SlideShare une entreprise Scribd logo
1  sur  52
AN INTRODUCTION TO
CSWIP 3.1

 By

 MR ANSAR BALOCH
Contents

Terms & Definition
Types of Welds
Types of Joints
Weld Preparations
Types of Single Butt Preparation
Butt Welded Joint
Fillet Weld Profile
Effect of a Poor Toe Blend Angle
Summary of Terms
Duties of Welding Inspector
Responsibilities of Welding Inspector
Imperfections in Welded Joints
Mechanical Testing
Macro Inspection
A Weld:*    A union between materials caused by heat,
            and or pressure



A Joint:*   A configuration of members




                     Text Page Ref 1:1
Butt welds:*


Fillet welds:*

Spot/Seam welds:*

Plug/Slot welds:*

Edge welds:*
Butt joints: *


T joints: *


Lap joints: *


Corner joints:*   Closed   Open
                  corner   corner*
Angle of bevel*
Root face*



                    Included angle*


     Root radius*     Root gap*




                      Root landing*
Single bevel


Single V


Single J


Single U*
Double bevel



Double V


Double J


Double U*
A butt welded butt joint*



A fillet welded butt joint*



A compound welded butt joint*
A fillet welded T joint*



A butt welded T joint*



A compound welded T joint*
A fillet welded Lap joint*



A spot welded Lap joint*



A compound welded Lap joint*
A fillet welded Closed Corner joint*



A butt welded Closed Corner joint*



A compound welded Closed Corner joint*
An inside fillet welded Open Corner joint*
                             C


An outside fillet welded Open Corner joint*



A double fillet welded Open Corner joint*
Weld Face*
Actual Throat Thickness*
                               Weld Width*
       1.2.3.4. Weld Toes*        Design Throat Thickness*

                    1             2
   A




   B                    3     4

         HAZ*
            Weld Root*

               A + B = Excess Weld Metal**
Vertical Leg Length*

                                    Weld face*




Horizontal Leg Length*
          Excess weld metal **
          Design throat*
          Actual throat*
6 mm


             80°
Very Poor Weld Toe Blend Angle

                         3 mm*

              20°
Improved Weld Toe Blend Angle
90°                         3 mm




Extremely poor toe blend, but excess weld metal is within limits*
Weld:                    A Union of materials
Joint:                   A Configuration of members
Weld Preparation:        Preparing a joint to allow access and fusion.
Types of Weld:           Butt. Fillet. Spot. Seam Plug. Slot. Edge.
Types of Joint:          Butt. T. Lap. Corner (Open & Closed)
Types of Preparation:    Bevel’s. V’s. J’s. U’s. Single & Double Sided.
Preparation Terms:       Bevel/included angle. Root face/gap. Land/Radius
Weldment Terms:          Weld face & root. HAZ. Weld toes.Weld width
Weld Sizing (Butts):     DTT. ATT. Excess weld metal.
Weld Sizing (Fillets):   DTT. ATT. Excess weld metal. Leg length *
It is the duty of all welding inspectors:
To ensure that welding operations are carried out in
accordance with written, or agreed practices or
specifications


   Before
                                                       *
   During
    After
Discuss the following
                        Before Welding:
1) Safety:
    Rules.
2) Documentation:
   Spec. Drawings. Procedures. Welder approvals. Certificates. Mill sheets

3) Welding Process and accessories:
   Equipment,Cables, Regulators, Ovens etc

4) Incoming Consumables:
    Materials/welding consumables (Size. Condition. Specification. Storage)
5) Marking out preparation & set up:
   Method. Angles/Root face/gap values. Distortion control. Pre-heat prior to
   tack welding if applicable*
During Welding:

1) Pre-Heating (Min 15 C as per UW-30 ASME Section VIII Div-I)
2) In process distortion control (Balance or sequence welding)
3) Consumable control. (Correct baking for E-7018 260-425 C and
   storage 30-140 C prior to use)
4) Welding process (Related parameters i.e. volts/amps. gas flow rate)
5) Welding run sequence and inter-pass cleaning
6) Minimum/maximum Inter-pass temperatures (150 C for SS, 250 C
   for CS.
7) Full compliance with all elements given on the WPS*
After Welding:

