SlideShare une entreprise Scribd logo
1  sur  7
Télécharger pour lire hors ligne
NOVATEUR PUBLICATIONS
INTERNATIONAL JOURNAL OF INNOVATIONS IN ENGINEERING RESEARCH AND TECHNOLOGY [IJIERT]
ISSN: 2394-3696
VOLUME 6, ISSUE 12, Dec.-2019
7 | P a g e
RETOOLING NIGERIAS ELECTRICITY GENERATION SUB –
SYSTEM FOR SUSTAINABLE GRID OPERATION
C. U. OKOYE
S. A. OMOLOLA
N. O. ADELAKUN
I. BITRUS
Department of Electrical / Electronic Engineering, the Federal Polytechnic, Ilaro.
Ogun State, Nigeria, e-mail: cletusucheok@gmail.com
ABSTRACT
Experts are varied in estimating the amount of power needed for national development. One expert
estimated 297,900 MW by the year 2030 using a 13 percent Gross Domestic Product (GDP). The Power
Sector Road Map’s aspiration is 40,000 MW by the year 2020 while the preferred Vision 20:2020 target is
40GW (40,000 MW) available capacity. Vision 20:2020 further proposed that hydro sources contribute 10%
of this value; thermal, 80%; coal, 6% and renewables, 4%. However, as at December 2017, Nigeria’s total
installed generating capacity was 12,324.40 MW. In order to assess the fundamentals and proffer solutions
for the improvement of power generation to meet popular expectations, this work analyses the installed
capacities of the nation from 1986 – 1995, on the one hand and from 2007 – 2016, on the other hand using
graphical illustrations and tables. The gap between the two time phases was deliberate to create some effect.
The results show that over the years, there has been an apparent, non – challance towards systematic
development of Nigeria’s power sector. To put a check to this deteriorating condition / trend, useful
suggestions have been made.
KEYWORDS: power station, installed capacity, vandalisation, frequency control.
INTRODUCTION
According to Sambo et al (2009), the energy demand projection for Nigeria by the year 2030 is estimated at
297,900 MW based on 13 percent Gross Domestic Product (GDP). The corresponding energy supply within
the same period is projected to be 276,229 MW. The Power Sector Road Map aspiration is 40,000 MW by
the year 2020 (KPMG, 2012). In contrast, Nigeria has 27 power plants with total installed capacity of
12,324.40 MW as at the end of December, 2017 (Okoye, 2019a; NCC, 2017). However, quite a good
number of these are not operational, resulting in further decline in power produced for consumption. In fact,
the average available capacity is 6871.25 MW which is just 55.8% of the total installed capacity. Recently
(Ajibade, 2019a) shows that ten out of the 27 generating plants were shut down for some reasons. Worse
still, about 4,000 MWof electricity was said to be stranded (not evacuated) by the relevant authority
(Ajibade, 2019b).
In addition, the Afam power station (gas - powered) was constructed way back in 1965 and had six of its
units rehabilitated in 1982. The Delta plant (also gas - fired) was built in 1966; five of the generating units
were rehabilitated in 1990. Even Egbin gas powered plant with highest installed capacity of 1320 MW was
constructed in 1986. Nigeria’s oldest hydropower plant (Kainji) became operational in 1968 and is now
51year old (Okoro, 2001; Okoye& Ali, 2010; Okoye et al, 2017; Okoye et al, 2018a; Okoye et al, 2018b).
Gas Supply is critical factor in power value chain.Apart from the three hydropower stations, the rest of the
plants depend on gas for their operation. According to NSE (2017), Nigeria’s oil and gas infrastructure is in
power state and is on the verge of failure and needs urgent rehabilitation to prevent complete failure. All
along, the Generation companies (Gencos) Transmission Company (Transco) and the Distribution
Companies (Discos), the tripod on which power sector is standing keep shifting blames for poor power
generation. For instance, when the Gencos alleged sometime in October, 2019 that 4000 MW of power was
stranded, the Discos denied that no power was stranded. An argument levelled against Transco for inability
to wheel power to Discos is the fragile nature of the transmission network. Transco turned around to blame
poor generation on gas shortage on the one hand, and inability of Discos to take more load, on the other
hand. Vandals are also fingered at as contributing to the crisis in power sector because of their illegal
activities (NCC, 2018).
NOVATEUR PUBLICATIONS
INTERNATIONAL JOURNAL OF INNOVATIONS IN ENGINEERING RESEARCH AND TECHNOLOGY [IJIERT]
ISSN: 2394-3696
VOLUME 6, ISSUE 12, Dec.-2019
8 | P a g e
For instance, the Sagamu – Ijebu Ode 132 kV lines and the New Haven OturkpoYandev 132 kV lines were
some time ago vandalized; throwing some states into total darkness. (Okoye, 2015)
The result of all this is that power generation keeps fluctuating between 1500 MW and 3500 MW. This work
seeks to improve the power supply in Nigeria by data – based analysis of key issues.
MATERIALS AND METHODS
Part of the planning stage of this research work was visit to the National Control Centre. (NCC), the
Transmission Company of Nigeria (TCN) both at Osogbo, Nigeria; Olorunsogo thermal power station and
further field trips to 15 MVA, 33 / 11 kV substation at Ilaro, Ogun State, Nigeria.
Frequency control to enhance Voltage Profile and System Stability was observed at the NCC. Any time
there is less MW electrical load demanded, frequency would rise above 50Hz. An increase in MW electrical
load demanded would lead to a fall in frequency below the standard 50Hz. In both cases, poor voltage
profile and system instability would result.
Key technical staff at the various places visited were also interviewed and information garnered further
enriched the work. Besides useful information were gathered from literature such as Nigeria’s Economic
Recovery Growth Plan (ERGP) 2017 – 2020, Electric Power Infrastructure; The Nigerian Infrastructure
Report Card 2017, and various Annual Technical Reports of the NCC and selected publications of the
Central Bank of Nigeria Bulletins and Bureau for Public Enterprises.
To further organise the work, data on installed capacity by year for 10 years (1986 - 1995) was collected and
tagged Batch I. Then followed by data on installed capacity for another 10 years (2007 - 2016) called Batch
II. The gap (1996 - 2006) between Batch 1 and Batch II was deliberately created for effect so that the degree
of capacity addition 11 years after Batch I could be better felt or assessed.
Table 1.0 Installed capacity by year (1986 - 1995) in MW, Batch I
S/N Year Installed Capacity (MW)
1 1986 4548.0
2 1987 4548.0
3 1988 4548.0
4 1989 4548.0
5 1990 4548.0
6 1991 4548.0
7 1992 4548.0
8 1993 4548.6
9 1994 4548.6
10 1995 4548.6
Source: National Control Centre & Central Bank of Nigeria Bulletin
Table 2.0 Installed capacity by year (2007 - 2016) in MW, Batch II
S/N Year Installed Capacity (MW)
1 2007 8138.00
2 2008 8469.50
3 2009 8702.25
4 2010 8425.40
5 2011 8910.40
6 2012 9955.40
7 2013 10915.40
8 2014 11165.40
9 2015 12132.40
10 2016 12310.40
Source: National Control Centre
NOVATEUR PUBLICATIONS
INTERNATIONAL JOURNAL OF INNOVATIONS IN ENGINEERING RESEARCH AND TECHNOLOGY [IJIERT]
ISSN: 2394-3696
VOLUME 6, ISSUE 12, Dec.-2019
9 | P a g e
Table 3.0 Age of major power stations in Nigeria’s national grid
S/N Power station Location Installed capacity
MW
Source of
energy
Year of
Construction
1 Kainji Kaiji, Niger State 760 Hydro 1968
2 Jebba Jebba, Niger State 540 Hydro 1985
3 Shiroro Shiroro, Niger State 600 Hydro 1989
4 Egbin Egbin, Lagos State 1320 Gas 1986
5 Afam (IV - V) Afam, Rivers State 711 (6 x 77, 1982) Gas 1965, 1982
6 Sapele Sapele, Delta State 1020 Gas 1978 / 1981
7 Delta Ughelli, Delta State 912 (5 x 100, 1990) Gas 1966, 1990
8 Oji Oji, Achi, Enugu State 30 (scrapped) Coal 1956
Source: National Bureau of Public Enterprises and National Control Centre, Osogbo.
RESULTS AND DISCUSSION
To further deduce some meanings from Tables 1.0, the data is used to plot the graph shown in fig 1.0
Fig. 1.0: Graphical illustration of Capacity addition over the years (1986 - 1995)
It should be observed in Fig 1.0 that no new capacity was added in the entire seven years (1986 - 1992). It
was only in 1993 that a slight addition was made only to remain so for the rest of 1994 and 1995.
Similarly, Fig 2.0 results when data in Table 2.0 was plotted.
From Table 2.0 and Fig 2.0, after 11 years had elapsed, it was observed that installed capacity has risen to
8,138.0MW as at 2007. The argument is that it took about11 years from 1995 to attain an additional installed
capacity of about 3.6 MW from the 1995 level. Fig 2.0 further shows that from 2011, there was a rise in
capacity addition but it was not remarkable.
4545.0
4545.5
4546.0
4546.5
4547.0
4547.5
4548.0
4548.5
4549.0
1986 1987 1988 1989 1990 1991 1992 1993 1994 1995
InstalledCapacity(MW)
Years
NOVATEUR PUBLICATIONS
INTERNATIONAL JOURNAL OF INNOVATIONS IN ENGINEERING RESEARCH AND TECHNOLOGY [IJIERT]
ISSN: 2394-3696
VOLUME 6, ISSUE 12, Dec.-2019
10 | P a g e
Fig. 2.0: Graphical illustration of Capacity addition, (2007 - 2016)
Furthermore, attention is drawn to Table 3.0 where all the major power plants are fast aging and
approaching end of their service life with Kainji, for instance, being 51 years. It is, therefore obvious that
their performance has declined. Comparatively, the U.S. electric grid (Hicks, 2012) comprises over 5000
state-of-the-art power plants operating at high efficiency.
To further establish or size – up the extent capacity addition was pursued or carried out even after 11 whole
