SlideShare une entreprise Scribd logo
1  sur  63
MULTI MODAL
INTERCHANGE HUB
at Rourkela…

Action Area Plan :

TRANSPORTATION
A I M :
To promote the utility of the area
under consideration for the
purpose of functioning as a
multimodal interchange hub for
transit oriented development of
the area.

OBJECTIVES:
The major objectives of the study are:
 To strengthen the link between
various modes of transport present in
close proximity , thus achieving the
ultimate goal of a multi-modal
interchange that combines various
modes and their associated functions
in order to achieve a better degree
of transport network.
 Encourage integrated development
of traffic movement & networks,
transportation facilities & their
linkages and associated functions/
activities prompting landuse
modifications to suit the context of
the development.

MULTIMODAL INTERCHANGE HUB:
A PROLOGUE . . .

SCOPE:
 Development of transit facilities as per user rate,
multiple mode linking and passenger comfort and
affordability.
 Holistic approach to commercial bases and their
delineation along avenues of relevantly related
freight movement and logistics.
 Promotion of single landuse zones to facilitate
correlativity between the various activities that are
related to transport and traffic networking.

LIMITATIONS:
 The area under consideration is the stretch of road
between Madhusudan Chowk and Rourkela railway
station’s main entrance (longitudinal) and the
stretch of road from the other entrance of the
Rourkela railway station to the bus depot (traversal)
– as because this part experiences maximum traffic
congestion and which is to be addressed to
promote better transport network for the area.

MULTI MODAL INTERCHANGE : Aim, Need, Methodology, Scope and
Need:

SURVEYS & ANALYSIS

The need to develop the area under consideration was
defined by three basic necessities to be addressed:
VISUAL SURVEY






MULTIMODAL INTERCHANGE HUB:
A PROLOGUE . . .

The LANDUSE ANALYSIS
location:
 The multiple modes of transport concentrated within
USER PERCEPTION SURVEY
the same area;
 CONNECTIVITY ANALYSIS of the daily market in the vicinity.
Strategic location
INTERSECTION VOLUME
SURVEY
The trip generation factor:
FACILITIES ANALYSIS
 The high O-D data generated to and fro in this area –
due to location of varied typology including the huge
base of hospitality sector and commercial sector;
 Also location of the major railway station for the city –
DESIGNING
major source for translocation of passengers and
goods – major issue: traffic congestion and
mismanagement.
ACCESS FOR
FOOTPATHS
DISABLED
The importance of Rourkela on the industrial and
commercial scenario of India:
 Steel industry based development, major
INTER.
V/C RATIOS
transshipment ofVOLUME and materials – both in
goods
processed and unprocessed states – requires railway
services and railway stations in the vicinity helps curb
STREETSCAPE
transportation charges agglutinating to the
production cost / market price. Also passengers
consists majorly of entrepreneurs, business based
STREET DESIGN
companies and individuals.
 The Bus stand may act as a major source for easy
movement of labor and can prompt affordable rates
for travel for the workforce that travels long distances
daily – to and fro – within or outside the urban
M O D I F I C A T I O N S I N . . .
agglomeration.

PLANNING
PEDESTRIAN
MGMT.

TRANSPORT

VEHICULAR
MGMT.
SAFETY/
SECURITY
COMM. /
KIOSKS
DRAINAGE

STREET
LIGHTING

SOCIAL INFRA.

PHY. INFRA.

FREIGHT
PARKING
CAFETERIA

FACILITIES

TOILETS

WAITING ROOM

LANDUSE

MULTI MODAL INTERCHANGE : Aim, Need ,Methodology, Scope and
INTRODUCTION
A Multi modal Interchange hub is one in which co-ordination and integration of different modes of transport takes place
to decongest road, reduce journey time, enhance environment, provide greater convenience for commuters, efficiency and
cost effectiveness.

The act of changing between modes –
The place where one changes the modes –
A purpose built facility to improve interchange quality –

Interchange
Interchange Zone
Interchange facility

Source: The Intermodal Transport Interchange For London: Best Practice Guidelines

MULTI MODAL INTERCHANGE :
DECISION SPACES
Areas
where
passenger
decisions
take
priority.
Examples include decision
points such as entrances, ticket
offices or corridor
junctions.
At these locations there
should be good sight lines/clear
signing
or
transport
information. There should be
no
nonessential
physical
infrastructure
or
visual
distractions such as
advertising/ retail or other
land uses that would serve to
distract or confuse passengers.

INTRODUCTION
OPPORTUNITY SPACES
Opportunity spaces include those areas
of the interchange
zone outside the core corridors of
movement or decisions.
They can accommodate cafés, retail
entrances, retail display, seating or
landscaping.
Street furniture, advertising or other
fixed or temporary infrastructure located
in these zones must be managed so as
not to protrude or interfere with the
requirements of decision or movement
spaces in adjacent areas.

MOVEMENT SPACES
Movement spaces connect decision spaces.
Typically these include corridors and paths specially reserved for passenger movement
and connections to/ from/ between transport modes or the surrounding area.
These spaces should provide clear, unobstructed routes matched to desire lines.
Street furniture, plantings, advertising, information displays, retail boards or any other
fixed items should not protrude into these zones but may be located adjacent to them.

