SlideShare une entreprise Scribd logo
1  sur  30
Project Time Management
Knowledge
Area
Process
Initiating Planning Executing
Monitoring &
Control
Closing
Time
Activity Definition
Activity Sequencing
Activity Resource Estimating
Activity Duration Estimating
Schedule Development
Schedule Control
Enter phase/
Start project
Exit phase/
End project
Initiating
Processes
Closing
Processes
Planning
Processes
Executing
Processes
Monitoring &
Controlling Processes
Project Time Management
Critical Path
• Critical Path is the longest duration path
• Identify the shortest time needed to complete a project
• There can be more than one critical path
• Float (Slack)
– Total float: the amount of time an activity can be
delayed without delaying the project end date or
intermediary milestone.
– Free float: the amount of time an activity can be
delayed without delaying the early start date of its
successor(s).
Critical Chain Method
The longest duration path through the project considering both activity
dependencies and resource constraints.
Type of buffers
Project buffer
Feeding buffer
Resource buffer
To keep resource usage at a
constant level. Resource leveling is
necessary when resources have
been over-allocated , such as
when a resource has been
assigned to two or more activities
during the same time period
Resource Leveling
What-if Scenario Analysis
Analysis on effect of
changes on a particular
thing (assumption) on
the project which make
activity duration change.
Monte Carlo Simulation
Used when there is
possibility that the
critical path will be
different for a given set
of project conditions.
Using computer software
• Schedule Compression :
• 1- crashing
• additional resources will add to shorten the
duration (increase cost)
• 2- fast tracking :
• activities normally performed in sequence are performed
in parallel
• (increase risk )
• E.g. Design is half finished and start coding.
Schedule Network Analysis
Schedule network analysis is a
technique that generates the
project schedule. It employs
various analytical techniques,
such as critical path method,
critical chain method, what-if
analysis, and resource leveling to
calculate the early and late start
and finish dates for the
uncompleted portions of project
activities.
• Develop Schedule
• Process of analyzing activity sequences, durations, resource requirements,
and schedule constraints to create the project schedule.
Inputs
1. Activity list
2. Activity attributes
3. Project schedule
network diagram
4. Activity resource
requirements
5. Resource Calendars
6. Activity duration
estimates
7. Project scope statement
8. Enterprise
environmental factors
9. Organizational process
assets
Tools &
Techniques
1. Schedule network
analysis
2. Critical path method
3. Critical chain method
4. Resource leveling
5. What-if scenario
analysis
6. Applying leads and lags
7. Schedule compression
8. Scheduling tool
Outputs
1. Project schedule
2. Schedule baseline
3. Schedule data
4. Project document
updates
Schedule formats:
Milestone charts.
scheduled start or
completion of major
deliverables and key
external interfaces.
Bar charts
- show activity start and end dates ,as well as
expected durations
- easy to read, and are frequently used in
management presentations
Network Diagramming
‫التالية‬ ‫االنشطة‬ ‫من‬ ‫مكون‬ ‫مشروع‬ ‫لدينا‬
‫النشاط‬ ‫اسم‬ ‫النشاط‬ ‫وصف‬ ‫الموارد‬ ‫احتياجات‬ ‫االصلية‬ ‫المدة‬
‫المنطقى‬ ‫النشاط‬
‫السابق‬
Start 0 -------------
A 2 Start
D 6 Start
B 12 A
C 5 B & D
E 7 D
F 3 E
Finish 0 C & F
Start
Finish
A B C
D E F
2 Days 12 Days 5 Days
6 Days 7 Days 3 Days
Network Diagramming Analysis
Start Finish
A B C
D E F
2 Days 12 Days 5 Days
6 Days 7 Days 3 Days
0
0
0
0 2 2 14 14 19
6 6 13 13 16
19 19
Highest of predecessor’s
Early Finish Times
Early Start =
Critical Path Method (PDM), Forward Pass
Start Finish
A B C
D E F
2 Days 12 Days 5 Days
6 Days 7 Days 3 Days
0
0
0
0 2 2 14 14 19
6 6 13 13 16
19 19
Lowest of successor’s Late Start Times
Late Finish =
2 14
19
16
14 19
19
19
0 0
0 2
3 9 9 16
Critical Path Method (PDM), Backward Pass
Start
Finish
A B C
D E F
2 Days 12 Days 5 Days
6 Days 7 Days 3 Days
