Activity Definition Activity List Resource Plan Activity sequencing Activity Resource Estimating Activity Duration  Estimating Duration    Estimate Network Diagram Schedule Development Integrated Schedule
Making a Schedule that “Works” Identify schedule “problems” Incorrect activity definition:  work packages vs activities Incorrect sequencing: Unhealthy networks Over-allocated resources:  resource levelling Making the schedule “useful” “Just in time” scheduling:  The Rolling Wave Getting done on time Making status visible:  Reports and Milestones The final product is the Time Management Plan called the “Integrated Schedule”
Activities vs. Work Packages Activities describe the processes performed to complete all the “work” in the Work Package
Activities vs Work Packages Example: Work Package = Qualification Test Report Activities: Collate Test Results Provide Data Package to Publications Prepare Report Check Report Project Manager Review Submit through Data Management
The “reality check” Once the links are entered, they should form a complete network Everything ties in to “something” As much as possible, all the “loose ends” tie back together at the end
Resource Levelling When the “ideal” schedule is viewed to check the “resource usage”, many resources maybe “overutilized” Example: If you have only one carpenter, you can’t have “Saw table legs” happen at the same time as “Assemble chair back” This is usually showed via a “histogram” that plots resource demand over time vs. the defined team size
Options for dealing for overutilized resources Negotiate increased resources with functional manager Increase “productivity” through overtime, or procurement of enabling technology  Consider options for work re-allocation: Outsourcing Work segmentation to allow partial performance by another under-utilized function (eg. Getting an Admin Assistant to perform “clerical” tasks of writing a technical report) “Resource levelling” = re-arranging existing program resources and task sequence to minimize impacts to the “critical path” – delay “non-critical” tasks with conflicting resources
“Rolling Wave” Schedule Definition Some projects can be scheduled in detail at the beginning: Repeat of previous projects (eg. Building a house) Technology well understood, with little chance for environmental impact (eg. Database design) For many projects, however, only near term tasks are scheduled in detail: Technology not well developed or developed during project (eg.cold fusion reactor) Project involves significant “trade studies” or selection of alternative approaches (eg. Project to “develop corporate network” – Client/server vs. stand-alone? Mac vs. PC? Wireless vs broadband?)  Project is lengthy and act of activity definition is a significant cost driver Latter using “Rolling Wave” scheduling
“Rolling Wave” Definition Near term/known events scheduled and resource loaded in detail to “activity” level Longer term activities scheduled at increasingly reduced levels of detail Depending on risk reduction philosophy, these may either have no budget/ resources allocated, or may be “lumped” as “Planning Packages”
Techniques for Shortening a Project Schedule Focus on the Critical Path Crashing: shortening the “calendar” duration of a task Apply more resources Apply overtime Introduce enabling technologies, eg. Automation “re-design” the work (eg.  Current process requires 4 approvals – change process to require 2) Fast tracking:  doing tasks - normally done in sequence - in parallel Eg. you eat breakfast, then drive to work      eat breakfast while driving Eg. Test product, then ship it       perform “minimum”/safety-critical tests and ship while completing remainder Remember the “Constraint Triangle”, any schedule reduction means: Cost, scope or quality trade-off Risk impact – especially when fast-tracking
Shortening Project Schedules Original  schedule Crashing Shortenedduration Fast tracking Overlapped tasks
Milestones Milestones = zero duration tasks inserted into the schedule to provide visibility to key dates May be mandated by contract or management, at PM discretion or both Location: “Milestone” section at the top of the project Provides immediate summary of program goals and status Easy access for changing and “What-if” analyses “Embedded” in the related task path if needed to clarify inputs critical to that path Definition methods: “Hard dates”:   Typed in as a “date” no “driving” dependencies Used to flow information “into” the schedule “Status Dates”: Hooked on to the end of a task network leading up to the state to be tracked Used to flow information “out of” the schedule
Application of Milestones Flow “down” key commitments from the contract/program plan (eg. First shipment; inputs to customer activities) “Hard” dates in the “milestone” section Flow “up” estimated completion dates (eg. Design complete; Foundation complete) “Status” dates usually embedded in schedule  Indicate “external” inputs to the program from other schedules or program entities (eg.  Parts available from supplier; test equipment available in shared facility) “Hard” dates embedded or at the top Measurement of performance – discussed in integration section Estimated vs committed “Burndown” Earned Value recognition Contractual basis for invoicing progress payments Usually attached to the “key commitments”
Schedule Reports the “schedule” is actually a database that integrates task cost, time and logic – often called:  integrated schedule Integrated master schedule Cost/budget Can be used to generate various views and reports: WBS (sometimes) Network diagram (PERT chart) “Schedule”  (GANTT chart) Resource/cost profiles