MULTI MODAL INTERCHANGE :
INTRODUCTION
Example of an Multi modal Interchange

Four interchange themes
which should be considered
at transport hubs:
Efficiency:
moving
sustainability

Operations,
around,

Usability:
Accessibility,
safety
and
preventing
accidents, personal security,
protection
Understanding: Legibility,
permeability, way-finding,
information

Quality:
Perception,
design, spaces, sense of
place

MULTI MODAL INTERCHANGE :
Access to Transit Station by
Non-Motorized Transport

MULTI MODAL TRANSPORT SYSTEM, DELHI
INFERENCES

1. Pedestrian access
- Provisions for pedestrians and their safe movement are an essential access consideration.
- Direct and safe approach for pedestrians
•
•
•

Pedestrian access-ways that reduce distances to bus services on the adjacent higher order bus streets.
Continuous and direct footpath networks that permeate neighborhoods.
Safe, convenient and/or controlled road crossing points should be provided to stops with high passenger
usage.

2. Bicycle access
• Can increase the service area of transit stations.
• Bicycle parking facilities located to provide protection from weather, theft and conflicts with other modes.
Parking areas i.e. active areas with high pedestrian activity, or under the observation of station attendants
preferred.
• Well Lit and designated by signages.

Accessibility by Intermediate Para Transit (IPT)
•
•

Various modes of IPT such as auto, taxi, phatphat, etc are considered as feeder modes to bring passengers from
various parts of the neighborhood to the multi modal transit station.
IPT zone is desirable. IPT area must be covered and seating may be provided.

MULTI MODAL INTERCHANGE :
Accessibility by Public Transport
•
•

MULTI MODAL TRANSPORT SYSTEM, DELHI
INFERENCES

Bus stop design capacity for a station is based on the individual requirements for each station either as a single
station, interchange station or integration point.
The following designs may be used for various types of bus loading zones, depending on specific conditions:

i. Recessed Bus Bay: It is used where more mixed traffics are on the road. The bus loading
zone is recessed from the through traffic lane. A recessed bus bay is designed parallel to close enough to the curb so
that passengers may enter and leave any door by an easy step to the curb. Upon leaving, the merging lane enables
the bus an easy re-entry into the through traffic lane.
ii. Parallel- to-curb Bus Bays
It should have 3 mt wide lanes and an overall length of 73.2 mt. This layout for bus loading area provides the
minimum roadway width but requires the longest length for a bus loading zone. The critical movement in this layout
is moving into position ahead of the parked bus. This leaves the rear door of the bus offset from the platform curb by
approximately 0.45 mt.
iii. Sawtooth Bus Bays
Sawtooth bus bays reduces the length of loading zone and therefore reduces walking distances but increases the
width of the roadway.

MULTI MODAL INTERCHANGE :
Accessibility by Private Modes
•
•
•
•

MULTI MODAL TRANSPORT SYSTEM, DELHI
INFERENCES

Parking space for car, two wheelers at the station. Entry and exit points should be at mid block.
Parking aisles should be lined perpendicular to the station entrance/exit are to minimize the no. of potential conflicts
between pedestrians and automobiles.
Collapsible posts or signs should be used to delineate drives and pedestrian. Major pedestrian walkways should be
raised 0.15 mt above the parking pavement.
Right angle parking should be used because it allows better circulation, more orderly parking, and in most cases has
lower average area requirement per space.

Accessibility to Transit Station/Stops: Current Practices in Delhi
•
•

“Cycle-for-Hire Scheme” Encourage people to use bicycles for short distances at Delhi University Metro station and
near by areas. The charge of a bicycle on rent is Rs 10/= for 4 hours.
Pedestrian way to the BRT Corridor in Delhi: To provide safe and comfortable sidewalk to access public transport.
•
•
•
•

Continuity of the sidewalks. Wide and well surfaced sidewalks and is disable friendly.
Sidewalks are easily negotiable by women, children, senior citizens, as the height is close to 15 cm. Width of
sidewalks varies from 1.5 mt (min) to 4.5 mt (max) along the corridor. Sidewalks are well lit.
Crossings are easily accessible with kerbed ramps and there is a holding area for people to want at the side
and at the pedestrian refuge islands.
Pedestrian path on the BRT corridor has the least permanent and temporary obstructions on the sidewalks

MULTI MODAL INTERCHANGE :
Attributes to enhance the
accessibility to transit station:
•
•
•

•

•

MULTI MODAL TRANSIT ORIENTED DESIGN

People Place: Transit station area is a place for people/commuters. Hence, it must be well used,
safe, comfortable, and attractive; and need to be distinctive and offer variety, choice and fun.
Streetscape Design: M2OD should promote and enrich the qualities of existing urban places at
neighborhood and street level. It is important to develop streetscape design elements for each of
the transport corridor by incorporating various architectural elements.
Urban Form: Transit station is considered as a part of urban design and sky line. It is blended with
different building forms, colors, materials, textures, forms, etc. Such areas should be integrated
physically and visually with its surroundings having better access by foot, bicycles, bus, cars, metro,
etc. Amenities that are stimulating, enjoyable and convenient should be offered to a wide range of
possible users.
Transit in Landscape: These areas should provide balance between the natural and the manmade
environment and utilize each locations intrinsic resource – the climate, land form, landscape, and
ecology – to maximize the experience. Design must put such built environment in proper land
scape environment.
Design in Flexibility: New development near and around transit station take very little time. New
development needs to be flexible enough to respond to future change in use, lifestyle, and
demographics. Flexibility must be evident in the use of property, public spaces, and infrastructure.
Integration of any new modes with the station area requires more space for loading, unloading,
transfer, integration, parking, traffic management, etc.

