Effectiveness of Purpose-Specific
Elevated Expressways in India: A Case
Study of PVNR Expressway, Hyderabad
Study of PVNR Expressway, Hyderabad
Study of PVNR Expressway, Hyderabad
1
By
Lahari Yaddanapudi
141109047, II year, Department of Planning and Architecture
Maulana Azad National Institute of Technology, Bhopal
Aim
Assess the effectiveness of purpose-specific expressways in
India by taking a case study of the P V Narsimha Rao
expressway in Hyderabad
2
Objectives
• Understanding the concept of expressways
• Elevated expressways or ground level expressways- practicality in the Indian context
• Understanding purpose specific expressways- where origin and destination were selected
to serve some purpose
• Study of the PVNR expressway-
• History
• Purpose
• Functioning- infrastructure, monitoring and control, safety
• Accidents and denomination of accident prone areas
• In this way, evaluating the PVNR expressway and the importance of purpose specific
elevated expressways in India
3
Introduction
• Elevated expressway- major road that is raised up above the ground level
with complete access control
• Expressway-
• Highest class of roads in the Indian road network
• Six or eight laned
• Indian context: most of the expressways have the term ‘expressway’ in
their name but do not confine to the norms that make it an expressway
• P V Narsimha Rao Elevated Expressway in Hyderabad-
• Longest flyover of India
4
• Starting at the Southern part of the core
city, Mehdipatnam, it passes through
Rethibowli, Laxmi Nagar, Attapur,
Hyderguda, Upperpally, Rajendra Nagar
and finally joins the National Highway-7
at Aramghar junction
• Total length: 11.6kms
• Inaugurated in October 2009
• Has six midway entry and exit ramps
• Approximately 2,500 vehicles take the
elevated expressway to the airport and
Bangalore everyday
• No-toll expressway as of now but
proposals to introduce toll tax are being
discussed
5
Fig.1: PVNR Elevated Expressway Stretch
Source: Maps of India
Background
• The Begumpet airport, which was the only international airport
• Due to the rapid growth of the city of Hyderabad, the Begumpet airport had
become a part of the integral part of the city
• This restricted the growth and expansion of the airport. So, an airport at the
present city outskirts was proposed at Shamshabad
• Shamshabad being an outskirt region, was not that accessible in terms of
the commuting time it took
• Common public had to travel for about 1 to 2 hours from any part of the city
to reach the airport
• An elevated expressway was proposed which will eventually lead to the
Rajiv Gandhi International Airport at Shamshabad
6
• P V Narasimha Rao who was from
Andhra Pradesh became the Prime
Minister of India in 1991
• He heralded economic reforms in India
by allowing private partnership in the
control and operation of airports in the
country
• Keeping this enormous contribution of
our former Prime Minister in mind, the
expressway proposed for the faster
access to the airport was named after
him
• The concept of this expressway was
conceived in 2003-04 during the tenure
of the TDP
• Inaugurated during the tenure of the
Congress Party on 19 October 2009
Begumpet
Airport
Shamshabad Airport
Fig.2: Begumpet and Shamshabad Airports
Source: IIT Hyderabad website (www.iith.ac.in)
7
Construction
• Initiated in 2004, the construction of this expressway was completed
by 2009 and was ready for operation
• Usually during the construction of elevated structures, accidents to
workers are a common sight
• But one important and major noticeable aspect of the entire process of
construction was that no casualties or accidents to the construction
workers occurred during the construction of this expressway
8
Structure
• The project consisted of three major components:
• Elevated Expressway: four lane divided carriageway stretching from
Mehdipatnam and passing through Rethibowli, Laxmi Nagar, Attapur,
Hyderguda, Upperpally, Rajendra Nagar and finally joining the National
highway- 7 at Aramgarh Junction
• Trumpet interchange: four lane divided carriageway built to facilitate free
flow of traffic towards airport from Hyderabad and Bangalore side with a
length of 3.9 km and width of 17.2 mts.
• Underpass at Aramgarh: length of 62 mts and width of 19.4 mts with a
vertical clearance of 5.5 mts was constructed to facilitate uninterrupted
flow of traffic at Aramgarh Junction on NH-7 with approach ramps on
either side i.e., towards Mehdipatnam and Chandrayangutta
9
• The two lane carriageway (one direction of flow) is of a width of
7.5 mts
• Narrows down to one and a half lane with a width of 6 mts at
Laxminagar, Upparpally and Shivrampally due to steep turnings
• Unique feature of the structure of this expressway is that it has
two or three areas dedicated for parking on the expressway for
the vehicles that break down during their journey on this elevated
platform
• Tow their vehicles to these places or call for help on the provided
helplines which promise to send their towing vehicle within 20
minutes of the emergency call
10
Infrastructure
• P V Narsimha Rao expressway was built by the Hyderabad
Metropolitan Development Authority (HMDA) in association with
Simplex Somdatta, the project contractors
• The project, which costed the government a total amount of Rs.
439 crore, included the construction of a total of 328 foundations,
327 spans, 291 pre-cast slabs, 36 cast-in-site slabs and 328 piers
• Carriageway is divided and thus chances of head-on collisions
with vehicles moving in opposite directions are avoided
11
Control and monitoring
• Maximum speed limit on the PVNR Expressway is 60 kmph for
light motor vehicles
• At sharp turns (i.e., at Laxminagar, Upparpally and Shivrampally)
where the carriageway narrows down from 7.5 mts to 6 mts, the
maximum speed has been restricted to 40 kmph
• Cycles, two wheelers, three wheelers, three and four wheeled
seven seaters, pushcarts and bullock carts are not allowed on to
the expressway
• All goods vehicles, be it light, medium or heavy vehicles are
prohibited to use this flyover
12
• Overtaking at sharp turnings has been strictly prohibited
