Load Blast Ventilate Scoop Scale Bolt Survey 8 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt Drill & Blast – Drilling Rates 0 1 2 3 4 5 0 20 40 60 80 100 120 140 Uniaxial Compressive Strength (MPa) DrillingRate(m/min) 0 1 2 3 4 5 0 100 200 300 400 500 Specific Energy (kJ/m3) DrillingRate(m/min) Thuro&Plinninger(2003)
  • 5. 5 9 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt Drill & Blast – Drilling Rates UNIT-NTH(1995) 10 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt Blasting Rounds – Burn Cut The correct design of a blast starts with the first hole to be detonated. In the case of a tunnel blast, the first requirement is to create a void into which rock broken by the blast can expand. This is generally achieved by a wedge or burn cut which is designed to create a clean void and to eject the rock originally contained in this void clear of the tunnel face. Burn cut designs using millisecond delays.
  • 6. 6 11 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt Blasting Rounds – Blast Pattern Design 12 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt Specialized Blasting Techniques During blasting, the explosive damage may not only occur according to the blasting round design, but there may also be extra rock damage behind the excavation boundary. To minimize damage to the rock, a smooth-wall blast may be used to create the final excavation surface. Hudson&Harrison(1997) The smooth-wall blast begins by creating a rough opening using a large bulk blast. This is followed by a smooth-wall blast along a series of closely spaced and lightly charged parallel holes, designed to create a fracture plane connecting the holes through by means of coalescing fractures.
  • 7. 7 13 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt Blasting Rounds – Fragmentation How efficiently muck from a working tunnel or surface excavation can be removed is a function of the blast fragmentation. Broken rock by volume is usually 50% greater than the in situ material. In mining, both the ore and waste has to be moved to surface for milling or disposal. Some waste material can be used underground to backfill mined voids. In tunnelling, everything has to be removed and dumped in fills – or if the material is right, may be removed and used for road ballast or concrete aggregate (which can sometimes then be re-used in the tunnel itself). 14 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt Blasting – Summary NTNU(1995)
  • 8. 8 15 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt Machine Excavation in Rock Tunnel Boring Machine (TBM) 16 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt Machine Excavation in Rock There are two basic types of machine for underground rock excavation: Partial-face machines: use a cutting head on the end of a movable boom (that itself may be track mounted). Full-face machines: use a rotating head armed with cutters, which fills the tunnel cross-section completely, and thus almost always excavates circular tunnels.
  • 9. 9 17 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt Machine Excavation in Rock Partial-face machines are cheaper, smaller and much more flexible in operation. cut scoop muck out 18 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt Machine Excavation in Rock Full-face machines – when used for relatively straight and long tunnels (>2 km) – permit high rates of advance in a smooth, automated construction operation. muck out cut scoop
  • 10. 10 19 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt Machine Excavation in Rock 20 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt Machine Excavation The advance rate at which the excavation proceeds is a function of the cutting rate and utilization factor (which is the amount of time that the machine is cutting rock). Factors contributing to low utilization rates are difficulties with ground support and steering, the need to frequently replace cutters, blocked scoops, broken conveyors, etc. The cutters may damage if the TBM is pushed forwards with too much force, or large blocks fall and strike them. Broken conveyor
  • 11. 11 21 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt TBM Operation Factors that may control TBM performance include: • TBM Penetration Rate (meters/machine hour) • TBM Downtime (minutes) • TBM Utilization (machine hours/shift hours) • Tool Wear (tool changes per shift) 22 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt Mechanics of Rock Cutting In tunnelling terms, a TBM applies both thrust (Fn) and torque (Ft) during the cutting process. In selecting the proper cutting tool, the engineer wishes to know how the tools should be configured on a machine cutting head, how to minimize the need to replace cutters, how to avoid damaging the cutter mounts, and how to minimize vibration. Hudson&Harrison(1997)
  • 12. 12 23 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt Mechanics of Rock Cutting NTNU-Anleggsdrift(1998) Cutting involves a complex mixture of tensile, shear and compressive modes of failure. With thrust, the cutting disc penetrates the rock and generates extensive crack propagation to the free surface. Further strain relief occurs as the disc edge rolls out of its cut, inducing further tensile cracking and slabbing at the rock surface. 24 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt Mechanics of Rock Cutting – Cutter Wear new uneven wear normal wear heavy wear The primary impact of disc wear on costs can be so severe that cutter costs are often considered as a separate item in bid preparation. In general, 1.5 hours are required for a single cutter change, and if several cutters are changed at one time, each may require 30-40 minutes. Even higher downtimes can be expected with large water inflows, which make cutter change activities more difficult and time-consuming.
