SlideShare une entreprise Scribd logo
1  sur  5
Télécharger pour lire hors ligne
he need to focus the fab productivity discussion on waste reduction has
          been widely discussed and recognized, (1-3) yet, the industry still lacks ba-
          sic tools to comprehend the complete productivity picture. For example,
          cycle time is relatively intractable and its value is difficult to quantify
because it consists of missed opportunity rather than incurred costs. In this study
we propose a basic toolkit for definition and valuation of cycle time, an important
first step towards focusing attention and action on improving fab agility.
                                                       Interest in reducing cycle time is grow-
                                                   ing across business models and market seg-
                                                   ments, from manufacturers of microproces-
                                                   sors (Intel and AMD), memory (Samsung,
                                                   Inotera, Spansion), foundry (TSMC), and
                                                   even development fabs.(4-17) However, since
                                                   there is no unified definition of cycle time,
                                                   we cannot calculate its value.
                                                       To remedy this, we are working with
                                                   ISMI and SEMI to formalize a simple set
                                                   of definitions, building on Little’s Law and
                                                   existing SEMI Standards (primarily E124-
                                                   1103). Little’s Law states that average
                                                   work-in-process (WIP) equals the product
                                                   of arrival rate and average cycle time, as
                                                   follows:

                                                   (Eq.1)


                                                      Simple manipulation and reflecting the
                                                   likelihood of loss during fab processing
                                                   (substituting output rate, like finished units
                                                   out, for input rate, like arrival rate) yields
tom-up” approach, typically focusing on modeling the
                                                                                     impact of longer time to market and reduced differen-
                                                                                     tiation, (18-21) slower yield learning, or simply inventory
                                                                                     carrying costs. (14, 22-24)
                                                                                         Our approach was instead to go to “first principles”
                                                                                     based on the assumption that a fab’s objective is to maxi-
                                                                                     mize profitability. Profitability is generally increased with
                                                                                     utilization, so with a simple representation like Eq. 4, we
                                                                                     can see a relationship as expressed in Figure 2 for any given
                                                                                     time period.

                                                                                     (Eq.4)




                                                                                    where GM is gross margin, u is utilization of available ca-
                                                                                    pacity, ASP is average selling price, UnitVarCost is variable
the definition of cycle time as the ratio of average WIP to                          cost per unit.
output rate (finished units out):                                                       As a result, fabs may be tempted to push utilization to
                                                                                    very high levels; however, extremely high utilization is rare
(Eq.2)                                                                              due to the conflict between agility and utilization. This rela-
                                                                                    tionship is known as the “fab operating curve,” illustrated in
    Note that this definition is based on a top-down view,                           Figure 3. The fab operating curve has been extensively ana-
as opposed to classical definitions based on the sum of cycle                        lyzed in queuing theory(4) and one model is shown in Eq 5.
times of individual process steps. Also, this definition is not
limited to fab-wide operations, but can be applied to any                           (Eq.5)                                            (G/G/1): one process-
productive part of it. Cycle time is typically calculated per                       ing path
wafer, and possibly per die.
    To enable graphic representation, we have adopted a                                 In this equation, Ce is coefficient of process time variation,
metric called “mean time between good units out,” or                                Ca is coefficient of arrival time variation, u stands for utiliza-
MTBG. MTBG is simply the inverse of the through-                                    tion of available capacity, and Te is average processing time.
put rate of the fab (or some element of it). In that case,
cycle time is the product of WIP and MTBG:
                                                                                            $10,000
(Eq.3)

   This relationship is shown in Figure 1, for example, where                                     $8,000
                                                                         Cost, Profit per Wafer




two states are compared: A, or current state, vs. B, or target (ideal)                                                      Gross Margin
case. The rectangle in orange, with corners A and B, can be                                       $6,000
viewed as the cycle time waste, or “waste” generated in the fab.
   The relative size of these rectangles can indicate the                                         $4,000                   Back-End Costs
overall level of waste. For example, the ratio of rectangle                                                              Fab Variable Costs
B (area defined from origin to B) to rectangle A (area de-                                         $2,000
fined by origin to A) is equivalent to the primary indica-                                                              Average Fab Fixed Costs
tor advocated by Hyder, namely, load-adjusted cycle time                                             $0
                                                                                                           60%   70%            80%              90%     100%
equivalent or LACTE. (5)                                                                                                     Utilization



Analysts and practitioners have traditionally quantified
the economic impact of cycle time waste using a “bot-
The mathematical approach uses the concept of “elasticity” ( ),
                                                                         or the ratio of the percent change in one variable to the percent
                                                                         change in another variable.

