SlideShare une entreprise Scribd logo
1  sur  39
VOCATIONAL TRAINING PRESENTATION
2014 - 15
NAME : LAKHAMAN B. VADHER
DEPTT : ELECTRICAL
COLLEGE : GOVERNMENT ENGNEERING
COLLEGE BHARUCH
Introduction
• In India 70% of total power is generated by the Thermal
Power Stations.
• Essar power is one leading company in electrical power
generation
• Essar Power Salaya
• Capacity:- 1200 MW (2*600 MW)
• It is based on coal fired power plant
• Project site area :- 330 Ha
• Narmada water used as condenser cooling water Boiler
water
• Power evacuation at 400 KV to state utility
Major Learning
• Boiler Unit
• TG (Turbine Generator) Unit
• Transformer Yard
• Switchyard(HV,MV,LV)
• Coal Handling System
• Ash Handling System
• ESP (Electrostatic Precipitator)
• Cooling Tower
• Different type of Motor and Pump
•
Basic Layout of Thermal Power
Plant
Boiler
• Boiler is steam generator. It convert water into high
pressure and high temperature steam
• In Essar power plant Salaya Subcritical type of boiler is
used.
• A subcritical steam generator is a type of boiler that
operates at subcritical pressure
• Main steam flow:- 2060 TPH
• Main steam outlet pres.:- 17.50 Mpa
• Main steam outlet temp.:- 541° C
• Feed water pres.:- 19.492 Mpa
• Feed water temp. :- 281.7 ° C
• Reheat steam flow :- 1725.9 TPH
6
Schematic Diagram of subcritical Boiler
BOILER SIDEVIEW
7
Steam Turbine
• A steam turbine is a device that extracts thermal energy
from pressurized steam and uses it to do mechanical
work on a rotating output shaft
• And main output shaft is coupled with electrical generator
• Turbine divided into 3 Stage
I. HP (High Pressure Turbine)
II. IP (Intermit Pressure Turbine)
III. LP (Low Pressure Turbine)
• Rated Output :- 600 MW
• Rated Speed :- 3000 RPM
• Steam pressure :- 16.7 Mpa
• Steam temperature :- 538 ° C
• Direction of rotation :- Clockwise
Steam Turbine
Electrical Generator
• Electric generator is a device that converts mechanical
energy to electrical energy.
• Main part of generator are stator and rotor.
• Output of electrical power taken from stator terminal.
• D.C. supply to the rotor winding through brush and slip
ring.
• In Essar power water hydrogen cool synchronous
generator is used
Generator
Generator Specification
Parameter Value
MW Rating 600MW
Rated Voltage 20KV
Rated Stator current 20377 A
Rated Speed 3000 RPM
Rated Frequency 50 Hz
Generator Cooling
• Cooling needed in large size generator
 Two Type of Cooling system
I.Water cooling
II.Hydrogen cooling
• Water is used for stator cooling.
• Hydrogen are used for rotor cooling as well as stator
cooling
STATOR
COOLING
WATER TANK
STATOR
COOLING
WATER TANK
MM
MM
COOLER
A
COOLER
A
COOLER
B
COOLER
B
STATOR COOLING
WATER PUMP A
STATOR COOLING
WATER PUMP B
GENERATORGENERATOR
STRAINER B
STRAINER A
Stator water cooling
cycle
Transformer Yard
 Main Equipment used Trafoyard
I. GCB (Generator Circuit Breaker)
II. ST (Station Transformer)
III. UT (Unit Transformer)
IV. GT (Generator Transformer)
V. NGR (Neutral Grounding Resistor)
Transformer Yard SLD
GCB
• Protection of the Generator against system-fed
shortcircuit currents
• The GCB is an effective protection device for the
transformer and the generator
I. Starting and maintenance stages
II. Synchronization and normal conditions
III. Abnormal conditions including
• Overvoltages, un-balanced load
•
Short circuit
–
Step up transformer side
–
Generator side
•
Out of Phase Requirements
Station Transformer
• ST is used supply station common load such as Coal
handling,DM plant, etc.
• Transformer used in salaya power plant is three winding
transformer
• Specification
Parameter Value
Rated MVA 70 MVA
Voltage 20/11/33KV
Frequency 50Hz
Number Phase 3
Vector Group Dyn11yn11
Unit Transformer
• Unit Transformer supply separate unit load such as
Boiler auxiliary,Cooling tower and Turbine auxiliary etc.
• Specification
Parameter Value
Rated MVA 45MVA
Rated Voltage 20/11.5KV
No. Of Phase 3
Vector Group Dy11
GT(Generator Transformer)
• As an essential element of all nuclear, thermal or
hydraulic power stations.
• GT are step-up transformer with delta connected LV
side and star connected HV side
• In Essar power salaya OLTC is used and GT consist of
three single phase transformer unit.
 GT Specification
Parameter Value
Rated MVA 250MVA
Rated Voltage at no load 21/420KV
Vector Group YNd1
Type Of cooling ONAN/ONAF/OFAF
NGR(Neutral Grounding
Resistor)
• The suitable Neutral Grounding Resistance (NGR)