Contenu connexe

Tendances

sMs project tutorial_iit
sMs project tutorial_iitsMs project tutorial_iit
sMs project tutorial_iitKushal Patel
 
Acumen Fuse: Enterprise Project Analysis Datasheet
Acumen Fuse: Enterprise Project Analysis DatasheetAcumen Fuse: Enterprise Project Analysis Datasheet
Acumen Fuse: Enterprise Project Analysis DatasheetCisco
 
MS Project Management (Overviews) | Software Mange Tool | Software Project Ma...
MS Project Management (Overviews) | Software Mange Tool | Software Project Ma...MS Project Management (Overviews) | Software Mange Tool | Software Project Ma...
MS Project Management (Overviews) | Software Mange Tool | Software Project Ma...Kuldeep Kumar
 
Primavera P6 basics-tips-and-tricks
Primavera P6 basics-tips-and-tricksPrimavera P6 basics-tips-and-tricks
Primavera P6 basics-tips-and-tricksMohammad khan
 
44259126 ms-project-presentation
44259126 ms-project-presentation44259126 ms-project-presentation
44259126 ms-project-presentationFarrukh Raja
 
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™Charlie Jackson
 
Project management with ms project 2007
Project management with ms project 2007Project management with ms project 2007
Project management with ms project 2007Fasil Ayele
 
Scheduling minimizing the input while maximizing the output white paper
Scheduling   minimizing the input while maximizing the output white paperScheduling   minimizing the input while maximizing the output white paper
Scheduling minimizing the input while maximizing the output white paperp6academy
 
Ms project training ppt
Ms project training pptMs project training ppt
Ms project training pptglobalp7
 
Microsoft project calender
Microsoft project calenderMicrosoft project calender
Microsoft project calenderMaheep Gupta
 
Ms Project 2010 Application For PMP
Ms Project 2010 Application For PMPMs Project 2010 Application For PMP
Ms Project 2010 Application For PMPAndy Pham, PMP
 
Microsoft Project and Portfolio Management
Microsoft Project and Portfolio ManagementMicrosoft Project and Portfolio Management
Microsoft Project and Portfolio ManagementDavid J Rosenthal
 
Project management by MS Project 2010
Project management by MS Project 2010Project management by MS Project 2010
Project management by MS Project 2010Wadhwani Foundation
 
Certificate IV Project Management - Activity Duration Estimating (Inputs)
Certificate IV Project Management - Activity Duration Estimating (Inputs)Certificate IV Project Management - Activity Duration Estimating (Inputs)
Certificate IV Project Management - Activity Duration Estimating (Inputs)danieljohn810
 
Ms Project Workshop
Ms Project WorkshopMs Project Workshop
Ms Project WorkshopEder Alves
 
Importance of Microsoft Project and Primavera
Importance of Microsoft Project and Primavera Importance of Microsoft Project and Primavera
Importance of Microsoft Project and Primavera Sagar Tilwani
 
MS Project 2010 Getting Started
MS Project 2010 Getting StartedMS Project 2010 Getting Started
MS Project 2010 Getting Startedmsprojectpros
 

Tendances (20)

sMs project tutorial_iit
sMs project tutorial_iitsMs project tutorial_iit
sMs project tutorial_iit
 
Acumen Fuse: Enterprise Project Analysis Datasheet
Acumen Fuse: Enterprise Project Analysis DatasheetAcumen Fuse: Enterprise Project Analysis Datasheet
Acumen Fuse: Enterprise Project Analysis Datasheet
 
MS Project Management (Overviews) | Software Mange Tool | Software Project Ma...
MS Project Management (Overviews) | Software Mange Tool | Software Project Ma...MS Project Management (Overviews) | Software Mange Tool | Software Project Ma...
MS Project Management (Overviews) | Software Mange Tool | Software Project Ma...
 