years have passed / elapsed, Tables 1.0 and 2.0 were plotted on the same graph to produce Fig 3.0.
Fig. 3.0: Graphical illustration of relative development in capacity addition, 1986 – 1995; 2007 – 2016
In addition, Fig 4.0. is the further representation of Tables 1.0 and 2.0 using bar chart. Where the picture of
the issues at stake are even much more clearer.
0.00
2000.00
4000.00
6000.00
8000.00
10000.00
12000.00
14000.00
2007 2008 2009 2010 2011 2012 2013 2014 2015 2016
InstalledCapacity(MW)
Years
0.0
2000.0
4000.0
6000.0
8000.0
10000.0
12000.0
14000.0
2007 2008 2009 2010 2011 2012 2013 2014 2015 2016
1986 1987 1988 1989 1990 1991 1992 1993 1994 1995
InstalledCapacity(MW)
Years
Installed Capacity 1986 - 1995 (MW) Installed Capacity 2007 - 2016 (MW)
NOVATEUR PUBLICATIONS
INTERNATIONAL JOURNAL OF INNOVATIONS IN ENGINEERING RESEARCH AND TECHNOLOGY [IJIERT]
ISSN: 2394-3696
VOLUME 6, ISSUE 12, Dec.-2019
11 | P a g e
Fig. 4.0: Chart comparing capacity addition, 1986 – 1995 and 2007 - 2016
The following are suggested for improvement of power generating capacity of Nigeria:
 Nigeria is not using her coal resources to generate electricity, though coal is abundant in 18 states of
the federation (Otenaike & Onifade, 2017) with astonishing reserve of 2.7 billion metric tonnes that
is said could last for 200 years (Amoda, 2016; Okoye 2018b). Whereas coal is used to generate 41%
of electricity used worldwide, 72 – 93% of South Africa’s energy demand is met from coal.
(ALAMAU, 2016). According to Otenaike and Onifade (2017), China generates 79% of her electric
power from coal; India (68%); Poland (87%); Morocco (51%) and U.S.A (45%). The 30MW coal –
fired power plant in Oji, Enugu State scrapped long time ago should be reactivated and new ones
added.
 The Independent Power Plants IPPs connected to the grid have approximated 2191 MW of installed
capacity with only 1203.40 MW available as at December, 2017 (NCC, 2017). More of such IPPs
should be built and conducive environment provided for them. Babcock University’s IPP generates
4.4 MW of power for its use 24 hours daily (Uwandu, 2019).
 Research has shown that one of the major problems faced by generating companies is inadequate gas
supply. For instance, Opara (2014) reports that 90% of the IPP licenses are non – operational as a
result of gas supply shortages. This is a country that has 187 trillion Standard Cubic Feet (SCF) of
proven gas reserves and 600 trillion SCF of unproven gas reserves (Sambo, 2008; FRN, 2012). The
Nigerian Gas Company (NGC) or whatever organ that is responsible for providing gas supplies
should find lasting solution to gas inadequacy.
 Huge debts (over one trillion naira) are being owed generating companies by distribution companies
(Ajibade, 2019d). The Nigerian Bulk Electricity Trading Company (NBET) Should ensure that
Discos pay these debts so that Gencos could improve on their power output. NBET was set up by the
federal government of Nigeria to administer and control energy pool.
 Another critical factor militating against generation is vandalisation of power infrastructure and gas
pipelines. This act of sabotage is obvious everywhere in Nigeria. Without putting this in check, all
efforts to improve electricity supply will pay little dividend.
 Table 3.0 shows that many power plants are already very old. Thus, they keep failing after due
maintenance. Though capital intensive, additional ones should be built as the economy is expanding
fast. After all, Nigeria is said to be the largest economy in Africa.
0.0
2000.0
4000.0
6000.0
8000.0
10000.0
12000.0
14000.0
2007 2008 2009 2010 2011 2012 2013 2014 2015 2016
1986 1987 1988 1989 1990 1991 1992 1993 1994 1995
Capacityaddition(MW)
Years
Installed Capacity 1986 - 1995 (MW) Installed Capacity 2007 - 2016 (MW)
NOVATEUR PUBLICATIONS
INTERNATIONAL JOURNAL OF INNOVATIONS IN ENGINEERING RESEARCH AND TECHNOLOGY [IJIERT]
ISSN: 2394-3696
VOLUME 6, ISSUE 12, Dec.-2019
12 | P a g e
 It is high time to scale up renewable energy development and deployment in Nigeria. Apart from the
advantage of having no obvious negative impact on the environment, it could also provide relief to
rural dwellers in remote areas in Nigeria. This will reduce dependence on grid electricity with all its
attendant disappointing performances.
CONCLUSION
As the largest economy in Africa, there is an urgent need to increase power supply in Nigeria. The minimum
installed generation capacity proposed by experts is 40,000 MW by the year 2020 but Nigeria is nowhere
near this optimistic figure as at present. Rather, the country is grappling with the installed capacity of only
12,324 MW with only about half of it suitable and ready for electricity generation. The study has shown
graphically that from 1986 to date, capacity addition has not been anything impressive and points at some
obvious neglect of power sector over the years, coal is a major source of power in countries like China
(79.1%), India (68%), Poland (87%), Germany (41%), Israel (58%), and even Morocco (51%). Nigeria with
coal deposits in 18 states and huge reserve of 2.7 billion metric tonnes is expected to have been a leader in
coal – fired power generation. Unfortunately, even the only coal – fired power station in Oji, Enugu State,
commissioned in 1956 has been scrapped and nobody appears to be thinking about it anymore.
Measures aimed at power supply for Nigeria’s 200 million people and, of course, Benin and Niger Republics
which Nigeria sales electricity to have been suggested.
REFERENCES
1) Ajibade, A. (2019a), Ending Incessant Output Shortfalls, The Nation Newspaper, Thursday November
14, P. 14.
2) Ajibade, A. (2019b), Much Ado about Stranded 4000 MW of Electricity, The Nation Newspaper,
Thursday October 24, P. 37
3) Ajibade, A. (2019c), Six Years after Privatisation, Power Woes Linger, The Nation Newspaper,
Thursday November 7, P. 35
4) Ajibade, A. (2019d), Why Power Generation is Low, The Nation Newspaper, Thursday 26, P. 35
5) Alamau,O. (2016), African Energy Commission: Accelerating Africa’s Economic Growth through
Efficient Energy Production
6) Amoda, O. (2016), Power Distribution Demand Side Management in Developing Economics, 13th
Distinguished Electrical / Electronic Engineering Annual Lecture, The Nigerian Institution of Electrical
/ Electronic Engineers (NIEEE).
7) FRN (2012), Investment Opportunities in the Nigerian Power Sector, Federal Republic of Nigeria.
8) Hicks, C (2012), The Smart Grid, ERB, University of Michigan
9) KPMG (2012), Nigeria Power Guide, Vol. 1
10) NCC (2017), Grid Operations 2017: Annual Technical Report, National Control Centre, Osogbo,
Nigeria.
11) NCC (2018), Grid Operations 2018: Annual Technical Report, National Control Centre, Osogbo,
Nigeria.
12) NSE (2017), The Nigerian Infrastructure Score Card (2017), The Nigerian Society of Engineers
13) Okoro, C. C. (2001), Towards Sustainable National Grid System, Proceedings, The Nigerian Society of
Engineers (Electrical Division).
14) Okoye, C.U & Ali, N.A. (2010), Towards Efficient Electricity Generation: A Case Study of
15) Nigeria’s Electricity Facilities, Journal of Engineering Science, Vol. 2, No. 1, Pan African Book
Company, Ghana
16) Okoye, C. U. (2015), Nigeria’s 132 / 330 kV transmission Line: Issues, Challenges and Solutions,
International Journal of Scientific Innovation and Sustainable Development, Vol. 5, No. 2.
17) Okoye, C. U., Adeniji, O. A. and Sunmonu, A. O. (2017), A Study and Performance Evaluation of
Olorunsogo Thermal Power Plant in Nigeria, International Journal of Engineering Sciences and
Research Technology, Vol. 6, issue 12.
NOVATEUR PUBLICATIONS
INTERNATIONAL JOURNAL OF INNOVATIONS IN ENGINEERING RESEARCH AND TECHNOLOGY [IJIERT]
ISSN: 2394-3696
VOLUME 6, ISSUE 12, Dec.-2019
13 | P a g e
18) Okoye, C. U., Bitrus, I., Alao, M. J., Adelakun, N. O. &Abdulhamid, I. G. (2018a), A Study and
Analysis of Energy Generation and Consumption in Dangote Cement Plant, Ibese, Nigeria, Global
Journal of Advanced Engineering Technologies and Sciences, Vol. 5, No 11.
19) Okoye, C. U.(2018b), Enhancing Electricity Generation Capacity in Africa Through
20) Revamping coal – fired power plants: A Case Study of Nigeria, Paper presented at 40th
Anniversary and
International Conference, The Commonwealth Association of Technical Universities and Polytechnics
in Africa (CAPA), Abuja, Nigeria.
21) Okoye, C. U., and Omolola, S. A. (2019a), A Study and Evaluation of Power Outages on 132kV
22) Transmission Network in Nigeria for Grid Security, The International Journal of Engineering and
Science, Vol. 8, Issue 11, Pp 53 - 57
23) Okoye, C. U. (2019b), Nigeria’s Electric Grid: Sharing Field Experience in Search of Grid Integrity,
Technical Paper presented at the Monthly Meeting of the Nigerian Society of Engineers, Ilaro Branch,
Ogun State, Nigeria, February 13.
24) Opara, S. (2014), 90% Power Licences Idle due to Gas Shortage, The Punch, June 13, P. 29.
25) Otenaike, S. &Onifade, G. (2017), Coal as a Source of Electricity in Nigeria, The Consulting
Engineer, May – August, Vol. 4, No. 1.
26) Sambo, A. S.; Garba, B.; Zarma, I. H. &Gaji, M. M. (2009), Electricity Generation and the present
challenges in the Nigeria Power Sector, Energy Commission of Nigeria, Abuja, Nigeria.
27) Sambo, A. S. (2008), Matching Electricity Supply with Demand in Nigeria, International Association
for Energy Economics, 4th
quarter.
28) Uwandu, E. (2019), How we Generate 24 – hour Power Supply, Vanguard Newspapers, Thursday
September 12, P. 38.