should be installed between neutral point (star point) and
the ground to restrict the earth fault current to 50 Amps
• it is used to limit the current flowing through ground.
• it measures the resistance between the neutral and the
GND.
• There two consideration to Select NGR
1) Plant capacity
2) Current carrieng capacity
Bus Duct
• Different types of bus-ducts are provided as per
application/ current and voltage rating.
I. IPBD (Isolated phase bus duct)
II. SPBD (segregated phase bus duct)
III. NSPBD (non segregated phase bus duct)
 IPBD: In 20 kV,22000A Generator to Generator
transformer main run
 SPBD:-11kV, 1500 A between Unit transformer to Unit
switchgear
 NSPBD:-0.433kv, 3333.43A between service transformer
to PMCC and MCC
IPBD (Isolated phase bus duct)
SPBD (segregated phase bus
duct)
NSPBD (non segregated phase bus duct)
Switch Yard
• Three type of switch yard in Essar salaya power it’s
divided in based on voltage level
I. HV (High Voltage Switch yard )
II. MV (Medium voltage)
III. LV (Low Voltage)
HV Switch yard
• Electric power is generated in Generation Station. The
voltage at which is power is generated in generation
station lies between 11kv to 25kv.
• SwitchYard Definition It is switching station with incoming
and outgoing feeders but without the transformer. It is a
type of substation but incoming feeders and outgoing
feeders are of same voltage level. Some times, the out
door area of a substation where the circuit breakers are
located are also called switchyard of the substation A
switchyard connects and disconnects lines on the grid for
various reasons. The operations and equipment are
essentially all at the same voltage level.
Equipment in switch yard
 Main Equipment used in HV switch yard
 CVT(capacitive voltage transformer)
 CT(current transformer)
 Isolator
 Circuit Breaker
 Bus bar
 Wave trip
 EMVT( electromagnetic voltage transformer)
 LA (lighting arrester)
 Earth switch
CVT(capacitive voltage transformer)
• Capacitor Voltage
Transformers convert
transmission
class voltages to
standardized low and
easily
measurable values,
which are used for
metering,
protection and control of
the high voltage
system.
CT (current transformer)
• A current transformer
(CT) is used for
measurement of
alternating electric
currents.
• A current transformer
produces a reduced
current accurately
proportional to the current
in the circuit, which can be
conveniently connected to
measuring and recording
instruments.
Isolator
• Isolator is an off load device
which is operated by remote
control or local. Isolators
provided in switchyard are
central break type.
 Types of Electrical
Isolators
1) Double Break Isolator
2) Single Break Isolator
3) Pantograph type Isolator
Circuit Breaker
• A circuit breaker is an
automatically operated
electrical switch designed to
protect an electrical circuit
from damage caused by
overload or short circuit
• Its basic function is to detect
a fault condition and
interrupt current flow
Busbar
• A busbar in electrical power distribution refers to thick
strips of copper or aluminium that conduct electricity
within a switchboard, distribution board, substation, or
other electrical apparatus
• The size of the busbar is important in determining the
maximum amount of current that can be safely carried.
Wave trap
• Wave traps are used
for communication
purpose during fault
conditions. Wave
traps offer high
impedance path for
high frequency
signals & low
impedance path for
power frequency
current.
EMVT (electromagnetic voltage
transformer)
EMVT- Electromagnetic voltage transformer . As the name
says its works in the principle of electromagnetic induction
principle.Its just a stepdown transformer,stepdown voltage i.e
higher voltage to meserable voltage by instruments
connected to measurement and protection.
LA (lighting arrester)
• A lightning arrester is a device used on electrical
power systems and telecommunication systems to
protect the insulation and conductors of the system from
the damaging effects of lightning
• Earth switches used in
substation . in that when
isolator
OPEN condition earth
switch is CLOSED. here
any induction
that passes through earth
switch to ground. when
isolator in
CLOSED condition Earth
switch should be Open
Earth Switch
CONCLUSION
The Overview of this project is about the various techniques
involved in 400 KV Switchyard Of Essar Power Plant. By
this we get To Know About the operation of different
equipments in Switch Yard and its maintenance.
THANK YOU