Primavera P6 basics-tips-and-tricks
Primavera P6 basics-tips-and-tricksPrimavera P6 basics-tips-and-tricks
Primavera P6 basics-tips-and-tricks
 
44259126 ms-project-presentation
44259126 ms-project-presentation44259126 ms-project-presentation
44259126 ms-project-presentation
 
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
 
Project management with ms project 2007
Project management with ms project 2007Project management with ms project 2007
Project management with ms project 2007
 
tcc primavera
tcc primaveratcc primavera
tcc primavera
 
Scheduling minimizing the input while maximizing the output white paper
Scheduling   minimizing the input while maximizing the output white paperScheduling   minimizing the input while maximizing the output white paper
Scheduling minimizing the input while maximizing the output white paper
 
Ms project training ppt
Ms project training pptMs project training ppt
Ms project training ppt
 
MS Project
MS Project MS Project
MS Project
 
Microsoft project calender
Microsoft project calenderMicrosoft project calender
Microsoft project calender
 
Ms Project 2010 Application For PMP
Ms Project 2010 Application For PMPMs Project 2010 Application For PMP
Ms Project 2010 Application For PMP
 
Ms project lectures
Ms project lecturesMs project lectures
Ms project lectures
 
Microsoft Project and Portfolio Management
Microsoft Project and Portfolio ManagementMicrosoft Project and Portfolio Management
Microsoft Project and Portfolio Management
 
Project management by MS Project 2010
Project management by MS Project 2010Project management by MS Project 2010
Project management by MS Project 2010
 
Certificate IV Project Management - Activity Duration Estimating (Inputs)
Certificate IV Project Management - Activity Duration Estimating (Inputs)Certificate IV Project Management - Activity Duration Estimating (Inputs)
Certificate IV Project Management - Activity Duration Estimating (Inputs)
 
Ms Project Workshop
Ms Project WorkshopMs Project Workshop
Ms Project Workshop
 
Importance of Microsoft Project and Primavera
Importance of Microsoft Project and Primavera Importance of Microsoft Project and Primavera
Importance of Microsoft Project and Primavera
 
MS Project 2010 Getting Started
MS Project 2010 Getting StartedMS Project 2010 Getting Started
MS Project 2010 Getting Started
 

Similaire à Activity Definition and Schedule Development

MS Project Presentation
MS Project PresentationMS Project Presentation
MS Project PresentationKhem Singh
 
dokumen.tips_ms-project-presentation.pptx
dokumen.tips_ms-project-presentation.pptxdokumen.tips_ms-project-presentation.pptx
dokumen.tips_ms-project-presentation.pptxSunilHotkar2
 
ms-project-presentation.pptx
ms-project-presentation.pptxms-project-presentation.pptx
ms-project-presentation.pptxSunilHotkar2
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULEAjeesh Mk
 
PMP Exam Prep - Time Management
PMP Exam Prep - Time ManagementPMP Exam Prep - Time Management
PMP Exam Prep - Time Managementtkrikau
 
L05 time management
L05 time managementL05 time management
L05 time managementAsa Chan
 
9 project planning
9 project planning9 project planning
9 project planningrandhirlpu
 
Project management
Project managementProject management
Project managementervinod
 
2.06 time management 1
2.06 time management 12.06 time management 1
2.06 time management 1reddvise
 
Chapter-5-Scheduling-and-Resource-Allocation.ppt
Chapter-5-Scheduling-and-Resource-Allocation.pptChapter-5-Scheduling-and-Resource-Allocation.ppt
Chapter-5-Scheduling-and-Resource-Allocation.pptTecnicoItca
 

Similaire à Activity Definition and Schedule Development (20)

MS Project Presentation
MS Project PresentationMS Project Presentation
MS Project Presentation
 
dokumen.tips_ms-project-presentation.pptx
dokumen.tips_ms-project-presentation.pptxdokumen.tips_ms-project-presentation.pptx
dokumen.tips_ms-project-presentation.pptx
 
ms-project-presentation.pptx
ms-project-presentation.pptxms-project-presentation.pptx
ms-project-presentation.pptx
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
PMP Exam Prep - Time Management
PMP Exam Prep - Time ManagementPMP Exam Prep - Time Management
PMP Exam Prep - Time Management
 