• Parking has been strictly prohibited on the highway
• However, special areas have been allocated on the
expressway for vehicles that break down or malfunction
during the course of travel
• This parking space and towing facility come with a minimal
fee
• Expressway is monitored by the traffic police of Hyderabad
• P V Narsimha Rao expressway is a toll free expressway
13
• Expressway comes under the maintenance of the
Hyderabad Metropolitan Development Authority as well
as the Greater Hyderabad Municipal Corporation
• Special attention to highways and thus, even this
expressway is given to ensure that the road is in perfect
condition- to accommodate free flow of vehicles and also
allow the smooth transit of vehicles at the high speeds
they travel at
14
Time efficiency
• Major reason for the construction of this expressway was to minimise
the travel time of the people going to the new International Airport at
Shamshabad and to ease the congestion on the roads of the integral
parts of the city that lead to the airport
• Purpose of construction of this prestigious structure was served as it
has reduced the travel time to quite an extent
• Earlier, for people to go to the airport, they had to pass through the
internal old parts of the city that had narrow roads or roads that could
not accommodate the volume of traffic, it used to take 1 to 1.5 hours
• The most efficient route that would save distance as well as time when
built on an elevated platform was identified and built
15
• Given that the entry point to the expressway is at Mehdipatnam, a core area in the
Southern part of the city and provisions of few other entry ramps in between, we can
assume the average travel time from any part of the city to the approach point to be
10 minutes
• Also, the length of the expressway is 11.6 kms, approx. 12 kms and a speed limit of 60
kmph with 40 kmph at narrow and steep turnings, the average speed can be taken as 50
kmph. At this speed, the stretch of 12 kms can be covered in
12*60/50 = 14.4 minutes
i.e., approximately 14 minutes
• Then, from the Aramgarh Junction to the Shamshabad airport on NH-7, assuming it to take
5 minutes
• The entire travel time from one’s origin to destination that used to take one to one and a half hour has been
brought down to
10+14+5= 29
which is again approximately 30 minutes.
16
Accident reports
• First accident- November, 2009 at around 7pm. The driver of a van
carrying three postal department officials suddenly felt giddy and
rammed into the third lamppost. The four of them suffered injuries in
the accident but everyone were declared out of danger in a short time
• January, 2013 where “an i10 car crashed into an Indica car which was
about to get on to the Rajendranagar-Retibowli main road from a down
ramp of the expressway at Upparapally, and did a somersault before
landing on the side of an Innova going towards Retibowli.” This
accident took place near pillar number 194 of the expressway at
Upparapally where the traffic coming from Shamshabad joins
Rajendranagar- Retibowli road via a ramp. The vehicles were heavily
damaged but luckily, no one suffered any major injuries
17
• First fatal accident- Septemper, 2014 in which two people lost their
lives due to reckless driving on the expressway. Their car hit a road
divider and both the victims are said to have died on the spot
• Recommendations given by the CRRI to the HMDA to reduce
accidents:
• Maximum speed on the expressway is only 60 kmph, this should
be mandated
• As there is no scope for building speed breakers on the
expressway use ‘Rumble Strips’
• Signage aren’t enough to control speed, use speed guns and levy
hefty fines for over speeding
• Remove all the central medians
18
• As another measure to reduce accidents at the Laxminagar crossroads, near
pillar number 68, the zonal commission was directed by the Greater Hyderabad
Municipal Corporation to remove illegal temporary huts near the said location
• Also, it was suggested to put up proposals to widen the road from Laxminagar
to Gudimalkapur
• So, the accident prone areas or structures thus identified are:
• (a) The entry of the expressway
• (b) Down ramp of the expressway at Upparapally
• (c) Near pillar number 194
• (d) Road dividers
• (e) Laxminagar Crossroads, near pillar number 68
19
Conclusion
• Expressways though not common in India, are actually a need in the Indian context
due the the fast developing metropolitan cities
• In cases where cities are old, the demolition of structures and acquisition of land is
not feasible. In such situations, the optimum solution is to construct elevated
expressways
• Elevated expressways can be expressways linking two specific places for a
purpose. This makes them purpose specific
• P V Narsimha Rao expressway, the purpose was to provide quick and efficient
access to the airport which had become difficult as the route was through the core
parts of the city
• The time efficiency has increased by double or more times it was before
• Elevated expressway not only eases congestion on the road below it but also if
built for for a specific trip from specified origin to destination- the most efficient
solution to routes that require such a service
20
References
• 1) “Speed Limit on elevated expressway 60 kmph"
The Hindu (19-10-2009)
• 2) “Longest Elevated Expressway Inaugurated in
Hyderabad | India Trends” Indiatrends.info (20-10-2009)
• 3) “Hyderabad gets India’s longest flyover”
ndtv.com (16-07-2010)
• 4) “PVNR Elevated Expressway”
mapsofindia.com
• 5) Begumpet and Shamshabad Airports- “IIT-H location
map”
www.iith.ac.in
• 6) “PVNR Expressway”
Hyderabad Metropolitan Development Authority website
• 7) “Severe resource crunch effects prestigious PVNR
Elevated Expressway” The Hindu (26-04-2009)
21
•
8) “First Accident on PVNR Expressway” Times of India (07-11-2009)
•
9) “Freak accident on PVNR expressway” Times of India (03-01-2013)
•
10) “Five killed in road accidents”
The Hindu (30-09-2014)
•
11) “Finally a solution to PVNR accidents”
The Hans India (16-09-2013)
•
12) “GHMC to Demolish Illegal Huts near PVNR Expressway” The New Indian Express ( 09-02-2014)
Thank you ^_^
22