‫المشروع‬ ‫تنفيذ‬ ‫من‬ ‫االنتهاء‬ ‫موعد‬ ‫تأخير‬ ‫دون‬ ‫المهمة‬ ‫تتاخرة‬ ‫ان‬ ‫يمكن‬ ‫الذى‬ ‫الوقت‬ ‫مقدار‬.
0
0
0
0 2 2 14 14 19
6 6 13 13 16
19 19
2 14
19
16
14 19
19
19
0 0
0 2
3 9 9 16
(0)
(0)
(0)
(3)(3)(3)
(0)
Float
Control Schedule
Process of analyzing activity sequences, durations, resource requirements,
and schedule constraints to create the project schedule.
Inputs
1. Project Management
Plan
2. Project Schedule
3. Work performance
information
4. Organizational process
assets
Tools &
Techniques
1. Performance reviews
2. Variance Analysis
3. Project Management
Software
4. Resource leveling
5. What-if scenario
analysis
6. Adjusting leads & lags
7. Schedule compression
8. Schedule tooling
Outputs
1. Work performance
measurements
2. Organizational process
assets updates
3. Change requests
4. Project management
plan updates
5. Project document
updates
1 Performance Reviews
measure, compare, and analyze
schedule performance such as
actual start and finish dates,
percent complete, and
remaining duration for work in
progress.
Network Diagramming
‫التالية‬ ‫االنشطة‬ ‫من‬ ‫مكون‬ ‫مشروع‬ ‫لدينا‬
‫النشاط‬ ‫اسم‬ ‫النشاط‬ ‫وصف‬ ‫الموارد‬ ‫احتياجات‬ ‫االصلية‬ ‫المدة‬
‫المنطقى‬ ‫النشاط‬
‫السابق‬
Start 0 -------------
A 4 Start
D 6 Start
F 7 D&A
E 8 D
G 5 F&E
B 5 F
H 7 G
c 8 H
Finish 0 C & B
QUESTIONS?
1-fast tracking the project usually :
A-decreases project costs
B- decreases Project duration
C- decreases the amount of management oversight
needed
D-decrease the number of resources used
2- free float is the amount of time an activity can
be delayed without delaying the
A- Project
B- completion date required by the customer
C-early start of its successor
D- project completion date
3-What-if scenario analysis is done as a part of which
process:
A-Sequence Activities
B-Define Activities
C-Control Schedule
D-Estimate resource
4- To crash a schedule you should:
A-Increase the time allowed on those tasks that have
float.
B-Try to increase expenditures of time only those
tasks that are behind schedule.
C-Replace those worker that are not performing up to
par with the busy.
D-Increase work efforts on those tasks that are
on the critical path
5-Resource leveling attempts to :
A-Reduce resource requirements by smoothing out period-
to period resource assignments.
B-Ensure that the budget abnormalities are overcome.
C-Reduce the amount of resources so that they can be
shared with on other endeavors.
D-Increase the amount of the project manager's
authority so that budget dollars can be appropriated
6-You are the project manager for the large
Project. You have identified and documented
relationship among the project activities and
created project schedule network diagram.
What is your NEXT step ?
A. Define Activities
B. Sequence Activities
C. Develop Schedule
D. Control Schedule
7- you are a project manager for a new Product development
Project that has four levels in the work breakdown structure and
has been sequenced using the precedence diagramming method
the activity duration estimates have been received . What time
management activity would you do NEXT?
A-schedule compression
B- collect historical records from previous projects
C- create an activity list
D- update the work breakdown structure
8- as project process is tracked according to the Project
Management plan the project manager discovers that
final deliverables will be completed two months after
the deliverable dates imposed by management
What should the project manager do?
A- look for options with stakeholders using some combination of
scaling back work , re evaluating discretionary dependencies,
and adding resources
B- evaluate the impact on the company of completing this
project late
C- drive the project team to work faster to make up for lost time
D- recalculate the project schedule and distribute it according to
the communications management plan
9-an activity has been delayed and the project
manager needs to deal with the situation. What
is the NEXT thing he should do ?
A-report to management
B-crash or fast track
C- determine how much of a problem it is
D-use contingency reserves
Thank you