MULTI MODAL INTERCHANGE :
CONNECTIVITY: CITY LEVEL

RAILWAY STATION

BUS TERMINAL
DAILY MARKET

CONNECTIVITY
NODE AND NETWORK

PHYSICAL ACCESSIBILITY
EXISTING SITUATION
ROURKELA RAILWAY STATION
ROURKELA
RAILWAY STATION

BUS STAND

SCHEMATIC LAYOUT OF RAILWAY STATION

RICKSHAWS

5- PLATFORMS
3- SIDINGS
11 TRACKS BROAD GAUGE
2 FOOT OVER BRIDGES.
BOOKING
OFFICE

CONCOURSE

CYCLE
PARKING

NO. OF USERS PER DAY
NO. OF PASSENGER TRAINS
CAR PARKING
2-WHEELER
PARKING

THE EXISTING SITUATION

6000
52

NO. OF GOODS TRAINS

38

MONTHLY TICKET SALE (OFF PEAK)

2 LAKHS

MONTHLY TICKET SALE (PEAK)

2.45 LAKHS
ROURKELA RAILWAY STATION
FACILITY
WAITING HALL (1ST CLASS)

1ST FLOOR

WAITING HALL (2ND CLASS)

PLATFORM 1

PAY AND USE TOILET

AT BOTH ENDS OF STATION

TRAIN INDICATION BOARD

CONCOURSE AND PLATFORM

FACILITATION CENTRE

FACING CONCOURSE AND PLATFORM 1

STD BOOTH

CONCOURSE AND PLATFORM 1

WATER COOLERS

PLATFORM 4 & 5

TOUCH SCREEN

CONCOURSE AREA

RESERVATION AND REFUND
COUNTERS

BOOKING OFFICE

ATM

CONCOURSE

DORMITORY

1ST FLOOR

RETIRING ROOMS

1ST FLOOR

CLOAK ROOM

GROUND FLOOR

POLICE STATION

ON FRONT SIDE OF STATION

POST OFFICE

ON FRONT SIDE OF STATION

CAFETERIA

1ST FLOOR

BOOKSTALL

PLATFORM 1

SNACKS SHOPS(6-7)

OBSERVATIONS:
•Ramps/ elevators/ lifts are not available at the
station
•Provision of seating is less
•No provision of proper drop off bay at the
entrance for arriving vehicles

LOCATION

ALL PLATFORMS

THE EXISTING SITUATION
FACILITY

CONDITION

WAITING HALL

ABSENT

PAY AND USE
TOILET

PRESENT

Poorly maintained. Requirement of
additional toilets for increase in
demand

SIGNAGES

ABSENT

Required

FACILITATION
CENTRE

PRESENT
PRESENT

-

DRINKING WATER

PRESENT

Unhygienic

RESERVATION AND
REFUND COUNTERS

PRESENT

Unhygienic

ATM

ABSENT

Required

CLOAK ROOM

PRESENT

-

POLICE STATION/
POST

ABSENT

Unsafe Environment

CAFETERIA

PRESENT

Sufficient

BOOKSTALL

PRESENT

-

COMMERCIAL ZONE

PRESENT

Meant for Hardware (Auto Spare parts
etc)

ROURKELA
RAILWAY STATION

Located in a corner. Difficult to locate

STD BOOTH

ROURKELA BUS STAND

THE EXISTING SITUATION

BUS STAND

NO. OF USERS PER DAY

2000

NO. OF DAILY BUSES

300

TIMINGS

7 PM TO 10 PM
6 AM TO 10 AM

(Departure)
(Arrival)
railway station

PARKING

800
600
400
200
0
BICYCLE

2W

CARS

GOODS
VEHICLES

43

877

62

3

railway station

Unauthorized parking at railway station:
Bicycles: 13
Two wheelers: 60
Cars: 11 (parked in wrong location despite space being
available in authorized parking)
Rickshaw parking:
Space given for 35 rickshaws
Around 20 rickshaws were observed
Auto rickshaw parking:
Space for 30 autos
18 autos observed
Parking lot

Peak timing

Railway station

7:30-9 am
6:30pm-8pm

Possibility
rejection
2w- no
4w- yes

6-8pm

no

Bus stand (pvt)

of

THE EXISTING SITUATION

Bus stand
no of vehicles

no of vehicles

1000

35
30
25
20
15
10
5
0
BICYCLE
Bus stand

2W

CARS

GOODS
VEHICLES

18

30

14

0
ON-STREET PARKING

Unauthorized on street
parking
Auto rickshaw stand

THE EXISTING SITUATION

•OBSERVATIONS:
•Unauthorized parking along the streets
is leading to congestion along the main
roads
•Trucks have been illegally parked near
the Fakir Mohan market hence
compromising on the space available to
commuters.
NO. OF AUTOS PRESENT

80

DAILY TRIPS

~ 20

FACILITY

ISSUES

Toilet Facility

Absent

Drinking Water facility

Absent

Shelter for Auto Drivers

Absent

Cleanliness

Garbage Disposed
along the stretch

PARA – TRANSIT STAND
ROURKELA
RAILWAY STATION

BUS STAND
PARA-TRANSIT

Routes taken by Autos from the Railway Station:
Station Road to Sectors
Station Road to Panposh
Station Road to Bandamunda
Station Road to Fertilizer colony
Station Road to Civil township
Station Road to Vedvyas
Station Road to Kaswal Rajganjpur
Station Road to Kwarmunda
Station Road to Birmitrapur
Data obtained from Primary Survey