Contenu connexe

Tendances

Tendances (20)

Geometric design
Geometric designGeometric design
Geometric design
 
Chapter 1 Introduction to road
Chapter 1 Introduction to roadChapter 1 Introduction to road
Chapter 1 Introduction to road
 
pakistan indus basin irrigation system
pakistan indus basin irrigation system pakistan indus basin irrigation system
pakistan indus basin irrigation system
 
LMRC summer training
LMRC summer trainingLMRC summer training
LMRC summer training
 
Highway unit-1-hand-outs
Highway unit-1-hand-outsHighway unit-1-hand-outs
Highway unit-1-hand-outs
 
Pakistan transport slideshare
Pakistan transport slidesharePakistan transport slideshare
Pakistan transport slideshare
 
Tre be civil
Tre be civilTre be civil
Tre be civil
 
GEOMETRIC DESIGN OF HIGHWAY
GEOMETRIC DESIGN OF HIGHWAYGEOMETRIC DESIGN OF HIGHWAY
GEOMETRIC DESIGN OF HIGHWAY
 
Making of mughal road..
Making of mughal road..Making of mughal road..
Making of mughal road..
 
Highway Engineering Introduction: Lecture 1
Highway Engineering  Introduction: Lecture 1Highway Engineering  Introduction: Lecture 1
Highway Engineering Introduction: Lecture 1
 
Chapter 2 Road geometrics
Chapter 2 Road geometricsChapter 2 Road geometrics
Chapter 2 Road geometrics
 
Canal System of Pakistan
Canal System of PakistanCanal System of Pakistan
Canal System of Pakistan
 
Introduction to highway engineering
Introduction to highway engineeringIntroduction to highway engineering
Introduction to highway engineering
 
Indian railway ( Information)
Indian railway ( Information)Indian railway ( Information)
Indian railway ( Information)
 
transportation
transportationtransportation
transportation
 
Cross section of road
Cross section of roadCross section of road
Cross section of road
 
Headworks and barrages in pakistan
Headworks and barrages in pakistan Headworks and barrages in pakistan
Headworks and barrages in pakistan
 
transportation Engineering.Highway planning,alignment and geometry.
transportation Engineering.Highway planning,alignment and geometry.transportation Engineering.Highway planning,alignment and geometry.
transportation Engineering.Highway planning,alignment and geometry.
 