Contenu connexe

Tendances

Project Management focused on Scheduling of a Project
Project Management focused on Scheduling of a ProjectProject Management focused on Scheduling of a Project
Project Management focused on Scheduling of a Project
Meryem Yıldız
 
Seven Basic Steps to Build Realistic Schedule in Project 2010
Seven Basic Steps to Build Realistic Schedule in Project 2010Seven Basic Steps to Build Realistic Schedule in Project 2010
Seven Basic Steps to Build Realistic Schedule in Project 2010
B Sai Prasad
 
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Charlie Jackson
 
2.06 time management 1
2.06 time management 12.06 time management 1
2.06 time management 1
reddvise
 

Tendances (19)

Project Management focused on Scheduling of a Project
Project Management focused on Scheduling of a ProjectProject Management focused on Scheduling of a Project
Project Management focused on Scheduling of a Project
 
Network diagrams
Network diagramsNetwork diagrams
Network diagrams
 
Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-
 
Project Scheduling
Project Scheduling Project Scheduling
Project Scheduling
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project scheduling
 
6.project timemanagement
6.project timemanagement6.project timemanagement
6.project timemanagement
 
Seven Basic Steps to Build Realistic Schedule in Project 2010
Seven Basic Steps to Build Realistic Schedule in Project 2010Seven Basic Steps to Build Realistic Schedule in Project 2010
Seven Basic Steps to Build Realistic Schedule in Project 2010
 
10 key features of microsoft project plan (mpp)
10 key features of microsoft project plan (mpp)10 key features of microsoft project plan (mpp)
10 key features of microsoft project plan (mpp)
 
Meeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsMeeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance Standards
 
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
 
Scheduling of a project
Scheduling of a projectScheduling of a project
Scheduling of a project
 
Project schedule Management - PMP/CAPM
Project schedule Management - PMP/CAPMProject schedule Management - PMP/CAPM
Project schedule Management - PMP/CAPM
 
2.06 time management 1
2.06 time management 12.06 time management 1
2.06 time management 1
 
Primavera P6
Primavera P6Primavera P6
Primavera P6
 
Scheduling of a five story residential apartment project
Scheduling of a five story residential apartment project Scheduling of a five story residential apartment project
Scheduling of a five story residential apartment project
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
Primavara
PrimavaraPrimavara
Primavara
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
6.3 sequence activities
6.3 sequence activities6.3 sequence activities
6.3 sequence activities
 

En vedette

Grade 8 Music and Arts Module
Grade 8 Music and Arts ModuleGrade 8 Music and Arts Module
Grade 8 Music and Arts Module
Andrew Cabugason
 

En vedette (19)

Session 7 4th edition PMP
Session 7 4th edition PMPSession 7 4th edition PMP
Session 7 4th edition PMP
 
Session 21 4th edition PMP
Session 21 4th edition PMPSession 21 4th edition PMP
Session 21 4th edition PMP
 
Session 15 4th edition PMP
Session 15 4th edition PMPSession 15 4th edition PMP
Session 15 4th edition PMP
 