Under - Construction Para-transit Stand

THE EXISTING SITUATION
LENGTH OF ROAD
WIDTH OF THE ROAD

ROAD STRETCH

400 m
Effective width 4.5 m to
7.5 m

B

A

B

THE EXISTING SITUATION
NODE AND NETWORK

PHYSICAL ACCESSIBILITY
LANDUSE
ANALYSIS

EXISTING SITUATION
EXISTING SITUATION

LANDUSE
Mixed use

767

Authorized parking

3350

vacant land (railways)

17465

vacant land (Govt)

2681

Public-semi public area

5069

hospitality zone

2267

Railway station/bus station

45702

commercial

Mixed use
1%
10%

1%

Authorized parking

2%

11%

3%

vacant land (railways)
1%

26%

14879

Informal Commercial

LANDUSE

vacant land (Govt)
Public-semi public area
hospitality zone

29%

1000

6%

Railway station/bus station
commercial

9%

Informal Commercial

Residential

9986

Informal residential

41582

Open Ground

15700

Residential

1%

Informal residential
Open Ground

EXISTING

ISSUES

Presence of discordant activities such as schools and
gurudwaras along the stretch

Might lead to chaos due to irrelevance in terms of
activities

Informal market along the stretch

Unorganised traffic movement and creation of
bottlenecks

Hospitality + Residential (Mixed Zones) present along the
road leading to Panposh road

Diametrically opposite to the proposed multi modal
interchange concept

Existing economic activities caters to auto service/ spare
parts etc which is incompatible with the proposed idea

Might lead to chaos due to irrelevance in terms of
activities

THE EXISTING SITUATION
FACILITY
ANALYSIS

EXISTING SITUATION
45.0
40.0
35.0
30.0
25.0
20.0
15.0
10.0
5.0
0.0

FACILITY ANALYSIS : User Profile
Mode used to reach station

< than once
/month
Series1

once
a/month

2
times/mont
h

1-2 times/
week

5-6
times/week

5.6

38.9

16.7

11.1

45.0
40.0
35.0
30.0
25.0
20.0
15.0
10.0
5.0
0.0

% of respondents

% of respondents

Frequency of using the station

27.8

auto

% of respondents

Trip purpose
50.0
45.0
40.0
35.0
30.0
25.0
20.0
15.0
10.0
5.0
0.0
Series1

Series1

work

education

shopping

other

38.9

5.6

11.1

44.4

USER – PERCEPTION SURVEY

bus

car

two
wheeler

walk

38.9

22.2

27.8

5.6

5.6

Observations:
•Most respondents use the station once every
month.
•Daily users amount to around 28 %.
•Work and other (including family engagements)
are the main reasons for making trips.
•Almost 40% respondents use auto rickshaw to
reach the station indicating importance of the
mode.
Requirement:
•Parking space for cars and auto rickshaws
•Drop off bay for passengers who are coming to
station .
120.0

FACILITY ANALYSIS :Accessibility

100.0
100.0
90.0

80.0

66.7
55.6

60.0

83.3

80.0
70.0

44.4
33.3

40.0

50.0

20.0
0.0
willing to use feeder
services

44.4
38.9

40.0

0.0
Buses conjested?

61.1
55.6

60.0

Do you think bus /auto
stops are too far?

30.0
16.7

20.0
10.0

yes %

no%

0.0
parking enough?

120.0

Direct entrance from road More no. of entrances to
to platform
station

100.0
100.0

88.9

80.0
60.0

yes %

72.2
55.6

50.0 50.0

44.4

40.0

27.8
11.1

20.0

0.0
0.0
Do you prefer
surface
walkways over
subway?

Are the
walkways
safe?`

Do you want
escalator?

yes %

Do you want
ramp?

travelator
necessary?

no%

USER – PERCEPTION SURVEY

no%

Observations:
•All respondents willing to opt for feeder
services
•Almost 2/3rd of the respondents feel that
bus/auto stops are too far from the station .
•An overwhelming majority in favor of
provision of ramps and escalators at the station.
•Safety of walkways a major concern.
Requirements:
•Feeder services
•Accessible interchange facilities
•Ramps/escalators for easy barrier free access
•Well lit secure walkways
100.0

88.9

90.0
80.0

77.8

72.2

FACILITY ANALYSIS : Facilities

77.8

70.0

Recreational facilities desired

60.0
120

50.0
27.8

30.0

22.2

100

22.2

20.0

11.1

10.0
0.0
Integrated ticket
system

ticket vending
machines?
yes %

internet booking?

do you have a
monthly pass?

% of respondents

40.0

80
60
40
20

no%

0
90.0
80.0
70.0
60.0
50.0
40.0
30.0
20.0
10.0
0.0

83.3

77.8

Series1
61.1
50.0

50.0

38.9
22.2

waiting areas be
air conditioned?