1) Visual Inspection
2) Non Destructive testing
3) Repairs*
4) Repair procedures (NDT/Welding/Welder approval)
5) PWHT
6) Hydro-static testing
7) Submission of all inspection reports to QC departments*
To Observe   Activities &
             Imperfections*

To Record    Activities &
             Imperfections*

             Activities &
To Compare
             Imperfections*
A Welding Inspectors toolbox should contain*
A welding gauge (Cambridge style, or high low gauges etc)
A tape measure and scale
A wire brush
A magnifying glass
A torch and mirror
A specification, pen and report, or note paper
Welding imperfections can be categorized into groups:

             1)     Cracks
             2)     Gas Pores & Porosity
             3)     Solid Inclusions
             4)     Lack of fusion
             5)     Profile & Lack of Filling
             6)     Mechanical or Surface damage
             7)     Misalignment*
A HAZ hydrogen crack, initiated at the weld toe
Most cracks are initiated from stress concentrations *
Surface breaking porosity
         Shrinkage cavity*
                                  Coarse cluster porosity
Fine cluster porosity
                                   Blow hole > 1.6 mm Ø




      Hollow root bead       An isolated internal porosity
Surface breaking solid inclusion
Internal solid inclusion causing
a lack of inter-run fusion*                      Internal solid inclusion causing
                                                 a lack of sidewall fusion




    Internal solid inclusion                 Solid inclusions caused by
                                             undercut in the previous weld
                                             run
Lack of sidewall fusion &
 incompletely filled grove*
                                            Overlap (Causing cold laps)




Lack of inter-run fusion               Lack of sidewall fusion

                           Lack of root fusion
Spatter                      An Incompletely filled groove


         A




       Lack of root fusion
                                    Bulbous, or irregular contour
        Arc Strikes
                                        Poor toe blend

          B



Incomplete root penetration
                              *
Root Run or “Hot pass” undercut




 Parent metal, surface undercut




 Weld metal, surface undercut*
Weld metal, surface undercut   Parent metal, “top toe” undercut*
Any surface damage caused by:
Grinding
Hammering/chisel marks
Slag chipping hammer marks

Arc strikes
Linear
  Excess weld metal height
  Lowest plate to highest point


                                                            3 mm
    Linear misalignment measured in mm (over 13mm to 19mm
    as per UW 33 of ASME Sec VIII Div-I)
                                  Angular

                                                               15°

Angular misalignment measured in degrees*
Why ?*   To establish the level of mechanical properties*
                                              properties

Which properties ?*
            1)     Hardness*
            2)     Toughness (Impact Test)*
            3)     Tensile strength*
            4)     Ductility*
We test welds to establish minimum levels of mechanical
properties, and soundness of the welded joint*

We divide tests into Quantitative & Qualitative methods:*


      1) Quantitative tests:
     1) Quantitative tests:       (Have units)*
                                 (Have units)*


      2) Qualitative tests:
     2) Qualitative tests:        (Have no units)*
                                 (Have no units)*
Types of tests include:
      1) Quantitative tests:
     1) Quantitative tests:
        Hardness tests
        Hardness tests
        Toughness tests
        Toughness tests
        Tensile strength tests*
        Tensile strength tests*
      2) Qualitative tests:
     2) Qualitative tests:
        Macro tests
        Macro tests
        Bend tests
        Bend tests
        Fracture tests*
        Fracture tests*
The specimen below has been polished and is
 ready to be hardness tested

   = Hardness Survey



Thickness



    Base metal   HAZ Fusion boundary Weld metal
Generally we use a diamond or steel ball to form an indentation




We measure the width of the indentation to gauge the hardness*
1)   Vickers Diamond Pyramid: Always uses a diamond*


2)   Brinell hardness test:    Always uses a steel ball*


3)   Rockwell hardness test:   Uses a ball, or diamond
                               depending on the scale*
Machined notch                                   10 x 10 mm




The specimen may be tested from different areas of the weld.*


Graduated scale                             Pendulum Hammer
of absorbed
energy in Joules*

                                          Location of specimen
1)   Charpy V test: 10 x 10 (Specimen horizontal) Joules*


2)   Izod test:      10 x 10 (Specimen vertical) Ft.lbs*
Radius
                                    (For radius reduced test specimens only)

