SlideShare une entreprise Scribd logo
1  sur  19
CRASHING AND
COST PLAN
PREPARED BY:
JULIUS N. CUARESMA
BSCE 5-1
REDUCING TIME AND COST
1. To avoid penalties for not completing the project on time.
2. To take advantage of monetary incentives for completing
the project on or before the target date.
3. To free the resources such as money, equipment and men
for use on other projects.
4. Reduce indirect costs associated with the project such as:
a. Facilities and equipment cost
b. Supervision cost
c. Labor cost
d. Personnel cost
Crashing Certain Activities
1. The use of additional funds to support the
following
2. Additional personnel
3. Have more efficient equipment
4. Relaxing of some work specification
The manager needs the
following informations:
1. Regular time and crash time estimates
for each activity.
2. Regular cost and crash estimate for each
activity.
3. A list of activities that are on the critical
path.
From the economic view, activities should
be crashed according to crashing costs.
1. The lowest cost should be crashed first
2. Crashing should continue as long as the
cost to crash is less than the benefits
received from crashing.
Procedure in Crashing Project
Time
1. Obtain an estimate of regular and crash time
plus the costs of each activity.
2. Determine the length of all paths and their float
time.
3. Determine which activities are on the critical
path.
4. Crash the critical activities in the order of
increasing costs as long as crashing costs do not
exceed benefits.
Example Problem
THE INDIRECT COSTS OF A PROJECT IS P10, 000
PER WEEK UP TO ITS DURATION. THE PROJECT
MANAGER WAS FURNISHED THE FOLLOWING
COST AND TIME INFORMATION.
1. DETERMINE AN OPTIMUM CRASHING PLAN
2. GRAPH THE TOTAL COSTS FOR THE PLAN
ACTIVITY CRASHING POTENTIAL WEEK COSTPER WEEK TOCRASH
A 3 8000
B 3FIRST WEEK 3000
2ND WEEK 4000
C 2 5000
D 1 1000
E 3 5000
F 1 2000
B-14
A-8
C-11 D-6
F-7
E-14
1
2
53
4
SOLUTION:
1. DETERMINE THE PATH LENGTHS AND
IDENTIFY THE CRITICAL PATH.
PATH DURATION IN WEEKS
A,B 22
C,D 17
E,F 21
2. RANK THE CRITICAL ACTIVITIES OF PATH A,B
ACCORDING TO CRASHING COSTS.
ACTIVITY COST PER WEEK TO CRASH
B 3000 1ST WEEK
A 8000
ACTIVITY B HAS THE LOWER CRASHING COST, HENCE, IT
SHOULD BE SHORTENED BY ONE WEEK. THIS WILL REDUCE THE
INDIRECT COSTS BY:
10,000 – 3,000 = 7,000 NET SAVINGS
AT THIS POINT, PATH A,B AND E,F WILL HAVE THE SAME
LENGTH OF 21 WEEKS, THUS BOTH WOULD BE CRITICAL PATH.
3. RANK ACTIVITIES BY CRASHING COSTS ON THE TWO
CRITICAL PATH.
PATH ACTIVITY COST PER WEEK TO CRASH
A-B B 4000
A 8000
E-F F 2000
E 5000
CHOOSE ONE ACTIVITY ON EACH PATH TO
CRASH. SAY B ON ACTIVITY A-B AND F ON
ACTIVITY E-F :
4000 + 2000 = 6000 CRASHING COSTS
10,000 – 6,000 = 4,000 NET SAVINGS
4. VERIFY WHICH PATH MIGHT BE CRITICAL.
PATH A-B AND E-F WOULD BE 20 WEEKS TO
CRASH ONE WEEK AND C-D WOULD STILL BE
17 WEEKS
5. AGAIN, RANK ACTIVITIES ON THE CRITICAL PATH.
CRASH B ON PATH A-B AND E ON PATH E-F:
4,000 + 5,000 = 9,000 CRASHING COSTS
10,000 – 9,000 = 1,000 NET SAVINGS
6. AT THIS POINT, NO FURTHER
IMPROVEMENT IS POSSIBLE. BOTH PATH A-B
ANG PATH E-F HAS 19 WEEKS AND TO
SHORTEN ONE MORE WEEK FROM EACH PATH
WOULD MEAN ANOTHER P8,000 FOR
ACTIVITY A AND P5,000 FOR ACTIVITY E OR A
TOTAL OF P13,000 WHICH EXCEEDS THE
P10,000 POTENTIAL SAVINGS IN INDIRECT
COSTS.
SUMMARY OF THE RESULT SHOWING THE LENGTH OF THE
PROJECT AFTER CRASHING N WEEKS.
SUMMARY OF COSTS
.