16.7

Do you use dorm Are seating areas
Do you want
facilities?
enough?
covered platform
for entire length?

yes %

no%

USER – PERCEPTION SURVEY

tv

magazine stands

audio

100

50

44.4

Observations:
•High demand for ticket vending machines.
•Maximum people are using internet booking
options.
•Air conditioned waiting areas desired
•Dorm facilities not required
•More seating required for the general public
Requirements:
•Ticket vending machines
•Internet kiosks for bookings
•More seating
•Recreational facilities: TV in the waiting areas
•Magazine stands required.
FACILITY ANALYSIS : Facilities

Requirement of more shops
yes %

no%

22%

120.0

100.0

100.0

88.9

94.4

88.9

80.0
60.0

78%

40.0

44.4

38.9

20.0
0.0

Willingness to pay for extra facilities
yes %

no%
Type of shop that you want

44%
56%

Requirements:
•snacks/juice bar
•fruits/veg shops
•books/magazine shops
•medicine shops

USER – PERCEPTION SURVEY

44.4
33.3
9

FACILITY ANALYSIS :Time

8.5
7.6

8

Observations

7
6

5.4

5.16

5

4.5

4.5

Average

3.7

4

Maximum

3

Desired

3
2

1.5

•Average present waiting time at the
bus stop was found to be 5.16
minutes which is more than the
desired ( 4.5 minutes)

1
0
Waiting time at autostop

Waiting time at bus stop

Ticketing time

20

•Average present ticketing time at
railway station was found to be
4.5minutes which is more than the
desired (1.5minutes)

17.5

18
16
14
12
10

10
8.5

Average

8.5

Maximum

8
5

6
4

•Average present waiting time at the
auto stop was found to be 3.7minutes
which is more than the desired ( 3
minutes)

Desired

•Average time spent walking was
found to be 8.5minutes which is more
than the desired (2.5minutes) and
which is equal to the maximum .

2.5

2
0
Average time spent walking

Average waiting time at platform

USER – PERCEPTION SURVEY

•Average waiting time at platform
was found to be 4.5minutes which is
more than the desired (5minutes) and
even more than the maximum which
is 10 minutes.
IMPORTANCE SATISFACTION ANALYSIS
Bus Stop
4.5
4
3.5
3
2.5
2
1.5
1
0.5
0

Interchange

importance
satisfaction

bus stop
performance

frequency of bus
service

6
5
4
3
2
1
0

importance
satisfaction

feeder service

Paratransit
3.5
3
2.5
2
1.5

importance

1

satisfaction

0.5
0
paratransit stop
performance

frequency of auto
service

safety of stand

distance from building

USER – PERCEPTION SURVEY
IMPORTANCE SATISFACTION ANALYSIS
Railway Station
6
5
4
3

2
1

importance
satisfaction

0

USER – PERCEPTION SURVEY
100%

90%
80%
70%
60%
50%

No

40%

Yes

30%
20%
10%
0%
Students

100%

LIG

MIG

90%
80%

70%
60%
50%

No

40%

Yes

30%
20%
10%
0%
LIG

MIG

APPROPRIATENESS

No
Yes

Primary

HIG

Willingness to pay for extra services v/s income
group

Students

100%
90%
80%
70%
60%
50%
40%
30%
20%
10%
0%

100%
90%
80%
70%
60%
50%
40%
30%
20%
10%
0%

HIG

Willingness to have more shopping area v/s income levels

USER – PERCEPTION SURVEY

Class XII

Graduate

Willingness to use internet booking v/s level of
education level

No
Yes

<18 yrs
18-40 yrs
40-60
Willingness to use ramps v/s age group

60<
Facilities at para transit stop
importance

satisfaction

paratransit stop
performance

1

3

frequency of auto service

2

2

1

3

safety of stand

ANALYSIS

IMPORTANCE SATISFACTION ANALYSIS
SATISFACTIO
N

5

4

3

2

IMPORTANCE

distance from building

2

2

importance

satisfaction

1

4

Facilities at bus stop
bus stop performance

1
2
3
4

frequency of bus service

3

2

4

importance

feeder service

1

satisfaction

1

4

1

4

1

5

2

3

1

3

1

4

1

4

1

5

2

4

2

3

Miscellaneous
parking areas
pedestrian pathways
disable access
level changes
Surveillance
Toilet facilities
Cleanliness
Organised areas in the
interchange
weather protection in
interchange areas
Safety

5

Observations

USER – PERCEPTION SURVEY

The most critical aspects which are to be
taken care of
- Feeder service
- Parking areas
- Pedestrian pathways
- Disable access
- Toilet facilities
- Cleanliness
- Weather protection
Second most critical aspects
-Safety of para transit stop
-frequency of bus service
- level changes in the railway station
-Safety

1
Facilities at railway station
importance
building entrances
accessible
location of entrances
walking distance to ticket
counter
queuing time
Queuing space

No. of ticket counters
Location of ticket counters
Real time information
Information system
placement
Walking distance (from
ticket counter to platform)
Alignment of platform and
the entrance location
Goods loading/unloading
area on platform
Safety or surveillance of
platform
Waiting area in platform
Railway station
performance

satisfaction ANALYSIS

IMPORTANCE SATISFACTION ANALYSIS

2

2

2

2

2

2

2

3

2

3

2

3

2

2

1

3

Second most critical aspects

2

3

2

3

2

3

2

5

-Queuing time
- Queuing space
– No. of ticket counters
– Real time information
–Information system
–Waiting area in plat form

2

3

1

3

2

4

USER – PERCEPTION SURVEY

Observations
The most critical aspects which are to be
taken care of
-Goods loading and unloading area
-Total railway station performance

Third most critical aspects
- Building entrances
- location of entrances
- walking distance to ticket counter
- Location of ticket counters
TRAFFIC
ANALYSIS

