Mgt 610 Strategic Perspectives on Project Management
(c) 2013, Thomas Lechler. All rights reserved.For academic use only. 1
MGT610
Lecture 4
Elements of the Project Value Scorecard
Dr. Thomas Lechler Phone: (201) 216-8174
Babbio Center 636 FAX: (201) 216-5385
email: tlechler@stevens.edu
Mgt 610 Strategic Perspectives on Project Management
(c) 2013, Thomas Lechler. All rights reserved.For academic use only. 2
Lecture 4: Topics and Objectives
Implementing a Project Value Strategy by Applying
Project Value Scorecard
– Defining project objectives with the SMART principle
– Applying the Principles of the Balanced Scorecard
– Translating Project Value Strategy™ into a Project Value
Scorecard™
– Defining the four project value perspectives
– Evaluating the strategic points of leverage to achieve the
project’s comparative advantage
Mgt 610 Strategic Perspectives on Project Management
(c) 2013, Thomas Lechler. All rights reserved.For academic use only. 3
Definition of Project Strategy
The project perspective, direction, and guidelines on what to do
and how to do it, to achieve the highest competitive advantage
with the project results.
It is the creation and the management of the degrees of freedom in
a project to maximize the competitive advantage of a project.
A strategy stipulates what resources are required, why they are
required, when they are required, where they are required, and
how they will be used to accomplish ends. (Cleland, King, 1988,
p.168)
Mgt 610 Strategic Perspectives on Project Management
(c) 2013, Thomas Lechler. All rights reserved.For academic use only. 4
Defining Project Value Strategy
The Three Strategy-Making Tasks
1. Vision/Mission,
2. Objectives,
3. Strategic Choice
Mgt 610 Strategic Perspectives on Project Management
(c) 2013, Thomas Lechler. All rights reserved.For academic use only. 5
Project Value Strategy: Elements
Mgt 610 Strategic Perspectives on Project Management
(c) 2013, Thomas Lechler. All rights reserved.For academic use only. 6
Mission Statement: Functions
Functions of a Mission Statement (what is our project?)
– To establish a sense of direction within the project and to guide the
project management process by providing a basis for objectives and
strategies
– To influence decisions about resource allocation
– To help build and communicate
among team members a sense of
shared purpose
– To communicate an attractive and
compelling image to external
stakeholders
– To support the core values
of the organization
Key Questions
– What is our project?
– What do we want to become?
– Who are our stakeholders?
– What do our stakeholders
value?
Mgt 610 Strategic Perspectives on Project Management
(c) 2013, Thomas Lechler. All rights reserved.For academic use only. 7
Defining the Project Value Mission
A MISSION STATEMENT should
• Set project apart from others
• Arouse strong sense of organizational identity &
business purpose of the project
A well-crafted mission statement
• Must be narrow enough to specify real arena of interest
• Serves as boundary for what to do & not do
• Serves as beacon of where project manager intends to
take project
A MISSION STATEMENT includes
• Business Need
• Business Justification
Mgt 610 Strategic Perspectives on Project Management
(c) 2013, Thomas Lechler. All rights reserved.For academic use only. 8
Business Need
• Expressed as a goal or as a problem
derived from the corporate strategy.
– A goal is a measurable outcome that is desirable to
achieve.
• I want to travel to Denver.
• I want to become a Project Management Professional.
– A problem is stated as the gap between “the desired
state” and “the current state.”
• I will travel from Newark to Denver.
• I will obtain 4,500 hours of project-related work experience
and pass the certification exam to qualify for the Project
Management Professional credential.
Mgt 610 Strategic Perspectives on Project Management
(c) 2013, Thomas Lechler. All rights reserved.For academic use only. 9
Project Justification
• States the reason for undertaking the
project. Explains why business need
described in previous header should be solved.
– I want to visit my family in Denver.
– I plan to seek new employment opportunities.
– I plan to relocate to the Denver area.
– I plan to sightsee while in Denver.
• The justification should influence future
decisions about what to do in the project.
Mgt 610 Strategic Perspectives on Project Management
(c) 2013, Thomas Lechler. All rights reserved.For academic use only. 10
Mission Statement: Examples
• Mission Statements
– Otis Elevator: Our mission is to
provide any customer a means
of moving people and things
up, down, and sideways over
short distances with higher
reliability than any similar
enterprise in the world.
– American Red Cross: To
improve the quality of human
life; to enhance self-reliance
and concern for others; and to
help people avoid, prepare for,
and cope with emergencies.
Key Questions
– What is our project?
– What do we want to become?
– Who are our stakeholders?
– What do our stakeholders
value?
Mgt 610 Strategic Perspectives on Project Management
(c) 2013, Thomas Lechler. All rights reserved.For academic use only. 11
Project Vision
A Project Value Vision
• Identifies activities project intends
to pursue
• Sets fourth long-term project direction
• Provides big picture perspective of
Who WE are, what WE do, where WE are
headed
• Expressed by highlighting the most important
value perspective to be achieved to maximize
the project value
Mgt 610 Strategic Perspectives on Project Management
(c) 2013, Thomas Lechler. All rights reserved.For academic use only. 12
Vision Statement: Functions
• Functions of a Vision Statement (what do we want to become?)
– To articulate where the project hopes to be in the future. Can be
3-5 years out or beyond.
– Vision statements are intended to challenge and energize people
to achieve. They do not necessarily
have to be 100% realistic.
– Vision statements should also
be memorable so that people
keep it in mind when creating
and implementing strategy.
Strategic Key Questions
– What is our project?
– What do we want to become?
– Who are our stakeholders?
– What do our stakeholders
value?
Mgt 610 Strategic Perspectives on Project Management
(c) 2013, Thomas Lechler. All rights reserved.For academic use only. 13
Vision Statement: Examples
• Vision Statements
– McDonald’s Corporation: McDonald’s vision is to dominate the
global foodservice industry. Global dominance means setting
the performance standard for customer satisfaction while
increasing market share and profitability through our
Convenience, Value, and Execution Strategies.
– Microsoft Corp: One vision drives
everything we do: A computer on
every desk in every home using
great software as an empowering
tool.
Strategic Key Questions
– What is our project?
– What do we want to become?
– Who are our stakeholders?
– What do our stakeholders
value?
Mgt 610 Strategic Perspectives on Project Management
(c) 2013, Thomas Lechler. All rights reserved.For academic use only. 14
Outcome: Description
• Provides a brief narrative description of
the solution to the identified business need .
• If the product scope has already been defined, then an
appropriate reference to supporting details such as the
operational definition and/or contract should also be
indicated.
– Fly roundtrip to Denver and make arrangements to
stay for two weeks. Visit family. Refer to travel
itinerary for details.
– Fly roundtrip to Denver and make arrangements to
stay for two weeks. Meet with potential employers.
Refer to travel itinerary and meeting schedule for
details
Mgt 610 Strategic Perspectives on Project Management
(c) 2013, Thomas Lechler. All rights reserved.For academic use only. 15
Project Value Statement: Elements
Elements of Project Value Statement:
• Mission: Project justification and its business need
• Outcome: Description and project deliverables
• Vision: Value Focus
• Project Value Scorecard: Objectives to implement project value
strategy
• Shareholder Value
• Stakeholder Value
• Outcome Value
• Effort Value
• Constraints
• Assumptions
Shareholder
Value
Outcome
Value
Stakeholder
Value
Effort
Value
Mgt 610 Strategic Perspectives on Project Management
(c) 2013, Thomas Lechler. All rights reserved.For academic use only. 16