Contenu connexe

Tendances

PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERSPLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERSHafiz JUNAID
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project managementRahul Dubey
 
PPT on Construction Costing
PPT on Construction CostingPPT on Construction Costing
PPT on Construction CostingManish Kandpal
 
Lec06 Analysis and Design of T Beams (Reinforced Concrete Design I & Prof. Ab...
Lec06 Analysis and Design of T Beams (Reinforced Concrete Design I & Prof. Ab...Lec06 Analysis and Design of T Beams (Reinforced Concrete Design I & Prof. Ab...
Lec06 Analysis and Design of T Beams (Reinforced Concrete Design I & Prof. Ab...Hossam Shafiq II
 
Construction Planing & Schedule
Construction Planing & ScheduleConstruction Planing & Schedule
Construction Planing & ScheduleVîñõđ Kůmåř
 
OWNERSHIP COST OF CONSTRUCTION PLANT & EQUIPMENT
OWNERSHIP COST OF CONSTRUCTION PLANT & EQUIPMENTOWNERSHIP COST OF CONSTRUCTION PLANT & EQUIPMENT
OWNERSHIP COST OF CONSTRUCTION PLANT & EQUIPMENTConstruction Mechanizer
 
7.2 equivalent uniform annual cost method
7.2 equivalent uniform annual cost method7.2 equivalent uniform annual cost method
7.2 equivalent uniform annual cost methodAli Juma Albahrani
 
8. Rate of return analysis
8. Rate of return analysis8. Rate of return analysis
8. Rate of return analysisMohsin Siddique
 
17. seepage through anisotropic soil (1)
17. seepage through anisotropic soil (1)17. seepage through anisotropic soil (1)
17. seepage through anisotropic soil (1)KingshukMukherjee10
 
Principles of transportation engineering
Principles of transportation engineeringPrinciples of transportation engineering
Principles of transportation engineeringShweta Vantamuri
 
Construction Project Management
Construction Project Management Construction Project Management
Construction Project Management Rajat Nainwal
 
Unit 02 unit – ii project planning and scheduling
Unit 02 unit – ii project planning and schedulingUnit 02 unit – ii project planning and scheduling
Unit 02 unit – ii project planning and schedulingRAMCHANDRA KODAM
 
Time cost optimisation
Time cost optimisationTime cost optimisation
Time cost optimisationCharul Sharma
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULEAjeesh Mk
 
Types of resources in civil engineering field
Types of resources in civil engineering fieldTypes of resources in civil engineering field
Types of resources in civil engineering fieldswetha110
 
Highway & Railway Engineering
Highway & Railway EngineeringHighway & Railway Engineering
Highway & Railway EngineeringGAURAV. H .TANDON
 

Tendances (20)

PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERSPLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
 
Examples on seepage
Examples on seepageExamples on seepage
Examples on seepage
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project management
 
PPT on Construction Costing
PPT on Construction CostingPPT on Construction Costing
PPT on Construction Costing
 
Construction Cost Control
Construction Cost ControlConstruction Cost Control
Construction Cost Control
 
Lec06 Analysis and Design of T Beams (Reinforced Concrete Design I & Prof. Ab...
Lec06 Analysis and Design of T Beams (Reinforced Concrete Design I & Prof. Ab...Lec06 Analysis and Design of T Beams (Reinforced Concrete Design I & Prof. Ab...
Lec06 Analysis and Design of T Beams (Reinforced Concrete Design I & Prof. Ab...
 