EXISTING SITUATION
TRAFFIC ANALYSIS

Traffic Volume Count

LINK NAME

PEDESTRIANS

PCU

V/C

PAVEMEN
T

ENCROACHMENT
OF PAVEMENT

ENCROACHMEN
T OF ROAD

ON STREET
PARKING

PROMINENT
MODE
ALONG THE
LINK

Railway Station to Panposh
Road, via Hotel Aastha

108

6.3%

130.8

0.12

Absent

NA

Very Less

Very Less

Two-Wheeler

Railway Station to
Madhusudhan Marg

456

26.6%

450.6

0.41

Absent

NA

Informal Sector
near the ParaTransit Stand

Present
along the
Commercial
Stretch

Non Specific

Towards the Railway
Station

586

34.1%

156.6

0.14

Absent

NA

Nil

Nil

Non Specific

Towards the Bus Stand

438

25.5%

180

0.16

Absent

NA

Informal shops
situated along
the stretch at
certain locations

Truck Parking
in front of
Fakir Mohan
market.
Otherwise
negligible

Pedestrians
Cyclists

Along Alternative
Entrance/ Exit

126

7.5%

51.6

-

Absent

NA

Very Less

Nil

Pedestrians
Two
Wheelers

TOTAL

1714

918

-
TRAFFIC ANALYSIS

Traffic Volume Count

-Traffic Count at Railway Station is 918 PCU’s in 1 hour time period. ( 5pm to 6pm)
- A large Volume of pedestrian movement was observed along the main entrance, towards the stretch to the Bus Stand and
Para Transit Stand present at Madhusudhan Chowk.
- The Traffic Volume Count at madhusudhan chowk at peak time is 3426.6 PCU which has to be considered into the
proposals.
4%

Mode Availability and Usage of Mode
-Pedestrians constitute most of the traffic, and no provisions are made
for their circulation.

Cycle

23%
11%

- Two wheelers ranks the highest in modal choice followed by four
wheelers and auto rickshaw.

5% 0%
Cycle rickshaw
2 Wheelers
57%

Auto Rickshaw
Car/jeep
Lcv

Parameters

Probable Solutions for Implementation

Responsive to street congestion

• Dedicated Corridors for Pedestrian and Motorized
Modes of transport
• Road Widening of roads at strategic locations
• Strategic Relocation of Encroachments

Responsive to travel costs

• Pedestrianisation of corridors to the possible extent
Reduction of unnecessary travel movements

Responsive to Availability of Public transport

• Explore scope of Para-Transit/ Feeder Service

Responsive to the
OBSERVATIONS growth of the Surroundings

• Incorporation of ancillary activities along the stretch
Mapping Pedestrian Routes & Demand

RAILWAY STATION

TRAFFIC ANALYSIS

438 Pedestrians

586 Pedestrians

BUS STAND

PARA-TRANSIT

456 Pedestrians

CONFLICT POINTS
MAX. DEMAND
INFRASTRUCTURE
ANALYSIS

EXISTING SITUATION
ELECTRIC LINES CROSSING OVER THE ROAD

NO STREET LIGHTING ON THE ROAD

NO PEDESTRAIN ON THE ROAD

NO PEDESTRAIN PATHWAY ON THE ROAD

STREET LIGHT ON THE 1 SIDE OF ROAD ONLY

NO PEDSTRAIN PATHWAY ON THE ROAD
ROAD LINKING THE RAILWAY
STATION AND BUS STAND

ROAD IN FRONT OF
RAILWAY STATION

OPEN DRAINS IN SOME AREA

ROAD IN FRONT OF
BUS STAND
NO PEDESTRAIN AREA
EXISTING STREET LIGHTING ,
ELECTRICTY DISTRIBUTION LINES

CCTV LOCATIONS
TRANSFORMER

FLOOD LIGHTS
Improper street
lighting

Crossing of the
electric lanes over
the road

STREET LIGHT
ELECTRIC LINE
NO Segregation
of pedestrian
and vehiclular
movement

STREET LIGHT WIRE

No Defined
pedestrain path

NO Flood lights at
the MADHUSUDAN
chowk

Existing road section of the road
linking bus stand to railway station
EXISTING DRAINAGE AND
SOLIDWATSE SITUATION

Major problems of
drainage and solid
waste
This area is
highly
polluted due
to the
presence of
vendor

Drains are not well
maintained as in some
area are these are open .

OPEN ROADSIDE DUMPING

CLOSED DRAINS
OPEN DRAINS
OPENING TO DRAINS

No proper waste disposal
area / collection area..

Existing section through the road in front

of the railway station

Existing section through road in
front of BUS STAND
PROPOSALS FOR THE ELECTRIC
LANES AND STREET LIGHTING

TRANSFORMER

FLOOD LIGHTS
STREET LIGHT
UNDERGROUND
ELECTRIC LINE
STREET LIGHT WIRE
Proposals
•Underground electric lane
•Flood lighting at junctions.
UNDERGROUND ELECTRIC LANES PITS

•Solar panel street lighting .
•Lighting also provided along the
pedestrian movement .
SOLAR PANEL STREET LIGHTING
•
•

Solar street lights require much less maintenance
compared to conventional street lights.

•

Since external wires are eliminated, risk of accidents is
minimized.

PROPOSALS FOR THE ELECTRIC
LANES AND STREET LIGHTING

Solar street lights are independent of the utility grid.
Hence, the operation costs are minimized.

