SlideShare une entreprise Scribd logo
1  sur  22
Télécharger pour lire hors ligne
Integrating technology providers into the
cost improvement plan
E.P.I.C. Inc.
EPICPWR.COM
An Action Plan For
The Automotive Industry
Presented & Prepared by
Jason Gallion
A budget and planning proposal
Let’s go beyond traditional methods in which
others generate cost reduction techniques.
2010 6-Year forecast 2016
Piece Price Reduction
It’s time to go beyond even the most advanced
supplier collaboration and innovative models and
invite strategic innovation opportunities
Forecast data
ROI Presentation
Identified opportunities
Project Planning
Innovative
Technology
Welding &
Drilling
Solutions
Advanced
materials
OEM & their
Suppliers
Opportunities
Solutions
Process Control
Solutions
The OEM Supplier Relationship
The Purpose is to fund
innovation through mutual
benefits.
The Objective is the alignment of
cost reduction Technology and
cost improvement requirements.
The Mission is to provide new
cost improvement opportunities.
4
Mandatory 3% annual cost reduction
Supplier
Supplier Supplier
OEM
$96 Million Annually
47 Suppliers
47 suppliers
$3.2 Billion Annual Sales
$96 Million Annual cost reduction
$27 Million Annual expenditures
To meet the OEM’s cost
reduction requirements, 47
suppliers will reduce their
annual sales by 3%
Approximately *$27 Million
allocated to meet the demand.
*$27M Allocated to
cost improvement
projects
$96M Cost
reduction
*Based on average cost improvement projects recorded during supplier survey
6
Min. Effort
Req’d Result
Effort vs. Result
OEM’s influence
8
Influence on process improvement... little with capital investment
Existing collaboration relationships limited to process improvement. Even
today, some suppliers resist or are reluctant to embrace influence from OEM
-Δ% Cost
Reduction
Target
OEM’s Problem…
Supplier
Base
Condition
Suppliers
individual
effort
9
Solution Categories:
Raw Materials
Material processing
Machining
Assembly
Packaging / Transportation
Tooling & Capital
Inspection & Testing
The Assured Cost Improvement Plan
10
“We must begin to collaborate at an even greater level to
achieve momentous cost reduction goals.”
• Supplier Survey
• Use forecast data…To, and when to consider three year forecast and six
year forecast
• Required cost reduction items
• Create piece price reduction targets
What you need to do…
11
Supplier
Supplier Supplier
Supplier
Supplier
3% Mandatory
Cost Reduction
Cost reduction
Met with actual cost improvement projects
Current State… The goal
The Goal
Supplier
12
The cost improvement platform
Forecast data
ROI Presentation
Identified opportunities
Project Planning
Solution Categories:
Raw Materials
Material processing
Machining
Assembly
Packaging / Transportation
Tooling & Capital
Inspection & Testing
Innovative
Technology
Welding &
Drilling
Solutions
High temp
insulation
materials
OEM & their
Suppliers
Cost Improvement
Opportunities
Technology Providers
Cost reduction
requirements
Opportunities
Solutions
Process Control
Solutions
13
Supplier Survey
Based on annual cost improvement
requirements an estimated $27 million
should be allocated towards cost
improvement expenditures, to meet the
annual 3% cost reduction.
14
Supplier survey, data intelligence
15
Forecast Data, 3-6 Year Plan
16
BPT Long Term Plan
ATM Summary Americas Mid-Term Supply Plan 10-1-071410
Part Daily Averages
KNT KD L4 L4 CRV
BPT L4
RDX 2WD
RDX 4WD
BPT 4Axis TL 4WD
TL 2WD
ODY
MDX
RIDGELINE
Accord V6
Accord V6 ( X-O ) 4WD
Accord V6 ( X-O ) 2WD
Acura V6 ( X-O )
Pilot 4WD
Pilot 2WD
BPT 6AT
BPT M/S & S/S
Total
110 87 87 85 85
0 0
6AT Total
ODY 6AT 6AT
B
4Axis BPT total
3085 1569
B
B
B
151
326
290 297 267
944
000
973
617 631
122122 120124
1263
29
50
117108
71
277
422
65 63
74
234 271
0 2919 2794
6778
176
144
1519
300
167
1592
3260
162
85 Ki 08-09M
1st 2nd
124 120
86 Ki 09-10M
1st 2nd 1st
87Ki 10-11M
1st 2nd 2nd
318
0
1241 1088 1741
310
25
465
0
88
0 0
84
2011
0 0 1656 1553
1st
304
89
476
1540
2012
568 727
1289
0
821
88 Ki 11-12M
2nd
M/S & S/S Total 5AT
DAYS
B
B
B
L4 CR-V 4WD (BPT Localize)
2680
2008
0
2009 2010
89 Ki 12-13M
289281
0
686
122 122
646
0
0
0
1154 0
0 0
323
36
410
102 102
44 44
1545
24
342
50 98
0
89
281
0
108
13
87
456483
33
0
00
0
327 327
134 132
467
280 605
73 73
171 155
86
1159
B
B
B
B
( L4 total )
L4 Element
L4 Accord
L4 CR-V 2WD
L4 Acc CT 2WD
B
B
122 122
131
101 89
86
0 0
364 351
774 746
0 0
43 43
102 102
0 0
449 436
523
259 259
0 0
33 205
85 85
69 69
76 76
370 370
169 156
314 290
954 1614
1236 676
147 635
1685 1112
2013
91 Ki 14-15M
1st 2nd
90 Ki 13-14M
1st 2nd
122 122
0 0
0 0
0 0
2014
0 0
BPT Long Term Plan
ATM Summary Americas Mid-Term Supply Plan 10-1-071410
Part Daily Averages
KNT KD L4 L4 CRV
BPT L4
RDX 2WD
RDX 4WD
BPT 4Axis TL 4WD
TL 2WD
ODY
MDX
RIDGELINE
Accord V6
Accord V6 ( X-O ) 4WD
Accord V6 ( X-O ) 2WD
Acura V6 ( X-O )
Pilot 4WD
Pilot 2WD
BPT 6AT
BPT M/S & S/S
Total
BPT
Counter
Shaft
Input Shaft
308 162
1432 1600 1400
2919 2794
110 87 87 85 85
T/S Total 144 280 605 954 1614
0
CR-V 4WD
M/S & S/S Total 5AT & 6AT
154 154
1563 1853
0 0
0 000
6AT
R97 C/S
RWE C/S
0
0
209
0 0
0 0 0
RWE Counter Shaft 0
R97 Counter Shaft
6AT Total
ODY 6AT 6AT
B
4Axis BPT total
1292 911
2174
3085 1569
3365
B
B
B
151
326
290 297 267
944
000
973
617 631
122122 120124
1263
29
50
117108
71
277
422
65 63
74
234 271
0 2919 2794
0
0 1327 1242
218 208
6778
176
1450 1508
313
1545
1195 1223
144
1519
3404
300
167
1592
2680
3260
162
85 Ki 08-09M
1st 2nd
124 120
86 Ki 09-10M
1st 2nd 1st
87Ki 10-11M
1st 2nd 2nd
318
0
1241 1088 1741
310
25
465
0
88
0 0
84
2011
0 0 1656 1553
1st
304
89
476
1540
2012
568 727
1289
0
821
88 Ki 11-12M
2nd
Total Counter Shaft
M/S & S/S Total 5AT
DAYS
B
B
B
L4 CR-V 4WD (BPT Localize)
2680
2008
0
2009 2010
89 Ki 12-13M
289281
0
686
122 122
646
0
0
0
1154 0
0 0
323
36
410
102 102
44 44
1545
24
342
50 98
0
89
281
0
108
13
87
456483
33
0
00
0
327 327
134 132
467
280 605
73 73
171 155
86
1159
B
B
B
B
( L4 total )
L4 Element
L4 Accord
L4 CR-V 2WD
L4 Acc CT 2WD
B
B
122 122
131
101 89
86
0 0
364 351
774 746
0 0
43 43
102 102
0 0
449 436
523
259 259
0 0
33 205
85 85
69 69
76 76
370 370
169 156
314 290
954 1614
1236 676
147 635
1685 1112
1039 446
27262639
2013
91 Ki 14-15M
1st 2nd
90 Ki 13-14M
1st 2nd
122 122
0 0
0 0
0 0
2014
0 0
0 0
0 0RV2A Counter Shaft 327 370 1253
1211I/S TotalAccord CVT 1220 1369
0
Expected parts to
Mfg every year,
production forecast
ROI Calculations
17
KNT US KNT US KNT US KNT US KNT US KNT US
¥12,500 $7,600.00 ¥0 $7,600.00 ¥12,500 $7,600.00 ¥0 $7,600.00 ¥25,000 $3,800.00 ¥0 $3,800.00
¥152,200 $2,492.00 ¥109,620 $2,492.00 ¥152,200 $2,634.00 ¥108,700 $2,270.00 ¥153,000 $2,362.00 ¥166,800 $2,362.00
¥182,640 - ¥131,544 - ¥182,640 - ¥130,440 - ¥183,600 - ¥200,160 -
$2,200.49 $1,584.87 $2,200.49 $1,571.57 $2,212.05 $2,411.57
¥83/$ ¥83/$ ¥83/$ ¥83/$ ¥83/$ ¥83/$
175 180 218 220 175 200 218 220 195 200 198 200
Total Charges 101charge 98charge 81charge 80charge 101charge 88charge 81charge 80charge 91charge 88charge 89charge 88charge
RWE 185,318
8 8 8 8 8 8 8 8 8 8 8 8
$17,754.46 $27,536.00 $12,678.94 $27,536.00 $17,754.46 $28,672.00 $12,572.53 $25,760.00 $17,997.59 $22,696.00 $19,292.53 $22,696.00
Total Charges 231charge 224charge 185charge 184charge 231charge 202charge 185charge 184charge 207charge 202charge 204charge 202charge
RWE 187,880
0 0 0 0 0 0 0 0 0 0 0 0
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Charges 498charge 484charge 400charge 396charge 498charge 436charge 400charge 396charge 447charge 436charge 440charge 436charge
141,398
5 4 2 2 5 3 2 2 3 3 3 3
$11,002.41 $9,968.00 $3,169.73 $4,984.00 $11,002.41 $7,902.00 $3,143.13 $4,540.00 $6,636.14 $7,086.00 $7,234.70 $7,086.00
Total Charges 786charge 764charge 631charge 625charge 786charge 687charge 631charge 625charge 705charge 687charge 694charge 687charge
RWE 150,792
7 7 6 6 7 6 6 6 7 6 7 6
$15,403.37 $17,444.00 $9,509.20 $14,952.00 $15,403.37 $15,804.00 $9,429.40 $13,620.00 $15,484.34 $14,172.00 $16,880.96 $14,172.00
Total Charges 1329charge 1292charge 1067charge 1057charge 1329charge 1163charge 1067charge 1057charge 1192charge 1163charge 1174charge 1163charge
RWE 82,472
13 13 11 10 13 12 11 10 12 12 11 12
$28,606.27 $32,396.00 $17,433.54 $24,920.00 $28,606.27 $31,608.00 $17,287.23 $22,700.00 $26,544.58 $28,344.00 $26,527.23 $28,344.00
Total Charges 1255charge 1220charge 1008charge 999charge 1255charge 1098charge 1008charge 999charge 1127charge 1098charge 1110charge 1098charge
RWE 0
3 0 2 0 3 0 2 0 3 0 3 0
$6,601.45 $0.00 $3,169.73 $0.00 $6,601.45 $0.00 $3,143.13 $0.00 $6,636.14 $0.00 $7,234.70 $0.00
Total Charges 1255charge 1220charge 1008charge 999charge 1255charge 1098charge 1008charge 999charge 1127charge 1098charge 1110charge 1098charge
RWE 0
3 0 3 0 3 0 3 0 3 0 3 0
$6,601.45 $0.00 $4,754.60 $0.00 $6,601.45 $0.00 $4,714.70 $0.00 $6,636.14 $0.00 $7,234.70 $0.00
Total Charges 1255charge 1220charge 1008charge 999charge 1255charge 1098charge 1008charge 999charge 1127charge 1098charge 1110charge 1098charge
RWE 0
7 0 5 0 5 0 5 0 5 0 5 0
$65,306.02 $0.00
$145,005.11 $168,312.00
$33,386.60 $0.00
$36,543.04 $0.00
$0.00 $0.00
$42,188.53 $41,566.00
$82,110.65 $90,164.00
NEW JIG INSTALL COST
KNT US
$98,050.51 $154,896.00
$0.0437$0.0889
$0.1614 $0.0665
JIG COST/pc
JIG COST/pc
JIG COST/pc
JIG COST/pc
JIG COST
NEED JIG QTY
$0.0376$0.0870$0.0568$0.0608
$0.1189
$0.0744
$0.0698 $0.0977 $0.0425
$0.1367
$0.1271 $0.0916 $0.0619
$0.1240$0.0986$0.0739
$0.1294 $0.1495 $0.0573 $0.1519 $0.1404
$0.0984$0.1141$0.0488$0.1169$0.0907