Outcome: Deliverables
• List the major, tangible components of the
solution (the major outputs) that must be
provided in order for project to be considered complete.
• Use bullet points to indicate each discrete deliverable.
– Roundtrip air transportation tickets
– Hotel reservation confirmation number
– Hotel room
– Rental car
– Three meals per day
• Listed deliverables will vary based upon product
description and the project’s justification.
Mgt 610 Strategic Perspectives on Project Management
(c) 2013, Thomas Lechler. All rights reserved.For academic use only. 17
The Elements of a Project Strategy
Project Mission
– Why is this project undertaken, why does it exist?
– What is the major contribution of the project to the company?
Project Vision
– What is the competitive advantage the project should achieve?
– Clear picture of the project overall goal in a measurable statement.
Project Strategy
– How to achieve the project mission and vision?
– It is the decision framework guiding the implementation.
Mgt 610 Strategic Perspectives on Project Management
(c) 2013, Thomas Lechler. All rights reserved.For academic use only. 18
Strategy Implementation Problems
What you measure is what you get!
• Measurement affects the behavior of employees and
• managers.
Traditional project performance measurements …
like Earned value status reports, critical path etc.
.. give misleading signals
No single measure can provide a clear performance target or
focus attention on the critical areas of the business.
Mgt 610 Strategic Perspectives on Project Management
(c) 2013, Thomas Lechler. All rights reserved.For academic use only. 19
Project Value Scorecard Functions
 Project Value Scorecard forces managers to focus on the
handful of measures that are most critical to maximize project
value.
 Project Value Scorecard forces managers to develop SMART
objectives.
 Project Value Scorecard guards against sub optimization.
 Project value scorecards measure the core competencies to
innovate, to efficiently deliver a specific value to the market,
which will lead to higher shareholder value.
Mgt 610 Strategic Perspectives on Project Management
(c) 2013, Thomas Lechler. All rights reserved.For academic use only. 20
Project Value Scorecard Functions
The Project Value Scorecard is a framework to define S.M.A.R.T
objectives:
– Specific – The objective tells exactly what, where, and how the
problem or need is to be addressed.
– Measurable – The objective tells exactly how much, how many,
and how well the problem/need will be resolved.
– Actionable - The objectives can be translated into a specific gap
that can be eliminated .
– Realistic – The objective can be achieved with the available
resources.
– Time – The objective includes a specific date for it's achievement.
Mgt 610 Strategic Perspectives on Project Management
(c) 2013, Thomas Lechler. All rights reserved.For academic use only. 21
Project Value Scorecard
Stakeholders Effort“To satisfy our
shareholders
and stakeholders,
what project
processes must
we excel at?”
Outcome
“To achieve our
vision, how
should we
develop the
outcome?”
Shareholder“To succeed, how
could we
maximize the
project value for
our
shareholders?”
Vision
and
Strategy
“To achieve our
project vision,
which needs of
the stakeholders
are to be
satisfied?”
Mgt 610 Strategic Perspectives on Project Management
(c) 2013, Thomas Lechler. All rights reserved.For academic use only. 22
Project Value Scorecard: Basic Structure
Stakeholder Value
“To achieve our project vision, how should we appear to our
stakeholders?”
Objectives Measures Targets Initiatives
During the
project
Project
Close Out
Long term
Mgt 610 Strategic Perspectives on Project Management
(c) 2013, Thomas Lechler. All rights reserved.For academic use only. 23
Project Scorecard Element: Objectives
Definition:
An objective is a statement, derived from a project goal, that
describes a short-term, specific, verifiable condition that must
exist to fulfill the affiliated goal. It is a need expressed as a want or
as a gap.
Examples:
1. Business Shareholder: Positive ROI (Return on
Investment)
2. Project Stakeholder: High satisfaction of end users and/or
customers
3. Project Outcome: High product/ process functionality
4. Project Effort: Fast-to-market
Mgt 610 Strategic Perspectives on Project Management
(c) 2013, Thomas Lechler. All rights reserved.For academic use only. 24
Project Value Scorecard: Measures
Definition:
A project related measure or metrics is a count or a measurement
that can be economically observed and captured. It is a basis for
comparison; a reference point against which other things can be
evaluated; or units to quantify project performance.
Examples:
1. Business Shareholder: ROI
2. Project Stakeholder: #Complaints
3. Project Outcome: #Defects
4. Project Effort: Schedule, budget
Mgt 610 Strategic Perspectives on Project Management
(c) 2013, Thomas Lechler. All rights reserved.For academic use only. 25
Project Value Scorecard: Targets
Definition:
A project target is a reference point and is expressed in units of
the measurement or metrics. It is a specific indicator value to be
accomplished.
Acceptable uncertainty expressed as USL – LSL.
(Upper Specification Limit – Lower Specification Limit)
Target = (USL – LSL) / 2
Examples:
1. Business Shareholder: ROI of 10%
2. Project Stakeholder: 10 complaints
3. Project Outcome: 0 Defects
4. Project Effort: 10% Schedule or budget overrun
Mgt 610 Strategic Perspectives on Project Management
(c) 2013, Thomas Lechler. All rights reserved.For academic use only. 26
Project Value Scorecard: Initiatives
Definition:
A project specific strategic initiative is not visible in the
project network and expresses an exceptional not
standard activity which has to take place in a specific
project to maximize project value.
Examples:
1. Business Shareholder: Top-management presentations
2. Project Stakeholder: Customer relations
3. Project Outcome: Creativity processes
4. Project Effort: Communication structure
Mgt 610 Strategic Perspectives on Project Management
(c) 2013, Thomas Lechler. All rights reserved.For academic use only. 27
Project Value Scorecard: Shareholder Perspective
A shareholder is a person (individual or corporation) who owns
shares in the corporation.
Goal: Create the “right” values!
How could we maximize the shareholder value?
– All project activities are related and lead to financial results.
– Return on capital employed improves
– Share price increases
Two Basic Strategies
1. Revenue Growth Strategy
– Revenue from new sources
– Customer profitability increases
2. Productivity Strategy
– Reduce operating cost per unit produced
– Improve asset utilization
Mgt 610 Strategic Perspectives on Project Management
(c) 2013, Thomas Lechler. All rights reserved.For academic use only. 28
Generic Shareholder Measures
• Return of Investment (ROI)
• Profitability Index
• Pay back period
• Net Present Value (NPV)
• Free cash flow
• Economic Value added (Profit-Opportunity
costs)
Mgt 610 Strategic Perspectives on Project Management
(c) 2013, Thomas Lechler. All rights reserved.For academic use only. 29
Project Value Scorecard: Stakeholder Perspective
Any party that has an interest ("stake") in a project.
Goal: Satisfy the “right” needs!
Four Categories of Stakeholder (Customer) Concerns:
Time – Quality – Performance and Service – Cost
1. Cost – Product Price, TCOO
2. Time – Lead Time from order to delivery (existing products)
Time to market of new products
3. Quality – Defect level of returned products
On time delivery
4. Performance and Service – % new products
% proprietary products, on time delivery
Mgt 610 Strategic Perspectives on Project Management
(c) 2013, Thomas Lechler. All rights reserved.For academic use only. 30
Generic Stakeholder Measures
Overall stakeholder satisfaction with deliverables in terms of:
• Reliability, Defects, Usability, Response time, Ease of use
• Availability, Flexibility, Intuitiveness, Security
• Easy to understand user documentation
• Application response time (calculated by the system)
• Number of approved business requirements satisfied by the
project
Overall client satisfaction with the project team in terms of:
• Responsiveness, Competence, Accessibility, Courteous,
Communication