Construction Planing & Schedule
Construction Planing & ScheduleConstruction Planing & Schedule
Construction Planing & Schedule
 
OWNERSHIP COST OF CONSTRUCTION PLANT & EQUIPMENT
OWNERSHIP COST OF CONSTRUCTION PLANT & EQUIPMENTOWNERSHIP COST OF CONSTRUCTION PLANT & EQUIPMENT
OWNERSHIP COST OF CONSTRUCTION PLANT & EQUIPMENT
 
7.2 equivalent uniform annual cost method
7.2 equivalent uniform annual cost method7.2 equivalent uniform annual cost method
7.2 equivalent uniform annual cost method
 
8. Rate of return analysis
8. Rate of return analysis8. Rate of return analysis
8. Rate of return analysis
 
17. seepage through anisotropic soil (1)
17. seepage through anisotropic soil (1)17. seepage through anisotropic soil (1)
17. seepage through anisotropic soil (1)
 
Principles of transportation engineering
Principles of transportation engineeringPrinciples of transportation engineering
Principles of transportation engineering
 
Construction Project Management
Construction Project Management Construction Project Management
Construction Project Management
 
Unit 02 unit – ii project planning and scheduling
Unit 02 unit – ii project planning and schedulingUnit 02 unit – ii project planning and scheduling
Unit 02 unit – ii project planning and scheduling
 
Construction Planning
Construction PlanningConstruction Planning
Construction Planning
 
Time cost optimisation
Time cost optimisationTime cost optimisation
Time cost optimisation
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
Types of resources in civil engineering field
Types of resources in civil engineering fieldTypes of resources in civil engineering field
Types of resources in civil engineering field
 
NSCP 2010 , Volume 1
NSCP 2010 , Volume 1NSCP 2010 , Volume 1
NSCP 2010 , Volume 1
 
Highway & Railway Engineering
Highway & Railway EngineeringHighway & Railway Engineering
Highway & Railway Engineering
 

Similaire à Crashing and cost plan-cpm

Rice husk power plant project for finance, subsidy & project related suppor...
Rice husk power plant project   for finance, subsidy & project related suppor...Rice husk power plant project   for finance, subsidy & project related suppor...
Rice husk power plant project for finance, subsidy & project related suppor...Radha Krishna Sahoo
 
Comparative characteristics of pert and cpm
Comparative characteristics of pert and cpmComparative characteristics of pert and cpm
Comparative characteristics of pert and cpmKinshook Chaturvedi
 
Lo4a benefit cost analysis (nabil)
Lo4a benefit  cost analysis (nabil)Lo4a benefit  cost analysis (nabil)
Lo4a benefit cost analysis (nabil)Abdulaziz AlSuwaidi
 
Development project appraisal and sd(L6)1
Development project appraisal and sd(L6)1Development project appraisal and sd(L6)1
Development project appraisal and sd(L6)1Farha Sharmin
 
CPM-PERT-Examples .pptx
CPM-PERT-Examples .pptxCPM-PERT-Examples .pptx
CPM-PERT-Examples .pptxssuser9b876d
 
Thailand UNDP-GIZ workshop on CBA - Enhancing resilience in Thailand through ...
Thailand UNDP-GIZ workshop on CBA - Enhancing resilience in Thailand through ...Thailand UNDP-GIZ workshop on CBA - Enhancing resilience in Thailand through ...
Thailand UNDP-GIZ workshop on CBA - Enhancing resilience in Thailand through ...UNDP Climate
 
Project Management Diagnostics for Time Management
Project Management Diagnostics for Time ManagementProject Management Diagnostics for Time Management
Project Management Diagnostics for Time ManagementApril Davies, MA, CAPM
 
Lecture7_2021_v2.pdf
Lecture7_2021_v2.pdfLecture7_2021_v2.pdf
Lecture7_2021_v2.pdfssuserc9da59
 
LectureProjectPlanning.ppt
LectureProjectPlanning.pptLectureProjectPlanning.ppt
LectureProjectPlanning.pptanhdbh
 
Cost Benefit Analysis in Public Project Appraisal (PPAC)
Cost Benefit Analysis in Public Project Appraisal (PPAC)Cost Benefit Analysis in Public Project Appraisal (PPAC)
Cost Benefit Analysis in Public Project Appraisal (PPAC)Neil Mathew
 
ACT04Ch7PM - Project Crashing.pptx
ACT04Ch7PM - Project Crashing.pptxACT04Ch7PM - Project Crashing.pptx
ACT04Ch7PM - Project Crashing.pptxssuser85ddaa
 
Devry proj 586 final exam set 3 new
Devry proj 586 final exam set 3 newDevry proj 586 final exam set 3 new
Devry proj 586 final exam set 3 newuopassignment
 

Similaire à Crashing and cost plan-cpm (20)

Rice husk power plant project for finance, subsidy & project related suppor...
Rice husk power plant project   for finance, subsidy & project related suppor...Rice husk power plant project   for finance, subsidy & project related suppor...
Rice husk power plant project for finance, subsidy & project related suppor...
 