Project Planning Scheduling
Project Planning SchedulingProject Planning Scheduling
Project Planning Scheduling
 
L05 time management
L05 time managementL05 time management
L05 time management
 
02-Key Definitions .pdf
02-Key Definitions .pdf02-Key Definitions .pdf
02-Key Definitions .pdf
 
9 project planning
9 project planning9 project planning
9 project planning
 
Project Management
Project ManagementProject Management
Project Management
 
Pert
PertPert
Pert
 
Project management
Project managementProject management
Project management
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
2.06 time management 1
2.06 time management 12.06 time management 1
2.06 time management 1
 
Chapter-5-Scheduling-and-Resource-Allocation.ppt
Chapter-5-Scheduling-and-Resource-Allocation.pptChapter-5-Scheduling-and-Resource-Allocation.ppt
Chapter-5-Scheduling-and-Resource-Allocation.ppt
 
PMNM101 Lesson 2 2022.pptx
PMNM101 Lesson 2 2022.pptxPMNM101 Lesson 2 2022.pptx
PMNM101 Lesson 2 2022.pptx
 
PERT CPM Intro
PERT CPM IntroPERT CPM Intro
PERT CPM Intro
 
Pert 182
Pert 182Pert 182
Pert 182
 
06 pert cpm
06 pert cpm06 pert cpm
06 pert cpm
 

Plus de harwoodr

3 pm3 t_we%20-%20setting%20up%20the%20control%20account%20structure
3 pm3 t_we%20-%20setting%20up%20the%20control%20account%20structure3 pm3 t_we%20-%20setting%20up%20the%20control%20account%20structure
3 pm3 t_we%20-%20setting%20up%20the%20control%20account%20structureharwoodr
 
3 pm3 t_we%20-%20creating%20the%20schedule%20network
3 pm3 t_we%20-%20creating%20the%20schedule%20network3 pm3 t_we%20-%20creating%20the%20schedule%20network
3 pm3 t_we%20-%20creating%20the%20schedule%20networkharwoodr
 
3 pm3 t_we%20-%20adding%20resources%20to%20the%20schedule
3 pm3 t_we%20-%20adding%20resources%20to%20the%20schedule3 pm3 t_we%20-%20adding%20resources%20to%20the%20schedule
3 pm3 t_we%20-%20adding%20resources%20to%20the%20scheduleharwoodr
 
3 pm3 t_3%20-%20activity%20resource%20estimating
3 pm3 t_3%20-%20activity%20resource%20estimating3 pm3 t_3%20-%20activity%20resource%20estimating
3 pm3 t_3%20-%20activity%20resource%20estimatingharwoodr
 
3 pm3 t_2%20-%20activity%20duration%20estimating
3 pm3 t_2%20-%20activity%20duration%20estimating3 pm3 t_2%20-%20activity%20duration%20estimating
3 pm3 t_2%20-%20activity%20duration%20estimatingharwoodr
 
3 pm3 t_1%20-%20activity%20sequencing
3 pm3 t_1%20-%20activity%20sequencing3 pm3 t_1%20-%20activity%20sequencing
3 pm3 t_1%20-%20activity%20sequencingharwoodr
 
3 pm3 c_5%20-%20work%20authorization
3 pm3 c_5%20-%20work%20authorization3 pm3 c_5%20-%20work%20authorization
3 pm3 c_5%20-%20work%20authorizationharwoodr
 
3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget
3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget
3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budgetharwoodr
 
3 pm3 c_3%20-%20the%20program%20budget
3 pm3 c_3%20-%20the%20program%20budget3 pm3 c_3%20-%20the%20program%20budget
3 pm3 c_3%20-%20the%20program%20budgetharwoodr
 
3 pm3 c_2-%20estimating%20costs
3 pm3 c_2-%20estimating%20costs3 pm3 c_2-%20estimating%20costs
3 pm3 c_2-%20estimating%20costsharwoodr
 
3 pm3 c_1%20-%20developing%20the%20cost%20plan
3 pm3 c_1%20-%20developing%20the%20cost%20plan3 pm3 c_1%20-%20developing%20the%20cost%20plan
3 pm3 c_1%20-%20developing%20the%20cost%20planharwoodr
 