  • 13. 13 25 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt Mechanical Excavation – Cutter Heads Delays: When the tunnel boring machine is inside the tunnel, the cutters must be changed from the inside the cutting head. 26 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt Mechanical Excavation – Cutter Heads
  • 14. 14 27 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt Mechanical Excavation – Cutter Heads 28 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt Mechanical Excavation – Cutter Heads
  • 15. 15 29 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt Mechanical Excavation – Cutter Heads 30 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt TBM Excavation & Design The two main factors that will stop tunnel boring machines are either the rock is too hard to cut or that the rock is too soft to sustain the reactionary force necessary to push the machine forward. TBM’s will operate within certain ranges of rock deformability and strength, where the machine can be tailored to a specific range to achieve maximum efficiency (the risk being if rock conditions diverge from those the TBM is designed for) . Instability problems at the tunnel face, encountered during excavation of the 12.9km long Pinglin tunnel in Taiwan. Barla&Pelizza(2000)
  • 16. 16 31 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt TBM Excavation & Design 32 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt TBM Excavation & Design Single & Double Shield TBM’s – Single-shield TBM’s are cheaper and are the preferred machine for hard rock tunnelling. Double shielded TBMs are normally used in unstable geology (as they offer more worker protection), or where a high rate of advancement is required. “Single” shield TBM “Double” shield TBM
  • 17. 17 33 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt TBM Excavation & Design U.S. Army Corps of Engineers (1997) 34 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt TBM Excavation & Design U.S. Army Corps of Engineers (1997)
  • 18. 18 35 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt TBM Excavation & Design TBM insertion through vertical shaft. TBM gripper used to provide reactionary force for forward thrust by gripping onto sidewalls of tunnel. TBM working platform for installing support (e.g. rock bolts, meshing, shotcrete). 36 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt TBM Operation
  • 19. 19 37 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt Tunnelling Breakthroughs 38 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt TBM Selection & Weak Rock The Yacambú-Quibor Tunnel is a prime example of tunnelling blind – the geology was largely unfamiliar and unpredictable. With little previous experience, it was unknown how the rock would react, especially under the high stresses of the Andes. 1975: Excavation begins on the 24 km tunnel, for which the use of a full-face TBM is specified (for rapid excavation). 1977: The weak phyllites fail to provide the TBM grippers with enough of a foundation to push off of. Supporting squeezing ground was another defeating problem. Geology: Weak, tectonically sheared graphitic phyllites were encountered giving rise to serious squeezing problems, which without adequate support would result in complete closure of the tunnel. Hoek(2001) Mining out the remains of the trapped TBM. 1979: During a holiday shutdown, squeezing rock conditions were left unchecked, resulting in the converging ground effectively “swallowing” one of the TBMs. 1980’s: A decision is made to permit the tunnel to be excavated by drill & blast. Recently completed, it took more than 33 years to tunnel the full 24 km.
  • 20. 20 39 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt Sequential Excavation & Design - Benches Benched excavations are used for large diameter tunnels in weak rock. The benefits are that the weak rock will be easier to control for a small opening and reinforcement can be progressively installed along the heading before benching downward. Variations may involve sequences in which the inverts, top heading and bench are excavated in different order. 40 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt Ground Reaction - Convergence A key principle in underground construction involving weak rock is the recognition that the main component of tunnel support is the strength of the rock mass and that it can be mobilized by minimizing deformations and preventing rock mass “loosening”. Whittaker&Frith(1990) During construction of a tunnel, some relaxation of the rock mass will occur above and along the sides of the tunnel.