River Ravi Situation
River Ravi SituationRiver Ravi Situation
River Ravi Situation
 
highway development in india
highway development in indiahighway development in india
highway development in india
 

Similaire à Effectiveness of Purpose-Specific Elevated Expressways in India: A Case Study of PVNR Expressway, Hyderabad

Communication Skills Highways
Communication Skills HighwaysCommunication Skills Highways
Communication Skills Highways
Hassan Altaf
 
Highway notes (planning, alignment, & geometric design )
Highway notes (planning, alignment, & geometric design )Highway notes (planning, alignment, & geometric design )
Highway notes (planning, alignment, & geometric design )
mohit kumar panchal
 
DAVV IET_ TraNSPORTATION [PPT LECTURES ALL 501.pptx
DAVV IET_ TraNSPORTATION [PPT LECTURES ALL 501.pptxDAVV IET_ TraNSPORTATION [PPT LECTURES ALL 501.pptx
DAVV IET_ TraNSPORTATION [PPT LECTURES ALL 501.pptx
prtaap1
 

Similaire à Effectiveness of Purpose-Specific Elevated Expressways in India: A Case Study of PVNR Expressway, Hyderabad (20)

01-Transportation Engg_Prof. Aamir.pptx
01-Transportation Engg_Prof. Aamir.pptx01-Transportation Engg_Prof. Aamir.pptx
01-Transportation Engg_Prof. Aamir.pptx
 
Expressway plan
Expressway planExpressway plan
Expressway plan
 
casestudy.pptx
casestudy.pptxcasestudy.pptx
casestudy.pptx
 
Modes of transports
Modes of transportsModes of transports
Modes of transports
 
Transportation Engineering
Transportation EngineeringTransportation Engineering
Transportation Engineering
 
Highway planning and alignment
Highway planning and alignmentHighway planning and alignment
Highway planning and alignment
 
CET 206(Transportation Engineering)_Module1_Part 1 - st .pdf
CET 206(Transportation Engineering)_Module1_Part 1 - st .pdfCET 206(Transportation Engineering)_Module1_Part 1 - st .pdf
CET 206(Transportation Engineering)_Module1_Part 1 - st .pdf
 
Transportation Engineering
Transportation EngineeringTransportation Engineering
Transportation Engineering
 
Communication Skills Highways
Communication Skills HighwaysCommunication Skills Highways
Communication Skills Highways
 
Highway Development and Planning Transportation Engineering
Highway Development and Planning Transportation EngineeringHighway Development and Planning Transportation Engineering
Highway Development and Planning Transportation Engineering
 
Transportation Engg.pptx
Transportation Engg.pptxTransportation Engg.pptx
Transportation Engg.pptx
 
TRANSPORTATION ENGINEERING.pptx
TRANSPORTATION ENGINEERING.pptxTRANSPORTATION ENGINEERING.pptx
TRANSPORTATION ENGINEERING.pptx
 
Highway notes (planning, alignment, & geometric design )
Highway notes (planning, alignment, & geometric design )Highway notes (planning, alignment, & geometric design )
Highway notes (planning, alignment, & geometric design )
 
DAVV IET_ TraNSPORTATION [PPT LECTURES ALL 501.pptx
DAVV IET_ TraNSPORTATION [PPT LECTURES ALL 501.pptxDAVV IET_ TraNSPORTATION [PPT LECTURES ALL 501.pptx
DAVV IET_ TraNSPORTATION [PPT LECTURES ALL 501.pptx
 
Pakistan Motorway
Pakistan MotorwayPakistan Motorway
Pakistan Motorway
 
1.introduction to highway engineering
1.introduction to highway engineering1.introduction to highway engineering
1.introduction to highway engineering
 
PORFOLIO.pdf
PORFOLIO.pdfPORFOLIO.pdf
PORFOLIO.pdf
 
Bullet train in india
Bullet train in indiaBullet train in india
Bullet train in india
 
History of roads
History of roadsHistory of roads
History of roads
 
Module 1(highway planning and scope of highway engineering)
Module 1(highway planning and scope of highway engineering)Module 1(highway planning and scope of highway engineering)
Module 1(highway planning and scope of highway engineering)
 

Plus de Lahari Yaddanapudi (8)

Kancheepuram - Urban Heritage and Conservation
Kancheepuram - Urban Heritage and ConservationKancheepuram - Urban Heritage and Conservation
Kancheepuram - Urban Heritage and Conservation
 