                             Weld
        Test gripping area              HAZ



Direction of test
        Plate material                        Reduced Section



        Used to assess the tensile strength of the weld metal
All Weld Metal Tensile Testing




Direction of the test *




                                    Tensile test piece cut
                                    along weld specimen.
Firstly, before the tensile test 2 marks are made 50mm

                          50 mm


During the test, Yield point & Tensile strength are measured

The specimen is put together and the marks are re-measured

                          75 mm

A new measurement of 75mm will indicate Elongation E50 %*
1) Excess Weld Metal Height             7) Poor Toe Blend*



                                                 6)Porosity


2) Lack of Sidewall Fusion
                                          5) Root Penetration
3) Lack of Root Fusion

4) Slag inclusion & Lack of inter-run fusion
Bend tests are used to establish fusion in the area under test
Guide                          A Guided root bend test*
                               Lack of root fusion shown here*




                          Former
Test Piece
                  Force

Further tests include face, side and longitudinal bend tests*

For material over 12 mm thickness, side bend test may be
used*
Specimen prior to test*   Specimen after test*
The main difference between Macro & Micro is that Micro is
the study of the micro-structure at much higher magnification


The limit of Macro inspection is magnification < X 10
The specimen is usually cut from a stop/start in the test piece
Remember! The process of inspection is to first:
Observe, then Report, then Compare!*

Contenu connexe

Tendances

dokumen.tips_5-weld-defect-repair.ppt
dokumen.tips_5-weld-defect-repair.pptdokumen.tips_5-weld-defect-repair.ppt
dokumen.tips_5-weld-defect-repair.ppt
StevenConda2
 
86177188-Wps-Pqr-Guide.ppt
86177188-Wps-Pqr-Guide.ppt86177188-Wps-Pqr-Guide.ppt
86177188-Wps-Pqr-Guide.ppt
peter770054
 
Welding for engineers chapter 1
Welding for engineers   chapter 1Welding for engineers   chapter 1
Welding for engineers chapter 1
hakimm
 
Welders visual inspection_handbook-2013_web
Welders visual inspection_handbook-2013_webWelders visual inspection_handbook-2013_web
Welders visual inspection_handbook-2013_web
miguelbravo
 

Tendances (20)

Wis5 weldability n.ppt 1 11
Wis5 weldability n.ppt 1 11Wis5 weldability n.ppt 1 11
Wis5 weldability n.ppt 1 11
 
Twi welding training_6
Twi welding training_6Twi welding training_6
Twi welding training_6
 
Welding symbol
Welding symbolWelding symbol
Welding symbol
 
Welding Defects.pdf
Welding Defects.pdfWelding Defects.pdf
Welding Defects.pdf
 
Piping welding notes for beginners
Piping welding notes for beginnersPiping welding notes for beginners
Piping welding notes for beginners
 
dokumen.tips_5-weld-defect-repair.ppt
dokumen.tips_5-weld-defect-repair.pptdokumen.tips_5-weld-defect-repair.ppt
dokumen.tips_5-weld-defect-repair.ppt
 
86177188-Wps-Pqr-Guide.ppt
86177188-Wps-Pqr-Guide.ppt86177188-Wps-Pqr-Guide.ppt
86177188-Wps-Pqr-Guide.ppt
 
Basic welding
Basic weldingBasic welding
Basic welding
 
Asme sec. ix bkr - 051010
Asme sec. ix   bkr - 051010Asme sec. ix   bkr - 051010
Asme sec. ix bkr - 051010
 
Welding Inspection
Welding InspectionWelding Inspection
Welding Inspection
 
Aws d1.1 guides
Aws d1.1 guidesAws d1.1 guides
Aws d1.1 guides
 
ASME SEC IX PPT.pdf
ASME SEC IX PPT.pdfASME SEC IX PPT.pdf
ASME SEC IX PPT.pdf
 
Cracking phenomena in welding
Cracking phenomena in weldingCracking phenomena in welding
Cracking phenomena in welding
 
Welding for engineers chapter 1
Welding for engineers   chapter 1Welding for engineers   chapter 1
Welding for engineers chapter 1
 
Welders visual inspection_handbook-2013_web
Welders visual inspection_handbook-2013_webWelders visual inspection_handbook-2013_web
Welders visual inspection_handbook-2013_web
 
