PROJECT MANAGEMENTPROJECT MANAGEMENT
CPM/PERT
V P B Chakravarthi . K
Abhijeet Kumar
ProjectProject
 “A project is a series of activities directed
to accomplishment of a desired objective.”
Plan your work first…..then work
your plan
Network analysis
Introduction
Network analysis is the general name given to certain specific
techniques which can be used for the planning, management and
control of projects.
One definition of a project:
“A project is a temporary endeavour undertaken to create a "unique"
product or service”
HistoryHistory
 Developed in 1950’s
 CPM by DuPont for chemical plants
 PERT by U.S. Navy for Polaris missile
PERT was developed by the US Navy for the planning and control of
the Polaris missile program and the emphasis was on completing the
program in the shortest possible time. In addition PERT had the
ability to cope with uncertain activity completion times (e.g. for a
particular activity the most likely completion time is 4 weeks but it
could be anywhere between 3 weeks and 8 weeks).
CPM was developed by Du Pont and the emphasis was on the
trade-off between the cost of the project and its overall
completion time (e.g. for certain activities it may be possible
to decrease their completion times by spending more money -
how does this affect the overall completion time of the
project?)
CPM - Critical Path MethodCPM - Critical Path Method
 Definition: In CPM activities are shown as a network of
precedence relationships using activity-on-node network
construction
– Single estimate of activity time
– Deterministic activity times
USED IN : Production management - for the jobs of
repetitive in nature where the activity time estimates can
be predicted with considerable certainty due to the
existence of past experience.
PERT -PERT -
Project Evaluation & Review TechniquesProject Evaluation & Review Techniques
 Definition: In PERT activities are shown as a network of
precedence relationships using activity-on-arrow network
construction
– Multiple time estimates
– Probabilistic activity times
USED IN : Project management - for non-repetitive jobs
(research and development work), where the time and cost
estimates tend to be quite uncertain. This technique uses
probabilistic time estimates.
Originated by H.L.Gantt in 1918
Gantt chart
Advantages
- Gantt charts are quite commonly used.
They provide an easy graphical
representation of when activities (might)
take place.
Limitations
- Do not clearly indicate details regarding
the progress of activities
- Do not give a clear indication of
interrelation ship between the separate
activities
CPM/PERTCPM/PERT
These deficiencies can be eliminated to a large extent by
showing the interdependence of various activities by means of
connecting arrows called network technique.
 Overtime CPM and PERT became one technique
 ADVANTAGES:
– Precedence relationships
– large projects
– more efficient
The Project NetworkThe Project Network
 Use of nodes and arrows
Arrows An arrow leads from tail to head directionally
– Indicate ACTIVITY, a time consuming effort that is required to
perform a part of the work.
Nodes  A node is represented by a circle
- Indicate EVENT, a point in time where one or more activities start
and/or finish.
Activity on Node & Activity on ArrowActivity on Node & Activity on Arrow
Activity on Node
- A completion of an activity
is represented by a node
Activity on Arrow
- An arrow represents a task,
while a node is the
completion of a task
- Arrows represent order of
events
Activity SlackActivity Slack
Each event has two important times associated with it :
- Earliest time , Te , which is a calendar time when a event can
occur when all the predecessor events completed at the earliest
possible times
- Latest time , TL , which is the latest time the event can occur with
out delaying the subsequent events and completion of project.
 Difference between the latest time and the earliest time of an event
is the slack time for that event
Positive slack : Slack is the amount of time an event can be delayed
without delaying the project completion
Critical PathCritical Path
 Is that the sequence of activities and events where there is no
“slack” i.e.. Zero slack
 Longest path through a network
 minimum project completion time
Benefits of CPM/PERTBenefits of CPM/PERT
 Useful at many stages of project management
 Mathematically simple
 Give critical path and slack time
 Provide project documentation
 Useful in monitoring costs
Questions Answered by CPM & PERTQuestions Answered by CPM & PERT
 Completion date?
 On Schedule?
 Within Budget?
 Critical Activities?
 How can the project be finished early at the least cost?
exampleexample
Illustration of network analysis of a minor redesign of a product and
its associated packaging.
The key question is: How long will it take to complete this project ?
For clarity, this list is kept to a minimum by specifying only
immediate relationships, that is relationships involving activities
that "occur near to each other in time".
•"What activities must be finished before this activity can start"
•could we complete this project in 30 weeks?
•could we complete this project in 2 weeks?
One answer could be, if we first do activity 1, then activity 2, then activity
3, ...., then activity 10, then activity 11 and the project would then take the sum
of the activity completion times, 30 weeks.
“What is the minimum possible time in which we can complete this project ? “
Before starting any of the above activity, the questions
asked would be
We shall see below how the network analysis diagram/picture we construct
helps us to answer this question.
CRITICAL PATH TAKES 24 WEEKS FOR THE COMPLETION OF THE PROJECT
Packages are available to determine the shortest path
and other relevant information.
Data entry window
Output of the package
Limitations to CPM/PERTLimitations to CPM/PERT
 Clearly defined, independent and stable activities
 Specified precedence relationships
 Over emphasis on critical paths
Thank you