Principles of design
Principles of designPrinciples of design
Principles of design
 
Ecological footprint
Ecological footprint Ecological footprint
Ecological footprint
 
Sewage disposal methods- Sanitation and sewer system
Sewage disposal methods- Sanitation and sewer systemSewage disposal methods- Sanitation and sewer system
Sewage disposal methods- Sanitation and sewer system
 
Slum definitions
Slum definitionsSlum definitions
Slum definitions
 
City as an organism
City as an organismCity as an organism
City as an organism
 
Punjab- Amritsar
Punjab- AmritsarPunjab- Amritsar
Punjab- Amritsar
 
Techniques of planning
Techniques of planningTechniques of planning
Techniques of planning
 

Dernier

Top profile Call Girls In Morena [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Morena [ 7014168258 ] Call Me For Genuine Models We...Top profile Call Girls In Morena [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Morena [ 7014168258 ] Call Me For Genuine Models We...
gajnagarg
 
Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...
gajnagarg
 
Competitive Advantage slide deck___.pptx
Competitive Advantage slide deck___.pptxCompetitive Advantage slide deck___.pptx
Competitive Advantage slide deck___.pptx
ScottMeyers35
 

Dernier (20)

Panchayath circular KLC -Panchayath raj act s 169, 218
Panchayath circular KLC -Panchayath raj act s 169, 218Panchayath circular KLC -Panchayath raj act s 169, 218
Panchayath circular KLC -Panchayath raj act s 169, 218
 
Call Girls Koregaon Park - 8250092165 Our call girls are sure to provide you ...
Call Girls Koregaon Park - 8250092165 Our call girls are sure to provide you ...Call Girls Koregaon Park - 8250092165 Our call girls are sure to provide you ...
Call Girls Koregaon Park - 8250092165 Our call girls are sure to provide you ...
 
2024: The FAR, Federal Acquisition Regulations, Part 32
2024: The FAR, Federal Acquisition Regulations, Part 322024: The FAR, Federal Acquisition Regulations, Part 32
2024: The FAR, Federal Acquisition Regulations, Part 32
 
Lorain Road Business District Revitalization Plan Final Presentation
Lorain Road Business District Revitalization Plan Final PresentationLorain Road Business District Revitalization Plan Final Presentation
Lorain Road Business District Revitalization Plan Final Presentation
 
Tuvalu Coastal Adaptation Project (TCAP)
Tuvalu Coastal Adaptation Project (TCAP)Tuvalu Coastal Adaptation Project (TCAP)
Tuvalu Coastal Adaptation Project (TCAP)
 
Top profile Call Girls In Morena [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Morena [ 7014168258 ] Call Me For Genuine Models We...Top profile Call Girls In Morena [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Morena [ 7014168258 ] Call Me For Genuine Models We...
 
74th Amendment of India PPT by Piyush(IC).pptx
74th Amendment of India PPT by Piyush(IC).pptx74th Amendment of India PPT by Piyush(IC).pptx
74th Amendment of India PPT by Piyush(IC).pptx
 
Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...
 
Just Call VIP Call Girls In Bangalore Kr Puram ☎️ 6378878445 Independent Fem...
Just Call VIP Call Girls In  Bangalore Kr Puram ☎️ 6378878445 Independent Fem...Just Call VIP Call Girls In  Bangalore Kr Puram ☎️ 6378878445 Independent Fem...
Just Call VIP Call Girls In Bangalore Kr Puram ☎️ 6378878445 Independent Fem...
 
Delivery in 20 Mins Call Girls Malappuram { 9332606886 } VVIP NISHA Call Girl...
Delivery in 20 Mins Call Girls Malappuram { 9332606886 } VVIP NISHA Call Girl...Delivery in 20 Mins Call Girls Malappuram { 9332606886 } VVIP NISHA Call Girl...
Delivery in 20 Mins Call Girls Malappuram { 9332606886 } VVIP NISHA Call Girl...
 
Kolkata Call Girls Halisahar 💯Call Us 🔝 8005736733 🔝 💃 Top Class Call Girl ...
Kolkata Call Girls Halisahar  💯Call Us 🔝 8005736733 🔝 💃  Top Class Call Girl ...Kolkata Call Girls Halisahar  💯Call Us 🔝 8005736733 🔝 💃  Top Class Call Girl ...
Kolkata Call Girls Halisahar 💯Call Us 🔝 8005736733 🔝 💃 Top Class Call Girl ...
 
