SlideShare une entreprise Scribd logo
1  sur  4
Télécharger pour lire hors ligne
CHANNEL TUNNEL
TUNNELS CONSTRUCTION
Author Pierre-Jean Pompée

Scope
Within the 5 years following contract award,
3 parallel tunnels, 50.5 km each, had to be
driven and lined with high-strengh precast
segments : 38 km undersea, 3.2 underland
in France, 9.3 km underland in UK. 2/3 of
the total had to be excavated from UK side,
and 1/3 from French side where ground
conditions were unfavourable. 6 drives
(total 12), 3 to the sea and 3 to the land
have been conducted from each of the two
tunneling sites, located as close as possible
to the sea : Shakespeare Cliff (west of
Dover) on the UK side, and Sangatte (west
of Calais) in France.
The service tunnel (ST) has a internal
diameter of 4.8 m (excavated diam.5.8 m).
The two running tunnels (RT) are at 30 m
distance, lined diameter is 7.6 m
(excavated diam.8.8 m). They are
connected together by 194 piston relief
ducts (every 250 m, diam 2 m), and by 270
cross passages (every 375 m) and 210
technical rooms (all diam 3.3 m) to the
service tunnel, requiring special cast iron
segments at each junction.

Geology and alignment
Many geotechnical investigations have
been carried out across the Channel since
1875, including over 100 boreholes. Total
information available including final
investigation after contract award and
geophysical survey undertaken in 1988,
(specifically for crossing beneath the Fosse
Dangeard and crossovers sites),comprised:
- 120 marine boreholes and about 1,000
km of geophysical (seismic reflection),
traverse lines,
- adits and short lenght of tunnels
excavated during previous attempts.
Optimum tunnelling conditions are within
the Chalk Marl, clayey carbonate
mudstone, weak (20 to 200 bars),
homogeneous rock, believed to be mainly
impermeable, with any water restricted to
discontinuities such as faults or fissures
concentrated on French side. It is a
tunnelling medium adequate for TBMs.

High precision alignment
The tunnel alignment was a critical stage in
the design process. It was later optimised
using experience gained while driving the
service tunnel itself, and design
developments at the crossover and
pumping stations, avoiding fault zones
which would reduce tunnelling progress.
Geometrical criterias applicable to a high-

Above : View of a running tunnel on French side at the beginning of the tunneling phase (1988), showing temporary
fixed equipments (water pipes, ventilation duct diam 1600mm, power and radio communications cables, double track
and walways...). Below : Tunneling progress on 29th of April 1990, 7 months before first undersea breakthrough,
showing forecasted ("M"), and final (black balls) meeting points.

speed railway impose large radius curves,
leading to drive 150 km of tunnels within
150 mm tolerances: 40 mm for
topography, 55 for TBM steering, 25 for
segments manufacturing/erection (ring
axis), 30 between surfaces of adjacent
segments. TBMs, launched over 38 km
distance, had to meet with precision !

Topographical survey
Different systems in UK and France
British maps are based on Mercator
system, French maps on Lambert system.
Sea level on both sides differed by 440 mm
according to a 1958 study, reduced at 300±
80 mm in 1987, measured at 360 mm after
breakthrough.
Joint mapping and levelling
Mercator system was adopted, but based
on the mid-Channel 1°30 East meridian.
Satellite Global Positioning System (GPS,
precision 5 cm for 50 km) was used and
water movement studies reduced levelling
uncertainty , leading to the RTM87 grid,
and the NTM88 levelling ("Reseau" and
"Niveau TransManche"). Final orientation

to the North required a gyrotheodolite with
precise astronomical calibration and
correction of all horizontal angles, locally
different due to the Mercator system.
Survey brough underground
RTM87 was brought underground trough
the inclined adits of the UK side and the
Sangatte shaft in France through
benchmarks set at the tunnels starting
points with a precision of 0.6 mm (5 mm
error would have meant 1.5 m at 15 km
distance). Grid was relayed along TBMs
journey with computer correction of
temperature, pressure, hygrometry. After
first breakthrough, a reference point was at
least available for running tunnels survey.
Geological profile and description of the works. Tunnel slope is between 0.2% and 1.1 %, often found at 0.6% on UK side and at 1.1% on French side.

Breakthrough actual precision
Once the marine service tunnel TBMs
stopped at 100 m distance, measured
lateral offset was 358 mm; levelling : 58
mm; chainage :75 mm. Readjustment over
the final 50 m, hand excavated, produced a
smooth junctioning of the two drives.
Running tunnels all came out within the 15
cm tolerance.Underland TBMs came out at
less than 2 cm from the original alignment.

Tunnel Boring Machines
Design criteria on French side
Critical programme and unfavourable
geology determined a whole tunnelling
system (TBMs, back-up systems, linings,
and overall logistics). Design criteria were:
- progress without ground treatment in
watery conditions in France, especially
the first 4 km undersea (where the chalk
is fractured), and 3.2 km underland,
(below water table).
- progress at high speed (4.4 lm/h) in
dry, fair to good, ground conditions.
- ensure safety and reliability for a
highly complex, massive, tunnelling

logistics designed for peak boring
rates. A huge, waterproof, shaft housed
all French tunnels logistics at Sangatte.

TBMs description
11 TBMs were ordered by TML. On the UK
side, 6 open, full-face TBMs (3 undersea
and 3 underland) were used in conjunction
with unbolted, expanded precast concrete
linings by use of wedge-shaped key.
The 5 French TBMs have been launched
from the Sangatte Shaft: 3 undersea, 2
underland, one being turned back to drive
the north running tunel underland. There
are full face, earth-pressure type, and allow
erection of watertight precast segments
inside the shield concurrently with face
excavation. Their unique design combines
technologies for both soft ground
underwater and hard rock.
The 3 undersea French TBMs include
articulated double shield operating in closed
mode in wet zones (minimum rate of 3
m/h), or in open mode at high speed in dry
zones. Cutter chambers are sealed to
withstand a hydrostatic pressure of 11 bars:
excavated chalk had to pass through a twostage pressure lock before being ejected at
atmospheric pressure into the muck
wagons. Containment is achieved at the
end of the spoil extraction screw either
through a dual discharge pump system or
through a second screw creating a plug.
The 2 underland French TBMs included a
single shield, Archimedes screw
containment and a ″casing rotator″, to

withstand a hydrostatic pressure of 3 bars.