  • 21. 21 41 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt Terzaghi’s Rock Load Terzaghi (1946) formulated the first rational method of evaluating rock loads appropriate to the design of steel sets. The movement of the loosened area of rock (acdb) will be resisted by friction forces along its lateral boundaries and these friction forces help to transfer the major portion of the overburden weight onto the material on either side of the tunnel. As such, the roof and sides of the tunnel are required only to support the balance which is equivalent to a height Hp. Terzaghi related this parameter to the tunnel dimensions and characteristics of the rock mass to define a series of steel arch support guidelines. 42 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt Terzaghi’s Rock Load Terzaghi(1946) Deere et al. (1970)
  • 22. 22 43 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt Tunnelling in Weak Rock Terzaghi’s ”Rock Load” implicitly relates the benefits gained through the grounds natural tendency to arch. The essence of tunnelling in many respects is to disturb the natural arch as little as possible while excavating the material. In weak rock, ground loosening breaches the integrity of this natural arch. The consequence is that without supporting the excavation soon after it is completed – the walls may squeeze together and the roof collapse. Besides the strength of the rock mass, a second key factor controlling the extent of loosening is the size of the excavation. Several difficulties relating to the size of the face include: • increased volume of ground disturbed • decreased accessibility to all parts of the face • increasing difficulty in supporting and controlling face stability 44 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt Building on Past Experiences – Ground Control
  • 23. 23 45 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt Early Tunnel Experiences in Weak Rock Through much trial and error, the lesson commonly learned was that with a small tunnel face, the volume of ground moving and relaxing is also smaller and can often be tolerated or kept within acceptable limits by relatively simple timbering or other temporary support. Belgium method 46 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt Early Tunnel Experiences in Weak Rock Belgium method The method was first employed in building the Chaleroy tunnel (in Belgium) in 1828. The great advantage claimed for the system by Belgian and French engineers was the speed whereby the roof of the tunnel could be secured, a desirable advantage in poor rock. The method fell out of favour as a result of catastrophic experiences encountered during the construction of the Gotthard Tunnel (1872-1882). The key problem was that the sequencing following Stage 3 required the arch to be underpinned. However, this proved difficult in the yielding ground conditions encountered, leading to the timbers giving way, followed by the cracking or total collapse of the masonry arch. Beaver(1972)
  • 24. 24 47 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt Early Tunnel Experiences in Weak Rock German system The “German System” introduced the principle of leaving a central bench of ground to be excavated last and to use it to support roof and wall timbering. This allowed the arching to be built in one operation, unlike the Belgium method which had the disadvantage of building the arch and walls separately. The German system proved disastrous when applied to the Cžernitz tunnel in Austria (1866), where the timbers supporting the heading either pushed into the core, whereupon they became loose, or were crushed by swelling pressures that developed in the core. 48 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt Early Tunnel Experiences in Weak Rock Austrian methodThe “Old” Austrian Tunnelling Method was first used for the Oberau tunnel in 1837, which was constructed through marls, gneiss and granite. The method differed from others in that it required the full section to be excavated before the masonry was added, with the excavation being carried out in small sections. A centre-bottom heading was first driven for a distance of about 5 m. This ‘pilot tunnel’ served to ventilate the workings, drain the surrounding area, and establish the tunnel alignment. Sandström(1963) A centre-top heading then followed (driven for the same distance). Section 3 was then removed by men working from the top heading, enabling the top structures to rest on the undisturbed timbers below.
  • 25. 25 49 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt Early Tunnel Experiences in Weak Rock Austrian methodSandström(1963) Once the excavation was fully opened, the masonry lining was built up from the foundations to the crown of the arch in consecutive 5 m long sections. Breaking out of the tunnel to full width then began at the shoulders, working down. 50 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt Sequential Excavation Methods (SEM) Although the use of these early systems eventually died out due to the huge quantity and high cost of timber required, and the replacement of masonry linings with concrete, their underlying principles still live on. That is the benefits of driving one or more small headings that are later enlarged, enabling for ground deformations to be controlled better.
  • 26. 26 51 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt The Observational Method in Design “In geotechnical engineering, vast goes towards securing approximate values for required parameter inputs. Many additional variables are not considered or remain unknown. Thus, the results of computations are no more than working hypotheses, subject to confirmation or modification during construction.” In the 1940’s, Karl Terzaghi introduced a systematic means to manage geological uncertainty in geotechnical design: “These uncertainties require either the adoption of an excessive factor of safety, or else assumptions based on general experience. The first of these is wasteful; the second is dangerous as most failures occur due to unanticipated ground conditions.” “As an alternative, the observational method provides a ‘learn as you go’ approach. First, base the design on whatever information can be secured, making note of all possible differences between reality and the assumptions (i.e. worst case scenarios), and computing for the assumed conditions, various quantities that can be measured in the field. Then, based on these measurements, gradually close the gaps in knowledge and, if necessary, modify the design during construction.” Terzaghi&Peck(1948) 52 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt The Observation Method in Design a) Sufficient exploration to establish the general nature, pattern and properties of the soil deposits or rock mass; b) Assessment of the most probable conditions and the most unfavourable conceivable deviations from these conditions; c) Establishment of the design based on a working hypothesis of behaviour anticipated under the most probable conditions; d) Selection of quantities to be observed during construction and calculation of their anticipated values on the basis of the working hypothesis; In brief, the method embodies the following components: e) Calculation of values of the same quantities under the most unfavourable conditions compatible with the available subsurface data; f) Selection in advance of a course of action or modification of design for every foreseeable significant deviation of the observational findings from those predicted on the basis of the working hypothesis; g) Measurement of quantities to be observed and evaluation of actual conditions; h) Modification of design to suit actual conditions.