Comparative characteristics of pert and cpm
Comparative characteristics of pert and cpmComparative characteristics of pert and cpm
Comparative characteristics of pert and cpm
 
Pert Analysis
Pert AnalysisPert Analysis
Pert Analysis
 
Cost studies model_answers_2014_jan
Cost studies model_answers_2014_janCost studies model_answers_2014_jan
Cost studies model_answers_2014_jan
 
Activity Based Costing
Activity Based CostingActivity Based Costing
Activity Based Costing
 
vk1
vk1vk1
vk1
 
Lo4a benefit cost analysis (nabil)
Lo4a benefit  cost analysis (nabil)Lo4a benefit  cost analysis (nabil)
Lo4a benefit cost analysis (nabil)
 
Development project appraisal and sd(L6)1
Development project appraisal and sd(L6)1Development project appraisal and sd(L6)1
Development project appraisal and sd(L6)1
 
Project control
Project controlProject control
Project control
 
Unit-7.pdf
Unit-7.pdfUnit-7.pdf
Unit-7.pdf
 
CPM-PERT-Examples .pptx
CPM-PERT-Examples .pptxCPM-PERT-Examples .pptx
CPM-PERT-Examples .pptx
 
Thailand UNDP-GIZ workshop on CBA - Enhancing resilience in Thailand through ...
Thailand UNDP-GIZ workshop on CBA - Enhancing resilience in Thailand through ...Thailand UNDP-GIZ workshop on CBA - Enhancing resilience in Thailand through ...
Thailand UNDP-GIZ workshop on CBA - Enhancing resilience in Thailand through ...
 
feasibility study
 feasibility study feasibility study
feasibility study
 
Project Management Diagnostics for Time Management
Project Management Diagnostics for Time ManagementProject Management Diagnostics for Time Management
Project Management Diagnostics for Time Management
 
Lecture7_2021_v2.pdf
Lecture7_2021_v2.pdfLecture7_2021_v2.pdf
Lecture7_2021_v2.pdf
 
LectureProjectPlanning.ppt
LectureProjectPlanning.pptLectureProjectPlanning.ppt
LectureProjectPlanning.ppt
 
Cost Benefit Analysis in Public Project Appraisal (PPAC)
Cost Benefit Analysis in Public Project Appraisal (PPAC)Cost Benefit Analysis in Public Project Appraisal (PPAC)
Cost Benefit Analysis in Public Project Appraisal (PPAC)
 
ACT04Ch7PM - Project Crashing.pptx
ACT04Ch7PM - Project Crashing.pptxACT04Ch7PM - Project Crashing.pptx
ACT04Ch7PM - Project Crashing.pptx
 
Devry proj 586 final exam set 3 new
Devry proj 586 final exam set 3 newDevry proj 586 final exam set 3 new
Devry proj 586 final exam set 3 new
 
Crashing
CrashingCrashing
Crashing
 

Dernier

VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapRishantSharmaFr
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Standamitlee9823
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 
22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf203318pmpc
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Arindam Chakraborty, Ph.D., P.E. (CA, TX)
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaOmar Fathy
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptxJIT KUMAR GUPTA
 
Unit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfUnit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfRagavanV2
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projectssmsksolar
 
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueBhangaleSonal
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringmulugeta48
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfRagavanV2
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptNANDHAKUMARA10
 

Dernier (20)

VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
Unit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfUnit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdf
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects
 