Plus de harwoodr (12)

3 pm3 t_we%20-%20setting%20up%20the%20control%20account%20structure
3 pm3 t_we%20-%20setting%20up%20the%20control%20account%20structure3 pm3 t_we%20-%20setting%20up%20the%20control%20account%20structure
3 pm3 t_we%20-%20setting%20up%20the%20control%20account%20structure
 
3 pm3 t_we%20-%20creating%20the%20schedule%20network
3 pm3 t_we%20-%20creating%20the%20schedule%20network3 pm3 t_we%20-%20creating%20the%20schedule%20network
3 pm3 t_we%20-%20creating%20the%20schedule%20network
 
3 pm3 t_we%20-%20adding%20resources%20to%20the%20schedule
3 pm3 t_we%20-%20adding%20resources%20to%20the%20schedule3 pm3 t_we%20-%20adding%20resources%20to%20the%20schedule
3 pm3 t_we%20-%20adding%20resources%20to%20the%20schedule
 
3 pm3 t_3%20-%20activity%20resource%20estimating
3 pm3 t_3%20-%20activity%20resource%20estimating3 pm3 t_3%20-%20activity%20resource%20estimating
3 pm3 t_3%20-%20activity%20resource%20estimating
 
3 pm3 t_2%20-%20activity%20duration%20estimating
3 pm3 t_2%20-%20activity%20duration%20estimating3 pm3 t_2%20-%20activity%20duration%20estimating
3 pm3 t_2%20-%20activity%20duration%20estimating
 
3 pm3 t_1%20-%20activity%20sequencing
3 pm3 t_1%20-%20activity%20sequencing3 pm3 t_1%20-%20activity%20sequencing
3 pm3 t_1%20-%20activity%20sequencing
 
3 pm3 c_5%20-%20work%20authorization
3 pm3 c_5%20-%20work%20authorization3 pm3 c_5%20-%20work%20authorization
3 pm3 c_5%20-%20work%20authorization
 
3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget
3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget
3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget
 
3 pm3 c_3%20-%20the%20program%20budget
3 pm3 c_3%20-%20the%20program%20budget3 pm3 c_3%20-%20the%20program%20budget
3 pm3 c_3%20-%20the%20program%20budget
 
3 pm3 c_2-%20estimating%20costs
3 pm3 c_2-%20estimating%20costs3 pm3 c_2-%20estimating%20costs
3 pm3 c_2-%20estimating%20costs
 
3 pm3 c_1%20-%20developing%20the%20cost%20plan
3 pm3 c_1%20-%20developing%20the%20cost%20plan3 pm3 c_1%20-%20developing%20the%20cost%20plan
3 pm3 c_1%20-%20developing%20the%20cost%20plan
 
PHP games
PHP gamesPHP games
PHP games
 

Dernier

What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?Antenna Manufacturer Coco
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)Gabriella Davis
 
Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)wesley chun
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationRadu Cotescu
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking MenDelhi Call girls
 
Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsJoaquim Jorge
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processorsdebabhi2
 
Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024The Digital Insurer
 
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEarley Information Science
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...Martijn de Jong
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking MenDelhi Call girls
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountPuma Security, LLC
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘RTylerCroy
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...apidays
 
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdfUnderstanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdfUK Journal
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdfhans926745
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationSafe Software
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slidevu2urc
 
A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024Results
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsMaria Levchenko
 

Dernier (20)

What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)
 
Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organization
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men
 
Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and Myths
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processors
 
Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024
 
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path Mount
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
 
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdfUnderstanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slide
 