AHMR volume 10 number 1 January-April 2024
AHMR volume 10 number 1 January-April 2024AHMR volume 10 number 1 January-April 2024
AHMR volume 10 number 1 January-April 2024
 
Call Girls Basheerbagh ( 8250092165 ) Cheap rates call girls | Get low budget
Call Girls Basheerbagh ( 8250092165 ) Cheap rates call girls | Get low budgetCall Girls Basheerbagh ( 8250092165 ) Cheap rates call girls | Get low budget
Call Girls Basheerbagh ( 8250092165 ) Cheap rates call girls | Get low budget
 
Genuine Call Girls in Salem 9332606886 HOT & SEXY Models beautiful and charm...
Genuine Call Girls in Salem  9332606886 HOT & SEXY Models beautiful and charm...Genuine Call Girls in Salem  9332606886 HOT & SEXY Models beautiful and charm...
Genuine Call Girls in Salem 9332606886 HOT & SEXY Models beautiful and charm...
 
2024: The FAR, Federal Acquisition Regulations, Part 31
2024: The FAR, Federal Acquisition Regulations, Part 312024: The FAR, Federal Acquisition Regulations, Part 31
2024: The FAR, Federal Acquisition Regulations, Part 31
 
Honasa Consumer Limited Impact Report 2024.pdf
Honasa Consumer Limited Impact Report 2024.pdfHonasa Consumer Limited Impact Report 2024.pdf
Honasa Consumer Limited Impact Report 2024.pdf
 
Finance strategies for adaptation. Presentation for CANCC
Finance strategies for adaptation. Presentation for CANCCFinance strategies for adaptation. Presentation for CANCC
Finance strategies for adaptation. Presentation for CANCC
 
Peace-Conflict-and-National-Adaptation-Plan-NAP-Processes-.pdf
Peace-Conflict-and-National-Adaptation-Plan-NAP-Processes-.pdfPeace-Conflict-and-National-Adaptation-Plan-NAP-Processes-.pdf
Peace-Conflict-and-National-Adaptation-Plan-NAP-Processes-.pdf
 
Sustainability by Design: Assessment Tool for Just Energy Transition Plans
Sustainability by Design: Assessment Tool for Just Energy Transition PlansSustainability by Design: Assessment Tool for Just Energy Transition Plans
Sustainability by Design: Assessment Tool for Just Energy Transition Plans
 
Competitive Advantage slide deck___.pptx
Competitive Advantage slide deck___.pptxCompetitive Advantage slide deck___.pptx
Competitive Advantage slide deck___.pptx
 

Effectiveness of Purpose-Specific Elevated Expressways in India: A Case Study of PVNR Expressway, Hyderabad