  • 27. 27 53 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt Observation Method Example – Jubilee Extension The Jubilee Line Extension to the London Underground, started in 1994 and called for twin tunnels 11 km long, crossing the river in four places, with eleven new stations to be built, eight of which were to be underground. One of the more problematic of these was a station placed right opposite Big Ben. 54 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt Observation Method Example – Jubilee Extension The technical implications were immense. Built in 1858, Big Ben is known to be on a shallow foundation. It started to lean towards the North shortly after completion. Any ground movement in the vicinity would exaggerate this lean, and threaten the stability of the structure.
  • 28. 28 55 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt Observation Method Example – Jubilee Extension To deal with excavation-induced settlements that may irreversibly damage historic buildings in the area, the design called for the use of compensation grouting during tunnelling. In this process, a network of horizontal tubes between the tunnels and the ground surface is introduced, from which a series of grout holes are drilled. From these, liquid cement can be injected into the ground from multiple points to control/prevent movement during excavation of the main tunnels. 56 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt Observation Method Example – Jubilee Extension Instrumentation was attached to Big Ben and to the buildings in the vicinity to measure movement (with some 7000 monitoring points), and computers were used to analyze the data to calculate where and when the grout has to be injected. For Big Ben, a movement of 15 mm at a height of 55m (approximately the height of the clock face above ground level) was taken to be the point at which movement had to be controlled. Throughout the 28 month construction period, experience had to be gained as to which tube to use for grouting, the volume of grout to be injected and at what rate.
  • 29. 29 57 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt Observation Method Example – Jubilee Extension It was calculated that without the grouting, the movement of Big Ben would have gone well over 100 mm, which would have caused unacceptable damage. Following construction, the grouting pipes were left in place and monitoring continued. Thus, compensation grouting can be restarted if required. However, instrumentation is showing that no further grouting is necessary. 58 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt Lecture References Barla, G & Pelizza, S (2000). TBM Tunneling in difficult conditions. In GeoEng2000, Melbourne. Technomic Publishing Company: Lancaster, pp. 329-354. Beaver, P. (1972). “A History of Tunnels”. Peter Davies: London. 155 pp. Burland JB, Standing JR & Jardine FM (2001). Building Response to Tunnelling - Case Studies from Construction of the Jubilee Line Extension, London. Thomas Telford: London. Deere, DU, Peck, RB, Parker, H, Monsees, JE & Schmidt, B (1970). Design of tunnel support systems. Highway Research Record, 339: 26-33. Harding, H (1981). “Tunnelling History and My Own Involvement”. Golder Associates: Toronto, 258pp. Hoek, E & Guevara, R (1999). Overcoming squeezing in the Yacambu´-Quibor Tunnel, Venezuela. Rock Mechanics Rock Engineering, 42: 389–418. Hudson, JA & Harrison, JP (1997). “Engineering Rock Mechanics – An Introduction to the Principles ”. Elsevier Science: Oxford, 444pp. Maidl, B, Herrenknecht, M & Anheuser, L (1996). “Mechanised Shield Tunnelling”. Ernst & Sohn: Berlin, 428pp. NTNU (1995). “Tunnel: Blast Design”. Department of Building and Construction Engineering, Norwegian University of Science and Technology (NTNU), Trondheim, Project Report 2A-95.
  • 30. 30 59 of 59 Tunnelling Grad Class (2015) Dr. Erik Eberhardt Lecture References NTNU-Anleggsdrift (1998). “Hard Rock Tunnel Boring: The Boring Process”. Norwegian University of Science and Technology (NTNU), Trondheim, Project Report 1F-98. Sandström, G.E. (1963). “The History of Tunnelling”. Barrie and Rockliff: London. 427pp. Terzagi, K (1946). Rock defects and loads on tunnel support. In Proctor & White (eds.), Rock Tunneling with Steel Supports, pp. 15-99. Terzaghi, K & Peck, RB (1948). “Soil mechanics in engineering practice”. Wiley: New York. 566pp. Thuro, K & Plinninger, RJ (2003). Hard rock tunnel boring, cutting, drilling and blasting: rock parameters for excavatability. In: Proc., 10th ISRM Congress, Johannesburg. SAIMM: Johannesburg, pp. 1227-1234. UNIT-NTH (1995). “Tunnel: Prognosis for Drill and Blast”. Department of Building and Construction Engineering, Norwegian University of Science and Technology (NTNU), Trondheim, Project Report 2B-95. Whittaker, BN & Frith, RC (1990). “Tunnelling: Design, Stability and Construction”. Institution of Mining and Metallurgy: London, 460pp.