Procedure qualification
Procedure qualificationProcedure qualification
Procedure qualification
 
Welding defects
Welding defectsWelding defects
Welding defects
 
How to Qualify a Welding Procedure
How to Qualify a Welding ProcedureHow to Qualify a Welding Procedure
How to Qualify a Welding Procedure
 
Structural Steel Welding Inspection
Structural Steel Welding InspectionStructural Steel Welding Inspection
Structural Steel Welding Inspection
 
How to write a Welding Procedure Specification (ISO 15614-1
How to write a Welding Procedure Specification (ISO 15614-1How to write a Welding Procedure Specification (ISO 15614-1
How to write a Welding Procedure Specification (ISO 15614-1
 

En vedette

Smsvn pmp training_slides_chapter_3
Smsvn pmp training_slides_chapter_3Smsvn pmp training_slides_chapter_3
Smsvn pmp training_slides_chapter_3
Nam Trung
 
Smsvn conflicts
Smsvn conflictsSmsvn conflicts
Smsvn conflicts
Nam Trung
 
Smsvn pmp training_slides_review
Smsvn pmp training_slides_reviewSmsvn pmp training_slides_review
Smsvn pmp training_slides_review
Nam Trung
 
Smsvn pmp training_slides_chapter_8
Smsvn pmp training_slides_chapter_8Smsvn pmp training_slides_chapter_8
Smsvn pmp training_slides_chapter_8
Nam Trung
 
Smsvn pmp training_slides_chapter_7
Smsvn pmp training_slides_chapter_7Smsvn pmp training_slides_chapter_7
Smsvn pmp training_slides_chapter_7
Nam Trung
 
Smsvn pmp training_slides_chapter_5
Smsvn pmp training_slides_chapter_5Smsvn pmp training_slides_chapter_5
Smsvn pmp training_slides_chapter_5
Nam Trung
 

En vedette (19)

welding
 welding welding
welding
 
Electric Arc Welding
Electric Arc WeldingElectric Arc Welding
Electric Arc Welding
 
Welding and types
Welding and types Welding and types
Welding and types
 
Welding defects
Welding defectsWelding defects
Welding defects
 
Welding ppt
Welding pptWelding ppt
Welding ppt
 
cswip-3-1-new-book
 cswip-3-1-new-book cswip-3-1-new-book
cswip-3-1-new-book
 
Araldite Adhesives technology. Antala Industria (Spain).
Araldite Adhesives technology. Antala Industria (Spain).Araldite Adhesives technology. Antala Industria (Spain).
Araldite Adhesives technology. Antala Industria (Spain).
 
Aw
AwAw
Aw
 
CSWIP 3.1 Welding Inspection
CSWIP 3.1 Welding InspectionCSWIP 3.1 Welding Inspection
CSWIP 3.1 Welding Inspection
 
Smsvn quality attitude
Smsvn quality attitudeSmsvn quality attitude
Smsvn quality attitude
 
Smsvn pmp training_slides_chapter_3
Smsvn pmp training_slides_chapter_3Smsvn pmp training_slides_chapter_3
Smsvn pmp training_slides_chapter_3
 
Term paper - impact of organizational culture on enterprise risk management (...
Term paper - impact of organizational culture on enterprise risk management (...Term paper - impact of organizational culture on enterprise risk management (...
Term paper - impact of organizational culture on enterprise risk management (...
 
Smsvn conflicts
Smsvn conflictsSmsvn conflicts
Smsvn conflicts
 
Lean Process Improvement Techniques
Lean Process Improvement TechniquesLean Process Improvement Techniques
Lean Process Improvement Techniques
 
CSWIP 3.1
CSWIP 3.1CSWIP 3.1
CSWIP 3.1
 
Smsvn pmp training_slides_review
Smsvn pmp training_slides_reviewSmsvn pmp training_slides_review
Smsvn pmp training_slides_review
 
Smsvn pmp training_slides_chapter_8
Smsvn pmp training_slides_chapter_8Smsvn pmp training_slides_chapter_8
Smsvn pmp training_slides_chapter_8
 
Smsvn pmp training_slides_chapter_7
Smsvn pmp training_slides_chapter_7Smsvn pmp training_slides_chapter_7
Smsvn pmp training_slides_chapter_7
 