                                                                         Step 1: Determine the sensitivity of fab owner’s profitability to
                                                                         fab utilization, based on Eq.4:

                                                                         (Eq.6)

                                                                         In this equation, GM is gross margin, GM% is gross margin %
                                                                         of revenue; u is utilization of available capacity; FC% repre-
                                                                         sents fixed costs as a % of total manufacturing costs.

                                                                         Step 2: Determine the sensitivity of cycle time (in queue) to fab
                                                                         utilization using Eq.5:

                                                                         (Eq.7)




                                                                         where CTq is cycle time in queue, Ce is coefficient of process
As is evident from the fab operating curve shown in Fig-                 time variation, Ca is coefficient of arrival time variation, and Te
ure 3, the cycle time penalty tends to stand in the way of               is average processing time.
increased fab utilization. As utilization increases, cycle
time increases and reaches unacceptable levels, forcing                  Step 3: Divide the sensitivities to determine overall response of
fabs to limit fab loading. This relationship between in-                 profitability to cycle time (in queue):
creasing cycle time and increasing fab utilization provides
an important hint about how to quantify the cost of cycle                (Eq.8)
time waste. Instead of divining the way fabs should run
their business, it is more straightforward to observe how                Step 4: Adjust the calculation to represent the response of profits
they do it, then impute from their actions and priorities                to changes in total cycle time and to convert this profit impact
the relative value of cycle time.                                        to “equivalent costs” (shown as a % of wafer processing costs):
    Fabs use extensive analytical and planning tools to
strike an optimal trade-off. The rationale is to extend                                  100%
cycle time to increase utilization up to the point where                                                  LOW=1X
                                                              (queue % of total cycle time)




                                                                                                          LOW=2X                                    Lower Value of
                                                                                              80%                                                     Cycle Time
additional increases would make cycle time unacceptably                                                   LOW=3X
                                                                   Cycle Time Waste




long (resulting in lost business, worse operational per-                                                  LOW=4X
                                                                                              60%
formance). Alternatively, they cut cycle time up to the
point where further reductions would erode utilization                                        40%
and profitability more than the contribution of shorter                                                       Higher Value of
cycle time.                                                                                   20%              Cycle Time
    Based on this logic, we can identify a “sweet spot”
                                                                                              0%
where the value of incremental profit (from higher utiliza-                                          60%            70%               80%            90%              100%
tion) roughly equals the incremental economic cost (from                                                                       Target Utilization
longer cycle time). This allows us to find the “shadow
price” of cycle time by observing the fab’s actual perfor-
mance. From this we can attribute what we call the Lost
Opportunity due to waste, or LOW function, to each spe-
cific user situation.
$25,000,000




                                 LOW (Annual $ per one day reduction)
                                                                                                                       Scenario 1
                                                                                                                       Scenario 2
                                                                        $20,000,000
                                                                                                                                                                        Scenario 1    Scenario 2
                                                                                                                                           Wafer per day                  3,000         1,000
                                                                        $15,000,000                                                        Cycle time, days                 40            60
                                                                                                                                           Time in queue                   80%           90%
                                                                                                                                           Target utilization              90%           90%
                                                                        $10,000,000
                                                                                                                                           At targeted utilization:
                                                                                                                                           Cost per wafer                $2,000        $4,500
                                                                         $5,000,000                                                        GM%                             35%           55%
                                                                                                                                           Fixed Costs %                   70%           60%
                                                                                                                                           Front End %                     70%           50%
                                                                                 $0
                                                                                      80%    85%            90%      95%        100%
                                                                                                Utilization (Actual)