•

This is a non polluting source of electricity
Separate parts of solar system can be easily carried to the
remote areas

DX3 Solar Street Light

Uses standard size/connection

Uses standard size/connection

90 W high pressure sodium

30W Ultra High Efficient Array

5500 Lumens (3850 effective)

•

Regular Street Light

3400 Lumens

30-50 Lumen / Watt

120+ Lumen / Watt

Photo-sensor or wire control

Photo-sensor, wire or solar panel

No Back Up Power Source

Internal Battery, fully integrated
into Street Light Head (Approx. 3
nights autonomous
operation/battery reserve)

No solar array

Integrated solar array

Requires electricity

Solar powered

Works only when grid is
energized

Works during power outages

Cable requires expensive
trenching

No trenching

Additional wiring in the ground

No wire in ground

Wire in the pole

No wire in pole

Significant resources to install

Simple install

Special crews for safe
installation & commission

Safe to install (12V)

Attracts insects

Does not attract insect
Municipal
waste

B. Recyclables
A. Organic
•
•
•
•

Food waste
vegetables waste
Garden
trimmings
dry leaves

•
•
•
•
•
•
•
•

Paper
Plastics/polyethenes
Rubber, leather
Glass & ceramics
Textile/cottons
Earthen wares
Metal
Coconut shells

63.00

For B i o –
degradable
wastes

For
Re-cyclable
wastes

Solid waste management

C. Inert

• Dirt
• Sand
• Dust
• soil
Calculations
 The stretch will be mostly used by the floating population which depends on the transits
 Bins for Commercial Establishments/Shops : It is assumed that one bin will serve 25 shops.
 Organic waste will be collected daily & recyclable waste will be collected once in a week.
 Providing 100L capacity fibre glass bins for bio degradable waste and 500L capacity bins for recyclable wastes.
Waste density for bio degradable waste = 300 kg/cubic metre
Waste density for bio degradable waste = 150 kg/cubic metre

Total no. of people using the stretch from railway station to
Madhusudan chowk per day= around 5000
waste generated per day per pedestrians= 5000X.05kg=250 kg
waste generated by the shops=0.5X84=42kg
Total waste generated = 292 kg

Total no. of people using the stretch from railway station to
bus stand, per day= around 4500
Total waste generated per day= 4500X.05kg=225 kg
waste generated by the shops=0.5X80=40kg
Total waste generated = 265 kg

assuming that 1/4th of the total waste is organic
Amount of organic waste = 70 kg
Amount of recyclable waste= 222 kg

assuming that 1/4th of the total waste is organic
Amount of organic waste =70 kg
Amount of recyclable waste= 195kg

Bio degradable waste
N=70/(300X0.1X1X1)=3

Bio degradable waste
N=70/(300X0.1X1X1)=3

Recyclable waste
N=190/(150X.5X1X1.6)=2

Recyclable waste
N=195/(150X.5X1X1.6)=2

N=W/(DXSXF1XCF)Where
N = Number of collection bins
W = Total quantity of waste generated per day in Kg
D = Density of waste in Kg/m

Solid waste management: Calculations

S= Size of bins in m3
F1= Average filling rate of bin. (Generally 80 %)
CF = Collection Frequency
At railway station

At Bus stand

Total no. of people using railway station per day = 6000
Waste generated per person = 100g
Total waste generated= 600kg
assuming that 1/4th of the total waste is organic
Amount of organic waste = 150 kg
Amount of recyclable waste= 450 kg

Total no. of people using railway station per day = 1000
Waste generated per person = 100g
Total waste generated= 100kg
assuming that 1/4th of the total waste is organic
Amount of organic waste = 25 kg
Amount of recyclable waste= 75 kg

Bio degradable wastes
N=70/(300X0.1X1X1)=5

Bio degradable wastes
N=25/(300X0.1X1X1)=1

Recyclable wastes
N=190/(150X.5X1X1.6)=4

Recyclable wastes
N=75/(150X.5X1X1.6)=1

Bins for Institutions
It is assumed that two trash bin will be placed in each institution. Both Organic waste & recyclable waste will be collected
daily.

Bins for Hotel and Restaurant
2000 litres capacity will be placed at each hotels and restaurant for collection of bulk generation of organic waste.

Street sweeping
The width of t he roads are different. Considering 2 0% of road length having 12 Mt. width, 40% of the road length having 22
Mt. width & 40% of road length having 6 Mt.
width, the length of the roads of different width are as follows 12 Mt. width road = 260km; 22 Mt. width road = 520km; 6Mt.
width road = 520km Considering one sweeper can sweep 2500 Sqmt. of road/day and also be allotted the duty for primary
collection of waste from road side to dumper placer container.
The no of sweeper required For 12Mt.width road = (12x260)/2500 = 2nos. For 22Mt.width road = (22X520)/2500 = 5nos. For
6Mt.width road = (6X520)/2500 = nos. Total = 2 nos.
Total no. of workers=2+4+2=9

Solid waste management: calculations
100L capacity
fibre glass
green colour
bins for bio
degradable
waste

Two types of bins
will be placed
together

500L capacity
fibe glass black
colourbins for
recyclable
waste

Solid waste management: positions of bins
URBAN DESIGN

EXISTING SITUATION
VISUAL CONNECTIVITY
Observations:
•There street connecting railway
station and madhusudan chowk acts
as a view corridor.
•The statue in the madhusudhan
chowk is a focal point in the view
corridor.
•No visual connection between
railway station and bus stand.