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 

Crashing and cost plan-cpm

  • 1. CRASHING AND COST PLAN PREPARED BY: JULIUS N. CUARESMA BSCE 5-1
  • 2. REDUCING TIME AND COST 1. To avoid penalties for not completing the project on time. 2. To take advantage of monetary incentives for completing the project on or before the target date. 3. To free the resources such as money, equipment and men for use on other projects. 4. Reduce indirect costs associated with the project such as: a. Facilities and equipment cost b. Supervision cost c. Labor cost d. Personnel cost
  • 3. Crashing Certain Activities 1. The use of additional funds to support the following 2. Additional personnel 3. Have more efficient equipment 4. Relaxing of some work specification
  • 4. The manager needs the following informations: 1. Regular time and crash time estimates for each activity. 2. Regular cost and crash estimate for each activity. 3. A list of activities that are on the critical path.
  • 5. From the economic view, activities should be crashed according to crashing costs. 1. The lowest cost should be crashed first 2. Crashing should continue as long as the cost to crash is less than the benefits received from crashing.
  • 6. Procedure in Crashing Project Time 1. Obtain an estimate of regular and crash time plus the costs of each activity. 2. Determine the length of all paths and their float time. 3. Determine which activities are on the critical path. 4. Crash the critical activities in the order of increasing costs as long as crashing costs do not exceed benefits.
  • 7. Example Problem THE INDIRECT COSTS OF A PROJECT IS P10, 000 PER WEEK UP TO ITS DURATION. THE PROJECT MANAGER WAS FURNISHED THE FOLLOWING COST AND TIME INFORMATION. 1. DETERMINE AN OPTIMUM CRASHING PLAN 2. GRAPH THE TOTAL COSTS FOR THE PLAN
  • 8. ACTIVITY CRASHING POTENTIAL WEEK COSTPER WEEK TOCRASH A 3 8000 B 3FIRST WEEK 3000 2ND WEEK 4000 C 2 5000 D 1 1000 E 3 5000 F 1 2000
  • 10. SOLUTION: 1. DETERMINE THE PATH LENGTHS AND IDENTIFY THE CRITICAL PATH. PATH DURATION IN WEEKS A,B 22 C,D 17 E,F 21
  • 11. 2. RANK THE CRITICAL ACTIVITIES OF PATH A,B ACCORDING TO CRASHING COSTS. ACTIVITY COST PER WEEK TO CRASH B 3000 1ST WEEK A 8000 ACTIVITY B HAS THE LOWER CRASHING COST, HENCE, IT SHOULD BE SHORTENED BY ONE WEEK. THIS WILL REDUCE THE INDIRECT COSTS BY: 10,000 – 3,000 = 7,000 NET SAVINGS AT THIS POINT, PATH A,B AND E,F WILL HAVE THE SAME LENGTH OF 21 WEEKS, THUS BOTH WOULD BE CRITICAL PATH.
  • 12. 3. RANK ACTIVITIES BY CRASHING COSTS ON THE TWO CRITICAL PATH. PATH ACTIVITY COST PER WEEK TO CRASH A-B B 4000 A 8000 E-F F 2000 E 5000 CHOOSE ONE ACTIVITY ON EACH PATH TO CRASH. SAY B ON ACTIVITY A-B AND F ON ACTIVITY E-F : 4000 + 2000 = 6000 CRASHING COSTS 10,000 – 6,000 = 4,000 NET SAVINGS
  • 13. 4. VERIFY WHICH PATH MIGHT BE CRITICAL. PATH A-B AND E-F WOULD BE 20 WEEKS TO CRASH ONE WEEK AND C-D WOULD STILL BE 17 WEEKS
  • 14. 5. AGAIN, RANK ACTIVITIES ON THE CRITICAL PATH. CRASH B ON PATH A-B AND E ON PATH E-F: 4,000 + 5,000 = 9,000 CRASHING COSTS 10,000 – 9,000 = 1,000 NET SAVINGS
  • 15. 6. AT THIS POINT, NO FURTHER IMPROVEMENT IS POSSIBLE. BOTH PATH A-B ANG PATH E-F HAS 19 WEEKS AND TO SHORTEN ONE MORE WEEK FROM EACH PATH WOULD MEAN ANOTHER P8,000 FOR ACTIVITY A AND P5,000 FOR ACTIVITY E OR A TOTAL OF P13,000 WHICH EXCEEDS THE P10,000 POTENTIAL SAVINGS IN INDIRECT COSTS.
  • 16. SUMMARY OF THE RESULT SHOWING THE LENGTH OF THE PROJECT AFTER CRASHING N WEEKS.
  • 18.
  • 19. .