Contenu connexe

Tendances

Hydroelectric Power Plant (and Pumped Storage Power Plant)
Hydroelectric Power Plant (and Pumped Storage Power Plant)Hydroelectric Power Plant (and Pumped Storage Power Plant)
Hydroelectric Power Plant (and Pumped Storage Power Plant)Ryan Triadhitama
 
Transformer Parts and functions
Transformer Parts and functionsTransformer Parts and functions
Transformer Parts and functionsSourabh sharma
 
Substation Training presentation
Substation Training presentationSubstation Training presentation
Substation Training presentationKamal Mittal
 
2. station transformer 100 mva 230kv-datasheet revb
2. station transformer 100 mva 230kv-datasheet revb2. station transformer 100 mva 230kv-datasheet revb
2. station transformer 100 mva 230kv-datasheet revbVan Phuong Pham
 
Power factor presentation
Power factor presentationPower factor presentation
Power factor presentationAzhar Abbas
 
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMSSWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMSPartha Parida
 
Simple Capacitive Voltage Transformer (CVT) Testing for Switchyard Equipment
Simple Capacitive Voltage Transformer (CVT) Testing for Switchyard EquipmentSimple Capacitive Voltage Transformer (CVT) Testing for Switchyard Equipment
Simple Capacitive Voltage Transformer (CVT) Testing for Switchyard EquipmentSARAVANAN A
 
Introduction to power transformers
Introduction to power transformersIntroduction to power transformers
Introduction to power transformersLeonardo ENERGY
 
THERMAL POWER PLANT (COAL TO POWER)
THERMAL POWER PLANT (COAL TO POWER)THERMAL POWER PLANT (COAL TO POWER)
THERMAL POWER PLANT (COAL TO POWER)Baibhav Saha
 
Presentation on Power transformer
Presentation on Power transformerPresentation on Power transformer
Presentation on Power transformerSudarshan Pandey
 
switchgear and protection by vala kamlesh
switchgear and protection by vala kamleshswitchgear and protection by vala kamlesh
switchgear and protection by vala kamleshKamlesh Vala
 

Tendances (20)

Substation overview
Substation overviewSubstation overview
Substation overview
 
Hydroelectric Power Plant (and Pumped Storage Power Plant)
Hydroelectric Power Plant (and Pumped Storage Power Plant)Hydroelectric Power Plant (and Pumped Storage Power Plant)
Hydroelectric Power Plant (and Pumped Storage Power Plant)
 
Transformer Parts and functions
Transformer Parts and functionsTransformer Parts and functions
Transformer Parts and functions
 
Substation Training presentation
Substation Training presentationSubstation Training presentation
Substation Training presentation
 
2. station transformer 100 mva 230kv-datasheet revb
2. station transformer 100 mva 230kv-datasheet revb2. station transformer 100 mva 230kv-datasheet revb
2. station transformer 100 mva 230kv-datasheet revb
 
Power factor presentation
Power factor presentationPower factor presentation
Power factor presentation
 
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMSSWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
 
Dvr
DvrDvr
Dvr
 
Switchgear presentation
Switchgear presentationSwitchgear presentation
Switchgear presentation
 
Motor starter Design
Motor starter DesignMotor starter Design
Motor starter Design
 
Simple Capacitive Voltage Transformer (CVT) Testing for Switchyard Equipment
Simple Capacitive Voltage Transformer (CVT) Testing for Switchyard EquipmentSimple Capacitive Voltage Transformer (CVT) Testing for Switchyard Equipment
Simple Capacitive Voltage Transformer (CVT) Testing for Switchyard Equipment
 
Unit 1-2-a
Unit 1-2-aUnit 1-2-a
Unit 1-2-a
 
1.substation layouts
1.substation  layouts1.substation  layouts
1.substation layouts
 
Introduction to power transformers
Introduction to power transformersIntroduction to power transformers
Introduction to power transformers
 
Load list calculation
Load list calculationLoad list calculation
Load list calculation
 