Contenu connexe

Tendances

Ns cef market handbook q1 2020 08 sep20
Ns   cef market handbook q1 2020 08 sep20Ns   cef market handbook q1 2020 08 sep20
Ns cef market handbook q1 2020 08 sep20Mayank Munjal
 
Zimtu Research: Lakeland Resources Inc. Update - Athabasca Basin Uranium Expl...
Zimtu Research: Lakeland Resources Inc. Update - Athabasca Basin Uranium Expl...Zimtu Research: Lakeland Resources Inc. Update - Athabasca Basin Uranium Expl...
Zimtu Research: Lakeland Resources Inc. Update - Athabasca Basin Uranium Expl...Lakeland Resources Inc. (TSXv: LK)
 
Optimal Energy Mix and Power
Optimal Energy Mix and PowerOptimal Energy Mix and Power
Optimal Energy Mix and PowerH Janardan Prabhu
 
Transmission Summit West 2013
Transmission Summit West 2013Transmission Summit West 2013
Transmission Summit West 2013ScottMadden, Inc.
 
FERC & DOE Incentives for Renewables
FERC & DOE Incentives for RenewablesFERC & DOE Incentives for Renewables
FERC & DOE Incentives for Renewableselwalsh
 
Nepal Energy Scenario
Nepal Energy ScenarioNepal Energy Scenario
Nepal Energy ScenarioAvdesh Mandal
 
2008 Wind Technologies Market Report - USA
2008 Wind Technologies Market Report - USA2008 Wind Technologies Market Report - USA
2008 Wind Technologies Market Report - USAGlenn Klith Andersen
 
Cédric PHILIBERT Energy and Climate Change Analyst IEA (Atoms for the Future ...
Cédric PHILIBERT Energy and Climate Change Analyst IEA (Atoms for the Future ...Cédric PHILIBERT Energy and Climate Change Analyst IEA (Atoms for the Future ...
Cédric PHILIBERT Energy and Climate Change Analyst IEA (Atoms for the Future ...Société Française d'Energie Nucléaire
 
Energy generation 10_11
Energy generation 10_11Energy generation 10_11
Energy generation 10_11rameshgoudru
 
2018 useer executive summary presentation 6 12-18 business forward
2018 useer executive summary presentation 6 12-18 business forward2018 useer executive summary presentation 6 12-18 business forward
2018 useer executive summary presentation 6 12-18 business forwardbusinessforward
 
Ceew ceew cef market handbook q1 2020-21 10 sep20
Ceew   ceew cef market handbook q1 2020-21 10 sep20Ceew   ceew cef market handbook q1 2020-21 10 sep20
Ceew ceew cef market handbook q1 2020-21 10 sep20Mayank Munjal
 
MEGA PROJECT PLANS FOR DEVELOPING THE POWER AND
MEGA PROJECT PLANS FOR DEVELOPING THE POWER ANDMEGA PROJECT PLANS FOR DEVELOPING THE POWER AND
MEGA PROJECT PLANS FOR DEVELOPING THE POWER ANDBasil Issa
 
RCREEE-enerMENA_sudan renewable energy projects-21.08.2013
RCREEE-enerMENA_sudan renewable energy projects-21.08.2013RCREEE-enerMENA_sudan renewable energy projects-21.08.2013
RCREEE-enerMENA_sudan renewable energy projects-21.08.2013RCREEE
 
Energy Sector - 12th Plan (2012 - 2017)
Energy Sector - 12th Plan (2012 - 2017)Energy Sector - 12th Plan (2012 - 2017)
Energy Sector - 12th Plan (2012 - 2017)NITI Aayog
 
Energy Analysis of Nigeria
Energy Analysis of NigeriaEnergy Analysis of Nigeria
Energy Analysis of NigeriaSatya Sahoo
 
Development of the pathways to achieve SE4ALL 2030 objectives
Development of the pathways to achieve SE4ALL 2030 objectivesDevelopment of the pathways to achieve SE4ALL 2030 objectives
Development of the pathways to achieve SE4ALL 2030 objectivesIEA-ETSAP
 

Tendances (19)

Ns cef market handbook q1 2020 08 sep20
Ns   cef market handbook q1 2020 08 sep20Ns   cef market handbook q1 2020 08 sep20
Ns cef market handbook q1 2020 08 sep20
 
Zimtu Research: Lakeland Resources Inc. Update - Athabasca Basin Uranium Expl...
Zimtu Research: Lakeland Resources Inc. Update - Athabasca Basin Uranium Expl...Zimtu Research: Lakeland Resources Inc. Update - Athabasca Basin Uranium Expl...
Zimtu Research: Lakeland Resources Inc. Update - Athabasca Basin Uranium Expl...
 
Optimal Energy Mix and Power
Optimal Energy Mix and PowerOptimal Energy Mix and Power
Optimal Energy Mix and Power
 
Transmission Summit West 2013
Transmission Summit West 2013Transmission Summit West 2013
Transmission Summit West 2013
 
FERC & DOE Incentives for Renewables
FERC & DOE Incentives for RenewablesFERC & DOE Incentives for Renewables
FERC & DOE Incentives for Renewables
 
Nepal Energy Scenario
Nepal Energy ScenarioNepal Energy Scenario
Nepal Energy Scenario
 
9-Energy
9-Energy9-Energy
9-Energy
 
2008 Wind Technologies Market Report - USA
2008 Wind Technologies Market Report - USA2008 Wind Technologies Market Report - USA
2008 Wind Technologies Market Report - USA
 
Cédric PHILIBERT Energy and Climate Change Analyst IEA (Atoms for the Future ...
Cédric PHILIBERT Energy and Climate Change Analyst IEA (Atoms for the Future ...Cédric PHILIBERT Energy and Climate Change Analyst IEA (Atoms for the Future ...
Cédric PHILIBERT Energy and Climate Change Analyst IEA (Atoms for the Future ...
 