$0.1555$0.1068
$0.0985
$0.1794
$0.1597 $0.1697 $0.0980
$0.1741$0.1681$0.1023
$0.2012 $0.2054
$0.1557$0.1715$0.0464$0.1598
$0.3921
$0.2166 $0.2586 $0.1235 $0.2243 $0.2166 $0.0554 $0.1226 $0.2090 $0.1882
$1.2919
$0.3220 $0.4757 $0.2292 $0.4757 $0.3220 $0.0665 $0.2274 $0.4450 $0.3262
$1.01 $1.5674 $0.7217 $1.5674 $1.0106 $1.6321 $0.7156 $1.4663
$0.0553
JIG COST/pc
JIG COST/pc
NEED JIG QTY
6AT
$0.0617$0.0515
$0.0759
2013
2nd
1st
JIG COST
JIG COST
232,416
NEED JIG QTY
2014
JIG COST/pc
JIG COST/pc
1st
6AT
2nd
6AT
Third Shaft
CarborizeCarborize Normalize Carborize Normalize
Main Shaft Secoundary Shaft
Normalize
Shipping(include item)
NEED JIG QTY
JIG COST
2012
NEED JIG QTY
Production
Number
1st
JIG COST
Jig+Tray/1set
cast die price
137,376
$0.1379
1st
219,600
219,600
NEED JIG QTY
JIG COST
NEED JIG QTY
JIG COST
219,600
$0.0493 $0.0683
6AT
6AT
6AT
6AT
$0.1946
$0.1406
$0.0799$0.0567
87,120
NEED JIG QTY
2nd
17,568
unit jig price(not include cast die cost)
$0.1032
2nd
2011
40,320
US JIG
GET COST
DOWN
$6,185
$16,270
$26,755
$29,300
($56,845)
($5,332)
$0.0953 $0.0758
$0.0616$0.0810
【Jig cost analysis】
$32,623
$37,604
$1.0245 $1.2919 $1.0982
$0.0526 $0.3486
$0.0452
KNT US KNT US KNT US KNT US KNT US KNT US
¥12,500 $7,600.00 ¥0 $7,600.00 ¥12,500 $7,600.00 ¥0 $7,600.00 ¥25,000 $3,800.00 ¥0 $3,800.00
¥152,200 $2,492.00 ¥109,620 $2,492.00 ¥152,200 $2,634.00 ¥108,700 $2,270.00 ¥153,000 $2,362.00 ¥166,800 $2,362.00
¥182,640 - ¥131,544 - ¥182,640 - ¥130,440 - ¥183,600 - ¥200,160 -
$2,200.49 $1,584.87 $2,200.49 $1,571.57 $2,212.05 $2,411.57
¥83/$ ¥83/$ ¥83/$ ¥83/$ ¥83/$ ¥83/$
175 180 218 220 175 200 218 220 195 200 198 200
Total Charges 101charge 98charge 81charge 80charge 101charge 88charge 81charge 80charge 91charge 88charge 89charge 88charge
RWE 185,318
8 8 8 8 8 8 8 8 8 8 8 8
$17,754.46 $27,536.00 $12,678.94 $27,536.00 $17,754.46 $28,672.00 $12,572.53 $25,760.00 $17,997.59 $22,696.00 $19,292.53 $22,696.00
Total Charges 231charge 224charge 185charge 184charge 231charge 202charge 185charge 184charge 207charge 202charge 204charge 202charge
RWE 187,880
0 0 0 0 0 0 0 0 0 0 0 0
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Charges 498charge 484charge 400charge 396charge 498charge 436charge 400charge 396charge 447charge 436charge 440charge 436charge
141,398
5 4 2 2 5 3 2 2 3 3 3 3
$11,002.41 $9,968.00 $3,169.73 $4,984.00 $11,002.41 $7,902.00 $3,143.13 $4,540.00 $6,636.14 $7,086.00 $7,234.70 $7,086.00
Total Charges 786charge 764charge 631charge 625charge 786charge 687charge 631charge 625charge 705charge 687charge 694charge 687charge
RWE 150,792
7 7 6 6 7 6 6 6 7 6 7 6
$15,403.37 $17,444.00 $9,509.20 $14,952.00 $15,403.37 $15,804.00 $9,429.40 $13,620.00 $15,484.34 $14,172.00 $16,880.96 $14,172.00
Total Charges 1329charge 1292charge 1067charge 1057charge 1329charge 1163charge 1067charge 1057charge 1192charge 1163charge 1174charge 1163charge
RWE 82,472
13 13 11 10 13 12 11 10 12 12 11 12
$28,606.27 $32,396.00 $17,433.54 $24,920.00 $28,606.27 $31,608.00 $17,287.23 $22,700.00 $26,544.58 $28,344.00 $26,527.23 $28,344.00
Total Charges 1255charge 1220charge 1008charge 999charge 1255charge 1098charge 1008charge 999charge 1127charge 1098charge 1110charge 1098charge
RWE 0
3 0 2 0 3 0 2 0 3 0 3 0
$6,601.45 $0.00 $3,169.73 $0.00 $6,601.45 $0.00 $3,143.13 $0.00 $6,636.14 $0.00 $7,234.70 $0.00
Total Charges 1255charge 1220charge 1008charge 999charge 1255charge 1098charge 1008charge 999charge 1127charge 1098charge 1110charge 1098charge
RWE 0
3 0 3 0 3 0 3 0 3 0 3 0
$6,601.45 $0.00 $4,754.60 $0.00 $6,601.45 $0.00 $4,714.70 $0.00 $6,636.14 $0.00 $7,234.70 $0.00
Total Charges 1255charge 1220charge 1008charge 999charge 1255charge 1098charge 1008charge 999charge 1127charge 1098charge 1110charge 1098charge
RWE 0
7 0 5 0 5 0 5 0 5 0 5 0
$15,403.37 $0.00 $7,924.34 $0.00 $11,002.41 $0.00 $7,857.83 $0.00 $11,060.24 $0.00 $12,057.83 $0.00
Total Charges 1255charge 1220charge 1008charge 999charge 1255charge 1098charge 1008charge 999charge 1127charge 1098charge 1110charge 1098charge
RWE 0
7 0 6 0 7 0 6 0 7 0 7 0
$15,403.37 $0.00 $9,509.20 $0.00 $15,403.37 $0.00 $9,429.40 $0.00 $15,484.34 $0.00 $16,880.96 $0.00
ACTUAL RCL M/S PRP S/S RWE M/S RWE S/S
NORMALIZE $0.1940 $0.0720 $0.0570 $0.2670
CARBURIZE $0.3470 $0.0980 $0.0800 $0.3370
2012 2nd~2015 2nd
TOTAL COST
*Repair jig of KANETA timing are every 50 charges . Repair cost of one time need $295 .
*Production number after 2014 1st are forecast
*KNT JIG of life are 200 charges . US JIG of target life are 400 charges (actual result is 212 charges for wheel spindle .
 These have some cruck . But we can still use if fix .)
JIG made by KANETA are -5pcs of capacity for Normalize jig
JIG made by KANETA are -2pcs of capacity for Carborize jig
So US JIG can reduce charge times . But those cost are not include .
$65,306.02 $0.00
$82,110.65 $0.00
$145,005.11 $168,312.00
$33,386.60 $0.00
$36,543.04 $0.00
$0.00 $0.00
$42,188.53 $41,566.00
$82,110.65 $90,164.00
NEW JIG INSTALL COST
KNT US
$98,050.51 $154,896.00
$0.0338 $0.0709 $0.0519
*THIS NUMBER ARE ACTUAL JIG COST BY JUNE,2010. NOT INCLUDE REPAIR JIG COST.
*CAST JIG WILL MAKE JIG COST DOWN.
$0.0392 $0.0478 $0.0771
$0.0437$0.0889
$0.1614 $0.0665
JIG COST/pc
JIG COST/pc
JIG COST/pc
JIG COST/pc
JIG COST
NEED JIG QTY
$0.0376$0.0870$0.0568$0.0608
$0.1189
$0.0535
$0.0744
$0.0464 $0.0520 $0.1309
$0.0698 $0.0977 $0.0425
$0.1367
$0.1271 $0.0916 $0.0619
$0.1240$0.0986$0.0739
$0.1294 $0.1495 $0.0573 $0.1519 $0.1404
$0.0984$0.1141$0.0488$0.1169$0.0907
$0.1555$0.1068
$0.0985
$0.1794
$0.1597 $0.1697 $0.0980
$0.1741$0.1681$0.1023
$0.2012 $0.2054
$0.1557$0.1715$0.0464$0.1598
$0.3921
$0.2166 $0.2586 $0.1235 $0.2243 $0.2166 $0.0554 $0.1226 $0.2090 $0.1882
$1.2919
$0.3220 $0.4757 $0.2292 $0.4757 $0.3220 $0.0665 $0.2274 $0.4450 $0.3262
$1.01 $1.5674 $0.7217 $1.5674 $1.0106 $1.6321 $0.7156 $1.4663
$0.0553
JIG COST/pc
JIG COST/pc
2015
2nd
NEED JIG QTY
6AT
$0.0617$0.0515
$0.0759
JIG COST
2013
2nd
1st
JIG COST
JIG COST
232,416
NEED JIG QTY
2014
JIG COST/pc
JIG COST/pc
NEED JIG QTY
1st
6AT
2nd
6AT
Third Shaft
CarborizeCarborize Normalize Carborize Normalize
Main Shaft Secoundary Shaft
Normalize
Renewal of jig to reaching life(200charges)
Shipping(include item)
NEED JIG QTY
JIG COST
2012
NEED JIG QTY
Production
Number
1st
JIG COST
Jig+Tray/1set
cast die price
137,376
$0.0627JIG COST/pc
6AT
JIG COST
$0.1379
$0.1321
1st
Red mark are Jig cost higer
219,600
219,600
219,600
NEED JIG QTY
JIG COST
NEED JIG QTY
JIG COST
219,600
$0.0493 $0.0683
6AT
6AT
6AT
6AT
$0.1946
$0.1406
$0.0799$0.0567
87,120
NEED JIG QTY
2nd
17,568
unit jig price(not include cast die cost)
$0.1032
2nd
2011
40,320
US JIG
GET COST
DOWN
$6,185
$16,270
$26,755
$29,300
($56,845)
($5,332)
$0.0953 $0.0758
$0.0616$0.0810
$135,662
【Jig cost analysis】
$32,623
$37,604
$49,102
$1.0245 $1.2919 $1.0982
$0.0526 $0.3486
$0.0452
If we use US jig for every parts,
we will get this number cost down.
A complex ROI calculation
represents changing part types
from old model to new model
Idea Annual Impact ($) Idea Item Annual Impact ($)
Reduce gas and electric usage HT Process
Change to SCR type contactors
Reduce Cycle time T/S Lathes 3 4000.00 T/S Cycle time 20000.00
Reduce Cycle time T/S Oil Hole 3000.00 T/S Cycle time 16000.00
Replace Tool checkers with BK micro 0.00 Tool checker 40000.00
Reduce power costs 0.00 Energy
Reduce power costs 0.00 Energy
Rust issue at HPPG
Internal tool grinding (90% Complete) 21000.00 Tool Grinding Energy 63000.00
Replace plant lighting with T-5 Plant Lighting Energy 30000.00
Reduce tooling cost Increase tool life
Ttl. Potential $28,000.00 $169,000.00
Ttl. Sales $/yr $42,000,000.00 $40,000,000.00
0.1% 0.4%
7
Investment
(Tooling & Capital)
Ttl. Potential
Ttl. Sales $/yr
6
Logistics
Packaging
Transportation
3
MachineProc.
4
Assembly
Area
88KI (4/11 ~ 3/12) 89Ki Activity (4/12 ~ 3/13)
Supplier planned cost
improvement action items
18
Supplier Name:Bucyrus Precision Tech, Inc. Originator: Tad Shealy
Part Name: M/S, S/S, T/S Date: 5/13/2011
Item No. Idea Annual Impact ($) Idea Item
Annual Impact
($)
Idea Item
Annual Impact
($)
Localize M/S & S/S Coil Reduce import costs Localize Coil
Reduce gas and electric usage HT Process
Change to SCR type contactors
Reduce Cycle time T/S Lathes 3 4000.00 T/S Cycle time 20000.00 T/S Cycle time 70000.00
Reduce Cycle time T/S Oil Hole 3000.00 T/S Cycle time 16000.00 T/S Cycle time 50000.00
Replace Tool checkers with BK micro 0.00 Tool checker 40000.00 Tool Checker 40000.00
Reduce power costs - Solar 0.00 Solar Power Solar Power
Reduce power costs - Wind 0.00 Wind Power Wind Power
JSPS supply small parts in bulk
instead of daily lot supply
Rust issue at HPPG
Internal tool grinding (90% Complete) 21000.00 Tool Grinding Energy 63000.00 Tool Grinding Energy 63000.00
Replace plant lighting with T-5 Plant Lighting Energy 30000.00 Plant lighting Energy 30000.00
Reduce tooling cost Increase tool life
Ttl. Potential $28,000.00 Ttl. Potential $169,000.00 Ttl. Potential $253,000.00
Ttl. Sales $/yr $42,000,000.00 Ttl. Sales $/yr $40,000,000.00 Ttl. Sales $/yr $45,000,000.00
0.1% 0.4% 0.6%
S.G.A.P.
Investment
(Tooling & Capital)
Inspection & Testing
Purchased
Components
Logistics
Packaging
Transportation
90Ki Activity (4/13 ~ 3/14)
Raw Material
MachineProc.ForgingAssembly
Summary Page 11th Mid-Term Cost Improvement Plan
Area Item
88KI (4/11 ~ 3/12) 89Ki Activity (4/12 ~ 3/13)
Scheduled action items and $$ amount of impact
Identified
opportunity
gaps
Identified Cost Reduction Opportunities – planning