THERMAL POWER PLANT (COAL TO POWER)
THERMAL POWER PLANT (COAL TO POWER)THERMAL POWER PLANT (COAL TO POWER)
THERMAL POWER PLANT (COAL TO POWER)
 
Turbine safety protection
Turbine safety protectionTurbine safety protection
Turbine safety protection
 
Presentation on Power transformer
Presentation on Power transformerPresentation on Power transformer
Presentation on Power transformer
 
switchgear and protection by vala kamlesh
switchgear and protection by vala kamleshswitchgear and protection by vala kamlesh
switchgear and protection by vala kamlesh
 
C&i systems
C&i systemsC&i systems
C&i systems
 

En vedette

super critical power plant
super critical power plantsuper critical power plant
super critical power plantsridurga88
 
13.1.2 Line And Current
13.1.2 Line And Current13.1.2 Line And Current
13.1.2 Line And CurrentTalia Carbis
 
Report on power line career communication by ramanand sagar
Report on power line career communication by ramanand sagarReport on power line career communication by ramanand sagar
Report on power line career communication by ramanand sagarRamanand Sagar
 
Better efficiency of eletrostatic precipitator
Better efficiency of eletrostatic precipitatorBetter efficiency of eletrostatic precipitator
Better efficiency of eletrostatic precipitatorIRS srl
 
Steam Boilers, Hot Water Boilers, Thermic Fluid Heater, Waste Heat recovery S...
Steam Boilers, Hot Water Boilers, Thermic Fluid Heater, Waste Heat recovery S...Steam Boilers, Hot Water Boilers, Thermic Fluid Heater, Waste Heat recovery S...
Steam Boilers, Hot Water Boilers, Thermic Fluid Heater, Waste Heat recovery S...Thermodyne Engineering systems
 
Trainning And Development
Trainning And DevelopmentTrainning And Development
Trainning And Developmentjim
 
Training at 132 kv substation
Training at 132 kv substation Training at 132 kv substation
Training at 132 kv substation Tejveer Choudhary
 
Measurement of high_voltage_and_high_currentunit_iv_full_version
Measurement of high_voltage_and_high_currentunit_iv_full_versionMeasurement of high_voltage_and_high_currentunit_iv_full_version
Measurement of high_voltage_and_high_currentunit_iv_full_versionAman Ansari
 
Supercritical boiler ntpc sipat
Supercritical boiler ntpc sipatSupercritical boiler ntpc sipat
Supercritical boiler ntpc sipatpratikguptateddy
 

En vedette (20)

Transformers
TransformersTransformers
Transformers
 
super critical power plant
super critical power plantsuper critical power plant
super critical power plant
 
Super critical boiler
Super critical boilerSuper critical boiler
Super critical boiler
 
Classic Resume
Classic ResumeClassic Resume
Classic Resume
 
13.1.2 Line And Current
13.1.2 Line And Current13.1.2 Line And Current
13.1.2 Line And Current
 
JBPM5 Community Trainning Baby Steps Examples
JBPM5 Community Trainning Baby Steps ExamplesJBPM5 Community Trainning Baby Steps Examples
JBPM5 Community Trainning Baby Steps Examples
 
cheema boiler
cheema boilercheema boiler
cheema boiler
 
Cheema
CheemaCheema
Cheema
 
220 kv G.S.S (report)
220 kv G.S.S (report)220 kv G.S.S (report)
220 kv G.S.S (report)
 
Sde tm6
Sde tm6Sde tm6
Sde tm6
 
132 kv gss
132 kv gss132 kv gss
132 kv gss
 
Report on power line career communication by ramanand sagar
Report on power line career communication by ramanand sagarReport on power line career communication by ramanand sagar
Report on power line career communication by ramanand sagar
 
Sml isuzu limited
Sml isuzu limitedSml isuzu limited
Sml isuzu limited
 
Better efficiency of eletrostatic precipitator
Better efficiency of eletrostatic precipitatorBetter efficiency of eletrostatic precipitator
Better efficiency of eletrostatic precipitator
 
Steam Boilers, Hot Water Boilers, Thermic Fluid Heater, Waste Heat recovery S...
Steam Boilers, Hot Water Boilers, Thermic Fluid Heater, Waste Heat recovery S...Steam Boilers, Hot Water Boilers, Thermic Fluid Heater, Waste Heat recovery S...
Steam Boilers, Hot Water Boilers, Thermic Fluid Heater, Waste Heat recovery S...
 