French TBMs guidance system
The ZED 260 guidance system used a laser
beam, set up to a predetermined alignment,
and received on a screen on the cutting
head. After analisis, an on-board computer
displayed, in the cab, differences betwwen
designed and actual TBM's 3 dimensional
position, allowing the driver to correct by
steering to zero. Steering was achieved by
selection of the push rams housed in the
telescopic section.
Real time monitoring in the cab of
complete operational status of the TBM
T3 process was ensured by an IBM 7532
superviser: pressures, speed, stroke of
hydraulic jacks, spoil rotating screws and
tail seals, but also electrical intensity and
instant power of the 12 motors, water
injected flows - 20 bars and 30 bars - and
earthpressure at 5 different locations of
cutting chamber, plus rotating head
position. Programmable controlers
managed overall process safety and failure
detection (ALSPA C350, 2000 I/O), grout
injection (SIEMENS 115V), and segments
feeder (TELEMECANIQUE TSX47-20).
Main data were plotted and/or transmitted
to surface. Long term tracing of segments
rings main data was automatically
available. Video screens showed conveyors
operations.

Probes, ground treatment
Site investigation boreholes covered a grid
of 1 km width only, leading to use the

Left : Probes on French side around the T1 (marine Service tunnel TBM). Below : Description of the TBM T3 (Marine
running tunnel south, french side). it was followed by a 16 cars, 250 m long, backup system.
Above, top : Tunneling programme on UK side (left) and
French side (right). Above image : Inside the control cab
of TBM T3 (French marine south running tunnel). Right
image : TBM T3 during preassembly at the factory.
Bottom table, right : TBMs data on French side.

service tunnel as a pilot tunnel by probing
ahead of the TBM, to locate: water bearing
fissures, site investigation boreholes, deep
weathering, and proximity of Grey
Chalk/Gault Clay/Fosse Dangeard fault.
On the UK side, grout injections through
holes drilled from the marine service tunnel
improved conditions ahead of running
tunnels TBMs, producing a 3 m annulus of
treated ground at the upper half of both
tunnels. It had to be carried out with
minimum interferences. It proved to be
successful since the average rates
increased from 85 m/week to 210 m/week
in the treated ground.
In France, overlaping destructive probe
holes were drilled from the face of T1
(marine service tunnel), to give advance
warning of unstable ground and high or
saline water inflows. Micropalaeontological
examination of the returns was used to
determine the level of the Chalk Marl.
Detailed geotechnical logs were made of
the side walls and (where possible) at the
front. The water inflow prooved to be
considerably lower than the specified
values (7 l/s/km for RTs, 6 l/s/km for ST).

High boring rates
The best rates achieved in 30 consecutive
days, were, in dry ground: 1,716 m (UK
land south running tunnel), and in
waterbearing ground: 1,232 m (French
south running tunnel).

Innovating approach on French Side
Many refinements have been found, in
positioning of cutting-head tools as well as
in operating the machines. Anticipated
progress rates have been considerably

exceeded in France, leading to increase the
original excavation length by 8125 m.
TBM T4 (French land service tunnel)
achieved 837 m in the waterbearing zone
under a pressure of 3 bar. TBM T1 (marine
Above : "Pinched" rings on French side allow to bolt and seal the rings, and contribute to TBM steering : while
following curves, rings are kept in contact. Straight drive, vertical or horizontal curves are achieved by rotation of the
ring around tunnel axis (for example, red "key" segments are not in the same position than the blue ones).
Right : Service tunnel with temporary tunneling fixed equipment on UK side (above) compared with French side
(below, and also cover page). In UK, the temporary track is ballasted;the key segment of each ring is at a fixed
location, and lining is unbolted. In France, temporary track is installed on metal frame; the key segment is at different
locations on two adjacent rings; bolt boxes are visible on each segment.

service tunnel), T2 and T3 (marine running
tunnels) reached a final daily rate over 50
m, following a slow start of T1 in difficult
ground, but using the experience gained in
the service tunnel to optimize T2 and T3.
Air cushions allowed to turn the land TBM
T5, renamed T6, back to Sangatte.Only 16
Tonnes of traction were needed instead of
dismantling/displacing a 600 T TBM.

Lining
Lining was the critical operation that
dictated tunnelling progress.
UK side:
Service Tunnel machines were designed for
a cycle of 18 min, and 22.5 min for running
tunnel machines. The lining was a precast
concrete unbolted wedge block with pads
on the extrados to allow for a 20 mm grout
layer. There were 7 segments per ring in
the service tunnel and 9 segments per ring,
all different, in the running tunnels, with a
thickness varying depending of the
overburden, from 54 cm (land), to 27 cm
(sea, from 0 to 7 km to the shore) or 36 cm
(sea, over 7 km from the shore). The
placing of segments was considerably
altered when the stability of the ground was
not adequate.
French side:
The main design constraint was
waterproofing with hydrostatic water
pressure up to 11 bars. Complex numerical
models were used - in addition to the
convergence-confinement method - to
evaluate the interaction between tunnels,
the influence of the proximity of a Gault
Clay layer, and the quality of grouting
behind the segments. Optimization studies
led to adopt a high-performance concrete
(80 to 100 MPA) and different types of
reinforcement. "Pinched" rings allowed
the lining to follow the curves, by rotating
the position of the ring into 4 possible
locations.

ring of 1.6 m wide for running tunnels.
These six components arrived at the tailend of the backup train and were lifted by
an overhead conveyor. They were moved
by vacuum lifting arms to one of two
idependent vacuum erectors, which
installed them into position. The designed
cycle was about 30 minutes but rings could
be placed in 15 minutes.
In « open » mode, it was possible to erect
segments during excavation, the TBM
pushing against the ground by means of
lateral grippers. In« closed » mode,
excavation and placing of segments could
not be done simultaneously.
Grout is injected afterward in the 15 cm gap
between segments and ground, about 300
m behind the TBM head. It consists of two
components prepared on surface (retarded
sand mortar, aluminous cement slurry). The
10 cm gap between the tail of the
pressurized chamber and the concrete
lining rings was sealed by grease injected
into four rings of metallic brushes inside the
TBM shield.