                                                                                                                            lization (u) is and the longer the relative queue time (r) is. This
      (Eq.9)                                                                                                                mathematical behavior and its graphical representation (Figure
                                                                                                                            4) reflects the real-world situation. Fab managers who choose to
                                                                                                                            run their factories at high utilization/high queue time regimes
                                                                                                                            (upper right-hand corner of Figure 4) are responding to the ex-
                                                                                                                            pectations of the overall enterprise by putting throughput ahead
      where Rev is Revenues,                       and FE% represents                                                       of time to market. Their actions reveal the relatively low value
      the share of front-end (fab processing) costs of total chip costs.                                                    that they assign to cycle time. The reverse would be true in
                                                                                                                            situations of lower utilization and queue time (lower left-hand
                                                                                                                            corner of Figure 4).
      Equation 9 provides a simple model to evaluate the LOW (or                                                                The second argument in Eq 9 reflects the basic financial
      the economic value of cycle time) based on information about a                                                        model of the particular fab. Figure 5 illustrates the calculation of
      fab’s current operational characteristics and business model.                                                         the LOW function for two fabs with different business models.
         It is instructive to consider the equation in some detail. The                                                     Even for high-utilization fabs like these, an extra day of cycle
      first argument           , reflects the operational characteristics of                                                  time costs many millions in missed economic opportunity (this
      the fab. The behavior of this term is consistent with our in-                                                         is consistent with other observations).(5, 18)
      tuition. Mathematically, it drives the opportunity cost of cycle                                                          More importantly, this model allows us to contrast the cost
      time (LOW) to be lower, the higher the currently targeted uti-                                                        of lost opportunity due to waste with the direct fabrication costs
                                                                                                                            (CoO). There is always some element of waste, and this adds
                 $10,000                                                                                                    to the total wafer cost. As utilization rates are pushed higher,
                                                                                                                            this waste component grows, and can grow to the point where
                 $8,000                                                                                                     it more than doubles the total economic cost per wafer. Figure 6
                                                                                                                            shows this comparison for a given scenario (fab-wide situation).
Cost per Wafer




                                                                                                                            LOW clearly becomes comparable to and even overwhelms
                  $6,000
                                                                                                                            CoO in typical situations.
                                                                                                                                Interestingly, total economic costs can actually be minimized
                 $4,000                                                                                       LOW           at lower utilization (77%), saving 4% vs. target utilization.


                 $2,000                                                 CoO                                                 We have shown that cycle time can be clearly defined and that the lost
                                                                                                                            opportunity incurred by fab owners due to cycle time waste may be
                     $0                                                                                                     on the same order of magnitude as the direct fabrication costs.
                           60%                                           70%           80%            90%           100%
                                                                                                                               Can this lost opportunity be addressed? A detailed approach is
                                                                               Utilization (Actual)
                                                                                                                            beyond the scope of this paper, but we have discussed elsewhere (1, 3)
                                                                                                                            that the key levers for cycle time waste reduction consist of:
                                                                                                                               a. Predictable, low-variability, “smart” tools
                                                                                                                               b. High-capacity AMHS and factory systems
c. Universal, high-productivity, single-wafer proces tools
    This report lays out a straightforward toolkit for the definition
and measurement of cycle time, waste, and its economic impact.
It is our hope that with the greater clarity and visibility into cycle
time waste and its economic implications that these tools provide,
agility will receive the recognition it deserves within the fab pro-
ductivity agenda.


The authors wish to thank Applied’s Dr. Dajiang Xu for his
critical contributions in preparing this report.




                                                                         Authors: Iddo Hadar and Eric Englhardt.
                                                                         For additional information, please contact
                                                                         Iddo_Hadar@amat.com

Contenu connexe

Similaire à Semiconductor Fab Productivity--Cycle Time

Cloud Economics
Cloud EconomicsCloud Economics
Cloud EconomicsRackspace
 
Generalized Capital Investment Planning w/ Sequence-Dependent Setups Industri...
Generalized Capital Investment Planning w/ Sequence-Dependent Setups Industri...Generalized Capital Investment Planning w/ Sequence-Dependent Setups Industri...
Generalized Capital Investment Planning w/ Sequence-Dependent Setups Industri...Alkis Vazacopoulos
 
Balancing WIP and Throughput with Machine Utilization in a Manufacturing Faci...
Balancing WIP and Throughput with Machine Utilization in a Manufacturing Faci...Balancing WIP and Throughput with Machine Utilization in a Manufacturing Faci...
Balancing WIP and Throughput with Machine Utilization in a Manufacturing Faci...IDES Editor
 
4 production and cost
4  production and cost4  production and cost
4 production and costdannygriff1
 
Profit based unit commitment for GENCOs using Parallel PSO in a distributed c...
Profit based unit commitment for GENCOs using Parallel PSO in a distributed c...Profit based unit commitment for GENCOs using Parallel PSO in a distributed c...
Profit based unit commitment for GENCOs using Parallel PSO in a distributed c...IDES Editor
 