19
Data Integration =
20
2010 6-Year forecast 2016
BPT Long Term Plan
ATM Summary Americas Mid-Term Supply Plan 10-1-071410
Part Daily Averages
KNT KD L4 L4 CRV
BPT L4
RDX 2WD
RDX 4WD
BPT 4Axis TL 4WD
TL 2WD
ODY
MDX
RIDGELINE
Accord V6
Accord V6 ( X-O ) 4WD
Accord V6 ( X-O ) 2WD
Acura V6 ( X-O )
Pilot 4WD
Pilot 2WD
BPT 6AT
BPT M/S & S/S
Total
BPT
Counter
Shaft
Input Shaft
308 162
1432 1600 1400
2919 2794
110 87 87 85 85
T/S Total 144 280 605 954 1614
0
CR-V 4WD
M/S & S/S Total 5AT & 6AT
154 154
1563 1853
0 0
0 000
6AT
R97 C/S
RWE C/S
0
0
209
0 0
0 0 0
RWE Counter Shaft 0
R97 Counter Shaft
6AT Total
ODY 6AT 6AT
B
4Axis BPT total
1292 911
2174
3085 1569
3365
B
B
B
151
326
290 297 267
944
000
973
617 631
122122 120124
1263
29
50
117108
71
277
422
65 63
74
234 271
0 2919 2794
0
0 1327 1242
218 208
6778
176
1450 1508
313
1545
1195 1223
144
1519
3404
300
167
1592
2680
3260
162
85 Ki 08-09M
1st 2nd
124 120
86 Ki 09-10M
1st 2nd 1st
87Ki 10-11M
1st 2nd 2nd
318
0
1241 1088 1741
310
25
465
0
88
0 0
84
2011
0 0 1656 1553
1st
304
89
476
1540
2012
568 727
1289
0
821
88 Ki 11-12M
2nd
Total Counter Shaft
M/S & S/S Total 5AT
DAYS
B
B
B
L4 CR-V 4WD (BPT Localize)
2680
2008
0
2009 2010
89 Ki 12-13M
289281
0
686
122 122
646
0
0
0
1154 0
0 0
323
36
410
102 102
44 44
1545
24
342
50 98
0
89
281
0
108
13
87
456483
33
0
00
0
327 327
134 132
467
280 605
73 73
171 155
86
1159
B
B
B
B
( L4 total )
L4 Element
L4 Accord
L4 CR-V 2WD
L4 Acc CT 2WD
B
B
122 122
131
101 89
86
0 0
364 351
774 746
0 0
43 43
102 102
0 0
449 436
523
259 259
0 0
33 205
85 85
69 69
76 76
370 370
169 156
314 290
954 1614
1236 676
147 635
1685 1112
1039 446
27262639
2013
91 Ki 14-15M
1st 2nd
90 Ki 13-14M
1st 2nd
122 122
0 0
0 0
0 0
2014
0 0
0 0
0 0RV2A Counter Shaft 327 370 1253
1211I/S TotalAccord CVT 1220 1369
0
KNT US KNT US KNT US KNT US KNT US KNT US
¥12,500 $7,600.00 ¥0 $7,600.00 ¥12,500 $7,600.00 ¥0 $7,600.00 ¥25,000 $3,800.00 ¥0 $3,800.00
¥152,200 $2,492.00 ¥109,620 $2,492.00 ¥152,200 $2,634.00 ¥108,700 $2,270.00 ¥153,000 $2,362.00 ¥166,800 $2,362.00
¥182,640 - ¥131,544 - ¥182,640 - ¥130,440 - ¥183,600 - ¥200,160 -
$2,200.49 $1,584.87 $2,200.49 $1,571.57 $2,212.05 $2,411.57
¥83/$ ¥83/$ ¥83/$ ¥83/$ ¥83/$ ¥83/$
175 180 218 220 175 200 218 220 195 200 198 200
Total Charges 101charge 98charge 81charge 80charge 101charge 88charge 81charge 80charge 91charge 88charge 89charge 88charge
RWE 185,318
8 8 8 8 8 8 8 8 8 8 8 8
$17,754.46 $27,536.00 $12,678.94 $27,536.00 $17,754.46 $28,672.00 $12,572.53 $25,760.00 $17,997.59 $22,696.00 $19,292.53 $22,696.00
Total Charges 231charge 224charge 185charge 184charge 231charge 202charge 185charge 184charge 207charge 202charge 204charge 202charge
RWE 187,880
0 0 0 0 0 0 0 0 0 0 0 0
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Charges 498charge 484charge 400charge 396charge 498charge 436charge 400charge 396charge 447charge 436charge 440charge 436charge
141,398
5 4 2 2 5 3 2 2 3 3 3 3
$11,002.41 $9,968.00 $3,169.73 $4,984.00 $11,002.41 $7,902.00 $3,143.13 $4,540.00 $6,636.14 $7,086.00 $7,234.70 $7,086.00
Total Charges 786charge 764charge 631charge 625charge 786charge 687charge 631charge 625charge 705charge 687charge 694charge 687charge
RWE 150,792
7 7 6 6 7 6 6 6 7 6 7 6
$15,403.37 $17,444.00 $9,509.20 $14,952.00 $15,403.37 $15,804.00 $9,429.40 $13,620.00 $15,484.34 $14,172.00 $16,880.96 $14,172.00
Total Charges 1329charge 1292charge 1067charge 1057charge 1329charge 1163charge 1067charge 1057charge 1192charge 1163charge 1174charge 1163charge
RWE 82,472
13 13 11 10 13 12 11 10 12 12 11 12
$28,606.27 $32,396.00 $17,433.54 $24,920.00 $28,606.27 $31,608.00 $17,287.23 $22,700.00 $26,544.58 $28,344.00 $26,527.23 $28,344.00
Total Charges 1255charge 1220charge 1008charge 999charge 1255charge 1098charge 1008charge 999charge 1127charge 1098charge 1110charge 1098charge
RWE 0
3 0 2 0 3 0 2 0 3 0 3 0
$6,601.45 $0.00 $3,169.73 $0.00 $6,601.45 $0.00 $3,143.13 $0.00 $6,636.14 $0.00 $7,234.70 $0.00
Total Charges 1255charge 1220charge 1008charge 999charge 1255charge 1098charge 1008charge 999charge 1127charge 1098charge 1110charge 1098charge
RWE 0
3 0 3 0 3 0 3 0 3 0 3 0
$6,601.45 $0.00 $4,754.60 $0.00 $6,601.45 $0.00 $4,714.70 $0.00 $6,636.14 $0.00 $7,234.70 $0.00
Total Charges 1255charge 1220charge 1008charge 999charge 1255charge 1098charge 1008charge 999charge 1127charge 1098charge 1110charge 1098charge
RWE 0
7 0 5 0 5 0 5 0 5 0 5 0
$15,403.37 $0.00 $7,924.34 $0.00 $11,002.41 $0.00 $7,857.83 $0.00 $11,060.24 $0.00 $12,057.83 $0.00
Total Charges 1255charge 1220charge 1008charge 999charge 1255charge 1098charge 1008charge 999charge 1127charge 1098charge 1110charge 1098charge
RWE 0
7 0 6 0 7 0 6 0 7 0 7 0
$15,403.37 $0.00 $9,509.20 $0.00 $15,403.37 $0.00 $9,429.40 $0.00 $15,484.34 $0.00 $16,880.96 $0.00
ACTUAL RCL M/S PRP S/S RWE M/S RWE S/S
NORMALIZE $0.1940 $0.0720 $0.0570 $0.2670
CARBURIZE $0.3470 $0.0980 $0.0800 $0.3370
2012 2nd~2015 2nd
TOTAL COST
*Repair jig of KANETA timing are every 50 charges . Repair cost of one time need $295 .
*Production number after 2014 1st are forecast
*KNT JIG of life are 200 charges . US JIG of target life are 400 charges (actual result is 212 charges for wheel spindle .
 These have some cruck . But we can still use if fix .)
JIG made by KANETA are -5pcs of capacity for Normalize jig
JIG made by KANETA are -2pcs of capacity for Carborize jig
So US JIG can reduce charge times . But those cost are not include .
$65,306.02 $0.00
$82,110.65 $0.00
$145,005.11 $168,312.00
$33,386.60 $0.00
$36,543.04 $0.00
$0.00 $0.00
$42,188.53 $41,566.00
$82,110.65 $90,164.00
NEW JIG INSTALL COST
KNT US
$98,050.51 $154,896.00
$0.0338 $0.0709 $0.0519
*THIS NUMBER ARE ACTUAL JIG COST BY JUNE,2010. NOT INCLUDE REPAIR JIG COST.
*CAST JIG WILL MAKE JIG COST DOWN.
$0.0392 $0.0478 $0.0771
$0.0437$0.0889
$0.1614 $0.0665
JIG COST/pc
JIG COST/pc
JIG COST/pc
JIG COST/pc
JIG COST
NEED JIG QTY
$0.0376$0.0870$0.0568$0.0608
$0.1189
$0.0535
$0.0744
$0.0464 $0.0520 $0.1309
$0.0698 $0.0977 $0.0425
$0.1367
$0.1271 $0.0916 $0.0619
$0.1240$0.0986$0.0739
$0.1294 $0.1495 $0.0573 $0.1519 $0.1404
$0.0984$0.1141$0.0488$0.1169$0.0907
$0.1555$0.1068
$0.0985
$0.1794
$0.1597 $0.1697 $0.0980
$0.1741$0.1681$0.1023
$0.2012 $0.2054
$0.1557$0.1715$0.0464$0.1598
$0.3921
$0.2166 $0.2586 $0.1235 $0.2243 $0.2166 $0.0554 $0.1226 $0.2090 $0.1882
$1.2919
$0.3220 $0.4757 $0.2292 $0.4757 $0.3220 $0.0665 $0.2274 $0.4450 $0.3262
$1.01 $1.5674 $0.7217 $1.5674 $1.0106 $1.6321 $0.7156 $1.4663
$0.0553
JIG COST/pc
JIG COST/pc
2015
2nd
NEED JIG QTY
6AT
$0.0617$0.0515
$0.0759
JIG COST
2013
2nd
1st
JIG COST
JIG COST
232,416
NEED JIG QTY
2014
JIG COST/pc
JIG COST/pc
NEED JIG QTY
1st
6AT
2nd
6AT
Third Shaft
CarborizeCarborize Normalize Carborize Normalize
Main Shaft Secoundary Shaft
Normalize
Renewal of jig to reaching life(200charges)
Shipping(include item)
NEED JIG QTY
JIG COST
2012
NEED JIG QTY
Production
Number
1st
JIG COST
Jig+Tray/1set
cast die price
137,376
$0.0627JIG COST/pc
6AT
JIG COST
$0.1379
$0.1321
1st
Red mark are Jig cost higer
219,600
219,600
219,600
NEED JIG QTY
JIG COST
NEED JIG QTY
JIG COST
219,600
$0.0493 $0.0683
6AT
6AT
6AT
6AT
$0.1946
$0.1406
$0.0799$0.0567
87,120
NEED JIG QTY
2nd
17,568
unit jig price(not include cast die cost)
$0.1032
2nd
2011
40,320
US JIG
GET COST
DOWN
$6,185
$16,270
$26,755
$29,300
($56,845)
($5,332)
$0.0953 $0.0758
$0.0616$0.0810
$135,662
【Jig cost analysis】
$32,623
$37,604
$49,102
$1.0245 $1.2919 $1.0982
$0.0526 $0.3486
$0.0452
If we use US jig for every parts,
we will get this number cost down.
Supplier Name:Bucyrus Precision Tech, Inc. Originator: Tad Shealy
Part Name: M/S, S/S, T/S Date: 5/13/2011
Item No. Idea Annual Impact ($) Idea Item
Annual Impact
($)
Idea Item
Annual Impact
($)
Localize M/S & S/S Coil Reduce import costs Localize Coil
Reduce gas and electric usage HT Process
Change to SCR type contactors
Reduce Cycle time T/S Lathes 3 4000.00 T/S Cycle time 20000.00 T/S Cycle time 70000.00
Reduce Cycle time T/S Oil Hole 3000.00 T/S Cycle time 16000.00 T/S Cycle time 50000.00
Replace Tool checkers with BK micro 0.00 Tool checker 40000.00 Tool Checker 40000.00
Reduce power costs - Solar 0.00 Solar Power Solar Power
Reduce power costs - Wind 0.00 Wind Power Wind Power
JSPS supply small parts in bulk
instead of daily lot supply
Rust issue at HPPG
Internal tool grinding (90% Complete) 21000.00 Tool Grinding Energy 63000.00 Tool Grinding Energy 63000.00
Replace plant lighting with T-5 Plant Lighting Energy 30000.00 Plant lighting Energy 30000.00
Reduce tooling cost Increase tool life
Ttl. Potential $28,000.00 Ttl. Potential $169,000.00 Ttl. Potential $253,000.00
Ttl. Sales $/yr $42,000,000.00 Ttl. Sales $/yr $40,000,000.00 Ttl. Sales $/yr $45,000,000.00
0.1% 0.4% 0.6%
S.G.A.P.
Investment
(Tooling & Capital)
Inspection & Testing
Purchased
Components
Logistics
Packaging
Transportation
90Ki Activity (4/13 ~ 3/14)
Raw Material
MachineProc.ForgingAssembly
Summary Page 11th Mid-Term Cost Improvement Plan
Area Item
88KI (4/11 ~ 3/12) 89Ki Activity (4/12 ~ 3/13)
Piece price reduction
from innovation
incorporation
Forecast data
ROI presentation
Identified
opportunities
Project planning
• The products and services provided will
help you achieve your cost improvement
objectives.
• Example:
• Using the research methodologies, we can
provide support in the following areas:
• Identified opportunities
• ROI presentation
• Project planning
21
• Contact Information:
• Jason Gallion
• Phone +1 (614) 286-5142
• Email: Info@Epicpwr.com
Thank You!
22