Breakthrough
Service tunnel
Once the TBMs surveyed after stopping at
100 m distance, a corrective line allowed a
further 50 m drive of the UK TBM, while the
French TBM was being dismantled. The UK
machine was then turned aside on a tight
curve and buried, the remaining being
excavated using hand-held tools (for a
small adit dedicated to the historical

breakthrough), and then roadheaders.
Running tunnels
Junctioning was achieved by diverting each
UK TBM downwards below floor level
(vertical curve, radius 300 m) and driving
the French TBM through to meet the last
UK permanent lining.Ground support
included temporary segments in the invert,
and shotcrete and fibre-glass rockbolts over
the crown. Once the British TBM below the
permanent line, it was backfilled with low
strength concrete (about 2,000 m3). British
lining was then extended through the
remaining skin of the French TBM once
dismantled.
150 km of tunnels have been built, 24 h a
day, on both sides in less than 3.5 years
(4th Jan.1988 to 28th June 1991).

Left : The historical first undersea breakthrough (service tunnel,1st of december 1990). Right: Last breakthrough
(28th of June 1991): French TBM T3 reaches UK cast iron segments,in running tunnel south undersea.

Contrarily to the UK side, the French
Tunnels were lined with bolted precast
concrete segments erected within the
shield. Five main segments (8 tonnes, 40
cm thickness) plus a key formed a complete
TML, THE CHANNEL TUNNEL CONTRACTOR, IS A JOINT VENTURE BETWEEN: Balfour Beatty constructions LTD, Bouygues
S.A., Costain Civil Engineering LTD, Dumez S.A., Société Auxiliaire d'Entreprises S.A., Société Générale d'Entreprises S.A., Spie
Batignolles S.A., Tarmac Constructions LTD, Taylor Woodrow construction holdings LTD, Wimpey major projects LTD.

AMICALE DES BATISSEURS DU TUNNEL SOUS LA MANCHE - 70, rue Mollien 62100 CALAIS
France – TEL/ FAX : +33 (0)3.21.34.06.66 – e-mail batisseurs.tunnel@wanadoo.fr
author Pierre-Jean Pompée, 1995

Contenu connexe

Tendances

Tunneling exploration
Tunneling explorationTunneling exploration
Tunneling explorationjamali husain
 
Lightening Ventiltion Dust control Safety And Safety in tunnel
Lightening Ventiltion Dust control Safety And Safety in tunnelLightening Ventiltion Dust control Safety And Safety in tunnel
Lightening Ventiltion Dust control Safety And Safety in tunnelAbhishek Kansara
 
Presentation about Ircon's SGEDT project in Malaysia.
Presentation about Ircon's SGEDT project in Malaysia.Presentation about Ircon's SGEDT project in Malaysia.
Presentation about Ircon's SGEDT project in Malaysia.Hitesh Khanna
 
Tunneling by tunnel boring machine
Tunneling by tunnel boring machineTunneling by tunnel boring machine
Tunneling by tunnel boring machineVISHAL KUMAR SINGH
 
Rbte Drainage system in tunnel
 Rbte Drainage system in tunnel Rbte Drainage system in tunnel
Rbte Drainage system in tunnelSukhvinder Singh
 

Tendances (8)

Tunneling exploration
Tunneling explorationTunneling exploration
Tunneling exploration
 
Tunneling
Tunneling Tunneling
Tunneling
 
Lightening Ventiltion Dust control Safety And Safety in tunnel
Lightening Ventiltion Dust control Safety And Safety in tunnelLightening Ventiltion Dust control Safety And Safety in tunnel
Lightening Ventiltion Dust control Safety And Safety in tunnel
 
Presentation about Ircon's SGEDT project in Malaysia.
Presentation about Ircon's SGEDT project in Malaysia.Presentation about Ircon's SGEDT project in Malaysia.
Presentation about Ircon's SGEDT project in Malaysia.
 
Tunneling by tunnel boring machine
Tunneling by tunnel boring machineTunneling by tunnel boring machine
Tunneling by tunnel boring machine
 
Tunnel boring machines123
Tunnel boring machines123Tunnel boring machines123
Tunnel boring machines123
 
Under ground railway
Under ground railwayUnder ground railway
Under ground railway
 
Rbte Drainage system in tunnel
 Rbte Drainage system in tunnel Rbte Drainage system in tunnel
Rbte Drainage system in tunnel
 

En vedette

Analysis of piles under earthquakes
Analysis of piles under earthquakesAnalysis of piles under earthquakes
Analysis of piles under earthquakesJunaida Wally
 
Analysis of piles under earthquakes
Analysis of piles under earthquakesAnalysis of piles under earthquakes
Analysis of piles under earthquakesJunaida Wally
 
583 24650 emperical method
583 24650 emperical method583 24650 emperical method
583 24650 emperical methodJunaida Wally
 
302 settlement of piled foundations
302 settlement of piled foundations302 settlement of piled foundations
302 settlement of piled foundationsJunaida Wally
 
Diamond Dollars 2015 Presentation
Diamond Dollars 2015 PresentationDiamond Dollars 2015 Presentation
Diamond Dollars 2015 PresentationGregory Ackerman
 