Session 16 4th edition
Session 16 4th editionSession 16 4th edition
Session 16 4th edition
 
Session 19 4th edition PMP
Session  19 4th edition PMPSession  19 4th edition PMP
Session 19 4th edition PMP
 
Session 18 -2 PMP 4th edition
Session 18 -2  PMP 4th editionSession 18 -2  PMP 4th edition
Session 18 -2 PMP 4th edition
 
Session 10 4th edition PMP
Session   10 4th edition PMPSession   10 4th edition PMP
Session 10 4th edition PMP
 
Session 13 4th edition PMP
Session 13 4th edition PMPSession 13 4th edition PMP
Session 13 4th edition PMP
 
Session 2 PMP 4TH edition
Session 2 PMP 4TH editionSession 2 PMP 4TH edition
Session 2 PMP 4TH edition
 
Session 12 4th edition PMP
Session  12 4th edition PMPSession  12 4th edition PMP
Session 12 4th edition PMP
 
Session 20 4th edition PMP
Session 20 4th edition PMPSession 20 4th edition PMP
Session 20 4th edition PMP
 
Session 9 4th edition PMP
Session 9 4th edition PMPSession 9 4th edition PMP
Session 9 4th edition PMP
 
Session 22 4th edition PMP
Session 22 4th edition PMPSession 22 4th edition PMP
Session 22 4th edition PMP
 
Session 18 4th edition PMP
Session 18 4th edition PMPSession 18 4th edition PMP
Session 18 4th edition PMP
 
Session 14 4th edition PMP
Session  14 4th edition PMPSession  14 4th edition PMP
Session 14 4th edition PMP
 
Chinese Theater - MAPEH 8 (Music 4th Quarter)
Chinese Theater - MAPEH 8 (Music 4th Quarter)Chinese Theater - MAPEH 8 (Music 4th Quarter)
Chinese Theater - MAPEH 8 (Music 4th Quarter)
 
Grade 8 PE module(Q4)
Grade 8 PE module(Q4)Grade 8 PE module(Q4)
Grade 8 PE module(Q4)
 
Grade 8 Music 4th Quarter
Grade 8 Music 4th QuarterGrade 8 Music 4th Quarter
Grade 8 Music 4th Quarter
 
Grade 8 Music and Arts Module
Grade 8 Music and Arts ModuleGrade 8 Music and Arts Module
Grade 8 Music and Arts Module
 

Similaire à Session 8 4th edition PMP

Day 3 Schedule -walaa (3).pptx
Day 3 Schedule -walaa (3).pptxDay 3 Schedule -walaa (3).pptx
Day 3 Schedule -walaa (3).pptx
MohanadRabea1
 

Similaire à Session 8 4th edition PMP (20)

Time management
Time managementTime management
Time management
 
TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5
 
Topic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdfTopic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdf
 
06 projecttimemanagement
06 projecttimemanagement06 projecttimemanagement
06 projecttimemanagement
 
3- Project Time Management.ppt
3- Project Time Management.ppt3- Project Time Management.ppt
3- Project Time Management.ppt
 
4) PTM & PCM .pptx
4) PTM & PCM .pptx4) PTM & PCM .pptx
4) PTM & PCM .pptx
 
Day 3 Schedule -walaa (3).pptx
Day 3 Schedule -walaa (3).pptxDay 3 Schedule -walaa (3).pptx
Day 3 Schedule -walaa (3).pptx
 
PMNM101 Lesson 2 2022.pptx
PMNM101 Lesson 2 2022.pptxPMNM101 Lesson 2 2022.pptx
PMNM101 Lesson 2 2022.pptx
 
CHAPTER 1.pptx
CHAPTER 1.pptxCHAPTER 1.pptx
CHAPTER 1.pptx
 
CHAPTER 1.pptx
CHAPTER 1.pptxCHAPTER 1.pptx
CHAPTER 1.pptx
 
Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)
 