Awea Annual Wind Report 2009
Awea Annual Wind Report 2009Awea Annual Wind Report 2009
Awea Annual Wind Report 2009
 
F0513644
F0513644F0513644
F0513644
 
Energy generation 10_11
Energy generation 10_11Energy generation 10_11
Energy generation 10_11
 
2018 useer executive summary presentation 6 12-18 business forward
2018 useer executive summary presentation 6 12-18 business forward2018 useer executive summary presentation 6 12-18 business forward
2018 useer executive summary presentation 6 12-18 business forward
 
Ceew ceew cef market handbook q1 2020-21 10 sep20
Ceew   ceew cef market handbook q1 2020-21 10 sep20Ceew   ceew cef market handbook q1 2020-21 10 sep20
Ceew ceew cef market handbook q1 2020-21 10 sep20
 
MEGA PROJECT PLANS FOR DEVELOPING THE POWER AND
MEGA PROJECT PLANS FOR DEVELOPING THE POWER ANDMEGA PROJECT PLANS FOR DEVELOPING THE POWER AND
MEGA PROJECT PLANS FOR DEVELOPING THE POWER AND
 
RCREEE-enerMENA_sudan renewable energy projects-21.08.2013
RCREEE-enerMENA_sudan renewable energy projects-21.08.2013RCREEE-enerMENA_sudan renewable energy projects-21.08.2013
RCREEE-enerMENA_sudan renewable energy projects-21.08.2013
 
Energy Sector - 12th Plan (2012 - 2017)
Energy Sector - 12th Plan (2012 - 2017)Energy Sector - 12th Plan (2012 - 2017)
Energy Sector - 12th Plan (2012 - 2017)
 
Energy Analysis of Nigeria
Energy Analysis of NigeriaEnergy Analysis of Nigeria
Energy Analysis of Nigeria
 
Development of the pathways to achieve SE4ALL 2030 objectives
Development of the pathways to achieve SE4ALL 2030 objectivesDevelopment of the pathways to achieve SE4ALL 2030 objectives
Development of the pathways to achieve SE4ALL 2030 objectives
 

Similaire à RETOOLING NIGERIAS ELECTRICITY GENERATION SUB – SYSTEM FOR SUSTAINABLE GRID OPERATION

Impact of Price Expectation on the Demand of Electric Energy
Impact of Price Expectation on the Demand of Electric EnergyImpact of Price Expectation on the Demand of Electric Energy
Impact of Price Expectation on the Demand of Electric EnergyIOSR Journals
 
A Markov model of generator performance at the Kainji hydro-power station in...
A Markov model of generator performance at the Kainji  hydro-power station in...A Markov model of generator performance at the Kainji  hydro-power station in...
A Markov model of generator performance at the Kainji hydro-power station in...IJECEIAES
 
E N E R G Y M A N A G E M E N T
E N E R G Y  M A N A G E M E N TE N E R G Y  M A N A G E M E N T
E N E R G Y M A N A G E M E N Tsajid ghafoor
 
TECHNO-ECONOMIC EVALUATION OF COAL-FIRED POWER PLANT IN SOUTH EAST NIGERIA, A...
TECHNO-ECONOMIC EVALUATION OF COAL-FIRED POWER PLANT IN SOUTH EAST NIGERIA, A...TECHNO-ECONOMIC EVALUATION OF COAL-FIRED POWER PLANT IN SOUTH EAST NIGERIA, A...
TECHNO-ECONOMIC EVALUATION OF COAL-FIRED POWER PLANT IN SOUTH EAST NIGERIA, A...IAEME Publication
 
A feasibility study of electrical energy generation from municipal solid wast...
A feasibility study of electrical energy generation from municipal solid wast...A feasibility study of electrical energy generation from municipal solid wast...
A feasibility study of electrical energy generation from municipal solid wast...IJECEIAES
 
A STUDY AND ANALYSIS OF ENERGY GENERATION AND CONSUMPTION IN DANGOTE CEMENT ...
A STUDY AND ANALYSIS OF ENERGY GENERATION AND CONSUMPTION IN  DANGOTE CEMENT ...A STUDY AND ANALYSIS OF ENERGY GENERATION AND CONSUMPTION IN  DANGOTE CEMENT ...
A STUDY AND ANALYSIS OF ENERGY GENERATION AND CONSUMPTION IN DANGOTE CEMENT ...Najeem Olawale Adelakun
 
Integrating Renewable Energy in Smart Grid: Opportunity, Challenges and Progr...
Integrating Renewable Energy in Smart Grid: Opportunity, Challenges and Progr...Integrating Renewable Energy in Smart Grid: Opportunity, Challenges and Progr...
Integrating Renewable Energy in Smart Grid: Opportunity, Challenges and Progr...IRJET Journal
 
IRJET- Energy Statistics in India
IRJET- Energy Statistics in IndiaIRJET- Energy Statistics in India
IRJET- Energy Statistics in IndiaIRJET Journal
 
DESIGN AND CONSTRUCTION OF A 0.5 KW SOLAR TREE FOR POWERING FARM SETTLEMENTS
DESIGN AND CONSTRUCTION OF A 0.5 KW SOLAR TREE FOR POWERING FARM SETTLEMENTSDESIGN AND CONSTRUCTION OF A 0.5 KW SOLAR TREE FOR POWERING FARM SETTLEMENTS
DESIGN AND CONSTRUCTION OF A 0.5 KW SOLAR TREE FOR POWERING FARM SETTLEMENTSIAEME Publication
 
B0314011017
B0314011017B0314011017
B0314011017theijes
 
Assessment of Energy Losses and Cost Implications in the Nigerian Distributio...
Assessment of Energy Losses and Cost Implications in the Nigerian Distributio...Assessment of Energy Losses and Cost Implications in the Nigerian Distributio...
Assessment of Energy Losses and Cost Implications in the Nigerian Distributio...Dr. Hachimenum Amadi
 
Mixed Energy(NEPRA- State of industry Report 2020-2021)- Presentation
Mixed Energy(NEPRA- State of industry Report 2020-2021)- PresentationMixed Energy(NEPRA- State of industry Report 2020-2021)- Presentation
Mixed Energy(NEPRA- State of industry Report 2020-2021)- PresentationNAUMAN NAEEM
 
Electricity crisis
Electricity crisisElectricity crisis
Electricity crisisshahin6120
 
IRJET - Power Generation, Consumption and Power Shortage in India
IRJET - Power Generation, Consumption and Power Shortage in IndiaIRJET - Power Generation, Consumption and Power Shortage in India
IRJET - Power Generation, Consumption and Power Shortage in IndiaIRJET Journal
 
Future potential of small hydro power project in india
Future potential of small hydro power project in indiaFuture potential of small hydro power project in india
Future potential of small hydro power project in indiaIAEME Publication
 
Sapele Thermal Power Station Generator Availability and Units Performance Stu...
Sapele Thermal Power Station Generator Availability and Units Performance Stu...Sapele Thermal Power Station Generator Availability and Units Performance Stu...
Sapele Thermal Power Station Generator Availability and Units Performance Stu...irjes
 
Cost implications analysis of grid supplied electricity and solar source of e...
Cost implications analysis of grid supplied electricity and solar source of e...Cost implications analysis of grid supplied electricity and solar source of e...
Cost implications analysis of grid supplied electricity and solar source of e...TELKOMNIKA JOURNAL
 
J0364057060
J0364057060J0364057060
J0364057060theijes
 
Energy crises in pakistan
Energy crises in pakistanEnergy crises in pakistan
Energy crises in pakistanShehzad Imran
 
Evaluation and Solution of energy Crisis in Nepal
Evaluation and Solution of energy Crisis in Nepal Evaluation and Solution of energy Crisis in Nepal
Evaluation and Solution of energy Crisis in Nepal Dr Ramhari Poudyal
 

Similaire à RETOOLING NIGERIAS ELECTRICITY GENERATION SUB – SYSTEM FOR SUSTAINABLE GRID OPERATION (20)

Impact of Price Expectation on the Demand of Electric Energy
Impact of Price Expectation on the Demand of Electric EnergyImpact of Price Expectation on the Demand of Electric Energy
Impact of Price Expectation on the Demand of Electric Energy
 
A Markov model of generator performance at the Kainji hydro-power station in...
A Markov model of generator performance at the Kainji  hydro-power station in...A Markov model of generator performance at the Kainji  hydro-power station in...
A Markov model of generator performance at the Kainji hydro-power station in...
 