• Credibility, Business knowledge, Reliability/follow through,
Professionalism, Training,
• Turnaround time required to respond to client queries and
problems, Average time required to resolve issues
Mgt 610 Strategic Perspectives on Project Management
(c) 2013, Thomas Lechler. All rights reserved.For academic use only. 31
Project Value Scorecard: Outcome Perspective
Any tangible or intangible asset a project generates: Process,
product, system, etc.
Goal: Doing the “right” things
Innovativeness and technical performance of outcome is critical.
Can we continue to improve and create value?
How are the TCO affected?
Does the installed or followed process create an acceptable
outcome quality?
Mgt 610 Strategic Perspectives on Project Management
(c) 2013, Thomas Lechler. All rights reserved.For academic use only. 32
Generic Outcome Measures
• Total support costs for x months after solution is complete
• Cost associated with building components for reuse
• Total cost per transaction
• Percentage of deliverables going through quality reviews
• Percentage of deliverable reviews resulting in acceptance the first time
• Number of defects discovered after initial acceptance
• Percentage of deliverables that comply with organization standards
• Number of hours or dollars saved from process improvements
• Number of hours of rework to previously completed deliverables
• Number of client change requests to revise scope
Mgt 610 Strategic Perspectives on Project Management
(c) 2013, Thomas Lechler. All rights reserved.For academic use only. 33
Project Value Scorecard: Effort Perspective
Goal: Doing the things “right”
What must the project do internally to meet its stakeholders’ and
shareholders’ expectation?
• Excellent performance for customers derived from processes,
decisions and actions occurring throughout an organization.
• Focus on those critical activities that enable them to satisfy
customer needs.
• Measures for those processes which have the greatest impact
on stakeholder and shareholder satisfaction.
• Identify and measure project core competencies
• Measures to develop and introduce the next generation of
existing products rapidly
Mgt 610 Strategic Perspectives on Project Management
(c) 2013, Thomas Lechler. All rights reserved.For academic use only. 34
Generic Effort Measures
– Total labor costs vs. non-labor (vs. budget)
– Total cost of employees vs. contract vs. consultant (vs. budget)
– Ideas for cost reductions implemented and cost savings realized
– Actual effort vs. budget (variance)
– Amount of project manager time vs. overall effort hours
– Actual duration vs. budget (variance)
– Effort hours per unit of work/function point
– Work units/function points produced per effort hour
– Effort hours reduced from standard project processes
– Effort hours saved through reuse of previous deliverables, models,
components
– Number of process improvement ideas implemented
– Number of best practices identified and applied on the project
Mgt 610 Strategic Perspectives on Project Management
(c) 2013, Thomas Lechler. All rights reserved.For academic use only. 35
Project Value Scorecard: Strategic Framework for Action
Clarifying and Translating
The Vision and Strategy
•Clarifying the vision
•Gaining Consensus
Communicating and
Linking
•Communicating and
Educating
•Setting Goals
•Linking rewards to
performance measures
Strategic Feedback and Learning
•Articulating the shared vision
•Supplying Strategic feedback
•Facilitating strategy review and
learning
Planning and Target Setting
•Setting Targets
•Aligning strategic initiatives
•Allocating resources
•Establishing milestones
Project Value
Scorecard
Mgt 610 Strategic Perspectives on Project Management
(c) 2013, Thomas Lechler. All rights reserved.For academic use only. 36
Planning a Project Strategy – Step 1
• Define your project and its objectives in support of:
• 1. What are the value propositions of the business?
Are they the same like the customer?
• 2. Who are the customers?
• What are the value propositions of the customer?
• 3. How should the products/ processes look like?
What technologies are needed? What are the specifications?
• 4. What resources are needed? What knowledge has to be
• developed? How will this contribute to future value?
Mgt 610 Strategic Perspectives on Project Management
(c) 2013, Thomas Lechler. All rights reserved.For academic use only. 37
Planning a Project Strategy – Step 2
Start with a status analysis of the project definition
What is the project mission, does it need clarification?
Define the project vision, what are the core values?
Assign the objectives to the four value perspectives
Which objectives are missing?
Which measures are missing?
What are the environmental issues?
Activate People
Mgt 610 Strategic Perspectives on Project Management
(c) 2013, Thomas Lechler. All rights reserved.For academic use only. 38
Project Value
Network
Perspective
Objective Measure Target Initiative
Effort On-time SV, SPI SV = 0d +/-
10ed
SPI = 1.0 +/-
0.05
Create bottom-
up schedule
using CPM
techniques
Outcome Authorized
work is fully
completed
Count of
deliverables
formally
accepted by
customer
Promised
deliverables =
formally
accepted
deliverables
Formal
acceptance
criteria
established in
scope
management
plan
Project Scorecard Basic Structure
Mgt 610 Strategic Perspectives on Project Management
(c) 2013, Thomas Lechler. All rights reserved.For academic use only. 39
Project Value
Network
Perspective
Objective Measure Target Initiative
Stakeholders Increase
satisfaction by
creating
quality
# Defects,
Response
time
Acceptable
quality
expressed as
USL – LSL.
Target = (USL –
LSL) / 2
Name of specific
quality activity
performed in the
project
Shareholders Increase
wealth by
receiving
stock
dividends
Free cash
flow
generated
from the
project
Payback
achieved in 12
months +/- 2
months
Establish PMIS
to track project
cashflows from
initiation until 6
months after
project
termination
Basic Scorecard Structure
Mgt 610 Strategic Perspectives on Project Management
(c) 2013, Thomas Lechler. All rights reserved.For academic use only. 40
Summary
• The Project Scorecard is a Planning Tool
• to implement a project strategy
• in form of a project metrics
• which covers all project value areas
Mgt 610 Strategic Perspectives on Project Management
(c) 2013, Thomas Lechler. All rights reserved.For academic use only. 41
Project Value Statement: Constraints
• Significant limitations to alternatives
that can be considered by the project
team in providing the solution to the
business need.
– Identifies the high-level limits (boundaries) that cannot be
crossed by the project team when providing the project’s
solution.
• Use bullet points to indicate each constraint.
– Relocation to Denver is not financially possible unless hiring
employer pays for relocation expenses.
– Interview appointments cannot be missed (due to late arrival at
the interview site).
Mgt 610 Strategic Perspectives on Project Management
(c) 2013, Thomas Lechler. All rights reserved.For academic use only. 42
Project Value Statement: Assumptions
• Identify significant factors that for
planning purposes have been assumed to
be real and/or true.
– These high-level assumptions will be useful in making future
decisions about work being performed by the project.
• If one of these assumptions turns out to be false, then
– the business need would no longer be relevant, and/or
– the product description would no longer provide a feasible
solution to the business need.
• Use bullet points to indicate each assumption.
– Employers in Denver will pay relocation expenses for the type of
job I am seeking.
– Interviewers will comply with EOE/AA guidelines and not
discriminate against a protected class of potential applicants.
Mgt 610 Strategic Perspectives on Project Management
(c) 2013, Thomas Lechler. All rights reserved.For academic use only. 43
Project Value Statement: Process
1. Define Project Mission
• Assumption is mission is
somewhat given
• Assumption of project value is
often not clearly defined
2. Define Project Vision
3. Describe Project Outcome
– Outcome
– Deliverables
4. Quantify Project Value
– Stakeholder Value
– Shareholder Value
– Outcome Value
– Effort Value
5. Document Key Assumptions
and Constraints
1
2
3
4
5
Minimum of 2
review loops