Trainning And Development
Trainning And DevelopmentTrainning And Development
Trainning And Development
 
Training at 132 kv substation
Training at 132 kv substation Training at 132 kv substation
Training at 132 kv substation
 
Measurement of high_voltage_and_high_currentunit_iv_full_version
Measurement of high_voltage_and_high_currentunit_iv_full_versionMeasurement of high_voltage_and_high_currentunit_iv_full_version
Measurement of high_voltage_and_high_currentunit_iv_full_version
 
Training presentation
Training presentationTraining presentation
Training presentation
 
Supercritical boiler ntpc sipat
Supercritical boiler ntpc sipatSupercritical boiler ntpc sipat
Supercritical boiler ntpc sipat
 

Similaire à Vocational trainning presentation at ESSAR Power Salaya (Electrical Engineering)

400 kv Heerapura gss ppt by ishan pdf
400 kv Heerapura gss ppt by ishan pdf 400 kv Heerapura gss ppt by ishan pdf
400 kv Heerapura gss ppt by ishan pdf Ishan Khandelwal
 
industrial-training-at-howrah-220-kv-substation.pptx
industrial-training-at-howrah-220-kv-substation.pptxindustrial-training-at-howrah-220-kv-substation.pptx
industrial-training-at-howrah-220-kv-substation.pptxShubhoDas5
 
Switchgear, protection and measurement
Switchgear, protection and measurementSwitchgear, protection and measurement
Switchgear, protection and measurementBishal Rimal
 
BASIC ELECTRO MECHANICAL ARRANGEMENTS.pptx
BASIC ELECTRO MECHANICAL ARRANGEMENTS.pptxBASIC ELECTRO MECHANICAL ARRANGEMENTS.pptx
BASIC ELECTRO MECHANICAL ARRANGEMENTS.pptxVenkataLokeshMamidis
 
A PPT ON 220 KV GSS HINDAUN CITY
A PPT ON 220 KV GSS HINDAUN CITYA PPT ON 220 KV GSS HINDAUN CITY
A PPT ON 220 KV GSS HINDAUN CITYRohitashav Goyal
 
220kv gss pindwara(sirohi)
220kv gss pindwara(sirohi)220kv gss pindwara(sirohi)
220kv gss pindwara(sirohi)Pankaj Rawal
 
220kv sub station kishangarh bas, alwar
220kv sub station kishangarh bas, alwar220kv sub station kishangarh bas, alwar
220kv sub station kishangarh bas, alwarDevendra khairiya
 
Vocational training
Vocational trainingVocational training
Vocational trainingSuraj prasad
 
fdocuments.in_presentation-on-substation-220-kv.pptx
fdocuments.in_presentation-on-substation-220-kv.pptxfdocuments.in_presentation-on-substation-220-kv.pptx
fdocuments.in_presentation-on-substation-220-kv.pptxAkshaiSai2
 
industrialsummertrainingon220kvsubstationppt-170413134021.pdf
industrialsummertrainingon220kvsubstationppt-170413134021.pdfindustrialsummertrainingon220kvsubstationppt-170413134021.pdf
industrialsummertrainingon220kvsubstationppt-170413134021.pdfDevesh54
 
Industrial summer training on 220 kv substation ppt
Industrial summer training on 220 kv substation pptIndustrial summer training on 220 kv substation ppt
Industrial summer training on 220 kv substation pptAshutosh Srivastava
 
220 kV GSS Mansarovar Jaipur (RVPNL) Training PPT SM54
220 kV GSS Mansarovar Jaipur (RVPNL) Training PPT SM54220 kV GSS Mansarovar Jaipur (RVPNL) Training PPT SM54
220 kV GSS Mansarovar Jaipur (RVPNL) Training PPT SM54Subhash Mahla
 
Modern electric trends in electric drives
Modern electric trends in electric drivesModern electric trends in electric drives
Modern electric trends in electric drivesSurinder Kumar
 
220 kv gss sitapua ppt sk95
220 kv gss sitapua ppt sk95220 kv gss sitapua ppt sk95
220 kv gss sitapua ppt sk95Sumit Kumar
 
MINI INVERTER PROJECT.pptx
MINI INVERTER PROJECT.pptxMINI INVERTER PROJECT.pptx
MINI INVERTER PROJECT.pptxshamlaK
 

Similaire à Vocational trainning presentation at ESSAR Power Salaya (Electrical Engineering) (20)