2013 NYU Diamond Dollars Case Competition Presentation
2013 NYU Diamond Dollars Case Competition Presentation2013 NYU Diamond Dollars Case Competition Presentation
2013 NYU Diamond Dollars Case Competition PresentationGregory Ackerman
 
Structural design finite
Structural design finiteStructural design finite
Structural design finiteJunaida Wally
 
Preparation of a piling paper
Preparation of a piling paperPreparation of a piling paper
Preparation of a piling paperJunaida Wally
 
80747511 tabel-profil
80747511 tabel-profil80747511 tabel-profil
80747511 tabel-profilJunaida Wally
 
Ecg533 rock-tunnel-engineering
Ecg533 rock-tunnel-engineeringEcg533 rock-tunnel-engineering
Ecg533 rock-tunnel-engineeringJunaida Wally
 
2010 04 tunneling-to_the_future
2010 04 tunneling-to_the_future2010 04 tunneling-to_the_future
2010 04 tunneling-to_the_futureJunaida Wally
 
Konstruksi baja-3 sambungan-baut
Konstruksi baja-3 sambungan-bautKonstruksi baja-3 sambungan-baut
Konstruksi baja-3 sambungan-bautJunaida Wally
 

En vedette (17)

Sni baja
Sni bajaSni baja
Sni baja
 
NGTVZRO EPK
NGTVZRO EPKNGTVZRO EPK
NGTVZRO EPK
 
Analysis of piles under earthquakes
Analysis of piles under earthquakesAnalysis of piles under earthquakes
Analysis of piles under earthquakes
 
Kaplan05analysis
Kaplan05analysisKaplan05analysis
Kaplan05analysis
 
Analysis of piles under earthquakes
Analysis of piles under earthquakesAnalysis of piles under earthquakes
Analysis of piles under earthquakes
 
Cv15 nalisis method
Cv15 nalisis methodCv15 nalisis method
Cv15 nalisis method
 
583 24650 emperical method
583 24650 emperical method583 24650 emperical method
583 24650 emperical method
 
302 settlement of piled foundations
302 settlement of piled foundations302 settlement of piled foundations
302 settlement of piled foundations
 
Diamond Dollars 2015 Presentation
Diamond Dollars 2015 PresentationDiamond Dollars 2015 Presentation
Diamond Dollars 2015 Presentation
 
2013 NYU Diamond Dollars Case Competition Presentation
2013 NYU Diamond Dollars Case Competition Presentation2013 NYU Diamond Dollars Case Competition Presentation
2013 NYU Diamond Dollars Case Competition Presentation
 
Structural design finite
Structural design finiteStructural design finite
Structural design finite
 
Preparation of a piling paper
Preparation of a piling paperPreparation of a piling paper
Preparation of a piling paper
 
Clamshell
ClamshellClamshell
Clamshell
 
80747511 tabel-profil
80747511 tabel-profil80747511 tabel-profil
80747511 tabel-profil
 
Ecg533 rock-tunnel-engineering
Ecg533 rock-tunnel-engineeringEcg533 rock-tunnel-engineering
Ecg533 rock-tunnel-engineering
 
2010 04 tunneling-to_the_future
2010 04 tunneling-to_the_future2010 04 tunneling-to_the_future
2010 04 tunneling-to_the_future
 
Konstruksi baja-3 sambungan-baut
Konstruksi baja-3 sambungan-bautKonstruksi baja-3 sambungan-baut
Konstruksi baja-3 sambungan-baut
 

Similaire à 3 tunnels tunnel sous la manche c

Metro Torino Extension - Design and construction problems
Metro Torino Extension - Design and construction problemsMetro Torino Extension - Design and construction problems
Metro Torino Extension - Design and construction problemsgifanta
 
Hybrid epb tunnelling in rio de janeiro 2015
Hybrid epb tunnelling in rio de janeiro 2015Hybrid epb tunnelling in rio de janeiro 2015
Hybrid epb tunnelling in rio de janeiro 2015Abner Silva
 
Presentazione Per Delegazione Metro Quing Dao
Presentazione Per Delegazione Metro Quing DaoPresentazione Per Delegazione Metro Quing Dao
Presentazione Per Delegazione Metro Quing Daogifanta
 
7. TUNNEL ENGINEERING
7. TUNNEL ENGINEERING7. TUNNEL ENGINEERING
7. TUNNEL ENGINEERINGVATSAL PATEL
 
Assessing the interaction between the excavation of a large cavern and existi...
Assessing the interaction between the excavation of a large cavern and existi...Assessing the interaction between the excavation of a large cavern and existi...
Assessing the interaction between the excavation of a large cavern and existi...SYSTRA
 
Back analysis of high tunnel convergences in clayey marls
Back analysis of high tunnel convergences in clayey marlsBack analysis of high tunnel convergences in clayey marls
Back analysis of high tunnel convergences in clayey marlsSYSTRA
 
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAMNhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAMIshant Gautam.
 
Technical seminar
Technical seminarTechnical seminar
Technical seminarUjwal Ujwal
 
Effect Of Water On Slope Stability And Investigation Of ΝΝw Drainage Techniqu...
Effect Of Water On Slope Stability And Investigation Of ΝΝw Drainage Techniqu...Effect Of Water On Slope Stability And Investigation Of ΝΝw Drainage Techniqu...
Effect Of Water On Slope Stability And Investigation Of ΝΝw Drainage Techniqu...IJMER
 
Trabajo final Hcanal ejercicios resueltos
Trabajo final Hcanal ejercicios resueltosTrabajo final Hcanal ejercicios resueltos
Trabajo final Hcanal ejercicios resueltosKeniaNamucheVite
 
unit-vi-tunnels-alignments-tunneling-methods-highway-tunnels-r-bhagat-2020.ppt
unit-vi-tunnels-alignments-tunneling-methods-highway-tunnels-r-bhagat-2020.pptunit-vi-tunnels-alignments-tunneling-methods-highway-tunnels-r-bhagat-2020.ppt
unit-vi-tunnels-alignments-tunneling-methods-highway-tunnels-r-bhagat-2020.pptPranaysandeepjadhav
 