Contenu connexe

Tendances

Project management from simple to complex
Project management   from simple to complexProject management   from simple to complex
Project management from simple to complexBui Huong
 
Project Management Proposal
Project Management ProposalProject Management Proposal
Project Management ProposalJordan Cambron
 
Project Management Methodology Guidelines
Project Management Methodology GuidelinesProject Management Methodology Guidelines
Project Management Methodology GuidelinesSyed Umair Javed
 
Ten rules of project risk management
Ten rules of project risk managementTen rules of project risk management
Ten rules of project risk managementTony
 
K2 Presentation 2012
K2 Presentation 2012K2 Presentation 2012
K2 Presentation 2012K2CLAI
 
Project scope management
 Project scope management Project scope management
Project scope managementSidraSaleem17
 
Translating a Strategy into Action with Strategic Doing
Translating a Strategy into Action with Strategic Doing Translating a Strategy into Action with Strategic Doing
Translating a Strategy into Action with Strategic Doing Ed Morrison
 
TLS Continuum How to Guide: Project Manifesto - the Project Charter
TLS Continuum How to Guide: Project Manifesto - the Project CharterTLS Continuum How to Guide: Project Manifesto - the Project Charter
TLS Continuum How to Guide: Project Manifesto - the Project CharterDaniel Bloom
 
Sample project-charter
Sample project-charterSample project-charter
Sample project-charterteehaa
 
Non Profit Organization Project Proposal PowerPoint Presentation Slides
Non Profit Organization Project Proposal PowerPoint Presentation SlidesNon Profit Organization Project Proposal PowerPoint Presentation Slides
Non Profit Organization Project Proposal PowerPoint Presentation SlidesSlideTeam
 
Project Launch Meeting PowerPoint Presentation Slides
Project Launch Meeting PowerPoint Presentation SlidesProject Launch Meeting PowerPoint Presentation Slides
Project Launch Meeting PowerPoint Presentation SlidesSlideTeam
 
Hend Mostafa AbdulMegied- October 2015
Hend Mostafa AbdulMegied- October 2015Hend Mostafa AbdulMegied- October 2015
Hend Mostafa AbdulMegied- October 2015Hend Mostafa
 
Sample project-charter-template
Sample project-charter-templateSample project-charter-template
Sample project-charter-templatewebtech46
 
Project Server and SharePoint Server - better together
Project Server and SharePoint Server - better togetherProject Server and SharePoint Server - better together
Project Server and SharePoint Server - better togetherAdis Jugo
 

Tendances (17)

Project management from simple to complex
Project management   from simple to complexProject management   from simple to complex
Project management from simple to complex
 
Project Management Proposal
Project Management ProposalProject Management Proposal
Project Management Proposal
 
Project Management Methodology Guidelines
Project Management Methodology GuidelinesProject Management Methodology Guidelines
Project Management Methodology Guidelines
 
Ten rules of project risk management
Ten rules of project risk managementTen rules of project risk management
Ten rules of project risk management
 
Business and project changing the paradigm
Business and project changing the paradigmBusiness and project changing the paradigm
Business and project changing the paradigm
 
K2 Presentation 2012
K2 Presentation 2012K2 Presentation 2012
K2 Presentation 2012
 
Project scope management
 Project scope management Project scope management
Project scope management
 
Translating a Strategy into Action with Strategic Doing
Translating a Strategy into Action with Strategic Doing Translating a Strategy into Action with Strategic Doing
Translating a Strategy into Action with Strategic Doing
 
TLS Continuum How to Guide: Project Manifesto - the Project Charter
TLS Continuum How to Guide: Project Manifesto - the Project CharterTLS Continuum How to Guide: Project Manifesto - the Project Charter
TLS Continuum How to Guide: Project Manifesto - the Project Charter
 
Project proposal
Project proposalProject proposal
Project proposal
 
Sample project-charter
Sample project-charterSample project-charter
Sample project-charter
 
SharePoint Conference Recap - Project Server
SharePoint Conference Recap - Project Server SharePoint Conference Recap - Project Server
SharePoint Conference Recap - Project Server
 
Non Profit Organization Project Proposal PowerPoint Presentation Slides
Non Profit Organization Project Proposal PowerPoint Presentation SlidesNon Profit Organization Project Proposal PowerPoint Presentation Slides
Non Profit Organization Project Proposal PowerPoint Presentation Slides
 
Project Launch Meeting PowerPoint Presentation Slides
Project Launch Meeting PowerPoint Presentation SlidesProject Launch Meeting PowerPoint Presentation Slides
Project Launch Meeting PowerPoint Presentation Slides
 
Hend Mostafa AbdulMegied- October 2015
Hend Mostafa AbdulMegied- October 2015Hend Mostafa AbdulMegied- October 2015
Hend Mostafa AbdulMegied- October 2015
 
Sample project-charter-template
Sample project-charter-templateSample project-charter-template
Sample project-charter-template
 
Project Server and SharePoint Server - better together
Project Server and SharePoint Server - better togetherProject Server and SharePoint Server - better together
Project Server and SharePoint Server - better together
 

Similaire à Lecture04 slides

Project Charter Scoring GuideCRITERIA NON-PERFORMANCE BASI.docx
Project Charter Scoring GuideCRITERIA NON-PERFORMANCE BASI.docxProject Charter Scoring GuideCRITERIA NON-PERFORMANCE BASI.docx
Project Charter Scoring GuideCRITERIA NON-PERFORMANCE BASI.docxstilliegeorgiana
 
Lecture07 vo customer
Lecture07 vo customerLecture07 vo customer
Lecture07 vo customertoushi0616
 
Week07 slides 2013_s
Week07 slides 2013_sWeek07 slides 2013_s
Week07 slides 2013_shenry KKK
 
Schaffner edited2 STRATEGIC PLAN AND PRESENTATION FINAL
Schaffner edited2 STRATEGIC PLAN AND PRESENTATION FINALSchaffner edited2 STRATEGIC PLAN AND PRESENTATION FINAL
Schaffner edited2 STRATEGIC PLAN AND PRESENTATION FINALStacey Schaffner-Moy
 
Busting Project Manager and Business Analyst Silo Mentality
Busting Project Manager and Business Analyst Silo MentalityBusting Project Manager and Business Analyst Silo Mentality
Busting Project Manager and Business Analyst Silo MentalityBusiness Change Academy
 
M Sc Pm Lecture No 4 Risk
M Sc Pm Lecture No 4    RiskM Sc Pm Lecture No 4    Risk
M Sc Pm Lecture No 4 RiskHoang Vuong
 
Project portfolio management - webinar
Project portfolio management - webinarProject portfolio management - webinar
Project portfolio management - webinarAli Zeeshan
 
Webinar: Project portfolio management - slides
Webinar: Project portfolio management - slidesWebinar: Project portfolio management - slides
Webinar: Project portfolio management - slidesAli Zeeshan
 
operatingmodelandorganizationdesigntoolkit-overviewandapproach-211220031125.pdf
operatingmodelandorganizationdesigntoolkit-overviewandapproach-211220031125.pdfoperatingmodelandorganizationdesigntoolkit-overviewandapproach-211220031125.pdf
operatingmodelandorganizationdesigntoolkit-overviewandapproach-211220031125.pdfddr95827
 
Operating Model and Organization Design Toolkit
Operating Model and Organization Design Toolkit Operating Model and Organization Design Toolkit
Operating Model and Organization Design Toolkit Aurelien Domont, MBA
 
[Insert project title, e.g. Cosmo Inc.”] Project Scope State.docx
[Insert project title, e.g. Cosmo Inc.”] Project Scope State.docx[Insert project title, e.g. Cosmo Inc.”] Project Scope State.docx
[Insert project title, e.g. Cosmo Inc.”] Project Scope State.docxgerardkortney
 
Project Management Kickoff Meeting Template PowerPoint Presentation Slides
Project Management Kickoff Meeting Template PowerPoint Presentation SlidesProject Management Kickoff Meeting Template PowerPoint Presentation Slides
Project Management Kickoff Meeting Template PowerPoint Presentation SlidesSlideTeam
 
Watch out Agile and Scrum are about
Watch out Agile and Scrum are aboutWatch out Agile and Scrum are about
Watch out Agile and Scrum are aboutIIBA UK Chapter
 
Mi0040 – technology management
Mi0040 – technology managementMi0040 – technology management
Mi0040 – technology managementsmumbahelp
 
MGT 6302, Project Management Strategy and Tactics 1 .docx
MGT 6302, Project Management Strategy and Tactics 1  .docxMGT 6302, Project Management Strategy and Tactics 1  .docx
MGT 6302, Project Management Strategy and Tactics 1 .docxpauline234567
 
Week03 slides spring_2013
Week03 slides spring_2013Week03 slides spring_2013
Week03 slides spring_2013henry KKK
 

Similaire à Lecture04 slides (20)