E N E R G Y M A N A G E M E N T
E N E R G Y  M A N A G E M E N TE N E R G Y  M A N A G E M E N T
E N E R G Y M A N A G E M E N T
 
TECHNO-ECONOMIC EVALUATION OF COAL-FIRED POWER PLANT IN SOUTH EAST NIGERIA, A...
TECHNO-ECONOMIC EVALUATION OF COAL-FIRED POWER PLANT IN SOUTH EAST NIGERIA, A...TECHNO-ECONOMIC EVALUATION OF COAL-FIRED POWER PLANT IN SOUTH EAST NIGERIA, A...
TECHNO-ECONOMIC EVALUATION OF COAL-FIRED POWER PLANT IN SOUTH EAST NIGERIA, A...
 
A feasibility study of electrical energy generation from municipal solid wast...
A feasibility study of electrical energy generation from municipal solid wast...A feasibility study of electrical energy generation from municipal solid wast...
A feasibility study of electrical energy generation from municipal solid wast...
 
A STUDY AND ANALYSIS OF ENERGY GENERATION AND CONSUMPTION IN DANGOTE CEMENT ...
A STUDY AND ANALYSIS OF ENERGY GENERATION AND CONSUMPTION IN  DANGOTE CEMENT ...A STUDY AND ANALYSIS OF ENERGY GENERATION AND CONSUMPTION IN  DANGOTE CEMENT ...
A STUDY AND ANALYSIS OF ENERGY GENERATION AND CONSUMPTION IN DANGOTE CEMENT ...
 
Integrating Renewable Energy in Smart Grid: Opportunity, Challenges and Progr...
Integrating Renewable Energy in Smart Grid: Opportunity, Challenges and Progr...Integrating Renewable Energy in Smart Grid: Opportunity, Challenges and Progr...
Integrating Renewable Energy in Smart Grid: Opportunity, Challenges and Progr...
 
IRJET- Energy Statistics in India
IRJET- Energy Statistics in IndiaIRJET- Energy Statistics in India
IRJET- Energy Statistics in India
 
DESIGN AND CONSTRUCTION OF A 0.5 KW SOLAR TREE FOR POWERING FARM SETTLEMENTS
DESIGN AND CONSTRUCTION OF A 0.5 KW SOLAR TREE FOR POWERING FARM SETTLEMENTSDESIGN AND CONSTRUCTION OF A 0.5 KW SOLAR TREE FOR POWERING FARM SETTLEMENTS
DESIGN AND CONSTRUCTION OF A 0.5 KW SOLAR TREE FOR POWERING FARM SETTLEMENTS
 
B0314011017
B0314011017B0314011017
B0314011017
 
Assessment of Energy Losses and Cost Implications in the Nigerian Distributio...
Assessment of Energy Losses and Cost Implications in the Nigerian Distributio...Assessment of Energy Losses and Cost Implications in the Nigerian Distributio...
Assessment of Energy Losses and Cost Implications in the Nigerian Distributio...
 
Mixed Energy(NEPRA- State of industry Report 2020-2021)- Presentation
Mixed Energy(NEPRA- State of industry Report 2020-2021)- PresentationMixed Energy(NEPRA- State of industry Report 2020-2021)- Presentation
Mixed Energy(NEPRA- State of industry Report 2020-2021)- Presentation
 
Electricity crisis
Electricity crisisElectricity crisis
Electricity crisis
 
IRJET - Power Generation, Consumption and Power Shortage in India
IRJET - Power Generation, Consumption and Power Shortage in IndiaIRJET - Power Generation, Consumption and Power Shortage in India
IRJET - Power Generation, Consumption and Power Shortage in India
 
Future potential of small hydro power project in india
Future potential of small hydro power project in indiaFuture potential of small hydro power project in india
Future potential of small hydro power project in india
 
Sapele Thermal Power Station Generator Availability and Units Performance Stu...
Sapele Thermal Power Station Generator Availability and Units Performance Stu...Sapele Thermal Power Station Generator Availability and Units Performance Stu...
Sapele Thermal Power Station Generator Availability and Units Performance Stu...
 
Cost implications analysis of grid supplied electricity and solar source of e...
Cost implications analysis of grid supplied electricity and solar source of e...Cost implications analysis of grid supplied electricity and solar source of e...
Cost implications analysis of grid supplied electricity and solar source of e...
 
J0364057060
J0364057060J0364057060
J0364057060
 
Energy crises in pakistan
Energy crises in pakistanEnergy crises in pakistan
Energy crises in pakistan
 
Evaluation and Solution of energy Crisis in Nepal
Evaluation and Solution of energy Crisis in Nepal Evaluation and Solution of energy Crisis in Nepal
Evaluation and Solution of energy Crisis in Nepal
 

Plus de Najeem Olawale Adelakun

A pragmatic study on e learning system for higher education in developing cou...
A pragmatic study on e learning system for higher education in developing cou...A pragmatic study on e learning system for higher education in developing cou...
A pragmatic study on e learning system for higher education in developing cou...Najeem Olawale Adelakun
 
Solar powered automatic wash hand basin system
Solar powered automatic wash hand basin systemSolar powered automatic wash hand basin system
Solar powered automatic wash hand basin systemNajeem Olawale Adelakun
 
The Relevance of Doubly – Fed Induction Generator (DFIG) in Modelling and Sim...
The Relevance of Doubly – Fed Induction Generator (DFIG) in Modelling and Sim...The Relevance of Doubly – Fed Induction Generator (DFIG) in Modelling and Sim...
The Relevance of Doubly – Fed Induction Generator (DFIG) in Modelling and Sim...Najeem Olawale Adelakun
 
Evaluation of Electrical Services using Energy Efficient Load
Evaluation of Electrical Services using Energy Efficient LoadEvaluation of Electrical Services using Energy Efficient Load
Evaluation of Electrical Services using Energy Efficient LoadNajeem Olawale Adelakun
 
Easy approach to a responsive website design using artisteer application soft...
Easy approach to a responsive website design using artisteer application soft...Easy approach to a responsive website design using artisteer application soft...
Easy approach to a responsive website design using artisteer application soft...Najeem Olawale Adelakun
 
Development of a two link robotic manipulator
Development of a two link robotic manipulatorDevelopment of a two link robotic manipulator
Development of a two link robotic manipulatorNajeem Olawale Adelakun
 
Outage analysis and system disturbances on 330k v and 132kv transmission syst...
Outage analysis and system disturbances on 330k v and 132kv transmission syst...Outage analysis and system disturbances on 330k v and 132kv transmission syst...
Outage analysis and system disturbances on 330k v and 132kv transmission syst...Najeem Olawale Adelakun
 
Assessment of renewable energy in nigeria, challenges and benefits.
Assessment of renewable energy in nigeria, challenges and benefits.Assessment of renewable energy in nigeria, challenges and benefits.
Assessment of renewable energy in nigeria, challenges and benefits.Najeem Olawale Adelakun
 
DESIGN OF AN ELECTRICAL INSTALLATION OF A STOREY BUILDING
DESIGN OF AN ELECTRICAL INSTALLATION OF A STOREY  BUILDINGDESIGN OF AN ELECTRICAL INSTALLATION OF A STOREY  BUILDING
DESIGN OF AN ELECTRICAL INSTALLATION OF A STOREY BUILDINGNajeem Olawale Adelakun
 
Design and Evaluation of Electrical Services for an Energy Efficient Home
Design and Evaluation of Electrical Services for an  Energy Efficient HomeDesign and Evaluation of Electrical Services for an  Energy Efficient Home
Design and Evaluation of Electrical Services for an Energy Efficient HomeNajeem Olawale Adelakun
 

Plus de Najeem Olawale Adelakun (11)

A pragmatic study on e learning system for higher education in developing cou...
A pragmatic study on e learning system for higher education in developing cou...A pragmatic study on e learning system for higher education in developing cou...
A pragmatic study on e learning system for higher education in developing cou...
 
Solar powered automatic wash hand basin system
Solar powered automatic wash hand basin systemSolar powered automatic wash hand basin system
Solar powered automatic wash hand basin system
 
The Relevance of Doubly – Fed Induction Generator (DFIG) in Modelling and Sim...
The Relevance of Doubly – Fed Induction Generator (DFIG) in Modelling and Sim...The Relevance of Doubly – Fed Induction Generator (DFIG) in Modelling and Sim...
The Relevance of Doubly – Fed Induction Generator (DFIG) in Modelling and Sim...
 