400 kv Heerapura gss ppt by ishan pdf
400 kv Heerapura gss ppt by ishan pdf 400 kv Heerapura gss ppt by ishan pdf
400 kv Heerapura gss ppt by ishan pdf
 
industrial-training-at-howrah-220-kv-substation.pptx
industrial-training-at-howrah-220-kv-substation.pptxindustrial-training-at-howrah-220-kv-substation.pptx
industrial-training-at-howrah-220-kv-substation.pptx
 
Switchgear, protection and measurement
Switchgear, protection and measurementSwitchgear, protection and measurement
Switchgear, protection and measurement
 
BASIC ELECTRO MECHANICAL ARRANGEMENTS.pptx
BASIC ELECTRO MECHANICAL ARRANGEMENTS.pptxBASIC ELECTRO MECHANICAL ARRANGEMENTS.pptx
BASIC ELECTRO MECHANICAL ARRANGEMENTS.pptx
 
various types of transformers.
various types of transformers.various types of transformers.
various types of transformers.
 
A PPT ON 220 KV GSS HINDAUN CITY
A PPT ON 220 KV GSS HINDAUN CITYA PPT ON 220 KV GSS HINDAUN CITY
A PPT ON 220 KV GSS HINDAUN CITY
 
220kv gss pindwara(sirohi)
220kv gss pindwara(sirohi)220kv gss pindwara(sirohi)
220kv gss pindwara(sirohi)
 
220kv sub station kishangarh bas, alwar
220kv sub station kishangarh bas, alwar220kv sub station kishangarh bas, alwar
220kv sub station kishangarh bas, alwar
 
132 KV GSS CHAMBAL JAIPUR
132 KV GSS CHAMBAL JAIPUR132 KV GSS CHAMBAL JAIPUR
132 KV GSS CHAMBAL JAIPUR
 
Vocational training
Vocational trainingVocational training
Vocational training
 
fdocuments.in_presentation-on-substation-220-kv.pptx
fdocuments.in_presentation-on-substation-220-kv.pptxfdocuments.in_presentation-on-substation-220-kv.pptx
fdocuments.in_presentation-on-substation-220-kv.pptx
 
industrialsummertrainingon220kvsubstationppt-170413134021.pdf
industrialsummertrainingon220kvsubstationppt-170413134021.pdfindustrialsummertrainingon220kvsubstationppt-170413134021.pdf
industrialsummertrainingon220kvsubstationppt-170413134021.pdf
 
Industrial summer training on 220 kv substation ppt
Industrial summer training on 220 kv substation pptIndustrial summer training on 220 kv substation ppt
Industrial summer training on 220 kv substation ppt
 
220 kV GSS Mansarovar Jaipur (RVPNL) Training PPT SM54
220 kV GSS Mansarovar Jaipur (RVPNL) Training PPT SM54220 kV GSS Mansarovar Jaipur (RVPNL) Training PPT SM54
220 kV GSS Mansarovar Jaipur (RVPNL) Training PPT SM54
 
ntpc ppt
ntpc pptntpc ppt
ntpc ppt
 
Modern electric trends in electric drives
Modern electric trends in electric drivesModern electric trends in electric drives
Modern electric trends in electric drives
 
Presentation1.pptx
Presentation1.pptxPresentation1.pptx
Presentation1.pptx
 
finalseminar.docx
finalseminar.docxfinalseminar.docx
finalseminar.docx
 
220 kv gss sitapua ppt sk95
220 kv gss sitapua ppt sk95220 kv gss sitapua ppt sk95
220 kv gss sitapua ppt sk95
 
MINI INVERTER PROJECT.pptx
MINI INVERTER PROJECT.pptxMINI INVERTER PROJECT.pptx
MINI INVERTER PROJECT.pptx
 

Dernier

"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"mphochane1998
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdfKamal Acharya
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdfKamal Acharya
 
Computer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to ComputersComputer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to ComputersMairaAshraf6
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Call Girls Mumbai
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdfKamal Acharya
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTbhaskargani46
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesMayuraD1
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiessarkmank1
 
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best ServiceTamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Servicemeghakumariji156
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARKOUSTAV SARKAR
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...Amil baba
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdfKamal Acharya
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayEpec Engineered Technologies
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Arindam Chakraborty, Ph.D., P.E. (CA, TX)
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityMorshed Ahmed Rahath
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdfAldoGarca30
 

Dernier (20)

"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdf
 
Computer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to ComputersComputer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to Computers
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and properties
 
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best ServiceTamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
 