Contenu connexe

Tendances

Brunswick (BC) Pitch - Jonathan Chang - FINAL COPY
Brunswick (BC) Pitch - Jonathan Chang - FINAL COPYBrunswick (BC) Pitch - Jonathan Chang - FINAL COPY
Brunswick (BC) Pitch - Jonathan Chang - FINAL COPY
Jonathan Chang
 
FIN 667 Hershey Valuation PPT- Final
FIN 667 Hershey Valuation PPT- FinalFIN 667 Hershey Valuation PPT- Final
FIN 667 Hershey Valuation PPT- Final
Lisa Lee
 
Results presentation 4 q12
Results presentation 4 q12Results presentation 4 q12
Results presentation 4 q12
comgasri
 
Gibson-Energy-Stock-Pitch
Gibson-Energy-Stock-PitchGibson-Energy-Stock-Pitch
Gibson-Energy-Stock-Pitch
Yousuf Aziz
 
Institucional 2 q14 padrão 2014 eng
Institucional 2 q14 padrão 2014   engInstitucional 2 q14 padrão 2014   eng
Institucional 2 q14 padrão 2014 eng
EquatorialRI
 
Copic sketch markers page color chart
Copic sketch markers page color chartCopic sketch markers page color chart
Copic sketch markers page color chart
simplyscrapping
 

Tendances (20)

Wipro – Ratio Analysis
Wipro – Ratio AnalysisWipro – Ratio Analysis
Wipro – Ratio Analysis
 
Dish TV: TRAI licence recos EBITDA positive but cash negative; Buy
Dish TV: TRAI licence recos EBITDA positive but cash negative; BuyDish TV: TRAI licence recos EBITDA positive but cash negative; Buy
Dish TV: TRAI licence recos EBITDA positive but cash negative; Buy
 
Tata Motors – Ratio Analysis
Tata Motors – Ratio AnalysisTata Motors – Ratio Analysis
Tata Motors – Ratio Analysis
 
William Blair 2017 Growth Stock Conference
William Blair 2017 Growth Stock ConferenceWilliam Blair 2017 Growth Stock Conference
William Blair 2017 Growth Stock Conference
 
Estimate Summary Example
Estimate Summary ExampleEstimate Summary Example
Estimate Summary Example
 
Brunswick (BC) Pitch - Jonathan Chang - FINAL COPY
Brunswick (BC) Pitch - Jonathan Chang - FINAL COPYBrunswick (BC) Pitch - Jonathan Chang - FINAL COPY
Brunswick (BC) Pitch - Jonathan Chang - FINAL COPY
 
FIN 667 Hershey Valuation PPT- Final
FIN 667 Hershey Valuation PPT- FinalFIN 667 Hershey Valuation PPT- Final
FIN 667 Hershey Valuation PPT- Final
 
Third Quarter 2014 Global ISG Outsourcing Index
Third Quarter 2014 Global ISG Outsourcing IndexThird Quarter 2014 Global ISG Outsourcing Index
Third Quarter 2014 Global ISG Outsourcing Index
 
So You Want to be a Forensic CPA?
So You Want to be a Forensic CPA?So You Want to be a Forensic CPA?
So You Want to be a Forensic CPA?
 
Fourth Quarter and Full Year 2013 Global ISG Outsourcing Index
Fourth Quarter and Full Year 2013 Global ISG Outsourcing IndexFourth Quarter and Full Year 2013 Global ISG Outsourcing Index
Fourth Quarter and Full Year 2013 Global ISG Outsourcing Index
 
MF
MFMF
MF
 
TCC Stock Pitch
TCC Stock PitchTCC Stock Pitch
TCC Stock Pitch
 
Third Quarter 2013 Global ISG Outsourcing Index
Third Quarter 2013 Global ISG Outsourcing IndexThird Quarter 2013 Global ISG Outsourcing Index
Third Quarter 2013 Global ISG Outsourcing Index
 
Tata Sponge: Q1 Net grows a whopping 145.45%, buy
Tata Sponge: Q1 Net grows a whopping 145.45%, buyTata Sponge: Q1 Net grows a whopping 145.45%, buy
Tata Sponge: Q1 Net grows a whopping 145.45%, buy
 
Results presentation 4 q12
Results presentation 4 q12Results presentation 4 q12
Results presentation 4 q12
 
Fourth Quarter and Full Year 2013 ISG EMEA Outsourcing Index
Fourth Quarter and Full Year 2013 ISG EMEA Outsourcing IndexFourth Quarter and Full Year 2013 ISG EMEA Outsourcing Index
Fourth Quarter and Full Year 2013 ISG EMEA Outsourcing Index
 
Gibson-Energy-Stock-Pitch
Gibson-Energy-Stock-PitchGibson-Energy-Stock-Pitch
Gibson-Energy-Stock-Pitch
 
Equity Research Report 09 October 2018 Ways2Capital
Equity Research Report  09 October 2018 Ways2CapitalEquity Research Report  09 October 2018 Ways2Capital
Equity Research Report 09 October 2018 Ways2Capital
 
Institucional 2 q14 padrão 2014 eng
Institucional 2 q14 padrão 2014   engInstitucional 2 q14 padrão 2014   eng
Institucional 2 q14 padrão 2014 eng
 
Copic sketch markers page color chart
Copic sketch markers page color chartCopic sketch markers page color chart
Copic sketch markers page color chart
 

En vedette

Higher Education in crisis - Role of OER, GUIDE Conference 2013
Higher Education in crisis - Role of OER, GUIDE Conference 2013Higher Education in crisis - Role of OER, GUIDE Conference 2013
Higher Education in crisis - Role of OER, GUIDE Conference 2013
Rosemary Juma
 
OER Africa A Health OER Case Study
OER Africa   A Health OER Case StudyOER Africa   A Health OER Case Study
OER Africa A Health OER Case Study
Rosemary Juma
 
Edwin murphy portfolio prezie
Edwin murphy portfolio prezieEdwin murphy portfolio prezie
Edwin murphy portfolio prezie
Edwin Murphy
 
Opening higher education in Africa OER and MOOCs
Opening higher education in Africa OER and MOOCsOpening higher education in Africa OER and MOOCs
Opening higher education in Africa OER and MOOCs
Rosemary Juma
 
Ama american medical association
Ama  american medical associationAma  american medical association
Ama american medical association
MrDBender
 
Higher Education in crisis: Role of OER as an equalizer - GUIDE Conference 20...
Higher Education in crisis: Role of OER as an equalizer - GUIDE Conference 20...Higher Education in crisis: Role of OER as an equalizer - GUIDE Conference 20...
Higher Education in crisis: Role of OER as an equalizer - GUIDE Conference 20...
Rosemary Juma
 
πειραματικό μοντέλο πολυτραυματία
πειραματικό μοντέλο πολυτραυματίαπειραματικό μοντέλο πολυτραυματία
πειραματικό μοντέλο πολυτραυματία
stefanos koutsostathis
 