  • 1. Effectiveness of Purpose-Specific Elevated Expressways in India: A Case Study of PVNR Expressway, Hyderabad Study of PVNR Expressway, Hyderabad Study of PVNR Expressway, Hyderabad 1 By Lahari Yaddanapudi 141109047, II year, Department of Planning and Architecture Maulana Azad National Institute of Technology, Bhopal
  • 2. Aim Assess the effectiveness of purpose-specific expressways in India by taking a case study of the P V Narsimha Rao expressway in Hyderabad 2
  • 3. Objectives • Understanding the concept of expressways • Elevated expressways or ground level expressways- practicality in the Indian context • Understanding purpose specific expressways- where origin and destination were selected to serve some purpose • Study of the PVNR expressway- • History • Purpose • Functioning- infrastructure, monitoring and control, safety • Accidents and denomination of accident prone areas • In this way, evaluating the PVNR expressway and the importance of purpose specific elevated expressways in India 3
  • 4. Introduction • Elevated expressway- major road that is raised up above the ground level with complete access control • Expressway- • Highest class of roads in the Indian road network • Six or eight laned • Indian context: most of the expressways have the term ‘expressway’ in their name but do not confine to the norms that make it an expressway • P V Narsimha Rao Elevated Expressway in Hyderabad- • Longest flyover of India 4
  • 5. • Starting at the Southern part of the core city, Mehdipatnam, it passes through Rethibowli, Laxmi Nagar, Attapur, Hyderguda, Upperpally, Rajendra Nagar and finally joins the National Highway-7 at Aramghar junction • Total length: 11.6kms • Inaugurated in October 2009 • Has six midway entry and exit ramps • Approximately 2,500 vehicles take the elevated expressway to the airport and Bangalore everyday • No-toll expressway as of now but proposals to introduce toll tax are being discussed 5 Fig.1: PVNR Elevated Expressway Stretch Source: Maps of India
  • 6. Background • The Begumpet airport, which was the only international airport • Due to the rapid growth of the city of Hyderabad, the Begumpet airport had become a part of the integral part of the city • This restricted the growth and expansion of the airport. So, an airport at the present city outskirts was proposed at Shamshabad • Shamshabad being an outskirt region, was not that accessible in terms of the commuting time it took • Common public had to travel for about 1 to 2 hours from any part of the city to reach the airport • An elevated expressway was proposed which will eventually lead to the Rajiv Gandhi International Airport at Shamshabad 6
  • 7. • P V Narasimha Rao who was from Andhra Pradesh became the Prime Minister of India in 1991 • He heralded economic reforms in India by allowing private partnership in the control and operation of airports in the country • Keeping this enormous contribution of our former Prime Minister in mind, the expressway proposed for the faster access to the airport was named after him • The concept of this expressway was conceived in 2003-04 during the tenure of the TDP • Inaugurated during the tenure of the Congress Party on 19 October 2009 Begumpet Airport Shamshabad Airport Fig.2: Begumpet and Shamshabad Airports Source: IIT Hyderabad website (www.iith.ac.in) 7
  • 8. Construction • Initiated in 2004, the construction of this expressway was completed by 2009 and was ready for operation • Usually during the construction of elevated structures, accidents to workers are a common sight • But one important and major noticeable aspect of the entire process of construction was that no casualties or accidents to the construction workers occurred during the construction of this expressway 8
  • 9. Structure • The project consisted of three major components: • Elevated Expressway: four lane divided carriageway stretching from Mehdipatnam and passing through Rethibowli, Laxmi Nagar, Attapur, Hyderguda, Upperpally, Rajendra Nagar and finally joining the National highway- 7 at Aramgarh Junction • Trumpet interchange: four lane divided carriageway built to facilitate free flow of traffic towards airport from Hyderabad and Bangalore side with a length of 3.9 km and width of 17.2 mts. • Underpass at Aramgarh: length of 62 mts and width of 19.4 mts with a vertical clearance of 5.5 mts was constructed to facilitate uninterrupted flow of traffic at Aramgarh Junction on NH-7 with approach ramps on either side i.e., towards Mehdipatnam and Chandrayangutta 9
  • 10. • The two lane carriageway (one direction of flow) is of a width of 7.5 mts • Narrows down to one and a half lane with a width of 6 mts at Laxminagar, Upparpally and Shivrampally due to steep turnings • Unique feature of the structure of this expressway is that it has two or three areas dedicated for parking on the expressway for the vehicles that break down during their journey on this elevated platform • Tow their vehicles to these places or call for help on the provided helplines which promise to send their towing vehicle within 20 minutes of the emergency call 10
  • 11. Infrastructure • P V Narsimha Rao expressway was built by the Hyderabad Metropolitan Development Authority (HMDA) in association with Simplex Somdatta, the project contractors • The project, which costed the government a total amount of Rs. 439 crore, included the construction of a total of 328 foundations, 327 spans, 291 pre-cast slabs, 36 cast-in-site slabs and 328 piers • Carriageway is divided and thus chances of head-on collisions with vehicles moving in opposite directions are avoided 11
  • 12. Control and monitoring • Maximum speed limit on the PVNR Expressway is 60 kmph for light motor vehicles • At sharp turns (i.e., at Laxminagar, Upparpally and Shivrampally) where the carriageway narrows down from 7.5 mts to 6 mts, the maximum speed has been restricted to 40 kmph • Cycles, two wheelers, three wheelers, three and four wheeled seven seaters, pushcarts and bullock carts are not allowed on to the expressway • All goods vehicles, be it light, medium or heavy vehicles are prohibited to use this flyover 12