Evaluation of Electrical Services using Energy Efficient Load
Evaluation of Electrical Services using Energy Efficient LoadEvaluation of Electrical Services using Energy Efficient Load
Evaluation of Electrical Services using Energy Efficient Load
 
Easy approach to a responsive website design using artisteer application soft...
Easy approach to a responsive website design using artisteer application soft...Easy approach to a responsive website design using artisteer application soft...
Easy approach to a responsive website design using artisteer application soft...
 
Development of a two link robotic manipulator
Development of a two link robotic manipulatorDevelopment of a two link robotic manipulator
Development of a two link robotic manipulator
 
Outage analysis and system disturbances on 330k v and 132kv transmission syst...
Outage analysis and system disturbances on 330k v and 132kv transmission syst...Outage analysis and system disturbances on 330k v and 132kv transmission syst...
Outage analysis and system disturbances on 330k v and 132kv transmission syst...
 
Assessment of renewable energy in nigeria, challenges and benefits.
Assessment of renewable energy in nigeria, challenges and benefits.Assessment of renewable energy in nigeria, challenges and benefits.
Assessment of renewable energy in nigeria, challenges and benefits.
 
DESIGN OF AN ELECTRICAL INSTALLATION OF A STOREY BUILDING
DESIGN OF AN ELECTRICAL INSTALLATION OF A STOREY  BUILDINGDESIGN OF AN ELECTRICAL INSTALLATION OF A STOREY  BUILDING
DESIGN OF AN ELECTRICAL INSTALLATION OF A STOREY BUILDING
 
Design and Evaluation of Electrical Services for an Energy Efficient Home
Design and Evaluation of Electrical Services for an  Energy Efficient HomeDesign and Evaluation of Electrical Services for an  Energy Efficient Home
Design and Evaluation of Electrical Services for an Energy Efficient Home
 
A Review Of Solar Energy
A Review Of Solar EnergyA Review Of Solar Energy
A Review Of Solar Energy
 

Dernier

Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...Orbitshub
 
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...apidays
 
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...apidays
 
Vector Search -An Introduction in Oracle Database 23ai.pptx
Vector Search -An Introduction in Oracle Database 23ai.pptxVector Search -An Introduction in Oracle Database 23ai.pptx
Vector Search -An Introduction in Oracle Database 23ai.pptxRemote DBA Services
 
Why Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businessWhy Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businesspanagenda
 
FWD Group - Insurer Innovation Award 2024
FWD Group - Insurer Innovation Award 2024FWD Group - Insurer Innovation Award 2024
FWD Group - Insurer Innovation Award 2024The Digital Insurer
 
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, AdobeApidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobeapidays
 
Platformless Horizons for Digital Adaptability
Platformless Horizons for Digital AdaptabilityPlatformless Horizons for Digital Adaptability
Platformless Horizons for Digital AdaptabilityWSO2
 
Strategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherStrategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherRemote DBA Services
 
presentation ICT roal in 21st century education
presentation ICT roal in 21st century educationpresentation ICT roal in 21st century education
presentation ICT roal in 21st century educationjfdjdjcjdnsjd
 
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...apidays
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerThousandEyes
 
Mcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Mcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot ModelMcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Mcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot ModelDeepika Singh
 
Exploring Multimodal Embeddings with Milvus
Exploring Multimodal Embeddings with MilvusExploring Multimodal Embeddings with Milvus
Exploring Multimodal Embeddings with MilvusZilliz
 
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024Victor Rentea
 
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024Victor Rentea
 
ICT role in 21st century education and its challenges
ICT role in 21st century education and its challengesICT role in 21st century education and its challenges
ICT role in 21st century education and its challengesrafiqahmad00786416
 
"I see eyes in my soup": How Delivery Hero implemented the safety system for ...
"I see eyes in my soup": How Delivery Hero implemented the safety system for ..."I see eyes in my soup": How Delivery Hero implemented the safety system for ...
"I see eyes in my soup": How Delivery Hero implemented the safety system for ...Zilliz
 

Dernier (20)

Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
 
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...
 
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
 
Vector Search -An Introduction in Oracle Database 23ai.pptx
Vector Search -An Introduction in Oracle Database 23ai.pptxVector Search -An Introduction in Oracle Database 23ai.pptx
Vector Search -An Introduction in Oracle Database 23ai.pptx
 
Why Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businessWhy Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire business
 
FWD Group - Insurer Innovation Award 2024
FWD Group - Insurer Innovation Award 2024FWD Group - Insurer Innovation Award 2024
FWD Group - Insurer Innovation Award 2024
 
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, AdobeApidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
 
Platformless Horizons for Digital Adaptability
Platformless Horizons for Digital AdaptabilityPlatformless Horizons for Digital Adaptability
Platformless Horizons for Digital Adaptability
 
Strategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherStrategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a Fresher
 
presentation ICT roal in 21st century education
presentation ICT roal in 21st century educationpresentation ICT roal in 21st century education
presentation ICT roal in 21st century education
 
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
Understanding the FAA Part 107 License ..
Understanding the FAA Part 107 License ..Understanding the FAA Part 107 License ..
Understanding the FAA Part 107 License ..
 
Mcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Mcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot ModelMcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Mcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot Model
 
Exploring Multimodal Embeddings with Milvus
Exploring Multimodal Embeddings with MilvusExploring Multimodal Embeddings with Milvus
Exploring Multimodal Embeddings with Milvus
 
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
 
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
 
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
 
ICT role in 21st century education and its challenges
ICT role in 21st century education and its challengesICT role in 21st century education and its challenges
ICT role in 21st century education and its challenges
 
"I see eyes in my soup": How Delivery Hero implemented the safety system for ...
"I see eyes in my soup": How Delivery Hero implemented the safety system for ..."I see eyes in my soup": How Delivery Hero implemented the safety system for ...
"I see eyes in my soup": How Delivery Hero implemented the safety system for ...
 