Contenu connexe

Tendances

Project mangement chp 1 12
Project mangement chp 1 12Project mangement chp 1 12
Project mangement chp 1 12Dreams Design
 
Project Scope Change Management
Project Scope Change ManagementProject Scope Change Management
Project Scope Change ManagementAlex Iskandar
 
PCM - Project Cycle Management, Training on Evaluation
PCM - Project Cycle Management, Training on EvaluationPCM - Project Cycle Management, Training on Evaluation
PCM - Project Cycle Management, Training on Evaluationrexcris
 
Construction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential BuildingConstruction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential BuildingSHAZEBALIKHAN1
 
Most Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management TermsMost Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management TermsSHAZEBALIKHAN1
 
Sample project plan
Sample project planSample project plan
Sample project planmamoonnift
 
Lect-1: Software Project Management - Project Dimensions, Players, SDLC and P...
Lect-1: Software Project Management - Project Dimensions, Players, SDLC and P...Lect-1: Software Project Management - Project Dimensions, Players, SDLC and P...
Lect-1: Software Project Management - Project Dimensions, Players, SDLC and P...Mubashir Ali
 
My 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project ManagementMy 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project ManagementSHAZEBALIKHAN1
 
Change management and dispute resolution
Change management and dispute resolutionChange management and dispute resolution
Change management and dispute resolutionAlex Iskandar
 
PM Session 4
PM Session 4PM Session 4
PM Session 4dmdk12
 
DCMA 14-Point Schedule Quality Check
DCMA 14-Point Schedule Quality CheckDCMA 14-Point Schedule Quality Check
DCMA 14-Point Schedule Quality CheckSHAZEBALIKHAN1
 
Project Time Estimation 6 Powerful Tips & Tricks
Project Time Estimation 6 Powerful Tips & TricksProject Time Estimation 6 Powerful Tips & Tricks
Project Time Estimation 6 Powerful Tips & TricksSHAZEBALIKHAN1
 
Project Plan And Estimation
Project Plan And EstimationProject Plan And Estimation
Project Plan And EstimationRajan Srivastava
 
Project Control- Overview Presentation Tafseer
Project Control- Overview Presentation   TafseerProject Control- Overview Presentation   Tafseer
Project Control- Overview Presentation TafseerKishan Solankimbaccepmp
 

Tendances (20)

Project mangement chp 1 12
Project mangement chp 1 12Project mangement chp 1 12
Project mangement chp 1 12
 
Project Scope Change Management
Project Scope Change ManagementProject Scope Change Management
Project Scope Change Management
 
Phases of a Project
Phases of a ProjectPhases of a Project
Phases of a Project
 
PCM - Project Cycle Management, Training on Evaluation
PCM - Project Cycle Management, Training on EvaluationPCM - Project Cycle Management, Training on Evaluation
PCM - Project Cycle Management, Training on Evaluation
 
Construction Management - New Trends
Construction Management - New TrendsConstruction Management - New Trends
Construction Management - New Trends
 
Construction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential BuildingConstruction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential Building
 
Most Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management TermsMost Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management Terms
 
Sample project plan
Sample project planSample project plan
Sample project plan
 
Project Management Introduction
Project Management IntroductionProject Management Introduction
Project Management Introduction
 
Lect-1: Software Project Management - Project Dimensions, Players, SDLC and P...
Lect-1: Software Project Management - Project Dimensions, Players, SDLC and P...Lect-1: Software Project Management - Project Dimensions, Players, SDLC and P...
Lect-1: Software Project Management - Project Dimensions, Players, SDLC and P...
 
Project control
Project controlProject control
Project control
 
My 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project ManagementMy 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project Management
 
Change management and dispute resolution
Change management and dispute resolutionChange management and dispute resolution
Change management and dispute resolution
 
It2403 spm
It2403 spmIt2403 spm
It2403 spm
 
PM Session 4
PM Session 4PM Session 4
PM Session 4
 
DCMA 14-Point Schedule Quality Check
DCMA 14-Point Schedule Quality CheckDCMA 14-Point Schedule Quality Check
DCMA 14-Point Schedule Quality Check
 
Project Time Estimation 6 Powerful Tips & Tricks
Project Time Estimation 6 Powerful Tips & TricksProject Time Estimation 6 Powerful Tips & Tricks
Project Time Estimation 6 Powerful Tips & Tricks
 