Поколения Y и менеджмент свободы. Марк Розин
Поколения Y и менеджмент свободы. Марк РозинПоколения Y и менеджмент свободы. Марк Розин
Поколения Y и менеджмент свободы. Марк Розин
Kseniya Pegushina
 

En vedette (16)

Public citizen (Arial Elsey)
Public citizen (Arial Elsey)Public citizen (Arial Elsey)
Public citizen (Arial Elsey)
 
First
FirstFirst
First
 
Higher Education in crisis - Role of OER, GUIDE Conference 2013
Higher Education in crisis - Role of OER, GUIDE Conference 2013Higher Education in crisis - Role of OER, GUIDE Conference 2013
Higher Education in crisis - Role of OER, GUIDE Conference 2013
 
παρουσίαση επιλεγμένων περιστατικών χειρουργικής αντιμετώπισης καταγμάτων
παρουσίαση επιλεγμένων περιστατικών χειρουργικής αντιμετώπισης καταγμάτωνπαρουσίαση επιλεγμένων περιστατικών χειρουργικής αντιμετώπισης καταγμάτων
παρουσίαση επιλεγμένων περιστατικών χειρουργικής αντιμετώπισης καταγμάτων
 
OER Africa A Health OER Case Study
OER Africa   A Health OER Case StudyOER Africa   A Health OER Case Study
OER Africa A Health OER Case Study
 
Edwin murphy portfolio prezie
Edwin murphy portfolio prezieEdwin murphy portfolio prezie
Edwin murphy portfolio prezie
 
Opening higher education in Africa OER and MOOCs
Opening higher education in Africa OER and MOOCsOpening higher education in Africa OER and MOOCs
Opening higher education in Africa OER and MOOCs
 
Ama american medical association
Ama  american medical associationAma  american medical association
Ama american medical association
 
Ama american medical association
Ama  american medical associationAma  american medical association
Ama american medical association
 
Ig research project 2016
Ig research project 2016Ig research project 2016
Ig research project 2016
 
Higher Education in crisis: Role of OER as an equalizer - GUIDE Conference 20...
Higher Education in crisis: Role of OER as an equalizer - GUIDE Conference 20...Higher Education in crisis: Role of OER as an equalizer - GUIDE Conference 20...
Higher Education in crisis: Role of OER as an equalizer - GUIDE Conference 20...
 
Jhoanny a. suarez g.
Jhoanny a. suarez g.Jhoanny a. suarez g.
Jhoanny a. suarez g.
 
πειραματικό μοντέλο πολυτραυματία
πειραματικό μοντέλο πολυτραυματίαπειραματικό μοντέλο πολυτραυματία
πειραματικό μοντέλο πολυτραυματία
 
Поколения Y и менеджмент свободы. Марк Розин
Поколения Y и менеджмент свободы. Марк РозинПоколения Y и менеджмент свободы. Марк Розин
Поколения Y и менеджмент свободы. Марк Розин
 
Placa mãe e seus componentes
Placa mãe e seus componentesPlaca mãe e seus componentes
Placa mãe e seus componentes
 
General Electric Presentation
General Electric PresentationGeneral Electric Presentation
General Electric Presentation
 

Similaire à Cost Improvement EPIC

Z Ships Presentation Oct 2015
Z Ships Presentation Oct 2015Z Ships Presentation Oct 2015
Z Ships Presentation Oct 2015
Laurent H Selles
 
Diamond Chemicals
Diamond ChemicalsDiamond Chemicals
Diamond Chemicals
jsilmon
 
2015 Denbury Presentation
2015 Denbury Presentation2015 Denbury Presentation
2015 Denbury Presentation
Perry Hawks
 
Seamless Pipes and Tubes - Market Survey cum Detailed Techno Economic Feasibi...
Seamless Pipes and Tubes - Market Survey cum Detailed Techno Economic Feasibi...Seamless Pipes and Tubes - Market Survey cum Detailed Techno Economic Feasibi...
Seamless Pipes and Tubes - Market Survey cum Detailed Techno Economic Feasibi...
Ajjay Kumar Gupta
 
Final Team BACAT (wk 16) power point
Final Team BACAT (wk 16) power pointFinal Team BACAT (wk 16) power point
Final Team BACAT (wk 16) power point
Brandon Dobson
 
NRB Bearings Ltd. - Company Valuation and Investment Recommendation
NRB Bearings Ltd. - Company Valuation and Investment RecommendationNRB Bearings Ltd. - Company Valuation and Investment Recommendation
NRB Bearings Ltd. - Company Valuation and Investment Recommendation
Ankur Agarwal
 

Similaire à Cost Improvement EPIC (20)

Z Ships Presentation Oct 2015
Z Ships Presentation Oct 2015Z Ships Presentation Oct 2015
Z Ships Presentation Oct 2015
 
Boeing Case Competition | Second Place
Boeing Case Competition | Second Place Boeing Case Competition | Second Place
Boeing Case Competition | Second Place
 
77565239 13-cost-benefit-analysis
77565239 13-cost-benefit-analysis77565239 13-cost-benefit-analysis
77565239 13-cost-benefit-analysis
 
Corporate Overview
Corporate OverviewCorporate Overview
Corporate Overview
 
Lkq corporation bairds 2017 global consumer technology and services conference
Lkq corporation bairds 2017 global consumer technology and services conferenceLkq corporation bairds 2017 global consumer technology and services conference
Lkq corporation bairds 2017 global consumer technology and services conference
 
Diamond Chemicals
Diamond ChemicalsDiamond Chemicals
Diamond Chemicals
 
May 2018 Investor Conference Presentation 2018
May 2018 Investor Conference Presentation 2018May 2018 Investor Conference Presentation 2018
May 2018 Investor Conference Presentation 2018
 
Magenta 3.5
Magenta 3.5Magenta 3.5
Magenta 3.5
 
Capital budgeting Slideshow for new product peneration
Capital budgeting Slideshow for new product penerationCapital budgeting Slideshow for new product peneration
Capital budgeting Slideshow for new product peneration
 
Exhibit 99.2 q3 2016 investor deck final
Exhibit 99.2   q3 2016 investor deck finalExhibit 99.2   q3 2016 investor deck final
Exhibit 99.2 q3 2016 investor deck final
 
Fixed Capital Analysis PowerPoint Presentation Slides
Fixed Capital Analysis PowerPoint Presentation SlidesFixed Capital Analysis PowerPoint Presentation Slides
Fixed Capital Analysis PowerPoint Presentation Slides
 
Berger
BergerBerger
Berger
 
2015 Denbury Presentation
2015 Denbury Presentation2015 Denbury Presentation
2015 Denbury Presentation
 
Power financials - how we work
Power financials - how we workPower financials - how we work
Power financials - how we work
 
Keeping PACE With Energy Efficiency in North America
Keeping PACE With Energy Efficiency in North AmericaKeeping PACE With Energy Efficiency in North America
Keeping PACE With Energy Efficiency in North America
 
Seamless Pipes and Tubes - Market Survey cum Detailed Techno Economic Feasibi...
Seamless Pipes and Tubes - Market Survey cum Detailed Techno Economic Feasibi...Seamless Pipes and Tubes - Market Survey cum Detailed Techno Economic Feasibi...
Seamless Pipes and Tubes - Market Survey cum Detailed Techno Economic Feasibi...
 
Final Team BACAT (wk 16) power point
Final Team BACAT (wk 16) power pointFinal Team BACAT (wk 16) power point
Final Team BACAT (wk 16) power point
 
Westport Corporate Overview
Westport Corporate OverviewWestport Corporate Overview
Westport Corporate Overview
 
NRB Bearings Ltd. - Company Valuation and Investment Recommendation
NRB Bearings Ltd. - Company Valuation and Investment RecommendationNRB Bearings Ltd. - Company Valuation and Investment Recommendation
NRB Bearings Ltd. - Company Valuation and Investment Recommendation
 