Lesson3 tunnel design
Lesson3 tunnel designLesson3 tunnel design
Lesson3 tunnel designkhan510459
 
Physical model for coastal inlet
Physical model for coastal inletPhysical model for coastal inlet
Physical model for coastal inletNguyen Thanh Luan
 
PPT CAVITY Tunnel P1 610M--05.02.2021.pptx
PPT CAVITY Tunnel P1 610M--05.02.2021.pptxPPT CAVITY Tunnel P1 610M--05.02.2021.pptx
PPT CAVITY Tunnel P1 610M--05.02.2021.pptxAGNIVORAY1
 
Dimapur-Kohima Rail Project Site Visit Report (1).docx
Dimapur-Kohima Rail Project Site Visit Report (1).docxDimapur-Kohima Rail Project Site Visit Report (1).docx
Dimapur-Kohima Rail Project Site Visit Report (1).docxAbdulMannan357156
 

Similaire à 3 tunnels tunnel sous la manche c (20)

Metro Torino Extension - Design and construction problems
Metro Torino Extension - Design and construction problemsMetro Torino Extension - Design and construction problems
Metro Torino Extension - Design and construction problems
 
Hybrid epb tunnelling in rio de janeiro 2015
Hybrid epb tunnelling in rio de janeiro 2015Hybrid epb tunnelling in rio de janeiro 2015
Hybrid epb tunnelling in rio de janeiro 2015
 
Lisbonne
LisbonneLisbonne
Lisbonne
 
Tunneling
TunnelingTunneling
Tunneling
 
Presentazione Per Delegazione Metro Quing Dao
Presentazione Per Delegazione Metro Quing DaoPresentazione Per Delegazione Metro Quing Dao
Presentazione Per Delegazione Metro Quing Dao
 
7. TUNNEL ENGINEERING
7. TUNNEL ENGINEERING7. TUNNEL ENGINEERING
7. TUNNEL ENGINEERING
 
Assessing the interaction between the excavation of a large cavern and existi...
Assessing the interaction between the excavation of a large cavern and existi...Assessing the interaction between the excavation of a large cavern and existi...
Assessing the interaction between the excavation of a large cavern and existi...
 
channel tunnel
channel tunnelchannel tunnel
channel tunnel
 
Back analysis of high tunnel convergences in clayey marls
Back analysis of high tunnel convergences in clayey marlsBack analysis of high tunnel convergences in clayey marls
Back analysis of high tunnel convergences in clayey marls
 
On the road
On the roadOn the road
On the road
 
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAMNhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
 
Technical seminar
Technical seminarTechnical seminar
Technical seminar
 
Effect Of Water On Slope Stability And Investigation Of ΝΝw Drainage Techniqu...
Effect Of Water On Slope Stability And Investigation Of ΝΝw Drainage Techniqu...Effect Of Water On Slope Stability And Investigation Of ΝΝw Drainage Techniqu...
Effect Of Water On Slope Stability And Investigation Of ΝΝw Drainage Techniqu...
 
Trabajo final Hcanal ejercicios resueltos
Trabajo final Hcanal ejercicios resueltosTrabajo final Hcanal ejercicios resueltos
Trabajo final Hcanal ejercicios resueltos
 
IPTC_12_2015
IPTC_12_2015IPTC_12_2015
IPTC_12_2015
 
unit-vi-tunnels-alignments-tunneling-methods-highway-tunnels-r-bhagat-2020.ppt
unit-vi-tunnels-alignments-tunneling-methods-highway-tunnels-r-bhagat-2020.pptunit-vi-tunnels-alignments-tunneling-methods-highway-tunnels-r-bhagat-2020.ppt
unit-vi-tunnels-alignments-tunneling-methods-highway-tunnels-r-bhagat-2020.ppt
 
Lesson3 tunnel design
Lesson3 tunnel designLesson3 tunnel design
Lesson3 tunnel design
 
Physical model for coastal inlet
Physical model for coastal inletPhysical model for coastal inlet
Physical model for coastal inlet
 
PPT CAVITY Tunnel P1 610M--05.02.2021.pptx
PPT CAVITY Tunnel P1 610M--05.02.2021.pptxPPT CAVITY Tunnel P1 610M--05.02.2021.pptx
PPT CAVITY Tunnel P1 610M--05.02.2021.pptx
 
Dimapur-Kohima Rail Project Site Visit Report (1).docx
Dimapur-Kohima Rail Project Site Visit Report (1).docxDimapur-Kohima Rail Project Site Visit Report (1).docx
Dimapur-Kohima Rail Project Site Visit Report (1).docx
 

Plus de Junaida Wally

Decision analysis applied to rock tunnel exploration 1978 baecher
Decision analysis applied to rock tunnel exploration 1978 baecherDecision analysis applied to rock tunnel exploration 1978 baecher
Decision analysis applied to rock tunnel exploration 1978 baecherJunaida Wally
 
Sni 03 2847-2002 (beton)
Sni 03 2847-2002 (beton)Sni 03 2847-2002 (beton)
Sni 03 2847-2002 (beton)Junaida Wally
 
Handout mer iv d iii
Handout mer iv d iiiHandout mer iv d iii
Handout mer iv d iiiJunaida Wally
 
Wide flange-shape-jisg3192
Wide flange-shape-jisg3192Wide flange-shape-jisg3192
Wide flange-shape-jisg3192Junaida Wally
 
Gg downstream of_wfhb_tbeam
Gg downstream of_wfhb_tbeamGg downstream of_wfhb_tbeam
Gg downstream of_wfhb_tbeamJunaida Wally
 

Plus de Junaida Wally (11)

Decision analysis applied to rock tunnel exploration 1978 baecher
Decision analysis applied to rock tunnel exploration 1978 baecherDecision analysis applied to rock tunnel exploration 1978 baecher
Decision analysis applied to rock tunnel exploration 1978 baecher
 