Project planning
Project planningProject planning
Project planning
 
Time management pressent
Time management pressentTime management pressent
Time management pressent
 
Pmbok 5th planning process group part two
Pmbok 5th planning process group part twoPmbok 5th planning process group part two
Pmbok 5th planning process group part two
 
Chapter 4.pptx
Chapter 4.pptxChapter 4.pptx
Chapter 4.pptx
 
Session 5 4th edition PMP
Session 5 4th edition PMPSession 5 4th edition PMP
Session 5 4th edition PMP
 
PMP Exam Preparation Course: 05 Project Time Management
PMP Exam Preparation Course: 05 Project Time ManagementPMP Exam Preparation Course: 05 Project Time Management
PMP Exam Preparation Course: 05 Project Time Management
 
Pm chapter 5...
Pm chapter 5...Pm chapter 5...
Pm chapter 5...
 
6.5 Develop Schedule
6.5 Develop Schedule6.5 Develop Schedule
6.5 Develop Schedule
 
project time management
 project time management project time management
project time management
 

Dernier

Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTECAbortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Riyadh +966572737505 get cytotec
 
internship thesis pakistan aeronautical complex kamra
internship thesis pakistan aeronautical complex kamrainternship thesis pakistan aeronautical complex kamra
internship thesis pakistan aeronautical complex kamra
AllTops
 
The Psychology Of Motivation - Richard Brown
The Psychology Of Motivation - Richard BrownThe Psychology Of Motivation - Richard Brown
The Psychology Of Motivation - Richard Brown
SandaliGurusinghe2
 
Beyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable developmentBeyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable development
Nimot Muili
 
Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptx
alinstan901
 

Dernier (16)

Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTECAbortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
 
Intro_University_Ranking_Introduction.pptx
Intro_University_Ranking_Introduction.pptxIntro_University_Ranking_Introduction.pptx
Intro_University_Ranking_Introduction.pptx
 
How Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptxHow Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptx
 
digital Human resource management presentation.pdf
digital Human resource management presentation.pdfdigital Human resource management presentation.pdf
digital Human resource management presentation.pdf
 
Reviewing and summarization of university ranking system to.pptx
Reviewing and summarization of university ranking system  to.pptxReviewing and summarization of university ranking system  to.pptx
Reviewing and summarization of university ranking system to.pptx
 
Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siliguri
Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime SiliguriSiliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siliguri
Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siliguri
 
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professionalW.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
 
Leaders enhance communication by actively listening, providing constructive f...
Leaders enhance communication by actively listening, providing constructive f...Leaders enhance communication by actively listening, providing constructive f...
Leaders enhance communication by actively listening, providing constructive f...
 
internship thesis pakistan aeronautical complex kamra
internship thesis pakistan aeronautical complex kamrainternship thesis pakistan aeronautical complex kamra
internship thesis pakistan aeronautical complex kamra
 
International Ocean Transportation p.pdf
International Ocean Transportation p.pdfInternational Ocean Transportation p.pdf
International Ocean Transportation p.pdf
 
Marketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docxMarketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docx
 
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot ModelGautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot Model
 
Safety T fire missions army field Artillery
Safety T fire missions army field ArtillerySafety T fire missions army field Artillery
Safety T fire missions army field Artillery
 
The Psychology Of Motivation - Richard Brown
The Psychology Of Motivation - Richard BrownThe Psychology Of Motivation - Richard Brown
The Psychology Of Motivation - Richard Brown
 
Beyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable developmentBeyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable development
 
Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptx
 

Session 8 4th edition PMP

  • 2. Knowledge Area Process Initiating Planning Executing Monitoring & Control Closing Time Activity Definition Activity Sequencing Activity Resource Estimating Activity Duration Estimating Schedule Development Schedule Control Enter phase/ Start project Exit phase/ End project Initiating Processes Closing Processes Planning Processes Executing Processes Monitoring & Controlling Processes Project Time Management
  • 3. Critical Path • Critical Path is the longest duration path • Identify the shortest time needed to complete a project • There can be more than one critical path • Float (Slack) – Total float: the amount of time an activity can be delayed without delaying the project end date or intermediary milestone. – Free float: the amount of time an activity can be delayed without delaying the early start date of its successor(s).
  • 4. Critical Chain Method The longest duration path through the project considering both activity dependencies and resource constraints. Type of buffers Project buffer Feeding buffer Resource buffer
  • 5. To keep resource usage at a constant level. Resource leveling is necessary when resources have been over-allocated , such as when a resource has been assigned to two or more activities during the same time period Resource Leveling
  • 6. What-if Scenario Analysis Analysis on effect of changes on a particular thing (assumption) on the project which make activity duration change. Monte Carlo Simulation Used when there is possibility that the critical path will be different for a given set of project conditions. Using computer software
  • 7. • Schedule Compression : • 1- crashing • additional resources will add to shorten the duration (increase cost) • 2- fast tracking : • activities normally performed in sequence are performed in parallel • (increase risk ) • E.g. Design is half finished and start coding.
  • 8. Schedule Network Analysis Schedule network analysis is a technique that generates the project schedule. It employs various analytical techniques, such as critical path method, critical chain method, what-if analysis, and resource leveling to calculate the early and late start and finish dates for the uncompleted portions of project activities.
  • 9. • Develop Schedule • Process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule. Inputs 1. Activity list 2. Activity attributes 3. Project schedule network diagram 4. Activity resource requirements 5. Resource Calendars 6. Activity duration estimates 7. Project scope statement 8. Enterprise environmental factors 9. Organizational process assets Tools & Techniques 1. Schedule network analysis 2. Critical path method 3. Critical chain method 4. Resource leveling 5. What-if scenario analysis 6. Applying leads and lags 7. Schedule compression 8. Scheduling tool Outputs 1. Project schedule 2. Schedule baseline 3. Schedule data 4. Project document updates
  • 10. Schedule formats: Milestone charts. scheduled start or completion of major deliverables and key external interfaces.
  • 11. Bar charts - show activity start and end dates ,as well as expected durations - easy to read, and are frequently used in management presentations
  • 12. Network Diagramming ‫التالية‬ ‫االنشطة‬ ‫من‬ ‫مكون‬ ‫مشروع‬ ‫لدينا‬ ‫النشاط‬ ‫اسم‬ ‫النشاط‬ ‫وصف‬ ‫الموارد‬ ‫احتياجات‬ ‫االصلية‬ ‫المدة‬ ‫المنطقى‬ ‫النشاط‬ ‫السابق‬ Start 0 ------------- A 2 Start D 6 Start B 12 A C 5 B & D E 7 D F 3 E Finish 0 C & F
  • 13. Start Finish A B C D E F 2 Days 12 Days 5 Days 6 Days 7 Days 3 Days Network Diagramming Analysis
  • 14. Start Finish A B C D E F 2 Days 12 Days 5 Days 6 Days 7 Days 3 Days 0 0 0 0 2 2 14 14 19 6 6 13 13 16 19 19 Highest of predecessor’s Early Finish Times Early Start = Critical Path Method (PDM), Forward Pass
  • 15. Start Finish A B C D E F 2 Days 12 Days 5 Days 6 Days 7 Days 3 Days 0 0 0 0 2 2 14 14 19 6 6 13 13 16 19 19 Lowest of successor’s Late Start Times Late Finish = 2 14 19 16 14 19 19 19 0 0 0 2 3 9 9 16 Critical Path Method (PDM), Backward Pass