Project Plan And Estimation
Project Plan And EstimationProject Plan And Estimation
Project Plan And Estimation
 
Project Scheduling, Planning and Risk Management
Project Scheduling, Planning and Risk ManagementProject Scheduling, Planning and Risk Management
Project Scheduling, Planning and Risk Management
 
Project Control- Overview Presentation Tafseer
Project Control- Overview Presentation   TafseerProject Control- Overview Presentation   Tafseer
Project Control- Overview Presentation Tafseer
 

Similaire à Pert -cpm (20)

time mamangement.ppt
time mamangement.ppttime mamangement.ppt
time mamangement.ppt
 
PERT CPM Intro
PERT CPM IntroPERT CPM Intro
PERT CPM Intro
 
Pert 182
Pert 182Pert 182
Pert 182
 
06 pert cpm
06 pert cpm06 pert cpm
06 pert cpm
 
Pert
PertPert
Pert
 
06 pert cpm
06 pert cpm06 pert cpm
06 pert cpm
 
3...06 pert cpm
3...06 pert cpm3...06 pert cpm
3...06 pert cpm
 
porject management
porject managementporject management
porject management
 
S pert cpm
S pert cpmS pert cpm
S pert cpm
 
06 pert cpm (1)
06 pert cpm (1)06 pert cpm (1)
06 pert cpm (1)
 
Cpm n pert
Cpm n pertCpm n pert
Cpm n pert
 
PERT/CPM
PERT/CPMPERT/CPM
PERT/CPM
 
Pert cpm
Pert  cpmPert  cpm
Pert cpm
 
project management-cpm and pert methods for managers
project management-cpm and pert methods for managersproject management-cpm and pert methods for managers
project management-cpm and pert methods for managers
 
Pert cpm
Pert cpm Pert cpm
Pert cpm
 
Project managemen PERT VS CPM
Project managemen  PERT VS CPMProject managemen  PERT VS CPM
Project managemen PERT VS CPM
 
CPM AND PERT
CPM AND PERTCPM AND PERT
CPM AND PERT
 
Chapter 3.pptx
Chapter 3.pptxChapter 3.pptx
Chapter 3.pptx
 
Ch 5.pptx
Ch 5.pptxCh 5.pptx
Ch 5.pptx
 
project network
project networkproject network
project network
 

Plus de kabirmahlotra

Top 10 sales trends for 2015 hbr
Top 10 sales trends for 2015   hbrTop 10 sales trends for 2015   hbr
Top 10 sales trends for 2015 hbrkabirmahlotra
 
Basic info on java intro
Basic info on java introBasic info on java intro
Basic info on java introkabirmahlotra
 
Chapter 1 introduction
Chapter 1 introductionChapter 1 introduction
Chapter 1 introductionkabirmahlotra
 
Basic info on java intro
Basic info on java introBasic info on java intro
Basic info on java introkabirmahlotra
 

Plus de kabirmahlotra (7)

Top 10 sales trends for 2015 hbr
Top 10 sales trends for 2015   hbrTop 10 sales trends for 2015   hbr
Top 10 sales trends for 2015 hbr
 
Basic info on java intro
Basic info on java introBasic info on java intro
Basic info on java intro
 
Pert -cpm
Pert  -cpmPert  -cpm
Pert -cpm
 
Some presentation
Some presentationSome presentation
Some presentation
 
Culture9 info
Culture9 infoCulture9 info
Culture9 info
 
Chapter 1 introduction
Chapter 1 introductionChapter 1 introduction
Chapter 1 introduction
 
Basic info on java intro
Basic info on java introBasic info on java intro
Basic info on java intro
 

Dernier

APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAssociation for Project Management
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3JemimahLaneBuaron
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesFatimaKhan178732
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppCeline George
 
MENTAL STATUS EXAMINATION format.docx
MENTAL     STATUS EXAMINATION format.docxMENTAL     STATUS EXAMINATION format.docx
MENTAL STATUS EXAMINATION format.docxPoojaSen20
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsKarinaGenton
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingTechSoup
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeThiyagu K
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docxPoojaSen20
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdfssuser54595a
 

Dernier (20)

APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and Actinides
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website App
 
MENTAL STATUS EXAMINATION format.docx
MENTAL     STATUS EXAMINATION format.docxMENTAL     STATUS EXAMINATION format.docx
MENTAL STATUS EXAMINATION format.docx
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its Characteristics
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docx
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
 