RETOOLING NIGERIAS ELECTRICITY GENERATION SUB – SYSTEM FOR SUSTAINABLE GRID OPERATION

  • 1. NOVATEUR PUBLICATIONS INTERNATIONAL JOURNAL OF INNOVATIONS IN ENGINEERING RESEARCH AND TECHNOLOGY [IJIERT] ISSN: 2394-3696 VOLUME 6, ISSUE 12, Dec.-2019 7 | P a g e RETOOLING NIGERIAS ELECTRICITY GENERATION SUB – SYSTEM FOR SUSTAINABLE GRID OPERATION C. U. OKOYE S. A. OMOLOLA N. O. ADELAKUN I. BITRUS Department of Electrical / Electronic Engineering, the Federal Polytechnic, Ilaro. Ogun State, Nigeria, e-mail: cletusucheok@gmail.com ABSTRACT Experts are varied in estimating the amount of power needed for national development. One expert estimated 297,900 MW by the year 2030 using a 13 percent Gross Domestic Product (GDP). The Power Sector Road Map’s aspiration is 40,000 MW by the year 2020 while the preferred Vision 20:2020 target is 40GW (40,000 MW) available capacity. Vision 20:2020 further proposed that hydro sources contribute 10% of this value; thermal, 80%; coal, 6% and renewables, 4%. However, as at December 2017, Nigeria’s total installed generating capacity was 12,324.40 MW. In order to assess the fundamentals and proffer solutions for the improvement of power generation to meet popular expectations, this work analyses the installed capacities of the nation from 1986 – 1995, on the one hand and from 2007 – 2016, on the other hand using graphical illustrations and tables. The gap between the two time phases was deliberate to create some effect. The results show that over the years, there has been an apparent, non – challance towards systematic development of Nigeria’s power sector. To put a check to this deteriorating condition / trend, useful suggestions have been made. KEYWORDS: power station, installed capacity, vandalisation, frequency control. INTRODUCTION According to Sambo et al (2009), the energy demand projection for Nigeria by the year 2030 is estimated at 297,900 MW based on 13 percent Gross Domestic Product (GDP). The corresponding energy supply within the same period is projected to be 276,229 MW. The Power Sector Road Map aspiration is 40,000 MW by the year 2020 (KPMG, 2012). In contrast, Nigeria has 27 power plants with total installed capacity of 12,324.40 MW as at the end of December, 2017 (Okoye, 2019a; NCC, 2017). However, quite a good number of these are not operational, resulting in further decline in power produced for consumption. In fact, the average available capacity is 6871.25 MW which is just 55.8% of the total installed capacity. Recently (Ajibade, 2019a) shows that ten out of the 27 generating plants were shut down for some reasons. Worse still, about 4,000 MWof electricity was said to be stranded (not evacuated) by the relevant authority (Ajibade, 2019b). In addition, the Afam power station (gas - powered) was constructed way back in 1965 and had six of its units rehabilitated in 1982. The Delta plant (also gas - fired) was built in 1966; five of the generating units were rehabilitated in 1990. Even Egbin gas powered plant with highest installed capacity of 1320 MW was constructed in 1986. Nigeria’s oldest hydropower plant (Kainji) became operational in 1968 and is now 51year old (Okoro, 2001; Okoye& Ali, 2010; Okoye et al, 2017; Okoye et al, 2018a; Okoye et al, 2018b). Gas Supply is critical factor in power value chain.Apart from the three hydropower stations, the rest of the plants depend on gas for their operation. According to NSE (2017), Nigeria’s oil and gas infrastructure is in power state and is on the verge of failure and needs urgent rehabilitation to prevent complete failure. All along, the Generation companies (Gencos) Transmission Company (Transco) and the Distribution Companies (Discos), the tripod on which power sector is standing keep shifting blames for poor power generation. For instance, when the Gencos alleged sometime in October, 2019 that 4000 MW of power was stranded, the Discos denied that no power was stranded. An argument levelled against Transco for inability to wheel power to Discos is the fragile nature of the transmission network. Transco turned around to blame poor generation on gas shortage on the one hand, and inability of Discos to take more load, on the other hand. Vandals are also fingered at as contributing to the crisis in power sector because of their illegal activities (NCC, 2018).
  • 2. NOVATEUR PUBLICATIONS INTERNATIONAL JOURNAL OF INNOVATIONS IN ENGINEERING RESEARCH AND TECHNOLOGY [IJIERT] ISSN: 2394-3696 VOLUME 6, ISSUE 12, Dec.-2019 8 | P a g e For instance, the Sagamu – Ijebu Ode 132 kV lines and the New Haven OturkpoYandev 132 kV lines were some time ago vandalized; throwing some states into total darkness. (Okoye, 2015) The result of all this is that power generation keeps fluctuating between 1500 MW and 3500 MW. This work seeks to improve the power supply in Nigeria by data – based analysis of key issues. MATERIALS AND METHODS Part of the planning stage of this research work was visit to the National Control Centre. (NCC), the Transmission Company of Nigeria (TCN) both at Osogbo, Nigeria; Olorunsogo thermal power station and further field trips to 15 MVA, 33 / 11 kV substation at Ilaro, Ogun State, Nigeria. Frequency control to enhance Voltage Profile and System Stability was observed at the NCC. Any time there is less MW electrical load demanded, frequency would rise above 50Hz. An increase in MW electrical load demanded would lead to a fall in frequency below the standard 50Hz. In both cases, poor voltage profile and system instability would result. Key technical staff at the various places visited were also interviewed and information garnered further enriched the work. Besides useful information were gathered from literature such as Nigeria’s Economic Recovery Growth Plan (ERGP) 2017 – 2020, Electric Power Infrastructure; The Nigerian Infrastructure Report Card 2017, and various Annual Technical Reports of the NCC and selected publications of the Central Bank of Nigeria Bulletins and Bureau for Public Enterprises. To further organise the work, data on installed capacity by year for 10 years (1986 - 1995) was collected and tagged Batch I. Then followed by data on installed capacity for another 10 years (2007 - 2016) called Batch II. The gap (1996 - 2006) between Batch 1 and Batch II was deliberately created for effect so that the degree of capacity addition 11 years after Batch I could be better felt or assessed. Table 1.0 Installed capacity by year (1986 - 1995) in MW, Batch I S/N Year Installed Capacity (MW) 1 1986 4548.0 2 1987 4548.0 3 1988 4548.0 4 1989 4548.0 5 1990 4548.0 6 1991 4548.0 7 1992 4548.0 8 1993 4548.6 9 1994 4548.6 10 1995 4548.6 Source: National Control Centre & Central Bank of Nigeria Bulletin Table 2.0 Installed capacity by year (2007 - 2016) in MW, Batch II S/N Year Installed Capacity (MW) 1 2007 8138.00 2 2008 8469.50 3 2009 8702.25 4 2010 8425.40 5 2011 8910.40 6 2012 9955.40 7 2013 10915.40 8 2014 11165.40 9 2015 12132.40 10 2016 12310.40 Source: National Control Centre
  • 3. NOVATEUR PUBLICATIONS INTERNATIONAL JOURNAL OF INNOVATIONS IN ENGINEERING RESEARCH AND TECHNOLOGY [IJIERT] ISSN: 2394-3696 VOLUME 6, ISSUE 12, Dec.-2019 9 | P a g e Table 3.0 Age of major power stations in Nigeria’s national grid S/N Power station Location Installed capacity MW Source of energy Year of Construction 1 Kainji Kaiji, Niger State 760 Hydro 1968 2 Jebba Jebba, Niger State 540 Hydro 1985 3 Shiroro Shiroro, Niger State 600 Hydro 1989 4 Egbin Egbin, Lagos State 1320 Gas 1986 5 Afam (IV - V) Afam, Rivers State 711 (6 x 77, 1982) Gas 1965, 1982 6 Sapele Sapele, Delta State 1020 Gas 1978 / 1981 7 Delta Ughelli, Delta State 912 (5 x 100, 1990) Gas 1966, 1990 8 Oji Oji, Achi, Enugu State 30 (scrapped) Coal 1956 Source: National Bureau of Public Enterprises and National Control Centre, Osogbo. RESULTS AND DISCUSSION To further deduce some meanings from Tables 1.0, the data is used to plot the graph shown in fig 1.0 Fig. 1.0: Graphical illustration of Capacity addition over the years (1986 - 1995) It should be observed in Fig 1.0 that no new capacity was added in the entire seven years (1986 - 1992). It was only in 1993 that a slight addition was made only to remain so for the rest of 1994 and 1995. Similarly, Fig 2.0 results when data in Table 2.0 was plotted. From Table 2.0 and Fig 2.0, after 11 years had elapsed, it was observed that installed capacity has risen to 8,138.0MW as at 2007. The argument is that it took about11 years from 1995 to attain an additional installed capacity of about 3.6 MW from the 1995 level. Fig 2.0 further shows that from 2011, there was a rise in capacity addition but it was not remarkable. 4545.0 4545.5 4546.0 4546.5 4547.0 4547.5 4548.0 4548.5 4549.0 1986 1987 1988 1989 1990 1991 1992 1993 1994 1995 InstalledCapacity(MW) Years