Project Charter Scoring GuideCRITERIA NON-PERFORMANCE BASI.docx
Project Charter Scoring GuideCRITERIA NON-PERFORMANCE BASI.docxProject Charter Scoring GuideCRITERIA NON-PERFORMANCE BASI.docx
Project Charter Scoring GuideCRITERIA NON-PERFORMANCE BASI.docx
 
Lecture07 vo customer
Lecture07 vo customerLecture07 vo customer
Lecture07 vo customer
 
Week07 slides 2013_s
Week07 slides 2013_sWeek07 slides 2013_s
Week07 slides 2013_s
 
Project Life Cycle and Phases
Project Life Cycle and PhasesProject Life Cycle and Phases
Project Life Cycle and Phases
 
Schaffner edited2 STRATEGIC PLAN AND PRESENTATION FINAL
Schaffner edited2 STRATEGIC PLAN AND PRESENTATION FINALSchaffner edited2 STRATEGIC PLAN AND PRESENTATION FINAL
Schaffner edited2 STRATEGIC PLAN AND PRESENTATION FINAL
 
Mintzberg 5 Ps of strategy
Mintzberg 5 Ps of strategyMintzberg 5 Ps of strategy
Mintzberg 5 Ps of strategy
 
Busting Project Manager and Business Analyst Silo Mentality
Busting Project Manager and Business Analyst Silo MentalityBusting Project Manager and Business Analyst Silo Mentality
Busting Project Manager and Business Analyst Silo Mentality
 
M Sc Pm Lecture No 4 Risk
M Sc Pm Lecture No 4    RiskM Sc Pm Lecture No 4    Risk
M Sc Pm Lecture No 4 Risk
 
Project portfolio management - webinar
Project portfolio management - webinarProject portfolio management - webinar
Project portfolio management - webinar
 
Webinar: Project portfolio management - slides
Webinar: Project portfolio management - slidesWebinar: Project portfolio management - slides
Webinar: Project portfolio management - slides
 
operatingmodelandorganizationdesigntoolkit-overviewandapproach-211220031125.pdf
operatingmodelandorganizationdesigntoolkit-overviewandapproach-211220031125.pdfoperatingmodelandorganizationdesigntoolkit-overviewandapproach-211220031125.pdf
operatingmodelandorganizationdesigntoolkit-overviewandapproach-211220031125.pdf
 
Operating Model and Organization Design Toolkit
Operating Model and Organization Design Toolkit Operating Model and Organization Design Toolkit
Operating Model and Organization Design Toolkit
 
[Insert project title, e.g. Cosmo Inc.”] Project Scope State.docx
[Insert project title, e.g. Cosmo Inc.”] Project Scope State.docx[Insert project title, e.g. Cosmo Inc.”] Project Scope State.docx
[Insert project title, e.g. Cosmo Inc.”] Project Scope State.docx
 
Project Management Kickoff Meeting Template PowerPoint Presentation Slides
Project Management Kickoff Meeting Template PowerPoint Presentation SlidesProject Management Kickoff Meeting Template PowerPoint Presentation Slides
Project Management Kickoff Meeting Template PowerPoint Presentation Slides
 
Watch out Agile and Scrum are about
Watch out Agile and Scrum are aboutWatch out Agile and Scrum are about
Watch out Agile and Scrum are about
 
Mi0040 – technology management
Mi0040 – technology managementMi0040 – technology management
Mi0040 – technology management
 
Amaresh resume
Amaresh resumeAmaresh resume
Amaresh resume
 
MGT 6302, Project Management Strategy and Tactics 1 .docx
MGT 6302, Project Management Strategy and Tactics 1  .docxMGT 6302, Project Management Strategy and Tactics 1  .docx
MGT 6302, Project Management Strategy and Tactics 1 .docx
 
Strategic Planning: Eight Steps To Implementation
Strategic Planning: Eight Steps To ImplementationStrategic Planning: Eight Steps To Implementation
Strategic Planning: Eight Steps To Implementation
 
Week03 slides spring_2013
Week03 slides spring_2013Week03 slides spring_2013
Week03 slides spring_2013
 

Plus de henry KKK

Yiheng deng hw3
Yiheng deng hw3Yiheng deng hw3
Yiheng deng hw3henry KKK
 
Yiheng deng hw2
Yiheng deng hw2Yiheng deng hw2
Yiheng deng hw2henry KKK
 
Yiheng deng hw1
Yiheng deng hw1Yiheng deng hw1
Yiheng deng hw1henry KKK
 
Examples of smart_objective_attributes
Examples of smart_objective_attributesExamples of smart_objective_attributes
Examples of smart_objective_attributeshenry KKK
 
Week10 slides
Week10 slidesWeek10 slides
Week10 slideshenry KKK
 
Week09 cc single_project_slides_v1
Week09 cc single_project_slides_v1Week09 cc single_project_slides_v1
Week09 cc single_project_slides_v1henry KKK
 
Week10 slides
Week10 slidesWeek10 slides
Week10 slideshenry KKK
 
Week11 slides
Week11 slidesWeek11 slides
Week11 slideshenry KKK
 
Week12 slides
Week12 slidesWeek12 slides
Week12 slideshenry KKK
 
Week10 slides
Week10 slidesWeek10 slides
Week10 slideshenry KKK
 
Week09 cc single_project_slides_v1
Week09 cc single_project_slides_v1Week09 cc single_project_slides_v1
Week09 cc single_project_slides_v1henry KKK
 
Week08 slides
Week08 slidesWeek08 slides
Week08 slideshenry KKK
 
Week06 slides
Week06 slidesWeek06 slides
Week06 slideshenry KKK
 
Week05 spc single_case
Week05 spc single_caseWeek05 spc single_case
Week05 spc single_casehenry KKK
 
Week05 slides
Week05 slidesWeek05 slides
Week05 slideshenry KKK
 
Week05 reading
Week05 readingWeek05 reading
Week05 readinghenry KKK
 
Week05 exercise
Week05 exerciseWeek05 exercise
Week05 exercisehenry KKK
 
Week03 reading lechler_pm_mindset
Week03 reading lechler_pm_mindsetWeek03 reading lechler_pm_mindset
Week03 reading lechler_pm_mindsethenry KKK
 
Week02 slides spring_2013
Week02 slides spring_2013Week02 slides spring_2013
Week02 slides spring_2013henry KKK
 
Week02 reading lechler_plan_and_changing
Week02 reading lechler_plan_and_changingWeek02 reading lechler_plan_and_changing
Week02 reading lechler_plan_and_changinghenry KKK
 

Plus de henry KKK (20)

Yiheng deng hw3
Yiheng deng hw3Yiheng deng hw3
Yiheng deng hw3
 
Yiheng deng hw2
Yiheng deng hw2Yiheng deng hw2
Yiheng deng hw2
 
Yiheng deng hw1
Yiheng deng hw1Yiheng deng hw1
Yiheng deng hw1
 
Examples of smart_objective_attributes
Examples of smart_objective_attributesExamples of smart_objective_attributes
Examples of smart_objective_attributes
 
Week10 slides
Week10 slidesWeek10 slides
Week10 slides
 
Week09 cc single_project_slides_v1
Week09 cc single_project_slides_v1Week09 cc single_project_slides_v1
Week09 cc single_project_slides_v1
 
Week10 slides
Week10 slidesWeek10 slides
Week10 slides
 
Week11 slides
Week11 slidesWeek11 slides
Week11 slides
 
Week12 slides
Week12 slidesWeek12 slides
Week12 slides
 
Week10 slides
Week10 slidesWeek10 slides
Week10 slides
 
Week09 cc single_project_slides_v1
Week09 cc single_project_slides_v1Week09 cc single_project_slides_v1
Week09 cc single_project_slides_v1
 
Week08 slides
Week08 slidesWeek08 slides
Week08 slides
 
Week06 slides
Week06 slidesWeek06 slides
Week06 slides
 
Week05 spc single_case
Week05 spc single_caseWeek05 spc single_case
Week05 spc single_case
 
