1. Project Schedule
Date Work Deadline
21 Oct - Video research document 28 October – 1st draft
(forms & conventions, target 4 January –completed and put
aud research, subject matter, on blogs
rep issues, inst context & pro
practice)
- Proposal
28 Oct Video script Development 28 October
2 Nov Meet up with the band – get to -
know the band & discuss the
ideas, also find out
background information on
the band
- Organise a stage – for band -
performance and a balcony
for the Romeo & Juliet scene
16 Nov Video shoot 23 November
23 Nov Begin video editing 14 December
30 Nov Prepare for print production -
7 Dec Print skills development 4 January
4 Jan DVD cover & Mag advert - -
construction
25 Jan “ ” -
completed
1 Feb - Target audience feedback Completed
(video & print products)
- Miscellaneous
1 Feb Unit evaluation 8 February
(1st draft) 1 March – final draft