4. Milestones
Deliverables
Date
Approval from top management
Project approval
09 Jan 2014
Finalizing on budget
Overcoming Financial constraints
16 Jan 2014
Finding the supplier
Found the supplier
23 Jan 2014
Negotiating and placing order
Purchasing equipment
30 Jan 2014
Transportation
Receiving equipment
07 Feb 2014
Installations
Installations through skilled man
power
21 Feb 2014
First phase of power production
Power production
28 Feb 2014
5.
6.
7.
8.
9.
10.
11.
12.
13. Activities
T p(Days)
Tm
To
T e( (T p+4*Tm +Te)/6
Approval from the top
management
11
9
7
9
Finalizing on the budget
7
5
6
5.5
Finding the supplier
8
7
6
7
Negotiating and placing the
order
10
7
6
7.3
Transportation
9
7
5
7
Installation
16
14
10
13.7
Testing
8
7
4
6.7
14. Data collection(5)
Finalizing the supplier(2)
Order processing&
Transportation(7)
Presentation(4)
Negotiating on budget(5.5)
Approaching the
supplier(3)
Negotiating(3)
Inverter
installatio
n(3)
Mounting(3)
Searching for
supplier(5)
Place the order(1.3)
Testing(6.7)
Welding(2)
Cement work(4)
CPM time=56.2 days
15.
16. Activities
Labour
Technicians
Materials
Approval from the top management
0
0
Stationery
Finalizing on the budget
0
0
Stationery
Finding the supplier
0
0
Internet, Telephone
Negotiating and placing the order
0
0
Internet, Telephone
Transportation
4
0
Truck, packaging material
4
2
1
2
Welding
2
1
Cement work
2
1
Cement etc
0
3
-
Installation
Testing
Mounting
Inverter installation
Iron rods, screws, solar panels
Inverters
Iron material etc