A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed texts
 

Activity Definition and Schedule Development

  • 1. Activity Definition Activity List Resource Plan Activity sequencing Activity Resource Estimating Activity Duration Estimating Duration Estimate Network Diagram Schedule Development Integrated Schedule
  • 2. Making a Schedule that “Works” Identify schedule “problems” Incorrect activity definition: work packages vs activities Incorrect sequencing: Unhealthy networks Over-allocated resources: resource levelling Making the schedule “useful” “Just in time” scheduling: The Rolling Wave Getting done on time Making status visible: Reports and Milestones The final product is the Time Management Plan called the “Integrated Schedule”
  • 3. Activities vs. Work Packages Activities describe the processes performed to complete all the “work” in the Work Package
  • 4. Activities vs Work Packages Example: Work Package = Qualification Test Report Activities: Collate Test Results Provide Data Package to Publications Prepare Report Check Report Project Manager Review Submit through Data Management
  • 5. The “reality check” Once the links are entered, they should form a complete network Everything ties in to “something” As much as possible, all the “loose ends” tie back together at the end
  • 6. Resource Levelling When the “ideal” schedule is viewed to check the “resource usage”, many resources maybe “overutilized” Example: If you have only one carpenter, you can’t have “Saw table legs” happen at the same time as “Assemble chair back” This is usually showed via a “histogram” that plots resource demand over time vs. the defined team size
  • 7. Options for dealing for overutilized resources Negotiate increased resources with functional manager Increase “productivity” through overtime, or procurement of enabling technology Consider options for work re-allocation: Outsourcing Work segmentation to allow partial performance by another under-utilized function (eg. Getting an Admin Assistant to perform “clerical” tasks of writing a technical report) “Resource levelling” = re-arranging existing program resources and task sequence to minimize impacts to the “critical path” – delay “non-critical” tasks with conflicting resources
  • 8. “Rolling Wave” Schedule Definition Some projects can be scheduled in detail at the beginning: Repeat of previous projects (eg. Building a house) Technology well understood, with little chance for environmental impact (eg. Database design) For many projects, however, only near term tasks are scheduled in detail: Technology not well developed or developed during project (eg.cold fusion reactor) Project involves significant “trade studies” or selection of alternative approaches (eg. Project to “develop corporate network” – Client/server vs. stand-alone? Mac vs. PC? Wireless vs broadband?) Project is lengthy and act of activity definition is a significant cost driver Latter using “Rolling Wave” scheduling
  • 9. “Rolling Wave” Definition Near term/known events scheduled and resource loaded in detail to “activity” level Longer term activities scheduled at increasingly reduced levels of detail Depending on risk reduction philosophy, these may either have no budget/ resources allocated, or may be “lumped” as “Planning Packages”
  • 10. Techniques for Shortening a Project Schedule Focus on the Critical Path Crashing: shortening the “calendar” duration of a task Apply more resources Apply overtime Introduce enabling technologies, eg. Automation “re-design” the work (eg. Current process requires 4 approvals – change process to require 2) Fast tracking: doing tasks - normally done in sequence - in parallel Eg. you eat breakfast, then drive to work eat breakfast while driving Eg. Test product, then ship it perform “minimum”/safety-critical tests and ship while completing remainder Remember the “Constraint Triangle”, any schedule reduction means: Cost, scope or quality trade-off Risk impact – especially when fast-tracking
  • 11. Shortening Project Schedules Original schedule Crashing Shortenedduration Fast tracking Overlapped tasks
  • 12. Milestones Milestones = zero duration tasks inserted into the schedule to provide visibility to key dates May be mandated by contract or management, at PM discretion or both Location: “Milestone” section at the top of the project Provides immediate summary of program goals and status Easy access for changing and “What-if” analyses “Embedded” in the related task path if needed to clarify inputs critical to that path Definition methods: “Hard dates”: Typed in as a “date” no “driving” dependencies Used to flow information “into” the schedule “Status Dates”: Hooked on to the end of a task network leading up to the state to be tracked Used to flow information “out of” the schedule
  • 13. Application of Milestones Flow “down” key commitments from the contract/program plan (eg. First shipment; inputs to customer activities) “Hard” dates in the “milestone” section Flow “up” estimated completion dates (eg. Design complete; Foundation complete) “Status” dates usually embedded in schedule Indicate “external” inputs to the program from other schedules or program entities (eg. Parts available from supplier; test equipment available in shared facility) “Hard” dates embedded or at the top Measurement of performance – discussed in integration section Estimated vs committed “Burndown” Earned Value recognition Contractual basis for invoicing progress payments Usually attached to the “key commitments”
  • 14. Schedule Reports the “schedule” is actually a database that integrates task cost, time and logic – often called: integrated schedule Integrated master schedule Cost/budget Can be used to generate various views and reports: WBS (sometimes) Network diagram (PERT chart) “Schedule” (GANTT chart) Resource/cost profiles