  • 13. • Overtaking at sharp turnings has been strictly prohibited • Parking has been strictly prohibited on the highway • However, special areas have been allocated on the expressway for vehicles that break down or malfunction during the course of travel • This parking space and towing facility come with a minimal fee • Expressway is monitored by the traffic police of Hyderabad • P V Narsimha Rao expressway is a toll free expressway 13
  • 14. • Expressway comes under the maintenance of the Hyderabad Metropolitan Development Authority as well as the Greater Hyderabad Municipal Corporation • Special attention to highways and thus, even this expressway is given to ensure that the road is in perfect condition- to accommodate free flow of vehicles and also allow the smooth transit of vehicles at the high speeds they travel at 14
  • 15. Time efficiency • Major reason for the construction of this expressway was to minimise the travel time of the people going to the new International Airport at Shamshabad and to ease the congestion on the roads of the integral parts of the city that lead to the airport • Purpose of construction of this prestigious structure was served as it has reduced the travel time to quite an extent • Earlier, for people to go to the airport, they had to pass through the internal old parts of the city that had narrow roads or roads that could not accommodate the volume of traffic, it used to take 1 to 1.5 hours • The most efficient route that would save distance as well as time when built on an elevated platform was identified and built 15
  • 16. • Given that the entry point to the expressway is at Mehdipatnam, a core area in the Southern part of the city and provisions of few other entry ramps in between, we can assume the average travel time from any part of the city to the approach point to be 10 minutes • Also, the length of the expressway is 11.6 kms, approx. 12 kms and a speed limit of 60 kmph with 40 kmph at narrow and steep turnings, the average speed can be taken as 50 kmph. At this speed, the stretch of 12 kms can be covered in 12*60/50 = 14.4 minutes i.e., approximately 14 minutes • Then, from the Aramgarh Junction to the Shamshabad airport on NH-7, assuming it to take 5 minutes • The entire travel time from one’s origin to destination that used to take one to one and a half hour has been brought down to 10+14+5= 29 which is again approximately 30 minutes. 16
  • 17. Accident reports • First accident- November, 2009 at around 7pm. The driver of a van carrying three postal department officials suddenly felt giddy and rammed into the third lamppost. The four of them suffered injuries in the accident but everyone were declared out of danger in a short time • January, 2013 where “an i10 car crashed into an Indica car which was about to get on to the Rajendranagar-Retibowli main road from a down ramp of the expressway at Upparapally, and did a somersault before landing on the side of an Innova going towards Retibowli.” This accident took place near pillar number 194 of the expressway at Upparapally where the traffic coming from Shamshabad joins Rajendranagar- Retibowli road via a ramp. The vehicles were heavily damaged but luckily, no one suffered any major injuries 17
  • 18. • First fatal accident- Septemper, 2014 in which two people lost their lives due to reckless driving on the expressway. Their car hit a road divider and both the victims are said to have died on the spot • Recommendations given by the CRRI to the HMDA to reduce accidents: • Maximum speed on the expressway is only 60 kmph, this should be mandated • As there is no scope for building speed breakers on the expressway use ‘Rumble Strips’ • Signage aren’t enough to control speed, use speed guns and levy hefty fines for over speeding • Remove all the central medians 18
  • 19. • As another measure to reduce accidents at the Laxminagar crossroads, near pillar number 68, the zonal commission was directed by the Greater Hyderabad Municipal Corporation to remove illegal temporary huts near the said location • Also, it was suggested to put up proposals to widen the road from Laxminagar to Gudimalkapur • So, the accident prone areas or structures thus identified are: • (a) The entry of the expressway • (b) Down ramp of the expressway at Upparapally • (c) Near pillar number 194 • (d) Road dividers • (e) Laxminagar Crossroads, near pillar number 68 19
  • 20. Conclusion • Expressways though not common in India, are actually a need in the Indian context due the the fast developing metropolitan cities • In cases where cities are old, the demolition of structures and acquisition of land is not feasible. In such situations, the optimum solution is to construct elevated expressways • Elevated expressways can be expressways linking two specific places for a purpose. This makes them purpose specific • P V Narsimha Rao expressway, the purpose was to provide quick and efficient access to the airport which had become difficult as the route was through the core parts of the city • The time efficiency has increased by double or more times it was before • Elevated expressway not only eases congestion on the road below it but also if built for for a specific trip from specified origin to destination- the most efficient solution to routes that require such a service 20
  • 21. References • 1) “Speed Limit on elevated expressway 60 kmph" The Hindu (19-10-2009) • 2) “Longest Elevated Expressway Inaugurated in Hyderabad | India Trends” Indiatrends.info (20-10-2009) • 3) “Hyderabad gets India’s longest flyover” ndtv.com (16-07-2010) • 4) “PVNR Elevated Expressway” mapsofindia.com • 5) Begumpet and Shamshabad Airports- “IIT-H location map” www.iith.ac.in • 6) “PVNR Expressway” Hyderabad Metropolitan Development Authority website • 7) “Severe resource crunch effects prestigious PVNR Elevated Expressway” The Hindu (26-04-2009) 21 • 8) “First Accident on PVNR Expressway” Times of India (07-11-2009) • 9) “Freak accident on PVNR expressway” Times of India (03-01-2013) • 10) “Five killed in road accidents” The Hindu (30-09-2014) • 11) “Finally a solution to PVNR accidents” The Hans India (16-09-2013) • 12) “GHMC to Demolish Illegal Huts near PVNR Expressway” The New Indian Express ( 09-02-2014)