Smsvn pmp training_slides_chapter_5
Smsvn pmp training_slides_chapter_5Smsvn pmp training_slides_chapter_5
Smsvn pmp training_slides_chapter_5
 

Similaire à CSWIP Intro

Cswipday1 slide71-email-1-130121013355-phpapp02
Cswipday1 slide71-email-1-130121013355-phpapp02Cswipday1 slide71-email-1-130121013355-phpapp02
Cswipday1 slide71-email-1-130121013355-phpapp02
MDSHAHID8797
 
Welding visual inspection
Welding visual inspectionWelding visual inspection
Welding visual inspection
businespartner
 
Weld 1 (nx power lite) (nxpowerlite) (nxpowerlite)
Weld 1 (nx power lite) (nxpowerlite) (nxpowerlite)Weld 1 (nx power lite) (nxpowerlite) (nxpowerlite)
Weld 1 (nx power lite) (nxpowerlite) (nxpowerlite)
Jitesh Gaurav
 
Flashings Fasteners & Accessories
Flashings Fasteners & AccessoriesFlashings Fasteners & Accessories
Flashings Fasteners & Accessories
durolast
 
WELDING_DESIGN_AND_PROCESS_SELECTION.ppt
WELDING_DESIGN_AND_PROCESS_SELECTION.pptWELDING_DESIGN_AND_PROCESS_SELECTION.ppt
WELDING_DESIGN_AND_PROCESS_SELECTION.ppt
KANWARGILL16
 
UNIT3-Special casting processmechanical.ppt
UNIT3-Special casting processmechanical.pptUNIT3-Special casting processmechanical.ppt
UNIT3-Special casting processmechanical.ppt
Praveen Kumar
 

Similaire à CSWIP Intro (20)

Weld introduction.ppt
Weld introduction.pptWeld introduction.ppt
Weld introduction.ppt
 
Cswipday1 slide71-email-1-130121013355-phpapp02
Cswipday1 slide71-email-1-130121013355-phpapp02Cswipday1 slide71-email-1-130121013355-phpapp02
Cswipday1 slide71-email-1-130121013355-phpapp02
 
lap joint .ppt
lap joint .pptlap joint .ppt
lap joint .ppt
 
Workshop Practices
Workshop PracticesWorkshop Practices
Workshop Practices
 
Welding visual inspection
Welding visual inspectionWelding visual inspection
Welding visual inspection
 
Welding joints ,GTAW
Welding joints ,GTAW Welding joints ,GTAW
Welding joints ,GTAW
 
Weld 1 (nx power lite) (nxpowerlite) (nxpowerlite)
Weld 1 (nx power lite) (nxpowerlite) (nxpowerlite)Weld 1 (nx power lite) (nxpowerlite) (nxpowerlite)
Weld 1 (nx power lite) (nxpowerlite) (nxpowerlite)
 
Welded connections in steel structures - Limit State Design of Steel Structures
Welded connections in steel structures - Limit State Design of Steel StructuresWelded connections in steel structures - Limit State Design of Steel Structures
Welded connections in steel structures - Limit State Design of Steel Structures
 
Cswip welding-inspection-notes-and-questions-1
Cswip welding-inspection-notes-and-questions-1Cswip welding-inspection-notes-and-questions-1
Cswip welding-inspection-notes-and-questions-1
 
Twi cswip welding inspection notes and questions
Twi cswip welding inspection notes and questionsTwi cswip welding inspection notes and questions
Twi cswip welding inspection notes and questions
 
Ndt Weld RepairCSWIP.pdf
Ndt Weld RepairCSWIP.pdfNdt Weld RepairCSWIP.pdf
Ndt Weld RepairCSWIP.pdf
 
Flashings Fasteners & Accessories
Flashings Fasteners & AccessoriesFlashings Fasteners & Accessories
Flashings Fasteners & Accessories
 
CMT based WAAM on SS 316L
CMT based WAAM on SS 316LCMT based WAAM on SS 316L
CMT based WAAM on SS 316L
 
WELDING JOINT DESING AND WELDINGSYMBOLS
WELDING JOINT DESING AND WELDINGSYMBOLSWELDING JOINT DESING AND WELDINGSYMBOLS
WELDING JOINT DESING AND WELDINGSYMBOLS
 