Vocational trainning presentation at ESSAR Power Salaya (Electrical Engineering)

  • 1. VOCATIONAL TRAINING PRESENTATION 2014 - 15 NAME : LAKHAMAN B. VADHER DEPTT : ELECTRICAL COLLEGE : GOVERNMENT ENGNEERING COLLEGE BHARUCH
  • 2. Introduction • In India 70% of total power is generated by the Thermal Power Stations. • Essar power is one leading company in electrical power generation • Essar Power Salaya • Capacity:- 1200 MW (2*600 MW) • It is based on coal fired power plant • Project site area :- 330 Ha • Narmada water used as condenser cooling water Boiler water • Power evacuation at 400 KV to state utility
  • 3. Major Learning • Boiler Unit • TG (Turbine Generator) Unit • Transformer Yard • Switchyard(HV,MV,LV) • Coal Handling System • Ash Handling System • ESP (Electrostatic Precipitator) • Cooling Tower • Different type of Motor and Pump •
  • 4. Basic Layout of Thermal Power Plant
  • 5. Boiler • Boiler is steam generator. It convert water into high pressure and high temperature steam • In Essar power plant Salaya Subcritical type of boiler is used. • A subcritical steam generator is a type of boiler that operates at subcritical pressure • Main steam flow:- 2060 TPH • Main steam outlet pres.:- 17.50 Mpa • Main steam outlet temp.:- 541° C • Feed water pres.:- 19.492 Mpa • Feed water temp. :- 281.7 ° C • Reheat steam flow :- 1725.9 TPH
  • 6. 6 Schematic Diagram of subcritical Boiler
  • 8. Steam Turbine • A steam turbine is a device that extracts thermal energy from pressurized steam and uses it to do mechanical work on a rotating output shaft • And main output shaft is coupled with electrical generator • Turbine divided into 3 Stage I. HP (High Pressure Turbine) II. IP (Intermit Pressure Turbine) III. LP (Low Pressure Turbine) • Rated Output :- 600 MW • Rated Speed :- 3000 RPM • Steam pressure :- 16.7 Mpa • Steam temperature :- 538 ° C • Direction of rotation :- Clockwise
  • 10. Electrical Generator • Electric generator is a device that converts mechanical energy to electrical energy. • Main part of generator are stator and rotor. • Output of electrical power taken from stator terminal. • D.C. supply to the rotor winding through brush and slip ring. • In Essar power water hydrogen cool synchronous generator is used
  • 12. Generator Specification Parameter Value MW Rating 600MW Rated Voltage 20KV Rated Stator current 20377 A Rated Speed 3000 RPM Rated Frequency 50 Hz
  • 13. Generator Cooling • Cooling needed in large size generator  Two Type of Cooling system I.Water cooling II.Hydrogen cooling • Water is used for stator cooling. • Hydrogen are used for rotor cooling as well as stator cooling
  • 14. STATOR COOLING WATER TANK STATOR COOLING WATER TANK MM MM COOLER A COOLER A COOLER B COOLER B STATOR COOLING WATER PUMP A STATOR COOLING WATER PUMP B GENERATORGENERATOR STRAINER B STRAINER A Stator water cooling cycle
  • 15. Transformer Yard  Main Equipment used Trafoyard I. GCB (Generator Circuit Breaker) II. ST (Station Transformer) III. UT (Unit Transformer) IV. GT (Generator Transformer) V. NGR (Neutral Grounding Resistor)
  • 17. GCB • Protection of the Generator against system-fed shortcircuit currents • The GCB is an effective protection device for the transformer and the generator I. Starting and maintenance stages II. Synchronization and normal conditions III. Abnormal conditions including • Overvoltages, un-balanced load • Short circuit – Step up transformer side – Generator side • Out of Phase Requirements
  • 18. Station Transformer • ST is used supply station common load such as Coal handling,DM plant, etc. • Transformer used in salaya power plant is three winding transformer • Specification Parameter Value Rated MVA 70 MVA Voltage 20/11/33KV Frequency 50Hz Number Phase 3 Vector Group Dyn11yn11
  • 19. Unit Transformer • Unit Transformer supply separate unit load such as Boiler auxiliary,Cooling tower and Turbine auxiliary etc. • Specification Parameter Value Rated MVA 45MVA Rated Voltage 20/11.5KV No. Of Phase 3 Vector Group Dy11
  • 20. GT(Generator Transformer) • As an essential element of all nuclear, thermal or hydraulic power stations. • GT are step-up transformer with delta connected LV side and star connected HV side • In Essar power salaya OLTC is used and GT consist of three single phase transformer unit.  GT Specification Parameter Value Rated MVA 250MVA Rated Voltage at no load 21/420KV Vector Group YNd1 Type Of cooling ONAN/ONAF/OFAF