Chapter6
Chapter6Chapter6
Chapter6
 
Sni 03 2847-2002 (beton)
Sni 03 2847-2002 (beton)Sni 03 2847-2002 (beton)
Sni 03 2847-2002 (beton)
 
Pp no 29_th_2000
Pp no 29_th_2000Pp no 29_th_2000
Pp no 29_th_2000
 
Bab ii1
Bab ii1Bab ii1
Bab ii1
 
Metode cross
Metode crossMetode cross
Metode cross
 
Handout mer iv d iii
Handout mer iv d iiiHandout mer iv d iii
Handout mer iv d iii
 
Contoh baja
Contoh bajaContoh baja
Contoh baja
 
Wide flange-shape-jisg3192
Wide flange-shape-jisg3192Wide flange-shape-jisg3192
Wide flange-shape-jisg3192
 
Gg downstream of_wfhb_tbeam
Gg downstream of_wfhb_tbeamGg downstream of_wfhb_tbeam
Gg downstream of_wfhb_tbeam
 
Power
PowerPower
Power
 

Dernier

Judging the Relevance and worth of ideas part 2.pptx
Judging the Relevance  and worth of ideas part 2.pptxJudging the Relevance  and worth of ideas part 2.pptx
Judging the Relevance and worth of ideas part 2.pptxSherlyMaeNeri
 
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptxAUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptxiammrhaywood
 
Science 7 Quarter 4 Module 2: Natural Resources.pptx
Science 7 Quarter 4 Module 2: Natural Resources.pptxScience 7 Quarter 4 Module 2: Natural Resources.pptx
Science 7 Quarter 4 Module 2: Natural Resources.pptxMaryGraceBautista27
 
Transaction Management in Database Management System
Transaction Management in Database Management SystemTransaction Management in Database Management System
Transaction Management in Database Management SystemChristalin Nelson
 
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxINTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxHumphrey A Beña
 
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITYISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITYKayeClaireEstoconing
 
ENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choomENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choomnelietumpap1
 
4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptxmary850239
 
Keynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designKeynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designMIPLM
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPCeline George
 
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Celine George
 
Global Lehigh Strategic Initiatives (without descriptions)
Global Lehigh Strategic Initiatives (without descriptions)Global Lehigh Strategic Initiatives (without descriptions)
Global Lehigh Strategic Initiatives (without descriptions)cama23
 
4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptx4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptxmary850239
 
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdfInclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdfTechSoup
 
Barangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptxBarangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptxCarlos105
 
How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17Celine George
 
Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Celine George
 

Dernier (20)

Judging the Relevance and worth of ideas part 2.pptx
Judging the Relevance  and worth of ideas part 2.pptxJudging the Relevance  and worth of ideas part 2.pptx
Judging the Relevance and worth of ideas part 2.pptx
 
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptxAUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptx
 
Science 7 Quarter 4 Module 2: Natural Resources.pptx
Science 7 Quarter 4 Module 2: Natural Resources.pptxScience 7 Quarter 4 Module 2: Natural Resources.pptx
Science 7 Quarter 4 Module 2: Natural Resources.pptx
 
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptxFINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
 
Transaction Management in Database Management System
Transaction Management in Database Management SystemTransaction Management in Database Management System
Transaction Management in Database Management System
 
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxINTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
 
YOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptx
YOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptxYOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptx
YOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptx
 
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITYISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
 
ENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choomENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choom
 
4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx
 
Keynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designKeynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-design
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERP
 
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
 
Global Lehigh Strategic Initiatives (without descriptions)
Global Lehigh Strategic Initiatives (without descriptions)Global Lehigh Strategic Initiatives (without descriptions)
Global Lehigh Strategic Initiatives (without descriptions)
 
4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptx4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptx
 
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdfInclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
 
LEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptx
LEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptxLEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptx
LEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptx
 
Barangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptxBarangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptx
 