Workshop Techanology, fitting shop
Workshop Techanology, fitting shopWorkshop Techanology, fitting shop
Workshop Techanology, fitting shop
 
WELDING_DESIGN_AND_PROCESS_SELECTION.ppt
WELDING_DESIGN_AND_PROCESS_SELECTION.pptWELDING_DESIGN_AND_PROCESS_SELECTION.ppt
WELDING_DESIGN_AND_PROCESS_SELECTION.ppt
 
Welded joints
Welded jointsWelded joints
Welded joints
 
BOLTED CONNECTION
BOLTED CONNECTIONBOLTED CONNECTION
BOLTED CONNECTION
 
UNIT3-Special casting processmechanical.ppt
UNIT3-Special casting processmechanical.pptUNIT3-Special casting processmechanical.ppt
UNIT3-Special casting processmechanical.ppt
 
all.ppt
all.pptall.ppt
all.ppt
 

Plus de Imran Jamil

Selection of filler wire
Selection of filler wireSelection of filler wire
Selection of filler wire
Imran Jamil
 
Role of qa&qc in manufacturing presentation
Role of qa&qc in manufacturing   presentationRole of qa&qc in manufacturing   presentation
Role of qa&qc in manufacturing presentation
Imran Jamil
 
Cost of poor quality presentation5
Cost of poor quality presentation5Cost of poor quality presentation5
Cost of poor quality presentation5
Imran Jamil
 

Plus de Imran Jamil (17)

A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost management
 
A brief on project time management
A brief on project time managementA brief on project time management
A brief on project time management
 
6 project quality management (ij)
6  project quality management (ij)6  project quality management (ij)
6 project quality management (ij)
 
Project risk management
Project risk managementProject risk management
Project risk management
 
Project time management
Project time managementProject time management
Project time management
 
Project management life cycle
Project management life cycleProject management life cycle
Project management life cycle
 
Project management a brief intro
Project management   a brief introProject management   a brief intro
Project management a brief intro
 
Copq benefits of correct measurement (for slideshare)
Copq   benefits of correct measurement (for slideshare)Copq   benefits of correct measurement (for slideshare)
Copq benefits of correct measurement (for slideshare)
 
Project Management - Basic Concepts
Project Management - Basic ConceptsProject Management - Basic Concepts
Project Management - Basic Concepts
 
PMI Project Risk Management
PMI Project Risk ManagementPMI Project Risk Management
PMI Project Risk Management
 
Quality Assurance and Quality Control - Areas of Improvement
Quality Assurance and Quality Control - Areas of ImprovementQuality Assurance and Quality Control - Areas of Improvement
Quality Assurance and Quality Control - Areas of Improvement
 
Project quality management - PMI PMBOK Knowledge Area
Project quality management - PMI PMBOK Knowledge AreaProject quality management - PMI PMBOK Knowledge Area
Project quality management - PMI PMBOK Knowledge Area
 
Quality assurance documentation
Quality assurance documentationQuality assurance documentation
Quality assurance documentation
 
Cost of quality concept and advantages
Cost of quality   concept and advantagesCost of quality   concept and advantages
Cost of quality concept and advantages
 
Selection of filler wire
Selection of filler wireSelection of filler wire
Selection of filler wire
 
Role of qa&qc in manufacturing presentation
Role of qa&qc in manufacturing   presentationRole of qa&qc in manufacturing   presentation
Role of qa&qc in manufacturing presentation
 
Cost of poor quality presentation5
Cost of poor quality presentation5Cost of poor quality presentation5
Cost of poor quality presentation5
 