IJERD(www.ijerd.com)International Journal of Engineering Research and Develop...
IJERD(www.ijerd.com)International Journal of Engineering Research and Develop...IJERD(www.ijerd.com)International Journal of Engineering Research and Develop...
IJERD(www.ijerd.com)International Journal of Engineering Research and Develop...IJERD Editor
 
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...IJERD Editor
 
GENERATIVE SCHEDULING OF EFFECTIVE MULTITASKING WORKLOADS FOR BIG-DATA ANALYT...
GENERATIVE SCHEDULING OF EFFECTIVE MULTITASKING WORKLOADS FOR BIG-DATA ANALYT...GENERATIVE SCHEDULING OF EFFECTIVE MULTITASKING WORKLOADS FOR BIG-DATA ANALYT...
GENERATIVE SCHEDULING OF EFFECTIVE MULTITASKING WORKLOADS FOR BIG-DATA ANALYT...IAEME Publication
 
Planning/Scheduling with CP Optimizer
Planning/Scheduling with CP OptimizerPlanning/Scheduling with CP Optimizer
Planning/Scheduling with CP OptimizerPhilippe Laborie
 
Weighted Flowtime on Capacitated Machines
Weighted Flowtime on Capacitated MachinesWeighted Flowtime on Capacitated Machines
Weighted Flowtime on Capacitated MachinesSunny Kr
 
The GREDOR project. Redesigning the decision chain for managing distribution ...
The GREDOR project. Redesigning the decision chain for managing distribution ...The GREDOR project. Redesigning the decision chain for managing distribution ...
The GREDOR project. Redesigning the decision chain for managing distribution ...Université de Liège (ULg)
 
IRJET- Advance Approach for Load Balancing in Cloud Computing using (HMSO) Hy...
IRJET- Advance Approach for Load Balancing in Cloud Computing using (HMSO) Hy...IRJET- Advance Approach for Load Balancing in Cloud Computing using (HMSO) Hy...
IRJET- Advance Approach for Load Balancing in Cloud Computing using (HMSO) Hy...IRJET Journal
 
Enhancements of Extended Locational Marginal Pricing – Advancing Practical Im...
Enhancements of Extended Locational Marginal Pricing – Advancing Practical Im...Enhancements of Extended Locational Marginal Pricing – Advancing Practical Im...
Enhancements of Extended Locational Marginal Pricing – Advancing Practical Im...Power System Operation
 

Similaire à Semiconductor Fab Productivity--Cycle Time (20)

Cloud Economics
Cloud EconomicsCloud Economics
Cloud Economics
 
Ch7 time cost
Ch7 time costCh7 time cost
Ch7 time cost
 
Generalized Capital Investment Planning w/ Sequence-Dependent Setups Industri...
Generalized Capital Investment Planning w/ Sequence-Dependent Setups Industri...Generalized Capital Investment Planning w/ Sequence-Dependent Setups Industri...
Generalized Capital Investment Planning w/ Sequence-Dependent Setups Industri...
 
Balancing WIP and Throughput with Machine Utilization in a Manufacturing Faci...
Balancing WIP and Throughput with Machine Utilization in a Manufacturing Faci...Balancing WIP and Throughput with Machine Utilization in a Manufacturing Faci...
Balancing WIP and Throughput with Machine Utilization in a Manufacturing Faci...
 
4 production and cost
4  production and cost4  production and cost
4 production and cost
 
Fault tolerance on cloud computing
Fault tolerance on cloud computingFault tolerance on cloud computing
Fault tolerance on cloud computing
 
Profit based unit commitment for GENCOs using Parallel PSO in a distributed c...
Profit based unit commitment for GENCOs using Parallel PSO in a distributed c...Profit based unit commitment for GENCOs using Parallel PSO in a distributed c...
Profit based unit commitment for GENCOs using Parallel PSO in a distributed c...
 
IJERD(www.ijerd.com)International Journal of Engineering Research and Develop...
IJERD(www.ijerd.com)International Journal of Engineering Research and Develop...IJERD(www.ijerd.com)International Journal of Engineering Research and Develop...
IJERD(www.ijerd.com)International Journal of Engineering Research and Develop...
 