How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17
 
Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17
 

3 tunnels tunnel sous la manche c

  • 1. CHANNEL TUNNEL TUNNELS CONSTRUCTION Author Pierre-Jean Pompée Scope Within the 5 years following contract award, 3 parallel tunnels, 50.5 km each, had to be driven and lined with high-strengh precast segments : 38 km undersea, 3.2 underland in France, 9.3 km underland in UK. 2/3 of the total had to be excavated from UK side, and 1/3 from French side where ground conditions were unfavourable. 6 drives (total 12), 3 to the sea and 3 to the land have been conducted from each of the two tunneling sites, located as close as possible to the sea : Shakespeare Cliff (west of Dover) on the UK side, and Sangatte (west of Calais) in France. The service tunnel (ST) has a internal diameter of 4.8 m (excavated diam.5.8 m). The two running tunnels (RT) are at 30 m distance, lined diameter is 7.6 m (excavated diam.8.8 m). They are connected together by 194 piston relief ducts (every 250 m, diam 2 m), and by 270 cross passages (every 375 m) and 210 technical rooms (all diam 3.3 m) to the service tunnel, requiring special cast iron segments at each junction. Geology and alignment Many geotechnical investigations have been carried out across the Channel since 1875, including over 100 boreholes. Total information available including final investigation after contract award and geophysical survey undertaken in 1988, (specifically for crossing beneath the Fosse Dangeard and crossovers sites),comprised: - 120 marine boreholes and about 1,000 km of geophysical (seismic reflection), traverse lines, - adits and short lenght of tunnels excavated during previous attempts. Optimum tunnelling conditions are within the Chalk Marl, clayey carbonate mudstone, weak (20 to 200 bars), homogeneous rock, believed to be mainly impermeable, with any water restricted to discontinuities such as faults or fissures concentrated on French side. It is a tunnelling medium adequate for TBMs. High precision alignment The tunnel alignment was a critical stage in the design process. It was later optimised using experience gained while driving the service tunnel itself, and design developments at the crossover and pumping stations, avoiding fault zones which would reduce tunnelling progress. Geometrical criterias applicable to a high- Above : View of a running tunnel on French side at the beginning of the tunneling phase (1988), showing temporary fixed equipments (water pipes, ventilation duct diam 1600mm, power and radio communications cables, double track and walways...). Below : Tunneling progress on 29th of April 1990, 7 months before first undersea breakthrough, showing forecasted ("M"), and final (black balls) meeting points. speed railway impose large radius curves, leading to drive 150 km of tunnels within 150 mm tolerances: 40 mm for topography, 55 for TBM steering, 25 for segments manufacturing/erection (ring axis), 30 between surfaces of adjacent segments. TBMs, launched over 38 km distance, had to meet with precision ! Topographical survey Different systems in UK and France British maps are based on Mercator system, French maps on Lambert system. Sea level on both sides differed by 440 mm according to a 1958 study, reduced at 300± 80 mm in 1987, measured at 360 mm after breakthrough. Joint mapping and levelling Mercator system was adopted, but based on the mid-Channel 1°30 East meridian. Satellite Global Positioning System (GPS, precision 5 cm for 50 km) was used and water movement studies reduced levelling uncertainty , leading to the RTM87 grid, and the NTM88 levelling ("Reseau" and "Niveau TransManche"). Final orientation to the North required a gyrotheodolite with precise astronomical calibration and correction of all horizontal angles, locally different due to the Mercator system. Survey brough underground RTM87 was brought underground trough the inclined adits of the UK side and the Sangatte shaft in France through benchmarks set at the tunnels starting points with a precision of 0.6 mm (5 mm error would have meant 1.5 m at 15 km distance). Grid was relayed along TBMs journey with computer correction of temperature, pressure, hygrometry. After first breakthrough, a reference point was at least available for running tunnels survey.
  • 2. Geological profile and description of the works. Tunnel slope is between 0.2% and 1.1 %, often found at 0.6% on UK side and at 1.1% on French side. Breakthrough actual precision Once the marine service tunnel TBMs stopped at 100 m distance, measured lateral offset was 358 mm; levelling : 58 mm; chainage :75 mm. Readjustment over the final 50 m, hand excavated, produced a smooth junctioning of the two drives. Running tunnels all came out within the 15 cm tolerance.Underland TBMs came out at less than 2 cm from the original alignment. Tunnel Boring Machines Design criteria on French side Critical programme and unfavourable geology determined a whole tunnelling system (TBMs, back-up systems, linings, and overall logistics). Design criteria were: - progress without ground treatment in watery conditions in France, especially the first 4 km undersea (where the chalk is fractured), and 3.2 km underland, (below water table). - progress at high speed (4.4 lm/h) in dry, fair to good, ground conditions. - ensure safety and reliability for a highly complex, massive, tunnelling logistics designed for peak boring rates. A huge, waterproof, shaft housed all French tunnels logistics at Sangatte. TBMs description 11 TBMs were ordered by TML. On the UK side, 6 open, full-face TBMs (3 undersea and 3 underland) were used in conjunction with unbolted, expanded precast concrete linings by use of wedge-shaped key. The 5 French TBMs have been launched from the Sangatte Shaft: 3 undersea, 2 underland, one being turned back to drive the north running tunel underland. There are full face, earth-pressure type, and allow erection of watertight precast segments inside the shield concurrently with face excavation. Their unique design combines technologies for both soft ground underwater and hard rock. The 3 undersea French TBMs include articulated double shield operating in closed mode in wet zones (minimum rate of 3 m/h), or in open mode at high speed in dry zones. Cutter chambers are sealed to withstand a hydrostatic pressure of 11 bars: excavated chalk had to pass through a twostage pressure lock before being ejected at atmospheric pressure into the muck wagons. Containment is achieved at the end of the spoil extraction screw either through a dual discharge pump system or through a second screw creating a plug. The 2 underland French TBMs included a single shield, Archimedes screw containment and a ″casing rotator″, to withstand a hydrostatic pressure of 3 bars. French TBMs guidance system The ZED 260 guidance system used a laser beam, set up to a predetermined alignment, and received on a screen on the cutting head. After analisis, an on-board computer displayed, in the cab, differences betwwen designed and actual TBM's 3 dimensional position, allowing the driver to correct by steering to zero. Steering was achieved by selection of the push rams housed in the telescopic section. Real time monitoring in the cab of complete operational status of the TBM T3 process was ensured by an IBM 7532 superviser: pressures, speed, stroke of hydraulic jacks, spoil rotating screws and tail seals, but also electrical intensity and instant power of the 12 motors, water injected flows - 20 bars and 30 bars - and earthpressure at 5 different locations of cutting chamber, plus rotating head position. Programmable controlers managed overall process safety and failure detection (ALSPA C350, 2000 I/O), grout injection (SIEMENS 115V), and segments feeder (TELEMECANIQUE TSX47-20). Main data were plotted and/or transmitted to surface. Long term tracing of segments rings main data was automatically available. Video screens showed conveyors operations. Probes, ground treatment Site investigation boreholes covered a grid of 1 km width only, leading to use the Left : Probes on French side around the T1 (marine Service tunnel TBM). Below : Description of the TBM T3 (Marine running tunnel south, french side). it was followed by a 16 cars, 250 m long, backup system.