CSWIP Intro

  • 1. AN INTRODUCTION TO CSWIP 3.1 By MR ANSAR BALOCH
  • 2. Contents Terms & Definition Types of Welds Types of Joints Weld Preparations Types of Single Butt Preparation Butt Welded Joint Fillet Weld Profile Effect of a Poor Toe Blend Angle Summary of Terms Duties of Welding Inspector Responsibilities of Welding Inspector Imperfections in Welded Joints Mechanical Testing Macro Inspection
  • 3. A Weld:* A union between materials caused by heat, and or pressure A Joint:* A configuration of members Text Page Ref 1:1
  • 4. Butt welds:* Fillet welds:* Spot/Seam welds:* Plug/Slot welds:* Edge welds:*
  • 5. Butt joints: * T joints: * Lap joints: * Corner joints:* Closed Open corner corner*
  • 6. Angle of bevel* Root face* Included angle* Root radius* Root gap* Root landing*
  • 9. A butt welded butt joint* A fillet welded butt joint* A compound welded butt joint*
  • 10. A fillet welded T joint* A butt welded T joint* A compound welded T joint*
  • 11. A fillet welded Lap joint* A spot welded Lap joint* A compound welded Lap joint*
  • 12. A fillet welded Closed Corner joint* A butt welded Closed Corner joint* A compound welded Closed Corner joint*
  • 13. An inside fillet welded Open Corner joint* C An outside fillet welded Open Corner joint* A double fillet welded Open Corner joint*
  • 14. Weld Face* Actual Throat Thickness* Weld Width* 1.2.3.4. Weld Toes* Design Throat Thickness* 1 2 A B 3 4 HAZ* Weld Root* A + B = Excess Weld Metal**
  • 15. Vertical Leg Length* Weld face* Horizontal Leg Length* Excess weld metal ** Design throat* Actual throat*
  • 16.
  • 17. 6 mm 80° Very Poor Weld Toe Blend Angle 3 mm* 20° Improved Weld Toe Blend Angle
  • 18. 90° 3 mm Extremely poor toe blend, but excess weld metal is within limits*
  • 19. Weld: A Union of materials Joint: A Configuration of members Weld Preparation: Preparing a joint to allow access and fusion. Types of Weld: Butt. Fillet. Spot. Seam Plug. Slot. Edge. Types of Joint: Butt. T. Lap. Corner (Open & Closed) Types of Preparation: Bevel’s. V’s. J’s. U’s. Single & Double Sided. Preparation Terms: Bevel/included angle. Root face/gap. Land/Radius Weldment Terms: Weld face & root. HAZ. Weld toes.Weld width Weld Sizing (Butts): DTT. ATT. Excess weld metal. Weld Sizing (Fillets): DTT. ATT. Excess weld metal. Leg length *
  • 20.
  • 21. It is the duty of all welding inspectors: To ensure that welding operations are carried out in accordance with written, or agreed practices or specifications Before * During After
  • 22. Discuss the following Before Welding: 1) Safety: Rules. 2) Documentation: Spec. Drawings. Procedures. Welder approvals. Certificates. Mill sheets 3) Welding Process and accessories: Equipment,Cables, Regulators, Ovens etc 4) Incoming Consumables: Materials/welding consumables (Size. Condition. Specification. Storage) 5) Marking out preparation & set up: Method. Angles/Root face/gap values. Distortion control. Pre-heat prior to tack welding if applicable*
  • 23. During Welding: 1) Pre-Heating (Min 15 C as per UW-30 ASME Section VIII Div-I) 2) In process distortion control (Balance or sequence welding) 3) Consumable control. (Correct baking for E-7018 260-425 C and storage 30-140 C prior to use) 4) Welding process (Related parameters i.e. volts/amps. gas flow rate) 5) Welding run sequence and inter-pass cleaning 6) Minimum/maximum Inter-pass temperatures (150 C for SS, 250 C for CS. 7) Full compliance with all elements given on the WPS*
  • 24. After Welding: 1) Visual Inspection 2) Non Destructive testing 3) Repairs* 4) Repair procedures (NDT/Welding/Welder approval) 5) PWHT 6) Hydro-static testing 7) Submission of all inspection reports to QC departments*
  • 25. To Observe Activities & Imperfections* To Record Activities & Imperfections* Activities & To Compare Imperfections*
  • 26. A Welding Inspectors toolbox should contain* A welding gauge (Cambridge style, or high low gauges etc) A tape measure and scale A wire brush A magnifying glass A torch and mirror A specification, pen and report, or note paper
  • 27. Welding imperfections can be categorized into groups: 1) Cracks 2) Gas Pores & Porosity 3) Solid Inclusions 4) Lack of fusion 5) Profile & Lack of Filling 6) Mechanical or Surface damage 7) Misalignment*