  • 4. NOVATEUR PUBLICATIONS INTERNATIONAL JOURNAL OF INNOVATIONS IN ENGINEERING RESEARCH AND TECHNOLOGY [IJIERT] ISSN: 2394-3696 VOLUME 6, ISSUE 12, Dec.-2019 10 | P a g e Fig. 2.0: Graphical illustration of Capacity addition, (2007 - 2016) Furthermore, attention is drawn to Table 3.0 where all the major power plants are fast aging and approaching end of their service life with Kainji, for instance, being 51 years. It is, therefore obvious that their performance has declined. Comparatively, the U.S. electric grid (Hicks, 2012) comprises over 5000 state-of-the-art power plants operating at high efficiency. To further establish or size – up the extent capacity addition was pursued or carried out even after 11 whole years have passed / elapsed, Tables 1.0 and 2.0 were plotted on the same graph to produce Fig 3.0. Fig. 3.0: Graphical illustration of relative development in capacity addition, 1986 – 1995; 2007 – 2016 In addition, Fig 4.0. is the further representation of Tables 1.0 and 2.0 using bar chart. Where the picture of the issues at stake are even much more clearer. 0.00 2000.00 4000.00 6000.00 8000.00 10000.00 12000.00 14000.00 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 InstalledCapacity(MW) Years 0.0 2000.0 4000.0 6000.0 8000.0 10000.0 12000.0 14000.0 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 1986 1987 1988 1989 1990 1991 1992 1993 1994 1995 InstalledCapacity(MW) Years Installed Capacity 1986 - 1995 (MW) Installed Capacity 2007 - 2016 (MW)
  • 5. NOVATEUR PUBLICATIONS INTERNATIONAL JOURNAL OF INNOVATIONS IN ENGINEERING RESEARCH AND TECHNOLOGY [IJIERT] ISSN: 2394-3696 VOLUME 6, ISSUE 12, Dec.-2019 11 | P a g e Fig. 4.0: Chart comparing capacity addition, 1986 – 1995 and 2007 - 2016 The following are suggested for improvement of power generating capacity of Nigeria:  Nigeria is not using her coal resources to generate electricity, though coal is abundant in 18 states of the federation (Otenaike & Onifade, 2017) with astonishing reserve of 2.7 billion metric tonnes that is said could last for 200 years (Amoda, 2016; Okoye 2018b). Whereas coal is used to generate 41% of electricity used worldwide, 72 – 93% of South Africa’s energy demand is met from coal. (ALAMAU, 2016). According to Otenaike and Onifade (2017), China generates 79% of her electric power from coal; India (68%); Poland (87%); Morocco (51%) and U.S.A (45%). The 30MW coal – fired power plant in Oji, Enugu State scrapped long time ago should be reactivated and new ones added.  The Independent Power Plants IPPs connected to the grid have approximated 2191 MW of installed capacity with only 1203.40 MW available as at December, 2017 (NCC, 2017). More of such IPPs should be built and conducive environment provided for them. Babcock University’s IPP generates 4.4 MW of power for its use 24 hours daily (Uwandu, 2019).  Research has shown that one of the major problems faced by generating companies is inadequate gas supply. For instance, Opara (2014) reports that 90% of the IPP licenses are non – operational as a result of gas supply shortages. This is a country that has 187 trillion Standard Cubic Feet (SCF) of proven gas reserves and 600 trillion SCF of unproven gas reserves (Sambo, 2008; FRN, 2012). The Nigerian Gas Company (NGC) or whatever organ that is responsible for providing gas supplies should find lasting solution to gas inadequacy.  Huge debts (over one trillion naira) are being owed generating companies by distribution companies (Ajibade, 2019d). The Nigerian Bulk Electricity Trading Company (NBET) Should ensure that Discos pay these debts so that Gencos could improve on their power output. NBET was set up by the federal government of Nigeria to administer and control energy pool.  Another critical factor militating against generation is vandalisation of power infrastructure and gas pipelines. This act of sabotage is obvious everywhere in Nigeria. Without putting this in check, all efforts to improve electricity supply will pay little dividend.  Table 3.0 shows that many power plants are already very old. Thus, they keep failing after due maintenance. Though capital intensive, additional ones should be built as the economy is expanding fast. After all, Nigeria is said to be the largest economy in Africa. 0.0 2000.0 4000.0 6000.0 8000.0 10000.0 12000.0 14000.0 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 1986 1987 1988 1989 1990 1991 1992 1993 1994 1995 Capacityaddition(MW) Years Installed Capacity 1986 - 1995 (MW) Installed Capacity 2007 - 2016 (MW)
  • 6. NOVATEUR PUBLICATIONS INTERNATIONAL JOURNAL OF INNOVATIONS IN ENGINEERING RESEARCH AND TECHNOLOGY [IJIERT] ISSN: 2394-3696 VOLUME 6, ISSUE 12, Dec.-2019 12 | P a g e  It is high time to scale up renewable energy development and deployment in Nigeria. Apart from the advantage of having no obvious negative impact on the environment, it could also provide relief to rural dwellers in remote areas in Nigeria. This will reduce dependence on grid electricity with all its attendant disappointing performances. CONCLUSION As the largest economy in Africa, there is an urgent need to increase power supply in Nigeria. The minimum installed generation capacity proposed by experts is 40,000 MW by the year 2020 but Nigeria is nowhere near this optimistic figure as at present. Rather, the country is grappling with the installed capacity of only 12,324 MW with only about half of it suitable and ready for electricity generation. The study has shown graphically that from 1986 to date, capacity addition has not been anything impressive and points at some obvious neglect of power sector over the years, coal is a major source of power in countries like China (79.1%), India (68%), Poland (87%), Germany (41%), Israel (58%), and even Morocco (51%). Nigeria with coal deposits in 18 states and huge reserve of 2.7 billion metric tonnes is expected to have been a leader in coal – fired power generation. Unfortunately, even the only coal – fired power station in Oji, Enugu State, commissioned in 1956 has been scrapped and nobody appears to be thinking about it anymore. Measures aimed at power supply for Nigeria’s 200 million people and, of course, Benin and Niger Republics which Nigeria sales electricity to have been suggested. REFERENCES 1) Ajibade, A. (2019a), Ending Incessant Output Shortfalls, The Nation Newspaper, Thursday November 14, P. 14. 2) Ajibade, A. (2019b), Much Ado about Stranded 4000 MW of Electricity, The Nation Newspaper, Thursday October 24, P. 37 3) Ajibade, A. (2019c), Six Years after Privatisation, Power Woes Linger, The Nation Newspaper, Thursday November 7, P. 35 4) Ajibade, A. (2019d), Why Power Generation is Low, The Nation Newspaper, Thursday 26, P. 35 5) Alamau,O. (2016), African Energy Commission: Accelerating Africa’s Economic Growth through Efficient Energy Production 6) Amoda, O. (2016), Power Distribution Demand Side Management in Developing Economics, 13th Distinguished Electrical / Electronic Engineering Annual Lecture, The Nigerian Institution of Electrical / Electronic Engineers (NIEEE). 7) FRN (2012), Investment Opportunities in the Nigerian Power Sector, Federal Republic of Nigeria. 8) Hicks, C (2012), The Smart Grid, ERB, University of Michigan 9) KPMG (2012), Nigeria Power Guide, Vol. 1 10) NCC (2017), Grid Operations 2017: Annual Technical Report, National Control Centre, Osogbo, Nigeria. 11) NCC (2018), Grid Operations 2018: Annual Technical Report, National Control Centre, Osogbo, Nigeria. 12) NSE (2017), The Nigerian Infrastructure Score Card (2017), The Nigerian Society of Engineers 13) Okoro, C. C. (2001), Towards Sustainable National Grid System, Proceedings, The Nigerian Society of Engineers (Electrical Division). 14) Okoye, C.U & Ali, N.A. (2010), Towards Efficient Electricity Generation: A Case Study of 15) Nigeria’s Electricity Facilities, Journal of Engineering Science, Vol. 2, No. 1, Pan African Book Company, Ghana 16) Okoye, C. U. (2015), Nigeria’s 132 / 330 kV transmission Line: Issues, Challenges and Solutions, International Journal of Scientific Innovation and Sustainable Development, Vol. 5, No. 2. 17) Okoye, C. U., Adeniji, O. A. and Sunmonu, A. O. (2017), A Study and Performance Evaluation of Olorunsogo Thermal Power Plant in Nigeria, International Journal of Engineering Sciences and Research Technology, Vol. 6, issue 12.
  • 7. NOVATEUR PUBLICATIONS INTERNATIONAL JOURNAL OF INNOVATIONS IN ENGINEERING RESEARCH AND TECHNOLOGY [IJIERT] ISSN: 2394-3696 VOLUME 6, ISSUE 12, Dec.-2019 13 | P a g e 18) Okoye, C. U., Bitrus, I., Alao, M. J., Adelakun, N. O. &Abdulhamid, I. G. (2018a), A Study and Analysis of Energy Generation and Consumption in Dangote Cement Plant, Ibese, Nigeria, Global Journal of Advanced Engineering Technologies and Sciences, Vol. 5, No 11. 19) Okoye, C. U.(2018b), Enhancing Electricity Generation Capacity in Africa Through 20) Revamping coal – fired power plants: A Case Study of Nigeria, Paper presented at 40th Anniversary and International Conference, The Commonwealth Association of Technical Universities and Polytechnics in Africa (CAPA), Abuja, Nigeria. 21) Okoye, C. U., and Omolola, S. A. (2019a), A Study and Evaluation of Power Outages on 132kV 22) Transmission Network in Nigeria for Grid Security, The International Journal of Engineering and Science, Vol. 8, Issue 11, Pp 53 - 57 23) Okoye, C. U. (2019b), Nigeria’s Electric Grid: Sharing Field Experience in Search of Grid Integrity, Technical Paper presented at the Monthly Meeting of the Nigerian Society of Engineers, Ilaro Branch, Ogun State, Nigeria, February 13. 24) Opara, S. (2014), 90% Power Licences Idle due to Gas Shortage, The Punch, June 13, P. 29. 25) Otenaike, S. &Onifade, G. (2017), Coal as a Source of Electricity in Nigeria, The Consulting Engineer, May – August, Vol. 4, No. 1. 26) Sambo, A. S.; Garba, B.; Zarma, I. H. &Gaji, M. M. (2009), Electricity Generation and the present challenges in the Nigeria Power Sector, Energy Commission of Nigeria, Abuja, Nigeria. 27) Sambo, A. S. (2008), Matching Electricity Supply with Demand in Nigeria, International Association for Energy Economics, 4th quarter. 28) Uwandu, E. (2019), How we Generate 24 – hour Power Supply, Vanguard Newspapers, Thursday September 12, P. 38.