  • 21. NGR(Neutral Grounding Resistor) • The suitable Neutral Grounding Resistance (NGR) should be installed between neutral point (star point) and the ground to restrict the earth fault current to 50 Amps • it is used to limit the current flowing through ground. • it measures the resistance between the neutral and the GND. • There two consideration to Select NGR 1) Plant capacity 2) Current carrieng capacity
  • 22. Bus Duct • Different types of bus-ducts are provided as per application/ current and voltage rating. I. IPBD (Isolated phase bus duct) II. SPBD (segregated phase bus duct) III. NSPBD (non segregated phase bus duct)  IPBD: In 20 kV,22000A Generator to Generator transformer main run  SPBD:-11kV, 1500 A between Unit transformer to Unit switchgear  NSPBD:-0.433kv, 3333.43A between service transformer to PMCC and MCC
  • 23. IPBD (Isolated phase bus duct)
  • 25. NSPBD (non segregated phase bus duct)
  • 26. Switch Yard • Three type of switch yard in Essar salaya power it’s divided in based on voltage level I. HV (High Voltage Switch yard ) II. MV (Medium voltage) III. LV (Low Voltage)
  • 27. HV Switch yard • Electric power is generated in Generation Station. The voltage at which is power is generated in generation station lies between 11kv to 25kv. • SwitchYard Definition It is switching station with incoming and outgoing feeders but without the transformer. It is a type of substation but incoming feeders and outgoing feeders are of same voltage level. Some times, the out door area of a substation where the circuit breakers are located are also called switchyard of the substation A switchyard connects and disconnects lines on the grid for various reasons. The operations and equipment are essentially all at the same voltage level.
  • 28. Equipment in switch yard  Main Equipment used in HV switch yard  CVT(capacitive voltage transformer)  CT(current transformer)  Isolator  Circuit Breaker  Bus bar  Wave trip  EMVT( electromagnetic voltage transformer)  LA (lighting arrester)  Earth switch
  • 29. CVT(capacitive voltage transformer) • Capacitor Voltage Transformers convert transmission class voltages to standardized low and easily measurable values, which are used for metering, protection and control of the high voltage system.
  • 30. CT (current transformer) • A current transformer (CT) is used for measurement of alternating electric currents. • A current transformer produces a reduced current accurately proportional to the current in the circuit, which can be conveniently connected to measuring and recording instruments.
  • 31. Isolator • Isolator is an off load device which is operated by remote control or local. Isolators provided in switchyard are central break type.  Types of Electrical Isolators 1) Double Break Isolator 2) Single Break Isolator 3) Pantograph type Isolator
  • 32. Circuit Breaker • A circuit breaker is an automatically operated electrical switch designed to protect an electrical circuit from damage caused by overload or short circuit • Its basic function is to detect a fault condition and interrupt current flow
  • 33. Busbar • A busbar in electrical power distribution refers to thick strips of copper or aluminium that conduct electricity within a switchboard, distribution board, substation, or other electrical apparatus • The size of the busbar is important in determining the maximum amount of current that can be safely carried.
  • 34. Wave trap • Wave traps are used for communication purpose during fault conditions. Wave traps offer high impedance path for high frequency signals & low impedance path for power frequency current.
  • 35. EMVT (electromagnetic voltage transformer) EMVT- Electromagnetic voltage transformer . As the name says its works in the principle of electromagnetic induction principle.Its just a stepdown transformer,stepdown voltage i.e higher voltage to meserable voltage by instruments connected to measurement and protection.
  • 36. LA (lighting arrester) • A lightning arrester is a device used on electrical power systems and telecommunication systems to protect the insulation and conductors of the system from the damaging effects of lightning
  • 37. • Earth switches used in substation . in that when isolator OPEN condition earth switch is CLOSED. here any induction that passes through earth switch to ground. when isolator in CLOSED condition Earth switch should be Open Earth Switch
  • 38. CONCLUSION The Overview of this project is about the various techniques involved in 400 KV Switchyard Of Essar Power Plant. By this we get To Know About the operation of different equipments in Switch Yard and its maintenance.