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
 
GENERATIVE SCHEDULING OF EFFECTIVE MULTITASKING WORKLOADS FOR BIG-DATA ANALYT...
GENERATIVE SCHEDULING OF EFFECTIVE MULTITASKING WORKLOADS FOR BIG-DATA ANALYT...GENERATIVE SCHEDULING OF EFFECTIVE MULTITASKING WORKLOADS FOR BIG-DATA ANALYT...
GENERATIVE SCHEDULING OF EFFECTIVE MULTITASKING WORKLOADS FOR BIG-DATA ANALYT...
 
Planning/Scheduling with CP Optimizer
Planning/Scheduling with CP OptimizerPlanning/Scheduling with CP Optimizer
Planning/Scheduling with CP Optimizer
 
Weighted Flowtime on Capacitated Machines
Weighted Flowtime on Capacitated MachinesWeighted Flowtime on Capacitated Machines
Weighted Flowtime on Capacitated Machines
 
DEA-Solver-Pro Version 14d- Newsletter17
DEA-Solver-Pro Version 14d- Newsletter17DEA-Solver-Pro Version 14d- Newsletter17
DEA-Solver-Pro Version 14d- Newsletter17
 
50120140507009
5012014050700950120140507009
50120140507009
 
50120140507009 2
50120140507009 250120140507009 2
50120140507009 2
 
Costs
CostsCosts
Costs
 
The GREDOR project. Redesigning the decision chain for managing distribution ...
The GREDOR project. Redesigning the decision chain for managing distribution ...The GREDOR project. Redesigning the decision chain for managing distribution ...
The GREDOR project. Redesigning the decision chain for managing distribution ...
 
IRJET- Advance Approach for Load Balancing in Cloud Computing using (HMSO) Hy...
IRJET- Advance Approach for Load Balancing in Cloud Computing using (HMSO) Hy...IRJET- Advance Approach for Load Balancing in Cloud Computing using (HMSO) Hy...
IRJET- Advance Approach for Load Balancing in Cloud Computing using (HMSO) Hy...
 
Enhancements of Extended Locational Marginal Pricing – Advancing Practical Im...
Enhancements of Extended Locational Marginal Pricing – Advancing Practical Im...Enhancements of Extended Locational Marginal Pricing – Advancing Practical Im...
Enhancements of Extended Locational Marginal Pricing – Advancing Practical Im...
 
PRODUCTIVITY IMPROVEMENT OF AUTOMOTIVE ASSEMBLY LINE THROUGH LINE BALANCING
PRODUCTIVITY IMPROVEMENT OF AUTOMOTIVE ASSEMBLY LINE THROUGH LINE BALANCINGPRODUCTIVITY IMPROVEMENT OF AUTOMOTIVE ASSEMBLY LINE THROUGH LINE BALANCING
PRODUCTIVITY IMPROVEMENT OF AUTOMOTIVE ASSEMBLY LINE THROUGH LINE BALANCING
 

Dernier

Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1kcpayne
 
CROSS CULTURAL NEGOTIATION BY PANMISEM NS
CROSS CULTURAL NEGOTIATION BY PANMISEM NSCROSS CULTURAL NEGOTIATION BY PANMISEM NS
CROSS CULTURAL NEGOTIATION BY PANMISEM NSpanmisemningshen123
 
UAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur Dubai
UAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur DubaiUAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur Dubai
UAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur Dubaijaehdlyzca
 
Mckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for ViewingMckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for ViewingNauman Safdar
 
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGBerhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGpr788182
 
Lucknow Housewife Escorts by Sexy Bhabhi Service 8250092165
Lucknow Housewife Escorts  by Sexy Bhabhi Service 8250092165Lucknow Housewife Escorts  by Sexy Bhabhi Service 8250092165
Lucknow Housewife Escorts by Sexy Bhabhi Service 8250092165meghakumariji156
 
Falcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business PotentialFalcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business PotentialFalcon investment
 
Nashik Call Girl Just Call 7091819311 Top Class Call Girl Service Available
Nashik Call Girl Just Call 7091819311 Top Class Call Girl Service AvailableNashik Call Girl Just Call 7091819311 Top Class Call Girl Service Available
Nashik Call Girl Just Call 7091819311 Top Class Call Girl Service Availablepr788182
 
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGParadip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGpr788182
 
Challenges and Opportunities: A Qualitative Study on Tax Compliance in Pakistan
Challenges and Opportunities: A Qualitative Study on Tax Compliance in PakistanChallenges and Opportunities: A Qualitative Study on Tax Compliance in Pakistan
Challenges and Opportunities: A Qualitative Study on Tax Compliance in Pakistanvineshkumarsajnani12
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...daisycvs
 