Pert -cpm

  • 1. PROJECT MANAGEMENTPROJECT MANAGEMENT CPM/PERT V P B Chakravarthi . K Abhijeet Kumar
  • 2. ProjectProject  “A project is a series of activities directed to accomplishment of a desired objective.” Plan your work first…..then work your plan
  • 3. Network analysis Introduction Network analysis is the general name given to certain specific techniques which can be used for the planning, management and control of projects. One definition of a project: “A project is a temporary endeavour undertaken to create a "unique" product or service”
  • 4. HistoryHistory  Developed in 1950’s  CPM by DuPont for chemical plants  PERT by U.S. Navy for Polaris missile PERT was developed by the US Navy for the planning and control of the Polaris missile program and the emphasis was on completing the program in the shortest possible time. In addition PERT had the ability to cope with uncertain activity completion times (e.g. for a particular activity the most likely completion time is 4 weeks but it could be anywhere between 3 weeks and 8 weeks). CPM was developed by Du Pont and the emphasis was on the trade-off between the cost of the project and its overall completion time (e.g. for certain activities it may be possible to decrease their completion times by spending more money - how does this affect the overall completion time of the project?)
  • 5. CPM - Critical Path MethodCPM - Critical Path Method  Definition: In CPM activities are shown as a network of precedence relationships using activity-on-node network construction – Single estimate of activity time – Deterministic activity times USED IN : Production management - for the jobs of repetitive in nature where the activity time estimates can be predicted with considerable certainty due to the existence of past experience.
  • 6. PERT -PERT - Project Evaluation & Review TechniquesProject Evaluation & Review Techniques  Definition: In PERT activities are shown as a network of precedence relationships using activity-on-arrow network construction – Multiple time estimates – Probabilistic activity times USED IN : Project management - for non-repetitive jobs (research and development work), where the time and cost estimates tend to be quite uncertain. This technique uses probabilistic time estimates.
  • 7. Originated by H.L.Gantt in 1918 Gantt chart Advantages - Gantt charts are quite commonly used. They provide an easy graphical representation of when activities (might) take place. Limitations - Do not clearly indicate details regarding the progress of activities - Do not give a clear indication of interrelation ship between the separate activities
  • 8. CPM/PERTCPM/PERT These deficiencies can be eliminated to a large extent by showing the interdependence of various activities by means of connecting arrows called network technique.  Overtime CPM and PERT became one technique  ADVANTAGES: – Precedence relationships – large projects – more efficient
  • 9. The Project NetworkThe Project Network  Use of nodes and arrows Arrows An arrow leads from tail to head directionally – Indicate ACTIVITY, a time consuming effort that is required to perform a part of the work. Nodes  A node is represented by a circle - Indicate EVENT, a point in time where one or more activities start and/or finish.
  • 10. Activity on Node & Activity on ArrowActivity on Node & Activity on Arrow Activity on Node - A completion of an activity is represented by a node Activity on Arrow - An arrow represents a task, while a node is the completion of a task - Arrows represent order of events
  • 11. Activity SlackActivity Slack Each event has two important times associated with it : - Earliest time , Te , which is a calendar time when a event can occur when all the predecessor events completed at the earliest possible times - Latest time , TL , which is the latest time the event can occur with out delaying the subsequent events and completion of project.  Difference between the latest time and the earliest time of an event is the slack time for that event Positive slack : Slack is the amount of time an event can be delayed without delaying the project completion
  • 12. Critical PathCritical Path  Is that the sequence of activities and events where there is no “slack” i.e.. Zero slack  Longest path through a network  minimum project completion time
  • 13. Benefits of CPM/PERTBenefits of CPM/PERT  Useful at many stages of project management  Mathematically simple  Give critical path and slack time  Provide project documentation  Useful in monitoring costs
  • 14. Questions Answered by CPM & PERTQuestions Answered by CPM & PERT  Completion date?  On Schedule?  Within Budget?  Critical Activities?  How can the project be finished early at the least cost?
  • 15. exampleexample Illustration of network analysis of a minor redesign of a product and its associated packaging. The key question is: How long will it take to complete this project ?
  • 16. For clarity, this list is kept to a minimum by specifying only immediate relationships, that is relationships involving activities that "occur near to each other in time".
  • 17. •"What activities must be finished before this activity can start" •could we complete this project in 30 weeks? •could we complete this project in 2 weeks? One answer could be, if we first do activity 1, then activity 2, then activity 3, ...., then activity 10, then activity 11 and the project would then take the sum of the activity completion times, 30 weeks. “What is the minimum possible time in which we can complete this project ? “ Before starting any of the above activity, the questions asked would be
  • 18. We shall see below how the network analysis diagram/picture we construct helps us to answer this question.
  • 19. CRITICAL PATH TAKES 24 WEEKS FOR THE COMPLETION OF THE PROJECT
  • 20. Packages are available to determine the shortest path and other relevant information.
  • 22. Output of the package
  • 23. Limitations to CPM/PERTLimitations to CPM/PERT  Clearly defined, independent and stable activities  Specified precedence relationships  Over emphasis on critical paths