Tegtora final
Tegtora finalTegtora final
Tegtora final
 

Cost Improvement EPIC

  • 1. Integrating technology providers into the cost improvement plan E.P.I.C. Inc. EPICPWR.COM An Action Plan For The Automotive Industry Presented & Prepared by Jason Gallion A budget and planning proposal
  • 2. Let’s go beyond traditional methods in which others generate cost reduction techniques. 2010 6-Year forecast 2016 Piece Price Reduction
  • 3. It’s time to go beyond even the most advanced supplier collaboration and innovative models and invite strategic innovation opportunities Forecast data ROI Presentation Identified opportunities Project Planning Innovative Technology Welding & Drilling Solutions Advanced materials OEM & their Suppliers Opportunities Solutions Process Control Solutions
  • 4. The OEM Supplier Relationship The Purpose is to fund innovation through mutual benefits. The Objective is the alignment of cost reduction Technology and cost improvement requirements. The Mission is to provide new cost improvement opportunities. 4
  • 5. Mandatory 3% annual cost reduction Supplier Supplier Supplier OEM $96 Million Annually 47 Suppliers
  • 6. 47 suppliers $3.2 Billion Annual Sales $96 Million Annual cost reduction $27 Million Annual expenditures To meet the OEM’s cost reduction requirements, 47 suppliers will reduce their annual sales by 3% Approximately *$27 Million allocated to meet the demand. *$27M Allocated to cost improvement projects $96M Cost reduction *Based on average cost improvement projects recorded during supplier survey 6
  • 8. OEM’s influence 8 Influence on process improvement... little with capital investment Existing collaboration relationships limited to process improvement. Even today, some suppliers resist or are reluctant to embrace influence from OEM
  • 9. -Δ% Cost Reduction Target OEM’s Problem… Supplier Base Condition Suppliers individual effort 9 Solution Categories: Raw Materials Material processing Machining Assembly Packaging / Transportation Tooling & Capital Inspection & Testing
  • 10. The Assured Cost Improvement Plan 10 “We must begin to collaborate at an even greater level to achieve momentous cost reduction goals.”
  • 11. • Supplier Survey • Use forecast data…To, and when to consider three year forecast and six year forecast • Required cost reduction items • Create piece price reduction targets What you need to do… 11
  • 12. Supplier Supplier Supplier Supplier Supplier 3% Mandatory Cost Reduction Cost reduction Met with actual cost improvement projects Current State… The goal The Goal Supplier 12
  • 13. The cost improvement platform Forecast data ROI Presentation Identified opportunities Project Planning Solution Categories: Raw Materials Material processing Machining Assembly Packaging / Transportation Tooling & Capital Inspection & Testing Innovative Technology Welding & Drilling Solutions High temp insulation materials OEM & their Suppliers Cost Improvement Opportunities Technology Providers Cost reduction requirements Opportunities Solutions Process Control Solutions 13
  • 14. Supplier Survey Based on annual cost improvement requirements an estimated $27 million should be allocated towards cost improvement expenditures, to meet the annual 3% cost reduction. 14
  • 15. Supplier survey, data intelligence 15
  • 16. Forecast Data, 3-6 Year Plan 16 BPT Long Term Plan ATM Summary Americas Mid-Term Supply Plan 10-1-071410 Part Daily Averages KNT KD L4 L4 CRV BPT L4 RDX 2WD RDX 4WD BPT 4Axis TL 4WD TL 2WD ODY MDX RIDGELINE Accord V6 Accord V6 ( X-O ) 4WD Accord V6 ( X-O ) 2WD Acura V6 ( X-O ) Pilot 4WD Pilot 2WD BPT 6AT BPT M/S & S/S Total 110 87 87 85 85 0 0 6AT Total ODY 6AT 6AT B 4Axis BPT total 3085 1569 B B B 151 326 290 297 267 944 000 973 617 631 122122 120124 1263 29 50 117108 71 277 422 65 63 74 234 271 0 2919 2794 6778 176 144 1519 300 167 1592 3260 162 85 Ki 08-09M 1st 2nd 124 120 86 Ki 09-10M 1st 2nd 1st 87Ki 10-11M 1st 2nd 2nd 318 0 1241 1088 1741 310 25 465 0 88 0 0 84 2011 0 0 1656 1553 1st 304 89 476 1540 2012 568 727 1289 0 821 88 Ki 11-12M 2nd M/S & S/S Total 5AT DAYS B B B L4 CR-V 4WD (BPT Localize) 2680 2008 0 2009 2010 89 Ki 12-13M 289281 0 686 122 122 646 0 0 0 1154 0 0 0 323 36 410 102 102 44 44 1545 24 342 50 98 0 89 281 0 108 13 87 456483 33 0 00 0 327 327 134 132 467 280 605 73 73 171 155 86 1159 B B B B ( L4 total ) L4 Element L4 Accord L4 CR-V 2WD L4 Acc CT 2WD B B 122 122 131 101 89 86 0 0 364 351 774 746 0 0 43 43 102 102 0 0 449 436 523 259 259 0 0 33 205 85 85 69 69 76 76 370 370 169 156 314 290 954 1614 1236 676 147 635 1685 1112 2013 91 Ki 14-15M 1st 2nd 90 Ki 13-14M 1st 2nd 122 122 0 0 0 0 0 0 2014 0 0 BPT Long Term Plan ATM Summary Americas Mid-Term Supply Plan 10-1-071410 Part Daily Averages KNT KD L4 L4 CRV BPT L4 RDX 2WD RDX 4WD BPT 4Axis TL 4WD TL 2WD ODY MDX RIDGELINE Accord V6 Accord V6 ( X-O ) 4WD Accord V6 ( X-O ) 2WD Acura V6 ( X-O ) Pilot 4WD Pilot 2WD BPT 6AT BPT M/S & S/S Total BPT Counter Shaft Input Shaft 308 162 1432 1600 1400 2919 2794 110 87 87 85 85 T/S Total 144 280 605 954 1614 0 CR-V 4WD M/S & S/S Total 5AT & 6AT 154 154 1563 1853 0 0 0 000 6AT R97 C/S RWE C/S 0 0 209 0 0 0 0 0 RWE Counter Shaft 0 R97 Counter Shaft 6AT Total ODY 6AT 6AT B 4Axis BPT total 1292 911 2174 3085 1569 3365 B B B 151 326 290 297 267 944 000 973 617 631 122122 120124 1263 29 50 117108 71 277 422 65 63 74 234 271 0 2919 2794 0 0 1327 1242 218 208 6778 176 1450 1508 313 1545 1195 1223 144 1519 3404 300 167 1592 2680 3260 162 85 Ki 08-09M 1st 2nd 124 120 86 Ki 09-10M 1st 2nd 1st 87Ki 10-11M 1st 2nd 2nd 318 0 1241 1088 1741 310 25 465 0 88 0 0 84 2011 0 0 1656 1553 1st 304 89 476 1540 2012 568 727 1289 0 821 88 Ki 11-12M 2nd Total Counter Shaft M/S & S/S Total 5AT DAYS B B B L4 CR-V 4WD (BPT Localize) 2680 2008 0 2009 2010 89 Ki 12-13M 289281 0 686 122 122 646 0 0 0 1154 0 0 0 323 36 410 102 102 44 44 1545 24 342 50 98 0 89 281 0 108 13 87 456483 33 0 00 0 327 327 134 132 467 280 605 73 73 171 155 86 1159 B B B B ( L4 total ) L4 Element L4 Accord L4 CR-V 2WD L4 Acc CT 2WD B B 122 122 131 101 89 86 0 0 364 351 774 746 0 0 43 43 102 102 0 0 449 436 523 259 259 0 0 33 205 85 85 69 69 76 76 370 370 169 156 314 290 954 1614 1236 676 147 635 1685 1112 1039 446 27262639 2013 91 Ki 14-15M 1st 2nd 90 Ki 13-14M 1st 2nd 122 122 0 0 0 0 0 0 2014 0 0 0 0 0 0RV2A Counter Shaft 327 370 1253 1211I/S TotalAccord CVT 1220 1369 0 Expected parts to Mfg every year, production forecast
  • 17. ROI Calculations 17 KNT US KNT US KNT US KNT US KNT US KNT US ¥12,500 $7,600.00 ¥0 $7,600.00 ¥12,500 $7,600.00 ¥0 $7,600.00 ¥25,000 $3,800.00 ¥0 $3,800.00 ¥152,200 $2,492.00 ¥109,620 $2,492.00 ¥152,200 $2,634.00 ¥108,700 $2,270.00 ¥153,000 $2,362.00 ¥166,800 $2,362.00 ¥182,640 - ¥131,544 - ¥182,640 - ¥130,440 - ¥183,600 - ¥200,160 - $2,200.49 $1,584.87 $2,200.49 $1,571.57 $2,212.05 $2,411.57 ¥83/$ ¥83/$ ¥83/$ ¥83/$ ¥83/$ ¥83/$ 175 180 218 220 175 200 218 220 195 200 198 200 Total Charges 101charge 98charge 81charge 80charge 101charge 88charge 81charge 80charge 91charge 88charge 89charge 88charge RWE 185,318 8 8 8 8 8 8 8 8 8 8 8 8 $17,754.46 $27,536.00 $12,678.94 $27,536.00 $17,754.46 $28,672.00 $12,572.53 $25,760.00 $17,997.59 $22,696.00 $19,292.53 $22,696.00 Total Charges 231charge 224charge 185charge 184charge 231charge 202charge 185charge 184charge 207charge 202charge 204charge 202charge RWE 187,880 0 0 0 0 0 0 0 0 0 0 0 0 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Charges 498charge 484charge 400charge 396charge 498charge 436charge 400charge 396charge 447charge 436charge 440charge 436charge 141,398 5 4 2 2 5 3 2 2 3 3 3 3 $11,002.41 $9,968.00 $3,169.73 $4,984.00 $11,002.41 $7,902.00 $3,143.13 $4,540.00 $6,636.14 $7,086.00 $7,234.70 $7,086.00 Total Charges 786charge 764charge 631charge 625charge 786charge 687charge 631charge 625charge 705charge 687charge 694charge 687charge RWE 150,792 7 7 6 6 7 6 6 6 7 6 7 6 $15,403.37 $17,444.00 $9,509.20 $14,952.00 $15,403.37 $15,804.00 $9,429.40 $13,620.00 $15,484.34 $14,172.00 $16,880.96 $14,172.00 Total Charges 1329charge 1292charge 1067charge 1057charge 1329charge 1163charge 1067charge 1057charge 1192charge 1163charge 1174charge 1163charge RWE 82,472 13 13 11 10 13 12 11 10 12 12 11 12 $28,606.27 $32,396.00 $17,433.54 $24,920.00 $28,606.27 $31,608.00 $17,287.23 $22,700.00 $26,544.58 $28,344.00 $26,527.23 $28,344.00 Total Charges 1255charge 1220charge 1008charge 999charge 1255charge 1098charge 1008charge 999charge 1127charge 1098charge 1110charge 1098charge RWE 0 3 0 2 0 3 0 2 0 3 0 3 0 $6,601.45 $0.00 $3,169.73 $0.00 $6,601.45 $0.00 $3,143.13 $0.00 $6,636.14 $0.00 $7,234.70 $0.00 Total Charges 1255charge 1220charge 1008charge 999charge 1255charge 1098charge 1008charge 999charge 1127charge 1098charge 1110charge 1098charge RWE 0 3 0 3 0 3 0 3 0 3 0 3 0 $6,601.45 $0.00 $4,754.60 $0.00 $6,601.45 $0.00 $4,714.70 $0.00 $6,636.14 $0.00 $7,234.70 $0.00 Total Charges 1255charge 1220charge 1008charge 999charge 1255charge 1098charge 1008charge 999charge 1127charge 1098charge 1110charge 1098charge RWE 0 7 0 5 0 5 0 5 0 5 0 5 0 $65,306.02 $0.00 $145,005.11 $168,312.00 $33,386.60 $0.00 $36,543.04 $0.00 $0.00 $0.00 $42,188.53 $41,566.00 $82,110.65 $90,164.00 NEW JIG INSTALL COST KNT US $98,050.51 $154,896.00 $0.0437$0.0889 $0.1614 $0.0665 JIG COST/pc JIG COST/pc JIG COST/pc JIG COST/pc JIG COST NEED JIG QTY $0.0376$0.0870$0.0568$0.0608 $0.1189 $0.0744 $0.0698 $0.0977 $0.0425 $0.1367 $0.1271 $0.0916 $0.0619 $0.1240$0.0986$0.0739 $0.1294 $0.1495 $0.0573 $0.1519 $0.1404 $0.0984$0.1141$0.0488$0.1169$0.0907 $0.1555$0.1068 $0.0985 $0.1794 $0.1597 $0.1697 $0.0980 $0.1741$0.1681$0.1023 $0.2012 $0.2054 $0.1557$0.1715$0.0464$0.1598 $0.3921 $0.2166 $0.2586 $0.1235 $0.2243 $0.2166 $0.0554 $0.1226 $0.2090 $0.1882 $1.2919 $0.3220 $0.4757 $0.2292 $0.4757 $0.3220 $0.0665 $0.2274 $0.4450 $0.3262 $1.01 $1.5674 $0.7217 $1.5674 $1.0106 $1.6321 $0.7156 $1.4663 $0.0553 JIG COST/pc JIG COST/pc NEED JIG QTY 6AT $0.0617$0.0515 $0.0759 2013 2nd 1st JIG COST JIG COST 232,416 NEED JIG QTY 2014 JIG COST/pc JIG COST/pc 1st 6AT 2nd 6AT Third Shaft CarborizeCarborize Normalize Carborize Normalize Main Shaft Secoundary Shaft Normalize Shipping(include item) NEED JIG QTY JIG COST 2012 NEED JIG QTY Production Number 1st JIG COST Jig+Tray/1set cast die price 137,376 $0.1379 1st 219,600 219,600 NEED JIG QTY JIG COST NEED JIG QTY JIG COST 219,600 $0.0493 $0.0683 6AT 6AT 6AT 6AT $0.1946 $0.1406 $0.0799$0.0567 87,120 NEED JIG QTY 2nd 17,568 unit jig price(not include cast die cost) $0.1032 2nd 2011 40,320 US JIG GET COST DOWN $6,185 $16,270 $26,755 $29,300 ($56,845) ($5,332) $0.0953 $0.0758 $0.0616$0.0810 【Jig cost analysis】 $32,623 $37,604 $1.0245 $1.2919 $1.0982 $0.0526 $0.3486 $0.0452 KNT US KNT US KNT US KNT US KNT US KNT US ¥12,500 $7,600.00 ¥0 $7,600.00 ¥12,500 $7,600.00 ¥0 $7,600.00 ¥25,000 $3,800.00 ¥0 $3,800.00 ¥152,200 $2,492.00 ¥109,620 $2,492.00 ¥152,200 $2,634.00 ¥108,700 $2,270.00 ¥153,000 $2,362.00 ¥166,800 $2,362.00 ¥182,640 - ¥131,544 - ¥182,640 - ¥130,440 - ¥183,600 - ¥200,160 - $2,200.49 $1,584.87 $2,200.49 $1,571.57 $2,212.05 $2,411.57 ¥83/$ ¥83/$ ¥83/$ ¥83/$ ¥83/$ ¥83/$ 175 180 218 220 175 200 218 220 195 200 198 200 Total Charges 101charge 98charge 81charge 80charge 101charge 88charge 81charge 80charge 91charge 88charge 89charge 88charge RWE 185,318 8 8 8 8 8 8 8 8 8 8 8 8 $17,754.46 $27,536.00 $12,678.94 $27,536.00 $17,754.46 $28,672.00 $12,572.53 $25,760.00 $17,997.59 $22,696.00 $19,292.53 $22,696.00 Total Charges 231charge 224charge 185charge 184charge 231charge 202charge 185charge 184charge 207charge 202charge 204charge 202charge RWE 187,880 0 0 0 0 0 0 0 0 0 0 0 0 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Charges 498charge 484charge 400charge 396charge 498charge 436charge 400charge 396charge 447charge 436charge 440charge 436charge 141,398 5 4 2 2 5 3 2 2 3 3 3 3 $11,002.41 $9,968.00 $3,169.73 $4,984.00 $11,002.41 $7,902.00 $3,143.13 $4,540.00 $6,636.14 $7,086.00 $7,234.70 $7,086.00 Total Charges 786charge 764charge 631charge 625charge 786charge 687charge 631charge 625charge 705charge 687charge 694charge 687charge RWE 150,792 7 7 6 6 7 6 6 6 7 6 7 6 $15,403.37 $17,444.00 $9,509.20 $14,952.00 $15,403.37 $15,804.00 $9,429.40 $13,620.00 $15,484.34 $14,172.00 $16,880.96 $14,172.00 Total Charges 1329charge 1292charge 1067charge 1057charge 1329charge 1163charge 1067charge 1057charge 1192charge 1163charge 1174charge 1163charge RWE 82,472 13 13 11 10 13 12 11 10 12 12 11 12 $28,606.27 $32,396.00 $17,433.54 $24,920.00 $28,606.27 $31,608.00 $17,287.23 $22,700.00 $26,544.58 $28,344.00 $26,527.23 $28,344.00 Total Charges 1255charge 1220charge 1008charge 999charge 1255charge 1098charge 1008charge 999charge 1127charge 1098charge 1110charge 1098charge RWE 0 3 0 2 0 3 0 2 0 3 0 3 0 $6,601.45 $0.00 $3,169.73 $0.00 $6,601.45 $0.00 $3,143.13 $0.00 $6,636.14 $0.00 $7,234.70 $0.00 Total Charges 1255charge 1220charge 1008charge 999charge 1255charge 1098charge 1008charge 999charge 1127charge 1098charge 1110charge 1098charge RWE 0 3 0 3 0 3 0 3 0 3 0 3 0 $6,601.45 $0.00 $4,754.60 $0.00 $6,601.45 $0.00 $4,714.70 $0.00 $6,636.14 $0.00 $7,234.70 $0.00 Total Charges 1255charge 1220charge 1008charge 999charge 1255charge 1098charge 1008charge 999charge 1127charge 1098charge 1110charge 1098charge RWE 0 7 0 5 0 5 0 5 0 5 0 5 0 $15,403.37 $0.00 $7,924.34 $0.00 $11,002.41 $0.00 $7,857.83 $0.00 $11,060.24 $0.00 $12,057.83 $0.00 Total Charges 1255charge 1220charge 1008charge 999charge 1255charge 1098charge 1008charge 999charge 1127charge 1098charge 1110charge 1098charge RWE 0 7 0 6 0 7 0 6 0 7 0 7 0 $15,403.37 $0.00 $9,509.20 $0.00 $15,403.37 $0.00 $9,429.40 $0.00 $15,484.34 $0.00 $16,880.96 $0.00 ACTUAL RCL M/S PRP S/S RWE M/S RWE S/S NORMALIZE $0.1940 $0.0720 $0.0570 $0.2670 CARBURIZE $0.3470 $0.0980 $0.0800 $0.3370 2012 2nd~2015 2nd TOTAL COST *Repair jig of KANETA timing are every 50 charges . Repair cost of one time need $295 . *Production number after 2014 1st are forecast *KNT JIG of life are 200 charges . US JIG of target life are 400 charges (actual result is 212 charges for wheel spindle .  These have some cruck . But we can still use if fix .) JIG made by KANETA are -5pcs of capacity for Normalize jig JIG made by KANETA are -2pcs of capacity for Carborize jig So US JIG can reduce charge times . But those cost are not include . $65,306.02 $0.00 $82,110.65 $0.00 $145,005.11 $168,312.00 $33,386.60 $0.00 $36,543.04 $0.00 $0.00 $0.00 $42,188.53 $41,566.00 $82,110.65 $90,164.00 NEW JIG INSTALL COST KNT US $98,050.51 $154,896.00 $0.0338 $0.0709 $0.0519 *THIS NUMBER ARE ACTUAL JIG COST BY JUNE,2010. NOT INCLUDE REPAIR JIG COST. *CAST JIG WILL MAKE JIG COST DOWN. $0.0392 $0.0478 $0.0771 $0.0437$0.0889 $0.1614 $0.0665 JIG COST/pc JIG COST/pc JIG COST/pc JIG COST/pc JIG COST NEED JIG QTY $0.0376$0.0870$0.0568$0.0608 $0.1189 $0.0535 $0.0744 $0.0464 $0.0520 $0.1309 $0.0698 $0.0977 $0.0425 $0.1367 $0.1271 $0.0916 $0.0619 $0.1240$0.0986$0.0739 $0.1294 $0.1495 $0.0573 $0.1519 $0.1404 $0.0984$0.1141$0.0488$0.1169$0.0907 $0.1555$0.1068 $0.0985 $0.1794 $0.1597 $0.1697 $0.0980 $0.1741$0.1681$0.1023 $0.2012 $0.2054 $0.1557$0.1715$0.0464$0.1598 $0.3921 $0.2166 $0.2586 $0.1235 $0.2243 $0.2166 $0.0554 $0.1226 $0.2090 $0.1882 $1.2919 $0.3220 $0.4757 $0.2292 $0.4757 $0.3220 $0.0665 $0.2274 $0.4450 $0.3262 $1.01 $1.5674 $0.7217 $1.5674 $1.0106 $1.6321 $0.7156 $1.4663 $0.0553 JIG COST/pc JIG COST/pc 2015 2nd NEED JIG QTY 6AT $0.0617$0.0515 $0.0759 JIG COST 2013 2nd 1st JIG COST JIG COST 232,416 NEED JIG QTY 2014 JIG COST/pc JIG COST/pc NEED JIG QTY 1st 6AT 2nd 6AT Third Shaft CarborizeCarborize Normalize Carborize Normalize Main Shaft Secoundary Shaft Normalize Renewal of jig to reaching life(200charges) Shipping(include item) NEED JIG QTY JIG COST 2012 NEED JIG QTY Production Number 1st JIG COST Jig+Tray/1set cast die price 137,376 $0.0627JIG COST/pc 6AT JIG COST $0.1379 $0.1321 1st Red mark are Jig cost higer 219,600 219,600 219,600 NEED JIG QTY JIG COST NEED JIG QTY JIG COST 219,600 $0.0493 $0.0683 6AT 6AT 6AT 6AT $0.1946 $0.1406 $0.0799$0.0567 87,120 NEED JIG QTY 2nd 17,568 unit jig price(not include cast die cost) $0.1032 2nd 2011 40,320 US JIG GET COST DOWN $6,185 $16,270 $26,755 $29,300 ($56,845) ($5,332) $0.0953 $0.0758 $0.0616$0.0810 $135,662 【Jig cost analysis】 $32,623 $37,604 $49,102 $1.0245 $1.2919 $1.0982 $0.0526 $0.3486 $0.0452 If we use US jig for every parts, we will get this number cost down. A complex ROI calculation represents changing part types from old model to new model
  • 18. Idea Annual Impact ($) Idea Item Annual Impact ($) Reduce gas and electric usage HT Process Change to SCR type contactors Reduce Cycle time T/S Lathes 3 4000.00 T/S Cycle time 20000.00 Reduce Cycle time T/S Oil Hole 3000.00 T/S Cycle time 16000.00 Replace Tool checkers with BK micro 0.00 Tool checker 40000.00 Reduce power costs 0.00 Energy Reduce power costs 0.00 Energy Rust issue at HPPG Internal tool grinding (90% Complete) 21000.00 Tool Grinding Energy 63000.00 Replace plant lighting with T-5 Plant Lighting Energy 30000.00 Reduce tooling cost Increase tool life Ttl. Potential $28,000.00 $169,000.00 Ttl. Sales $/yr $42,000,000.00 $40,000,000.00 0.1% 0.4% 7 Investment (Tooling & Capital) Ttl. Potential Ttl. Sales $/yr 6 Logistics Packaging Transportation 3 MachineProc. 4 Assembly Area 88KI (4/11 ~ 3/12) 89Ki Activity (4/12 ~ 3/13) Supplier planned cost improvement action items 18 Supplier Name:Bucyrus Precision Tech, Inc. Originator: Tad Shealy Part Name: M/S, S/S, T/S Date: 5/13/2011 Item No. Idea Annual Impact ($) Idea Item Annual Impact ($) Idea Item Annual Impact ($) Localize M/S & S/S Coil Reduce import costs Localize Coil Reduce gas and electric usage HT Process Change to SCR type contactors Reduce Cycle time T/S Lathes 3 4000.00 T/S Cycle time 20000.00 T/S Cycle time 70000.00 Reduce Cycle time T/S Oil Hole 3000.00 T/S Cycle time 16000.00 T/S Cycle time 50000.00 Replace Tool checkers with BK micro 0.00 Tool checker 40000.00 Tool Checker 40000.00 Reduce power costs - Solar 0.00 Solar Power Solar Power Reduce power costs - Wind 0.00 Wind Power Wind Power JSPS supply small parts in bulk instead of daily lot supply Rust issue at HPPG Internal tool grinding (90% Complete) 21000.00 Tool Grinding Energy 63000.00 Tool Grinding Energy 63000.00 Replace plant lighting with T-5 Plant Lighting Energy 30000.00 Plant lighting Energy 30000.00 Reduce tooling cost Increase tool life Ttl. Potential $28,000.00 Ttl. Potential $169,000.00 Ttl. Potential $253,000.00 Ttl. Sales $/yr $42,000,000.00 Ttl. Sales $/yr $40,000,000.00 Ttl. Sales $/yr $45,000,000.00 0.1% 0.4% 0.6% S.G.A.P. Investment (Tooling & Capital) Inspection & Testing Purchased Components Logistics Packaging Transportation 90Ki Activity (4/13 ~ 3/14) Raw Material MachineProc.ForgingAssembly Summary Page 11th Mid-Term Cost Improvement Plan Area Item 88KI (4/11 ~ 3/12) 89Ki Activity (4/12 ~ 3/13) Scheduled action items and $$ amount of impact Identified opportunity gaps Identified Cost Reduction Opportunities – planning