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 MonthsSEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 MonthsIndeedSEO
 
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAIGetting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAITim Wilson
 
QSM Chap 10 Service Culture in Tourism and Hospitality Industry.pptx
QSM Chap 10 Service Culture in Tourism and Hospitality Industry.pptxQSM Chap 10 Service Culture in Tourism and Hospitality Industry.pptx
QSM Chap 10 Service Culture in Tourism and Hospitality Industry.pptxDitasDelaCruz
 
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All TimeCall 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Timegargpaaro
 
JAJPUR CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JAJPUR ESCORTS
JAJPUR CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JAJPUR  ESCORTSJAJPUR CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JAJPUR  ESCORTS
JAJPUR CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JAJPUR ESCORTSkajalroy875762
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxCynthia Clay
 
Phases of Negotiation .pptx
 Phases of Negotiation .pptx Phases of Negotiation .pptx
Phases of Negotiation .pptxnandhinijagan9867
 
Falcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting
 

Dernier (20)

HomeRoots Pitch Deck | Investor Insights | April 2024
HomeRoots Pitch Deck | Investor Insights | April 2024HomeRoots Pitch Deck | Investor Insights | April 2024
HomeRoots Pitch Deck | Investor Insights | April 2024
 
Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1
 
CROSS CULTURAL NEGOTIATION BY PANMISEM NS
CROSS CULTURAL NEGOTIATION BY PANMISEM NSCROSS CULTURAL NEGOTIATION BY PANMISEM NS
CROSS CULTURAL NEGOTIATION BY PANMISEM NS
 
UAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur Dubai
UAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur DubaiUAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur Dubai
UAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur Dubai
 
Mckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for ViewingMckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for Viewing
 
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGBerhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
 
Lucknow Housewife Escorts by Sexy Bhabhi Service 8250092165
Lucknow Housewife Escorts  by Sexy Bhabhi Service 8250092165Lucknow Housewife Escorts  by Sexy Bhabhi Service 8250092165
Lucknow Housewife Escorts by Sexy Bhabhi Service 8250092165
 
Falcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business PotentialFalcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business Potential
 
Nashik Call Girl Just Call 7091819311 Top Class Call Girl Service Available
Nashik Call Girl Just Call 7091819311 Top Class Call Girl Service AvailableNashik Call Girl Just Call 7091819311 Top Class Call Girl Service Available
Nashik Call Girl Just Call 7091819311 Top Class Call Girl Service Available
 
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGParadip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
 
Challenges and Opportunities: A Qualitative Study on Tax Compliance in Pakistan
Challenges and Opportunities: A Qualitative Study on Tax Compliance in PakistanChallenges and Opportunities: A Qualitative Study on Tax Compliance in Pakistan
Challenges and Opportunities: A Qualitative Study on Tax Compliance in Pakistan
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
 
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 MonthsSEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
 
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAIGetting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
 
QSM Chap 10 Service Culture in Tourism and Hospitality Industry.pptx
QSM Chap 10 Service Culture in Tourism and Hospitality Industry.pptxQSM Chap 10 Service Culture in Tourism and Hospitality Industry.pptx
QSM Chap 10 Service Culture in Tourism and Hospitality Industry.pptx
 
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All TimeCall 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
 
JAJPUR CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JAJPUR ESCORTS
JAJPUR CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JAJPUR  ESCORTSJAJPUR CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JAJPUR  ESCORTS
JAJPUR CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JAJPUR ESCORTS
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
 
Phases of Negotiation .pptx
 Phases of Negotiation .pptx Phases of Negotiation .pptx
Phases of Negotiation .pptx
 
Falcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investors
 

Semiconductor Fab Productivity--Cycle Time

  • 1. he need to focus the fab productivity discussion on waste reduction has been widely discussed and recognized, (1-3) yet, the industry still lacks ba- sic tools to comprehend the complete productivity picture. For example, cycle time is relatively intractable and its value is difficult to quantify because it consists of missed opportunity rather than incurred costs. In this study we propose a basic toolkit for definition and valuation of cycle time, an important first step towards focusing attention and action on improving fab agility. Interest in reducing cycle time is grow- ing across business models and market seg- ments, from manufacturers of microproces- sors (Intel and AMD), memory (Samsung, Inotera, Spansion), foundry (TSMC), and even development fabs.(4-17) However, since there is no unified definition of cycle time, we cannot calculate its value. To remedy this, we are working with ISMI and SEMI to formalize a simple set of definitions, building on Little’s Law and existing SEMI Standards (primarily E124- 1103). Little’s Law states that average work-in-process (WIP) equals the product of arrival rate and average cycle time, as follows: (Eq.1) Simple manipulation and reflecting the likelihood of loss during fab processing (substituting output rate, like finished units out, for input rate, like arrival rate) yields
  • 2. tom-up” approach, typically focusing on modeling the impact of longer time to market and reduced differen- tiation, (18-21) slower yield learning, or simply inventory carrying costs. (14, 22-24) Our approach was instead to go to “first principles” based on the assumption that a fab’s objective is to maxi- mize profitability. Profitability is generally increased with utilization, so with a simple representation like Eq. 4, we can see a relationship as expressed in Figure 2 for any given time period. (Eq.4) where GM is gross margin, u is utilization of available ca- pacity, ASP is average selling price, UnitVarCost is variable the definition of cycle time as the ratio of average WIP to cost per unit. output rate (finished units out): As a result, fabs may be tempted to push utilization to very high levels; however, extremely high utilization is rare (Eq.2) due to the conflict between agility and utilization. This rela- tionship is known as the “fab operating curve,” illustrated in Note that this definition is based on a top-down view, Figure 3. The fab operating curve has been extensively ana- as opposed to classical definitions based on the sum of cycle lyzed in queuing theory(4) and one model is shown in Eq 5. times of individual process steps. Also, this definition is not limited to fab-wide operations, but can be applied to any (Eq.5) (G/G/1): one process- productive part of it. Cycle time is typically calculated per ing path wafer, and possibly per die. To enable graphic representation, we have adopted a In this equation, Ce is coefficient of process time variation, metric called “mean time between good units out,” or Ca is coefficient of arrival time variation, u stands for utiliza- MTBG. MTBG is simply the inverse of the through- tion of available capacity, and Te is average processing time. put rate of the fab (or some element of it). In that case, cycle time is the product of WIP and MTBG: $10,000 (Eq.3) This relationship is shown in Figure 1, for example, where $8,000 Cost, Profit per Wafer two states are compared: A, or current state, vs. B, or target (ideal) Gross Margin case. The rectangle in orange, with corners A and B, can be $6,000 viewed as the cycle time waste, or “waste” generated in the fab. The relative size of these rectangles can indicate the $4,000 Back-End Costs overall level of waste. For example, the ratio of rectangle Fab Variable Costs B (area defined from origin to B) to rectangle A (area de- $2,000 fined by origin to A) is equivalent to the primary indica- Average Fab Fixed Costs tor advocated by Hyder, namely, load-adjusted cycle time $0 60% 70% 80% 90% 100% equivalent or LACTE. (5) Utilization Analysts and practitioners have traditionally quantified the economic impact of cycle time waste using a “bot-
  • 3. The mathematical approach uses the concept of “elasticity” ( ), or the ratio of the percent change in one variable to the percent change in another variable. Step 1: Determine the sensitivity of fab owner’s profitability to fab utilization, based on Eq.4: (Eq.6) In this equation, GM is gross margin, GM% is gross margin % of revenue; u is utilization of available capacity; FC% repre- sents fixed costs as a % of total manufacturing costs. Step 2: Determine the sensitivity of cycle time (in queue) to fab utilization using Eq.5: (Eq.7) where CTq is cycle time in queue, Ce is coefficient of process As is evident from the fab operating curve shown in Fig- time variation, Ca is coefficient of arrival time variation, and Te ure 3, the cycle time penalty tends to stand in the way of is average processing time. increased fab utilization. As utilization increases, cycle time increases and reaches unacceptable levels, forcing Step 3: Divide the sensitivities to determine overall response of fabs to limit fab loading. This relationship between in- profitability to cycle time (in queue): creasing cycle time and increasing fab