Week05 slides
Week05 slidesWeek05 slides
Week05 slides
 
Week05 reading
Week05 readingWeek05 reading
Week05 reading
 
Week05 exercise
Week05 exerciseWeek05 exercise
Week05 exercise
 
Week03 reading lechler_pm_mindset
Week03 reading lechler_pm_mindsetWeek03 reading lechler_pm_mindset
Week03 reading lechler_pm_mindset
 
Week02 slides spring_2013
Week02 slides spring_2013Week02 slides spring_2013
Week02 slides spring_2013
 
Week02 reading lechler_plan_and_changing
Week02 reading lechler_plan_and_changingWeek02 reading lechler_plan_and_changing
Week02 reading lechler_plan_and_changing
 

Dernier

NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdfKhaled Al Awadi
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCRashishs7044
 
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxContemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxMarkAnthonyAurellano
 
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...lizamodels9
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...lizamodels9
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...lizamodels9
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessSeta Wicaksana
 
Innovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfInnovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfrichard876048
 
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,noida100girls
 
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In.../:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...lizamodels9
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCRashishs7044
 
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...lizamodels9
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africaictsugar
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCRashishs7044
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Kirill Klimov
 
Future Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted VersionFuture Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted VersionMintel Group
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation SlidesKeppelCorporation
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607dollysharma2066
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCRashishs7044
 

Dernier (20)

Corporate Profile 47Billion Information Technology
Corporate Profile 47Billion Information TechnologyCorporate Profile 47Billion Information Technology
Corporate Profile 47Billion Information Technology
 
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
 
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxContemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
 
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful Business
 
Innovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfInnovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdf
 
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
 
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In.../:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
 
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africa
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024
 
Future Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted VersionFuture Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted Version
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR
 

