2. Riadenie
◦ HM Treasury
◦ Cabinet Office
◦ Departments
Kontrola
◦ Parliament -> Public Accounts Committee
◦ National Audit Office
Annual Accounts Audit
Ad-Hoc Value for Money Audits
“All expenditure requires approval by
Treasury unless Treasury has delegated
this authority to the department. Typically
delegated limits will be set in line with an
assessment of risk…”
3.
4.
5. •That the intervention is supported by a compelling case for change that
provides holistic fit with other parts of the organisation and public sector
Strategic Case
•That the intervention represent best public valueEconomic Case
•That the proposed spend is affordableFinancial Case
•That the proposed Deal is attractive to the market place, can be procured
and is commercially viable
Commercial Case
•That what is required from all parties is achievableManagement Case
7. Strategic Context
◦ Organisational Overview
◦ Current Business Strategies
The Case for Change
◦ Objectives
◦ Existing Arrangements
◦ Business Needs – current and future
◦ Potential Scope
◦ Benefits and Risks
◦ Constraints and Dependencies
8. Critical Success Factors
Long listed Options
Short Listed Options
◦ including do minimum
◦ three or four is the recommended number
Status quo; do nothing option
Economic Appraisals of Costs and Benefits
Optimism Bias adjustment
Risk Assessment
The Preferred Option
10. Public Capital and Revenue Requirements
Impact on Balance Sheet
Impact on Income and Expenditure Account
Overall Funding and Affordability
11. Programme and Project Management Methodology
(PPM) and Structure
Programme and Project Management Plans
Use of Specialist Advisers
Change and Contract Management Arrangements
Benefits Realisation
Risk Management
Monitoring during implementation (proportionate)
Post Implementation Evaluation Arrangements
Contingency Arrangements
12. “It is important to note that “five case model”
is a framework for “thinking” and that the
supporting methodology is flexible and can
be applied at both strategic (macro) and
tactical (micro) levels.”
„Firm boundaries on the
outside, flexible inside“
13. Minor spending
Major spending
Major Policy
Strategic Outline
Programme BC
Strategic Outline Case (SOC)
Outline Business Case (OBC)
Final Business Case (FBC)
Business Justification
Case (BJC)
14. SOC
60%
40%
20%
30%
10%
OBC
80%
70%
60%
60%
50%
FBC
100%
100%
100%
100%
100%
Strategic
Economic
Commercial
Financial
Management
• Case for change &
Objectives
• Scope
• Preferred way forward
• Longlist Options & SWOT
• Short list (incl. “Do
Nothing”)
• Risk identification
• Indicative CBA
• Benefits appraisal (cash
releasing, financial,
quantifiable, qualitative)
• Economic appraisal of
shortlisted options
• Risk assessment
• Identifying the preferred option
• Demonstrate affordability
• Procurement plan, draft OJEU &
criteria
• Risk assignment
• Plan delivery (strategies, plans)
• Update OBC based on
procurement
• Document contractual
arrangements
• Finalise delivery
• Plan evaluation
15. Chose a policy initiative and prepare the
Strategic Outline Case
Time: 45’
Tip: don’t worry too much about the detail.
The goal is to learn the BC structure, not to
get it all right.
16. Strategic Case
◦ Strategic fit
◦ Objectives
◦ Existing arrangements
◦ Business need
◦ Business Scope for the required
business needs (min / medium / max)
◦ Benefits (financial, non-financial
quantitative, qualitative, outcomes)
◦ Risks
Economic Case
◦ CSFs
◦ Long list options (scoping, delivery,
finance)
◦ Preferred way forward
◦ Short list
◦ Indicative economic costs
Commercial Case
◦ Procurement Strategy
◦ Risk transfer
◦ Contract length
Financial Case
◦ Affordability
Management Case
◦ Programme fit
◦ Methodologies
Recommendation