  • 16. Start Finish A B C D E F 2 Days 12 Days 5 Days 6 Days 7 Days 3 Days ‫المشروع‬ ‫تنفيذ‬ ‫من‬ ‫االنتهاء‬ ‫موعد‬ ‫تأخير‬ ‫دون‬ ‫المهمة‬ ‫تتاخرة‬ ‫ان‬ ‫يمكن‬ ‫الذى‬ ‫الوقت‬ ‫مقدار‬. 0 0 0 0 2 2 14 14 19 6 6 13 13 16 19 19 2 14 19 16 14 19 19 19 0 0 0 2 3 9 9 16 (0) (0) (0) (3)(3)(3) (0) Float
  • 17. Control Schedule Process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule. Inputs 1. Project Management Plan 2. Project Schedule 3. Work performance information 4. Organizational process assets Tools & Techniques 1. Performance reviews 2. Variance Analysis 3. Project Management Software 4. Resource leveling 5. What-if scenario analysis 6. Adjusting leads & lags 7. Schedule compression 8. Schedule tooling Outputs 1. Work performance measurements 2. Organizational process assets updates 3. Change requests 4. Project management plan updates 5. Project document updates
  • 18. 1 Performance Reviews measure, compare, and analyze schedule performance such as actual start and finish dates, percent complete, and remaining duration for work in progress.
  • 19. Network Diagramming ‫التالية‬ ‫االنشطة‬ ‫من‬ ‫مكون‬ ‫مشروع‬ ‫لدينا‬ ‫النشاط‬ ‫اسم‬ ‫النشاط‬ ‫وصف‬ ‫الموارد‬ ‫احتياجات‬ ‫االصلية‬ ‫المدة‬ ‫المنطقى‬ ‫النشاط‬ ‫السابق‬ Start 0 ------------- A 4 Start D 6 Start F 7 D&A E 8 D G 5 F&E B 5 F H 7 G c 8 H Finish 0 C & B
  • 21. 1-fast tracking the project usually : A-decreases project costs B- decreases Project duration C- decreases the amount of management oversight needed D-decrease the number of resources used
  • 22. 2- free float is the amount of time an activity can be delayed without delaying the A- Project B- completion date required by the customer C-early start of its successor D- project completion date
  • 23. 3-What-if scenario analysis is done as a part of which process: A-Sequence Activities B-Define Activities C-Control Schedule D-Estimate resource
  • 24. 4- To crash a schedule you should: A-Increase the time allowed on those tasks that have float. B-Try to increase expenditures of time only those tasks that are behind schedule. C-Replace those worker that are not performing up to par with the busy. D-Increase work efforts on those tasks that are on the critical path
  • 25. 5-Resource leveling attempts to : A-Reduce resource requirements by smoothing out period- to period resource assignments. B-Ensure that the budget abnormalities are overcome. C-Reduce the amount of resources so that they can be shared with on other endeavors. D-Increase the amount of the project manager's authority so that budget dollars can be appropriated
  • 26. 6-You are the project manager for the large Project. You have identified and documented relationship among the project activities and created project schedule network diagram. What is your NEXT step ? A. Define Activities B. Sequence Activities C. Develop Schedule D. Control Schedule
  • 27. 7- you are a project manager for a new Product development Project that has four levels in the work breakdown structure and has been sequenced using the precedence diagramming method the activity duration estimates have been received . What time management activity would you do NEXT? A-schedule compression B- collect historical records from previous projects C- create an activity list D- update the work breakdown structure
  • 28. 8- as project process is tracked according to the Project Management plan the project manager discovers that final deliverables will be completed two months after the deliverable dates imposed by management What should the project manager do? A- look for options with stakeholders using some combination of scaling back work , re evaluating discretionary dependencies, and adding resources B- evaluate the impact on the company of completing this project late C- drive the project team to work faster to make up for lost time D- recalculate the project schedule and distribute it according to the communications management plan
  • 29. 9-an activity has been delayed and the project manager needs to deal with the situation. What is the NEXT thing he should do ? A-report to management B-crash or fast track C- determine how much of a problem it is D-use contingency reserves