Lecture04 slides

  • 1. Mgt 610 Strategic Perspectives on Project Management (c) 2013, Thomas Lechler. All rights reserved.For academic use only. 1 MGT610 Lecture 4 Elements of the Project Value Scorecard Dr. Thomas Lechler Phone: (201) 216-8174 Babbio Center 636 FAX: (201) 216-5385 email: tlechler@stevens.edu
  • 2. Mgt 610 Strategic Perspectives on Project Management (c) 2013, Thomas Lechler. All rights reserved.For academic use only. 2 Lecture 4: Topics and Objectives Implementing a Project Value Strategy by Applying Project Value Scorecard – Defining project objectives with the SMART principle – Applying the Principles of the Balanced Scorecard – Translating Project Value Strategy™ into a Project Value Scorecard™ – Defining the four project value perspectives – Evaluating the strategic points of leverage to achieve the project’s comparative advantage
  • 3. Mgt 610 Strategic Perspectives on Project Management (c) 2013, Thomas Lechler. All rights reserved.For academic use only. 3 Definition of Project Strategy The project perspective, direction, and guidelines on what to do and how to do it, to achieve the highest competitive advantage with the project results. It is the creation and the management of the degrees of freedom in a project to maximize the competitive advantage of a project. A strategy stipulates what resources are required, why they are required, when they are required, where they are required, and how they will be used to accomplish ends. (Cleland, King, 1988, p.168)
  • 4. Mgt 610 Strategic Perspectives on Project Management (c) 2013, Thomas Lechler. All rights reserved.For academic use only. 4 Defining Project Value Strategy The Three Strategy-Making Tasks 1. Vision/Mission, 2. Objectives, 3. Strategic Choice
  • 5. Mgt 610 Strategic Perspectives on Project Management (c) 2013, Thomas Lechler. All rights reserved.For academic use only. 5 Project Value Strategy: Elements
  • 6. Mgt 610 Strategic Perspectives on Project Management (c) 2013, Thomas Lechler. All rights reserved.For academic use only. 6 Mission Statement: Functions Functions of a Mission Statement (what is our project?) – To establish a sense of direction within the project and to guide the project management process by providing a basis for objectives and strategies – To influence decisions about resource allocation – To help build and communicate among team members a sense of shared purpose – To communicate an attractive and compelling image to external stakeholders – To support the core values of the organization Key Questions – What is our project? – What do we want to become? – Who are our stakeholders? – What do our stakeholders value?
  • 7. Mgt 610 Strategic Perspectives on Project Management (c) 2013, Thomas Lechler. All rights reserved.For academic use only. 7 Defining the Project Value Mission A MISSION STATEMENT should • Set project apart from others • Arouse strong sense of organizational identity & business purpose of the project A well-crafted mission statement • Must be narrow enough to specify real arena of interest • Serves as boundary for what to do & not do • Serves as beacon of where project manager intends to take project A MISSION STATEMENT includes • Business Need • Business Justification
  • 8. Mgt 610 Strategic Perspectives on Project Management (c) 2013, Thomas Lechler. All rights reserved.For academic use only. 8 Business Need • Expressed as a goal or as a problem derived from the corporate strategy. – A goal is a measurable outcome that is desirable to achieve. • I want to travel to Denver. • I want to become a Project Management Professional. – A problem is stated as the gap between “the desired state” and “the current state.” • I will travel from Newark to Denver. • I will obtain 4,500 hours of project-related work experience and pass the certification exam to qualify for the Project Management Professional credential.
  • 9. Mgt 610 Strategic Perspectives on Project Management (c) 2013, Thomas Lechler. All rights reserved.For academic use only. 9 Project Justification • States the reason for undertaking the project. Explains why business need described in previous header should be solved. – I want to visit my family in Denver. – I plan to seek new employment opportunities. – I plan to relocate to the Denver area. – I plan to sightsee while in Denver. • The justification should influence future decisions about what to do in the project.
  • 10. Mgt 610 Strategic Perspectives on Project Management (c) 2013, Thomas Lechler. All rights reserved.For academic use only. 10 Mission Statement: Examples • Mission Statements – Otis Elevator: Our mission is to provide any customer a means of moving people and things up, down, and sideways over short distances with higher reliability than any similar enterprise in the world. – American Red Cross: To improve the quality of human life; to enhance self-reliance and concern for others; and to help people avoid, prepare for, and cope with emergencies. Key Questions – What is our project? – What do we want to become? – Who are our stakeholders? – What do our stakeholders value?
  • 11. Mgt 610 Strategic Perspectives on Project Management (c) 2013, Thomas Lechler. All rights reserved.For academic use only. 11 Project Vision A Project Value Vision • Identifies activities project intends to pursue • Sets fourth long-term project direction • Provides big picture perspective of Who WE are, what WE do, where WE are headed • Expressed by highlighting the most important value perspective to be achieved to maximize the project value
  • 12. Mgt 610 Strategic Perspectives on Project Management (c) 2013, Thomas Lechler. All rights reserved.For academic use only. 12 Vision Statement: Functions • Functions of a Vision Statement (what do we want to become?) – To articulate where the project hopes to be in the future. Can be 3-5 years out or beyond. – Vision statements are intended to challenge and energize people to achieve. They do not necessarily have to be 100% realistic. – Vision statements should also be memorable so that people keep it in mind when creating and implementing strategy. Strategic Key Questions – What is our project? – What do we want to become? – Who are our stakeholders? – What do our stakeholders value?
  • 13. Mgt 610 Strategic Perspectives on Project Management (c) 2013, Thomas Lechler. All rights reserved.For academic use only. 13 Vision Statement: Examples • Vision Statements – McDonald’s Corporation: McDonald’s vision is to dominate the global foodservice industry. Global dominance means setting the performance standard for customer satisfaction while increasing market share and profitability through our Convenience, Value, and Execution Strategies. – Microsoft Corp: One vision drives everything we do: A computer on every desk in every home using great software as an empowering tool. Strategic Key Questions – What is our project? – What do we want to become? – Who are our stakeholders? – What do our stakeholders value?
  • 14. Mgt 610 Strategic Perspectives on Project Management (c) 2013, Thomas Lechler. All rights reserved.For academic use only. 14 Outcome: Description • Provides a brief narrative description of the solution to the identified business need . • If the product scope has already been defined, then an appropriate reference to supporting details such as the operational definition and/or contract should also be indicated. – Fly roundtrip to Denver and make arrangements to stay for two weeks. Visit family. Refer to travel itinerary for details. – Fly roundtrip to Denver and make arrangements to stay for two weeks. Meet with potential employers. Refer to travel itinerary and meeting schedule for details
  • 15. Mgt 610 Strategic Perspectives on Project Management (c) 2013, Thomas Lechler. All rights reserved.For academic use only. 15 Project Value Statement: Elements Elements of Project Value Statement: • Mission: Project justification and its business need • Outcome: Description and project deliverables • Vision: Value Focus • Project Value Scorecard: Objectives to implement project value strategy • Shareholder Value • Stakeholder Value • Outcome Value • Effort Value • Constraints • Assumptions Shareholder Value Outcome Value Stakeholder Value Effort Value
  • 16. Mgt 610 Strategic Perspectives on Project Management (c) 2013, Thomas Lechler. All rights reserved.For academic use only. 16 Outcome: Deliverables • List the major, tangible components of the solution (the major outputs) that must be provided in order for project to be considered complete. • Use bullet points to indicate each discrete deliverable. – Roundtrip air transportation tickets – Hotel reservation confirmation number – Hotel room – Rental car – Three meals per day • Listed deliverables will vary based upon product description and the project’s justification.
  • 17. Mgt 610 Strategic Perspectives on Project Management (c) 2013, Thomas Lechler. All rights reserved.For academic use only. 17 The Elements of a Project Strategy Project Mission – Why is this project undertaken, why does it exist? – What is the major contribution of the project to the company? Project Vision – What is the competitive advantage the project should achieve? – Clear picture of the project overall goal in a measurable statement. Project Strategy – How to achieve the project mission and vision? – It is the decision framework guiding the implementation.
  • 18. Mgt 610 Strategic Perspectives on Project Management (c) 2013, Thomas Lechler. All rights reserved.For academic use only. 18 Strategy Implementation Problems What you measure is what you get! • Measurement affects the behavior of employees and • managers. Traditional project performance measurements … like Earned value status reports, critical path etc. .. give misleading signals No single measure can provide a clear performance target or focus attention on the critical areas of the business.
  • 19. Mgt 610 Strategic Perspectives on Project Management (c) 2013, Thomas Lechler. All rights reserved.For academic use only. 19 Project Value Scorecard Functions  Project Value Scorecard forces managers to focus on the handful of measures that are most critical to maximize project value.  Project Value Scorecard forces managers to develop SMART objectives.  Project Value Scorecard guards against sub optimization.  Project value scorecards measure the core competencies to innovate, to efficiently deliver a specific value to the market, which will lead to higher shareholder value.
  • 20. Mgt 610 Strategic Perspectives on Project Management (c) 2013, Thomas Lechler. All rights reserved.For academic use only. 20 Project Value Scorecard Functions The Project Value Scorecard is a framework to define S.M.A.R.T objectives: – Specific – The objective tells exactly what, where, and how the problem or need is to be addressed. – Measurable – The objective tells exactly how much, how many, and how well the problem/need will be resolved. – Actionable - The objectives can be translated into a specific gap that can be eliminated . – Realistic – The objective can be achieved with the available resources. – Time – The objective includes a specific date for it's achievement.
  • 21. Mgt 610 Strategic Perspectives on Project Management (c) 2013, Thomas Lechler. All rights reserved.For academic use only. 21 Project Value Scorecard Stakeholders Effort“To satisfy our shareholders and stakeholders, what project processes must we excel at?” Outcome “To achieve our vision, how should we develop the outcome?” Shareholder“To succeed, how could we maximize the project value for our shareholders?” Vision and Strategy “To achieve our project vision, which needs of the stakeholders are to be satisfied?”
  • 22. Mgt 610 Strategic Perspectives on Project Management (c) 2013, Thomas Lechler. All rights reserved.For academic use only. 22 Project Value Scorecard: Basic Structure Stakeholder Value “To achieve our project vision, how should we appear to our stakeholders?” Objectives Measures Targets Initiatives During the project Project Close Out Long term
  • 23. Mgt 610 Strategic Perspectives on Project Management (c) 2013, Thomas Lechler. All rights reserved.For academic use only. 23 Project Scorecard Element: Objectives Definition: An objective is a statement, derived from a project goal, that describes a short-term, specific, verifiable condition that must exist to fulfill the affiliated goal. It is a need expressed as a want or as a gap. Examples: 1. Business Shareholder: Positive ROI (Return on Investment) 2. Project Stakeholder: High satisfaction of end users and/or customers 3. Project Outcome: High product/ process functionality 4. Project Effort: Fast-to-market