  • 19. 19
  • 20. Data Integration = 20 2010 6-Year forecast 2016 BPT Long Term Plan ATM Summary Americas Mid-Term Supply Plan 10-1-071410 Part Daily Averages KNT KD L4 L4 CRV BPT L4 RDX 2WD RDX 4WD BPT 4Axis TL 4WD TL 2WD ODY MDX RIDGELINE Accord V6 Accord V6 ( X-O ) 4WD Accord V6 ( X-O ) 2WD Acura V6 ( X-O ) Pilot 4WD Pilot 2WD BPT 6AT BPT M/S & S/S Total BPT Counter Shaft Input Shaft 308 162 1432 1600 1400 2919 2794 110 87 87 85 85 T/S Total 144 280 605 954 1614 0 CR-V 4WD M/S & S/S Total 5AT & 6AT 154 154 1563 1853 0 0 0 000 6AT R97 C/S RWE C/S 0 0 209 0 0 0 0 0 RWE Counter Shaft 0 R97 Counter Shaft 6AT Total ODY 6AT 6AT B 4Axis BPT total 1292 911 2174 3085 1569 3365 B B B 151 326 290 297 267 944 000 973 617 631 122122 120124 1263 29 50 117108 71 277 422 65 63 74 234 271 0 2919 2794 0 0 1327 1242 218 208 6778 176 1450 1508 313 1545 1195 1223 144 1519 3404 300 167 1592 2680 3260 162 85 Ki 08-09M 1st 2nd 124 120 86 Ki 09-10M 1st 2nd 1st 87Ki 10-11M 1st 2nd 2nd 318 0 1241 1088 1741 310 25 465 0 88 0 0 84 2011 0 0 1656 1553 1st 304 89 476 1540 2012 568 727 1289 0 821 88 Ki 11-12M 2nd Total Counter Shaft M/S & S/S Total 5AT DAYS B B B L4 CR-V 4WD (BPT Localize) 2680 2008 0 2009 2010 89 Ki 12-13M 289281 0 686 122 122 646 0 0 0 1154 0 0 0 323 36 410 102 102 44 44 1545 24 342 50 98 0 89 281 0 108 13 87 456483 33 0 00 0 327 327 134 132 467 280 605 73 73 171 155 86 1159 B B B B ( L4 total ) L4 Element L4 Accord L4 CR-V 2WD L4 Acc CT 2WD B B 122 122 131 101 89 86 0 0 364 351 774 746 0 0 43 43 102 102 0 0 449 436 523 259 259 0 0 33 205 85 85 69 69 76 76 370 370 169 156 314 290 954 1614 1236 676 147 635 1685 1112 1039 446 27262639 2013 91 Ki 14-15M 1st 2nd 90 Ki 13-14M 1st 2nd 122 122 0 0 0 0 0 0 2014 0 0 0 0 0 0RV2A Counter Shaft 327 370 1253 1211I/S TotalAccord CVT 1220 1369 0 KNT US KNT US KNT US KNT US KNT US KNT US ¥12,500 $7,600.00 ¥0 $7,600.00 ¥12,500 $7,600.00 ¥0 $7,600.00 ¥25,000 $3,800.00 ¥0 $3,800.00 ¥152,200 $2,492.00 ¥109,620 $2,492.00 ¥152,200 $2,634.00 ¥108,700 $2,270.00 ¥153,000 $2,362.00 ¥166,800 $2,362.00 ¥182,640 - ¥131,544 - ¥182,640 - ¥130,440 - ¥183,600 - ¥200,160 - $2,200.49 $1,584.87 $2,200.49 $1,571.57 $2,212.05 $2,411.57 ¥83/$ ¥83/$ ¥83/$ ¥83/$ ¥83/$ ¥83/$ 175 180 218 220 175 200 218 220 195 200 198 200 Total Charges 101charge 98charge 81charge 80charge 101charge 88charge 81charge 80charge 91charge 88charge 89charge 88charge RWE 185,318 8 8 8 8 8 8 8 8 8 8 8 8 $17,754.46 $27,536.00 $12,678.94 $27,536.00 $17,754.46 $28,672.00 $12,572.53 $25,760.00 $17,997.59 $22,696.00 $19,292.53 $22,696.00 Total Charges 231charge 224charge 185charge 184charge 231charge 202charge 185charge 184charge 207charge 202charge 204charge 202charge RWE 187,880 0 0 0 0 0 0 0 0 0 0 0 0 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Charges 498charge 484charge 400charge 396charge 498charge 436charge 400charge 396charge 447charge 436charge 440charge 436charge 141,398 5 4 2 2 5 3 2 2 3 3 3 3 $11,002.41 $9,968.00 $3,169.73 $4,984.00 $11,002.41 $7,902.00 $3,143.13 $4,540.00 $6,636.14 $7,086.00 $7,234.70 $7,086.00 Total Charges 786charge 764charge 631charge 625charge 786charge 687charge 631charge 625charge 705charge 687charge 694charge 687charge RWE 150,792 7 7 6 6 7 6 6 6 7 6 7 6 $15,403.37 $17,444.00 $9,509.20 $14,952.00 $15,403.37 $15,804.00 $9,429.40 $13,620.00 $15,484.34 $14,172.00 $16,880.96 $14,172.00 Total Charges 1329charge 1292charge 1067charge 1057charge 1329charge 1163charge 1067charge 1057charge 1192charge 1163charge 1174charge 1163charge RWE 82,472 13 13 11 10 13 12 11 10 12 12 11 12 $28,606.27 $32,396.00 $17,433.54 $24,920.00 $28,606.27 $31,608.00 $17,287.23 $22,700.00 $26,544.58 $28,344.00 $26,527.23 $28,344.00 Total Charges 1255charge 1220charge 1008charge 999charge 1255charge 1098charge 1008charge 999charge 1127charge 1098charge 1110charge 1098charge RWE 0 3 0 2 0 3 0 2 0 3 0 3 0 $6,601.45 $0.00 $3,169.73 $0.00 $6,601.45 $0.00 $3,143.13 $0.00 $6,636.14 $0.00 $7,234.70 $0.00 Total Charges 1255charge 1220charge 1008charge 999charge 1255charge 1098charge 1008charge 999charge 1127charge 1098charge 1110charge 1098charge RWE 0 3 0 3 0 3 0 3 0 3 0 3 0 $6,601.45 $0.00 $4,754.60 $0.00 $6,601.45 $0.00 $4,714.70 $0.00 $6,636.14 $0.00 $7,234.70 $0.00 Total Charges 1255charge 1220charge 1008charge 999charge 1255charge 1098charge 1008charge 999charge 1127charge 1098charge 1110charge 1098charge RWE 0 7 0 5 0 5 0 5 0 5 0 5 0 $15,403.37 $0.00 $7,924.34 $0.00 $11,002.41 $0.00 $7,857.83 $0.00 $11,060.24 $0.00 $12,057.83 $0.00 Total Charges 1255charge 1220charge 1008charge 999charge 1255charge 1098charge 1008charge 999charge 1127charge 1098charge 1110charge 1098charge RWE 0 7 0 6 0 7 0 6 0 7 0 7 0 $15,403.37 $0.00 $9,509.20 $0.00 $15,403.37 $0.00 $9,429.40 $0.00 $15,484.34 $0.00 $16,880.96 $0.00 ACTUAL RCL M/S PRP S/S RWE M/S RWE S/S NORMALIZE $0.1940 $0.0720 $0.0570 $0.2670 CARBURIZE $0.3470 $0.0980 $0.0800 $0.3370 2012 2nd~2015 2nd TOTAL COST *Repair jig of KANETA timing are every 50 charges . Repair cost of one time need $295 . *Production number after 2014 1st are forecast *KNT JIG of life are 200 charges . US JIG of target life are 400 charges (actual result is 212 charges for wheel spindle .  These have some cruck . But we can still use if fix .) JIG made by KANETA are -5pcs of capacity for Normalize jig JIG made by KANETA are -2pcs of capacity for Carborize jig So US JIG can reduce charge times . But those cost are not include . $65,306.02 $0.00 $82,110.65 $0.00 $145,005.11 $168,312.00 $33,386.60 $0.00 $36,543.04 $0.00 $0.00 $0.00 $42,188.53 $41,566.00 $82,110.65 $90,164.00 NEW JIG INSTALL COST KNT US $98,050.51 $154,896.00 $0.0338 $0.0709 $0.0519 *THIS NUMBER ARE ACTUAL JIG COST BY JUNE,2010. NOT INCLUDE REPAIR JIG COST. *CAST JIG WILL MAKE JIG COST DOWN. $0.0392 $0.0478 $0.0771 $0.0437$0.0889 $0.1614 $0.0665 JIG COST/pc JIG COST/pc JIG COST/pc JIG COST/pc JIG COST NEED JIG QTY $0.0376$0.0870$0.0568$0.0608 $0.1189 $0.0535 $0.0744 $0.0464 $0.0520 $0.1309 $0.0698 $0.0977 $0.0425 $0.1367 $0.1271 $0.0916 $0.0619 $0.1240$0.0986$0.0739 $0.1294 $0.1495 $0.0573 $0.1519 $0.1404 $0.0984$0.1141$0.0488$0.1169$0.0907 $0.1555$0.1068 $0.0985 $0.1794 $0.1597 $0.1697 $0.0980 $0.1741$0.1681$0.1023 $0.2012 $0.2054 $0.1557$0.1715$0.0464$0.1598 $0.3921 $0.2166 $0.2586 $0.1235 $0.2243 $0.2166 $0.0554 $0.1226 $0.2090 $0.1882 $1.2919 $0.3220 $0.4757 $0.2292 $0.4757 $0.3220 $0.0665 $0.2274 $0.4450 $0.3262 $1.01 $1.5674 $0.7217 $1.5674 $1.0106 $1.6321 $0.7156 $1.4663 $0.0553 JIG COST/pc JIG COST/pc 2015 2nd NEED JIG QTY 6AT $0.0617$0.0515 $0.0759 JIG COST 2013 2nd 1st JIG COST JIG COST 232,416 NEED JIG QTY 2014 JIG COST/pc JIG COST/pc NEED JIG QTY 1st 6AT 2nd 6AT Third Shaft CarborizeCarborize Normalize Carborize Normalize Main Shaft Secoundary Shaft Normalize Renewal of jig to reaching life(200charges) Shipping(include item) NEED JIG QTY JIG COST 2012 NEED JIG QTY Production Number 1st JIG COST Jig+Tray/1set cast die price 137,376 $0.0627JIG COST/pc 6AT JIG COST $0.1379 $0.1321 1st Red mark are Jig cost higer 219,600 219,600 219,600 NEED JIG QTY JIG COST NEED JIG QTY JIG COST 219,600 $0.0493 $0.0683 6AT 6AT 6AT 6AT $0.1946 $0.1406 $0.0799$0.0567 87,120 NEED JIG QTY 2nd 17,568 unit jig price(not include cast die cost) $0.1032 2nd 2011 40,320 US JIG GET COST DOWN $6,185 $16,270 $26,755 $29,300 ($56,845) ($5,332) $0.0953 $0.0758 $0.0616$0.0810 $135,662 【Jig cost analysis】 $32,623 $37,604 $49,102 $1.0245 $1.2919 $1.0982 $0.0526 $0.3486 $0.0452 If we use US jig for every parts, we will get this number cost down. Supplier Name:Bucyrus Precision Tech, Inc. Originator: Tad Shealy Part Name: M/S, S/S, T/S Date: 5/13/2011 Item No. Idea Annual Impact ($) Idea Item Annual Impact ($) Idea Item Annual Impact ($) Localize M/S & S/S Coil Reduce import costs Localize Coil Reduce gas and electric usage HT Process Change to SCR type contactors Reduce Cycle time T/S Lathes 3 4000.00 T/S Cycle time 20000.00 T/S Cycle time 70000.00 Reduce Cycle time T/S Oil Hole 3000.00 T/S Cycle time 16000.00 T/S Cycle time 50000.00 Replace Tool checkers with BK micro 0.00 Tool checker 40000.00 Tool Checker 40000.00 Reduce power costs - Solar 0.00 Solar Power Solar Power Reduce power costs - Wind 0.00 Wind Power Wind Power JSPS supply small parts in bulk instead of daily lot supply Rust issue at HPPG Internal tool grinding (90% Complete) 21000.00 Tool Grinding Energy 63000.00 Tool Grinding Energy 63000.00 Replace plant lighting with T-5 Plant Lighting Energy 30000.00 Plant lighting Energy 30000.00 Reduce tooling cost Increase tool life Ttl. Potential $28,000.00 Ttl. Potential $169,000.00 Ttl. Potential $253,000.00 Ttl. Sales $/yr $42,000,000.00 Ttl. Sales $/yr $40,000,000.00 Ttl. Sales $/yr $45,000,000.00 0.1% 0.4% 0.6% S.G.A.P. Investment (Tooling & Capital) Inspection & Testing Purchased Components Logistics Packaging Transportation 90Ki Activity (4/13 ~ 3/14) Raw Material MachineProc.ForgingAssembly Summary Page 11th Mid-Term Cost Improvement Plan Area Item 88KI (4/11 ~ 3/12) 89Ki Activity (4/12 ~ 3/13) Piece price reduction from innovation incorporation
  • 21. Forecast data ROI presentation Identified opportunities Project planning • The products and services provided will help you achieve your cost improvement objectives. • Example: • Using the research methodologies, we can provide support in the following areas: • Identified opportunities • ROI presentation • Project planning 21
  • 22. • Contact Information: • Jason Gallion • Phone +1 (614) 286-5142 • Email: Info@Epicpwr.com Thank You! 22