utilization provides an important hint about how to quantify the cost of cycle (Eq.8) time waste. Instead of divining the way fabs should run their business, it is more straightforward to observe how Step 4: Adjust the calculation to represent the response of profits they do it, then impute from their actions and priorities to changes in total cycle time and to convert this profit impact the relative value of cycle time. to “equivalent costs” (shown as a % of wafer processing costs): Fabs use extensive analytical and planning tools to strike an optimal trade-off. The rationale is to extend 100% cycle time to increase utilization up to the point where LOW=1X (queue % of total cycle time) LOW=2X Lower Value of 80% Cycle Time additional increases would make cycle time unacceptably LOW=3X Cycle Time Waste long (resulting in lost business, worse operational per- LOW=4X 60% formance). Alternatively, they cut cycle time up to the point where further reductions would erode utilization 40% and profitability more than the contribution of shorter Higher Value of cycle time. 20% Cycle Time Based on this logic, we can identify a “sweet spot” 0% where the value of incremental profit (from higher utiliza- 60% 70% 80% 90% 100% tion) roughly equals the incremental economic cost (from Target Utilization longer cycle time). This allows us to find the “shadow price” of cycle time by observing the fab’s actual perfor- mance. From this we can attribute what we call the Lost Opportunity due to waste, or LOW function, to each spe- cific user situation.
  • 4. $25,000,000 LOW (Annual $ per one day reduction) Scenario 1 Scenario 2 $20,000,000 Scenario 1 Scenario 2 Wafer per day 3,000 1,000 $15,000,000 Cycle time, days 40 60 Time in queue 80% 90% Target utilization 90% 90% $10,000,000 At targeted utilization: Cost per wafer $2,000 $4,500 $5,000,000 GM% 35% 55% Fixed Costs % 70% 60% Front End % 70% 50% $0 80% 85% 90% 95% 100% Utilization (Actual) lization (u) is and the longer the relative queue time (r) is. This (Eq.9) mathematical behavior and its graphical representation (Figure 4) reflects the real-world situation. Fab managers who choose to run their factories at high utilization/high queue time regimes (upper right-hand corner of Figure 4) are responding to the ex- pectations of the overall enterprise by putting throughput ahead where Rev is Revenues, and FE% represents of time to market. Their actions reveal the relatively low value the share of front-end (fab processing) costs of total chip costs. that they assign to cycle time. The reverse would be true in situations of lower utilization and queue time (lower left-hand corner of Figure 4). Equation 9 provides a simple model to evaluate the LOW (or The second argument in Eq 9 reflects the basic financial the economic value of cycle time) based on information about a model of the particular fab. Figure 5 illustrates the calculation of fab’s current operational characteristics and business model. the LOW function for two fabs with different business models. It is instructive to consider the equation in some detail. The Even for high-utilization fabs like these, an extra day of cycle first argument , reflects the operational characteristics of time costs many millions in missed economic opportunity (this the fab. The behavior of this term is consistent with our in- is consistent with other observations).(5, 18) tuition. Mathematically, it drives the opportunity cost of cycle More importantly, this model allows us to contrast the cost time (LOW) to be lower, the higher the currently targeted uti- of lost opportunity due to waste with the direct fabrication costs (CoO). There is always some element of waste, and this adds $10,000 to the total wafer cost. As utilization rates are pushed higher, this waste component grows, and can grow to the point where $8,000 it more than doubles the total economic cost per wafer. Figure 6 shows this comparison for a given scenario (fab-wide situation). Cost per Wafer LOW clearly becomes comparable to and even overwhelms $6,000 CoO in typical situations. Interestingly, total economic costs can actually be minimized $4,000 LOW at lower utilization (77%), saving 4% vs. target utilization. $2,000 CoO We have shown that cycle time can be clearly defined and that the lost opportunity incurred by fab owners due to cycle time waste may be $0 on the same order of magnitude as the direct fabrication costs. 60% 70% 80% 90% 100% Can this lost opportunity be addressed? A detailed approach is Utilization (Actual) beyond the scope of this paper, but we have discussed elsewhere (1, 3) that the key levers for cycle time waste reduction consist of: a. Predictable, low-variability, “smart” tools b. High-capacity AMHS and factory systems
  • 5. c. Universal, high-productivity, single-wafer proces tools This report lays out a straightforward toolkit for the definition and measurement of cycle time, waste, and its economic impact. It is our hope that with the greater clarity and visibility into cycle time waste and its economic implications that these tools provide, agility will receive the recognition it deserves within the fab pro- ductivity agenda. The authors wish to thank Applied’s Dr. Dajiang Xu for his critical contributions in preparing this report. Authors: Iddo Hadar and Eric Englhardt. For additional information, please contact Iddo_Hadar@amat.com