  • 24. Mgt 610 Strategic Perspectives on Project Management (c) 2013, Thomas Lechler. All rights reserved.For academic use only. 24 Project Value Scorecard: Measures Definition: A project related measure or metrics is a count or a measurement that can be economically observed and captured. It is a basis for comparison; a reference point against which other things can be evaluated; or units to quantify project performance. Examples: 1. Business Shareholder: ROI 2. Project Stakeholder: #Complaints 3. Project Outcome: #Defects 4. Project Effort: Schedule, budget
  • 25. Mgt 610 Strategic Perspectives on Project Management (c) 2013, Thomas Lechler. All rights reserved.For academic use only. 25 Project Value Scorecard: Targets Definition: A project target is a reference point and is expressed in units of the measurement or metrics. It is a specific indicator value to be accomplished. Acceptable uncertainty expressed as USL – LSL. (Upper Specification Limit – Lower Specification Limit) Target = (USL – LSL) / 2 Examples: 1. Business Shareholder: ROI of 10% 2. Project Stakeholder: 10 complaints 3. Project Outcome: 0 Defects 4. Project Effort: 10% Schedule or budget overrun
  • 26. Mgt 610 Strategic Perspectives on Project Management (c) 2013, Thomas Lechler. All rights reserved.For academic use only. 26 Project Value Scorecard: Initiatives Definition: A project specific strategic initiative is not visible in the project network and expresses an exceptional not standard activity which has to take place in a specific project to maximize project value. Examples: 1. Business Shareholder: Top-management presentations 2. Project Stakeholder: Customer relations 3. Project Outcome: Creativity processes 4. Project Effort: Communication structure
  • 27. Mgt 610 Strategic Perspectives on Project Management (c) 2013, Thomas Lechler. All rights reserved.For academic use only. 27 Project Value Scorecard: Shareholder Perspective A shareholder is a person (individual or corporation) who owns shares in the corporation. Goal: Create the “right” values! How could we maximize the shareholder value? – All project activities are related and lead to financial results. – Return on capital employed improves – Share price increases Two Basic Strategies 1. Revenue Growth Strategy – Revenue from new sources – Customer profitability increases 2. Productivity Strategy – Reduce operating cost per unit produced – Improve asset utilization
  • 28. Mgt 610 Strategic Perspectives on Project Management (c) 2013, Thomas Lechler. All rights reserved.For academic use only. 28 Generic Shareholder Measures • Return of Investment (ROI) • Profitability Index • Pay back period • Net Present Value (NPV) • Free cash flow • Economic Value added (Profit-Opportunity costs)
  • 29. Mgt 610 Strategic Perspectives on Project Management (c) 2013, Thomas Lechler. All rights reserved.For academic use only. 29 Project Value Scorecard: Stakeholder Perspective Any party that has an interest ("stake") in a project. Goal: Satisfy the “right” needs! Four Categories of Stakeholder (Customer) Concerns: Time – Quality – Performance and Service – Cost 1. Cost – Product Price, TCOO 2. Time – Lead Time from order to delivery (existing products) Time to market of new products 3. Quality – Defect level of returned products On time delivery 4. Performance and Service – % new products % proprietary products, on time delivery
  • 30. Mgt 610 Strategic Perspectives on Project Management (c) 2013, Thomas Lechler. All rights reserved.For academic use only. 30 Generic Stakeholder Measures Overall stakeholder satisfaction with deliverables in terms of: • Reliability, Defects, Usability, Response time, Ease of use • Availability, Flexibility, Intuitiveness, Security • Easy to understand user documentation • Application response time (calculated by the system) • Number of approved business requirements satisfied by the project Overall client satisfaction with the project team in terms of: • Responsiveness, Competence, Accessibility, Courteous, Communication • Credibility, Business knowledge, Reliability/follow through, Professionalism, Training, • Turnaround time required to respond to client queries and problems, Average time required to resolve issues
  • 31. Mgt 610 Strategic Perspectives on Project Management (c) 2013, Thomas Lechler. All rights reserved.For academic use only. 31 Project Value Scorecard: Outcome Perspective Any tangible or intangible asset a project generates: Process, product, system, etc. Goal: Doing the “right” things Innovativeness and technical performance of outcome is critical. Can we continue to improve and create value? How are the TCO affected? Does the installed or followed process create an acceptable outcome quality?
  • 32. Mgt 610 Strategic Perspectives on Project Management (c) 2013, Thomas Lechler. All rights reserved.For academic use only. 32 Generic Outcome Measures • Total support costs for x months after solution is complete • Cost associated with building components for reuse • Total cost per transaction • Percentage of deliverables going through quality reviews • Percentage of deliverable reviews resulting in acceptance the first time • Number of defects discovered after initial acceptance • Percentage of deliverables that comply with organization standards • Number of hours or dollars saved from process improvements • Number of hours of rework to previously completed deliverables • Number of client change requests to revise scope
  • 33. Mgt 610 Strategic Perspectives on Project Management (c) 2013, Thomas Lechler. All rights reserved.For academic use only. 33 Project Value Scorecard: Effort Perspective Goal: Doing the things “right” What must the project do internally to meet its stakeholders’ and shareholders’ expectation? • Excellent performance for customers derived from processes, decisions and actions occurring throughout an organization. • Focus on those critical activities that enable them to satisfy customer needs. • Measures for those processes which have the greatest impact on stakeholder and shareholder satisfaction. • Identify and measure project core competencies • Measures to develop and introduce the next generation of existing products rapidly
  • 34. Mgt 610 Strategic Perspectives on Project Management (c) 2013, Thomas Lechler. All rights reserved.For academic use only. 34 Generic Effort Measures – Total labor costs vs. non-labor (vs. budget) – Total cost of employees vs. contract vs. consultant (vs. budget) – Ideas for cost reductions implemented and cost savings realized – Actual effort vs. budget (variance) – Amount of project manager time vs. overall effort hours – Actual duration vs. budget (variance) – Effort hours per unit of work/function point – Work units/function points produced per effort hour – Effort hours reduced from standard project processes – Effort hours saved through reuse of previous deliverables, models, components – Number of process improvement ideas implemented – Number of best practices identified and applied on the project
  • 35. Mgt 610 Strategic Perspectives on Project Management (c) 2013, Thomas Lechler. All rights reserved.For academic use only. 35 Project Value Scorecard: Strategic Framework for Action Clarifying and Translating The Vision and Strategy •Clarifying the vision •Gaining Consensus Communicating and Linking •Communicating and Educating •Setting Goals •Linking rewards to performance measures Strategic Feedback and Learning •Articulating the shared vision •Supplying Strategic feedback •Facilitating strategy review and learning Planning and Target Setting •Setting Targets •Aligning strategic initiatives •Allocating resources •Establishing milestones Project Value Scorecard
  • 36. Mgt 610 Strategic Perspectives on Project Management (c) 2013, Thomas Lechler. All rights reserved.For academic use only. 36 Planning a Project Strategy – Step 1 • Define your project and its objectives in support of: • 1. What are the value propositions of the business? Are they the same like the customer? • 2. Who are the customers? • What are the value propositions of the customer? • 3. How should the products/ processes look like? What technologies are needed? What are the specifications? • 4. What resources are needed? What knowledge has to be • developed? How will this contribute to future value?
  • 37. Mgt 610 Strategic Perspectives on Project Management (c) 2013, Thomas Lechler. All rights reserved.For academic use only. 37 Planning a Project Strategy – Step 2 Start with a status analysis of the project definition What is the project mission, does it need clarification? Define the project vision, what are the core values? Assign the objectives to the four value perspectives Which objectives are missing? Which measures are missing? What are the environmental issues? Activate People
  • 38. Mgt 610 Strategic Perspectives on Project Management (c) 2013, Thomas Lechler. All rights reserved.For academic use only. 38 Project Value Network Perspective Objective Measure Target Initiative Effort On-time SV, SPI SV = 0d +/- 10ed SPI = 1.0 +/- 0.05 Create bottom- up schedule using CPM techniques Outcome Authorized work is fully completed Count of deliverables formally accepted by customer Promised deliverables = formally accepted deliverables Formal acceptance criteria established in scope management plan Project Scorecard Basic Structure
  • 39. Mgt 610 Strategic Perspectives on Project Management (c) 2013, Thomas Lechler. All rights reserved.For academic use only. 39 Project Value Network Perspective Objective Measure Target Initiative Stakeholders Increase satisfaction by creating quality # Defects, Response time Acceptable quality expressed as USL – LSL. Target = (USL – LSL) / 2 Name of specific quality activity performed in the project Shareholders Increase wealth by receiving stock dividends Free cash flow generated from the project Payback achieved in 12 months +/- 2 months Establish PMIS to track project cashflows from initiation until 6 months after project termination Basic Scorecard Structure
  • 40. Mgt 610 Strategic Perspectives on Project Management (c) 2013, Thomas Lechler. All rights reserved.For academic use only. 40 Summary • The Project Scorecard is a Planning Tool • to implement a project strategy • in form of a project metrics • which covers all project value areas
  • 41. Mgt 610 Strategic Perspectives on Project Management (c) 2013, Thomas Lechler. All rights reserved.For academic use only. 41 Project Value Statement: Constraints • Significant limitations to alternatives that can be considered by the project team in providing the solution to the business need. – Identifies the high-level limits (boundaries) that cannot be crossed by the project team when providing the project’s solution. • Use bullet points to indicate each constraint. – Relocation to Denver is not financially possible unless hiring employer pays for relocation expenses. – Interview appointments cannot be missed (due to late arrival at the interview site).
  • 42. Mgt 610 Strategic Perspectives on Project Management (c) 2013, Thomas Lechler. All rights reserved.For academic use only. 42 Project Value Statement: Assumptions • Identify significant factors that for planning purposes have been assumed to be real and/or true. – These high-level assumptions will be useful in making future decisions about work being performed by the project. • If one of these assumptions turns out to be false, then – the business need would no longer be relevant, and/or – the product description would no longer provide a feasible solution to the business need. • Use bullet points to indicate each assumption. – Employers in Denver will pay relocation expenses for the type of job I am seeking. – Interviewers will comply with EOE/AA guidelines and not discriminate against a protected class of potential applicants.
  • 43. Mgt 610 Strategic Perspectives on Project Management (c) 2013, Thomas Lechler. All rights reserved.For academic use only. 43 Project Value Statement: Process 1. Define Project Mission • Assumption is mission is somewhat given • Assumption of project value is often not clearly defined 2. Define Project Vision 3. Describe Project Outcome – Outcome – Deliverables 4. Quantify Project Value – Stakeholder Value – Shareholder Value – Outcome Value – Effort Value 5. Document Key Assumptions and Constraints 1 2 3 4 5 Minimum of 2 review loops