  • 3. Above, top : Tunneling programme on UK side (left) and French side (right). Above image : Inside the control cab of TBM T3 (French marine south running tunnel). Right image : TBM T3 during preassembly at the factory. Bottom table, right : TBMs data on French side. service tunnel as a pilot tunnel by probing ahead of the TBM, to locate: water bearing fissures, site investigation boreholes, deep weathering, and proximity of Grey Chalk/Gault Clay/Fosse Dangeard fault. On the UK side, grout injections through holes drilled from the marine service tunnel improved conditions ahead of running tunnels TBMs, producing a 3 m annulus of treated ground at the upper half of both tunnels. It had to be carried out with minimum interferences. It proved to be successful since the average rates increased from 85 m/week to 210 m/week in the treated ground. In France, overlaping destructive probe holes were drilled from the face of T1 (marine service tunnel), to give advance warning of unstable ground and high or saline water inflows. Micropalaeontological examination of the returns was used to determine the level of the Chalk Marl. Detailed geotechnical logs were made of the side walls and (where possible) at the front. The water inflow prooved to be considerably lower than the specified values (7 l/s/km for RTs, 6 l/s/km for ST). High boring rates The best rates achieved in 30 consecutive days, were, in dry ground: 1,716 m (UK land south running tunnel), and in waterbearing ground: 1,232 m (French south running tunnel). Innovating approach on French Side Many refinements have been found, in positioning of cutting-head tools as well as in operating the machines. Anticipated progress rates have been considerably exceeded in France, leading to increase the original excavation length by 8125 m. TBM T4 (French land service tunnel) achieved 837 m in the waterbearing zone under a pressure of 3 bar. TBM T1 (marine
  • 4. Above : "Pinched" rings on French side allow to bolt and seal the rings, and contribute to TBM steering : while following curves, rings are kept in contact. Straight drive, vertical or horizontal curves are achieved by rotation of the ring around tunnel axis (for example, red "key" segments are not in the same position than the blue ones). Right : Service tunnel with temporary tunneling fixed equipment on UK side (above) compared with French side (below, and also cover page). In UK, the temporary track is ballasted;the key segment of each ring is at a fixed location, and lining is unbolted. In France, temporary track is installed on metal frame; the key segment is at different locations on two adjacent rings; bolt boxes are visible on each segment. service tunnel), T2 and T3 (marine running tunnels) reached a final daily rate over 50 m, following a slow start of T1 in difficult ground, but using the experience gained in the service tunnel to optimize T2 and T3. Air cushions allowed to turn the land TBM T5, renamed T6, back to Sangatte.Only 16 Tonnes of traction were needed instead of dismantling/displacing a 600 T TBM. Lining Lining was the critical operation that dictated tunnelling progress. UK side: Service Tunnel machines were designed for a cycle of 18 min, and 22.5 min for running tunnel machines. The lining was a precast concrete unbolted wedge block with pads on the extrados to allow for a 20 mm grout layer. There were 7 segments per ring in the service tunnel and 9 segments per ring, all different, in the running tunnels, with a thickness varying depending of the overburden, from 54 cm (land), to 27 cm (sea, from 0 to 7 km to the shore) or 36 cm (sea, over 7 km from the shore). The placing of segments was considerably altered when the stability of the ground was not adequate. French side: The main design constraint was waterproofing with hydrostatic water pressure up to 11 bars. Complex numerical models were used - in addition to the convergence-confinement method - to evaluate the interaction between tunnels, the influence of the proximity of a Gault Clay layer, and the quality of grouting behind the segments. Optimization studies led to adopt a high-performance concrete (80 to 100 MPA) and different types of reinforcement. "Pinched" rings allowed the lining to follow the curves, by rotating the position of the ring into 4 possible locations. ring of 1.6 m wide for running tunnels. These six components arrived at the tailend of the backup train and were lifted by an overhead conveyor. They were moved by vacuum lifting arms to one of two idependent vacuum erectors, which installed them into position. The designed cycle was about 30 minutes but rings could be placed in 15 minutes. In « open » mode, it was possible to erect segments during excavation, the TBM pushing against the ground by means of lateral grippers. In« closed » mode, excavation and placing of segments could not be done simultaneously. Grout is injected afterward in the 15 cm gap between segments and ground, about 300 m behind the TBM head. It consists of two components prepared on surface (retarded sand mortar, aluminous cement slurry). The 10 cm gap between the tail of the pressurized chamber and the concrete lining rings was sealed by grease injected into four rings of metallic brushes inside the TBM shield. Breakthrough Service tunnel Once the TBMs surveyed after stopping at 100 m distance, a corrective line allowed a further 50 m drive of the UK TBM, while the French TBM was being dismantled. The UK machine was then turned aside on a tight curve and buried, the remaining being excavated using hand-held tools (for a small adit dedicated to the historical breakthrough), and then roadheaders. Running tunnels Junctioning was achieved by diverting each UK TBM downwards below floor level (vertical curve, radius 300 m) and driving the French TBM through to meet the last UK permanent lining.Ground support included temporary segments in the invert, and shotcrete and fibre-glass rockbolts over the crown. Once the British TBM below the permanent line, it was backfilled with low strength concrete (about 2,000 m3). British lining was then extended through the remaining skin of the French TBM once dismantled. 150 km of tunnels have been built, 24 h a day, on both sides in less than 3.5 years (4th Jan.1988 to 28th June 1991). Left : The historical first undersea breakthrough (service tunnel,1st of december 1990). Right: Last breakthrough (28th of June 1991): French TBM T3 reaches UK cast iron segments,in running tunnel south undersea. Contrarily to the UK side, the French Tunnels were lined with bolted precast concrete segments erected within the shield. Five main segments (8 tonnes, 40 cm thickness) plus a key formed a complete TML, THE CHANNEL TUNNEL CONTRACTOR, IS A JOINT VENTURE BETWEEN: Balfour Beatty constructions LTD, Bouygues S.A., Costain Civil Engineering LTD, Dumez S.A., Société Auxiliaire d'Entreprises S.A., Société Générale d'Entreprises S.A., Spie Batignolles S.A., Tarmac Constructions LTD, Taylor Woodrow construction holdings LTD, Wimpey major projects LTD. AMICALE DES BATISSEURS DU TUNNEL SOUS LA MANCHE - 70, rue Mollien 62100 CALAIS France – TEL/ FAX : +33 (0)3.21.34.06.66 – e-mail batisseurs.tunnel@wanadoo.fr author Pierre-Jean Pompée, 1995