  • 28. A HAZ hydrogen crack, initiated at the weld toe Most cracks are initiated from stress concentrations *
  • 29. Surface breaking porosity Shrinkage cavity* Coarse cluster porosity Fine cluster porosity Blow hole > 1.6 mm Ø Hollow root bead An isolated internal porosity
  • 30. Surface breaking solid inclusion Internal solid inclusion causing a lack of inter-run fusion* Internal solid inclusion causing a lack of sidewall fusion Internal solid inclusion Solid inclusions caused by undercut in the previous weld run
  • 31. Lack of sidewall fusion & incompletely filled grove* Overlap (Causing cold laps) Lack of inter-run fusion Lack of sidewall fusion Lack of root fusion
  • 32. Spatter An Incompletely filled groove A Lack of root fusion Bulbous, or irregular contour Arc Strikes Poor toe blend B Incomplete root penetration *
  • 33. Root Run or “Hot pass” undercut Parent metal, surface undercut Weld metal, surface undercut*
  • 34. Weld metal, surface undercut Parent metal, “top toe” undercut*
  • 35. Any surface damage caused by: Grinding Hammering/chisel marks Slag chipping hammer marks Arc strikes
  • 36. Linear Excess weld metal height Lowest plate to highest point 3 mm Linear misalignment measured in mm (over 13mm to 19mm as per UW 33 of ASME Sec VIII Div-I) Angular 15° Angular misalignment measured in degrees*
  • 37. Why ?* To establish the level of mechanical properties* properties Which properties ?* 1) Hardness* 2) Toughness (Impact Test)* 3) Tensile strength* 4) Ductility*
  • 38. We test welds to establish minimum levels of mechanical properties, and soundness of the welded joint* We divide tests into Quantitative & Qualitative methods:* 1) Quantitative tests: 1) Quantitative tests: (Have units)* (Have units)* 2) Qualitative tests: 2) Qualitative tests: (Have no units)* (Have no units)*
  • 39. Types of tests include: 1) Quantitative tests: 1) Quantitative tests: Hardness tests Hardness tests Toughness tests Toughness tests Tensile strength tests* Tensile strength tests* 2) Qualitative tests: 2) Qualitative tests: Macro tests Macro tests Bend tests Bend tests Fracture tests* Fracture tests*
  • 40. The specimen below has been polished and is ready to be hardness tested = Hardness Survey Thickness Base metal HAZ Fusion boundary Weld metal
  • 41. Generally we use a diamond or steel ball to form an indentation We measure the width of the indentation to gauge the hardness*
  • 42. 1) Vickers Diamond Pyramid: Always uses a diamond* 2) Brinell hardness test: Always uses a steel ball* 3) Rockwell hardness test: Uses a ball, or diamond depending on the scale*
  • 43. Machined notch 10 x 10 mm The specimen may be tested from different areas of the weld.* Graduated scale Pendulum Hammer of absorbed energy in Joules* Location of specimen
  • 44. 1) Charpy V test: 10 x 10 (Specimen horizontal) Joules* 2) Izod test: 10 x 10 (Specimen vertical) Ft.lbs*
  • 45. Radius (For radius reduced test specimens only) Weld Test gripping area HAZ Direction of test Plate material Reduced Section Used to assess the tensile strength of the weld metal
  • 46. All Weld Metal Tensile Testing Direction of the test * Tensile test piece cut along weld specimen.
  • 47. Firstly, before the tensile test 2 marks are made 50mm 50 mm During the test, Yield point & Tensile strength are measured The specimen is put together and the marks are re-measured 75 mm A new measurement of 75mm will indicate Elongation E50 %*
  • 48. 1) Excess Weld Metal Height 7) Poor Toe Blend* 6)Porosity 2) Lack of Sidewall Fusion 5) Root Penetration 3) Lack of Root Fusion 4) Slag inclusion & Lack of inter-run fusion
  • 49. Bend tests are used to establish fusion in the area under test Guide A Guided root bend test* Lack of root fusion shown here* Former Test Piece Force Further tests include face, side and longitudinal bend tests* For material over 12 mm thickness, side bend test may be used*
  • 50. Specimen prior to test* Specimen after test*
  • 51. The main difference between Macro & Micro is that Micro is the study of the micro-structure at much higher magnification The limit of Macro inspection is magnification < X 10 The specimen is usually cut from a stop/start in the test piece
  • 52. Remember! The process of inspection is to first: Observe, then Report, then Compare!*