View
corridor

View corridor

Statue in the madhusudhan chowk

URBAN DESIGN

Ratio of enclosure in view corridor
(6m-9m height , 21m road width
VISUAL POLLUTION

5

1

3

2

4

URBAN DESIGN

Observations:
1.Billboards of various sizes cause visual pollution by making a
disturbance to view of street.
2.In some area electric cable is causing visual pollution, it may
create accidents also. Condition of road is not good.
3.Irregular parking in the roadside reduces the visual quality of
street.
4.Billboards in front of railway station also create visual
disturbance.
5.Advertisements in building walls also cause visual pollution.
Condition of road is not good.
6.Informal shops in the beginning of road to bus stand from
railway station also reduce visual quality of street.
Requirement:
•Defined parking area.
•Good condition road
•Control over bill boards and advertisements.
•Removal of big billboards over buildings.
•Proper maintenance of electric cables.
•New location for informal shops
STREETSCAPE
Observations:
•Signage: signage boards are absent (no signage board from
railway station to bus stand).
•Side walks: well designed pedestrian pathways are absent.
•Cross walks: cross walks are absent, people move
randomly, create chaos in the junction.
Requirement:
• There should be a proper designed signage. As a general
rule, it is suggested that the letter height should be at least
1% of the distance at which the message will usually be
read boards showing connection to each roads.

•Enhance the pedestrian linkage by:
1.Ensuring the continuity of sidewalks, lighting and paving
material.2Providing adequate width for both pedestrians and
Areas required signage
bicyclists.3Maintaining and enhancing accessibility for
boards
differently-abled individuals.
Areas required cross walks •Proper cross walks should be marked.
Areas required continues
pedestrian connectivity

1

URBAN DESIGN
STREETSCAPE

Observations:
•Screenings: Screening provides a visual buffer between
pedestrian and vehicular spaces and separation of public
areas from parking and circulation areas, as well as grade
Areas required landscape
changes. There are no such screenings present.
in road divider
•Landscape : trees and plants are less.
Area lacking street lighting
•utility: no trash receptacles, people drop plastic waste on
road side.
Areas that can be treated with
•Street lighting is not adequate in road connecting railway
vegetation
station to bus stand.
Requirement:
•There should be screenings between public parking
area and the street.
•The road divider can be treated with some small plants.
•Trash receptacles are required.
•There should be adequate street lighting

1

URBAN DESIGN
PROPOSALS
Issue identification & broad proposals
LANDUSE
Proposed Truck parking = 862 sq m on the land
available near informal sector. The area can
accommodate 15 trucks.
Area for 1 truck = 50 sqm . Therefore for 15 trucks = 750
sqm
Expansion of existing parking near commercial area =
2681 sqm
No. of cars parked = 50 , No. of Two wheelers = 400, No
of autos = 15
Proposal = 500 two wheelers, 60 cars and 20 autos
Area = (500* 2.5) + (60 * 15) + (20 *8) = 2310 sq m
Accquired railway land = 4700 sq m
Relocation of informal shops = 1000 sq m
Formal Commercial = 430 sq m
Plaza = 2200 sq m
Feeder Paking = 850 sq m
Toilets = 220 sq m

Effective road width of bus stand strech is 4.5 m
Encroached area = 1.5m
Encroachments removed and converted to pedestrian
pathway

PROPOSALS
PROPOSALS

LANDUSE
COMPARISON OF EXISTING AND
PROPOSED LANDUSE
50000
45000
40000
35000
30000
25000
20000
Existing
15000

Proposed

10000
5000
0

PROPOSALS
TRAFFIC MANAGEMENT PLAN
•

The vehicular movement
along the stretch of the
road is guided by the main
principle to decongest the
intersection in front of the
railway station and put the
alternate
entrance
to
maximum use.

•

The introduction of a
feeder service is looked
upon as a viable option to
make the link between the
railway station and the bus
stand more accessible. The
link being almost 400 m
long, cannot be accessed
easily by pedestrians.

•

The entry and exit for the
feeder service is separated
from the main entrance and
exit

Traffic Management Plan Indicating The Movement Of Vehicular Traffic

PROPOSALS
TRAFFIC MANAGEMENT PLAN
•

The
pedestrian
movement which was
otherwise chaotic at the
intersection is improved
by
provision
of
pavements along one
side of stretch 1 and
along both the sides of
stretch 2.

•

The pavement along
stretch 1 is integrated
with facilities such as
eateries,
fruit
and
vegetable
vendors, groceries, etc
and a plaza which
doubles
as
a
recreational zone.

Traffic Management Plan Indicating The Movement Of Pedestrian Traffic

PROPOSALS
PARKING MANAGEMENT (Inside Railway Station)
•

As observed with the help of the survey
data, most of the respondents use the station
almost once in every month and 28 % of the total
users surveyed use the station on a daily
basis, the reasons for the regular trips being work
and
other
personal
(including
family
engagements).

•

Almost 40% respondents use auto rickshaw to
reach the station indicating importance of this
particular mode. A large portion of the
respondents feel that the bus stand and auto
stands are too far to travel by foot.

•

The safety along the walkways to the same
mentioned facilities is a major concern here.

•

Hence as observed, the major concerns to be
looked upon here are:
• Parking spaces for cars and auto
rickshaws, and
• The unorganized Drop off/Drop in system
for passengers who are coming/leaving
to/from the station.
• Inconvenient accessibility to public modes
of travel.

PROPOSALS

Views of the Existing Parking and Circulation at the Railway Station
• The above illustrates the haphazard parking of the auto
rickshaws, taxis and private vehicles.
• Also there is no specific pathway demarcated for Pedestrians
especially with luggage. The station can be accessed by two entry/exit
gates which serve as a major reason for this unorganized vehicular
and pedestrian circulation.
• Absence of Facilitation centres and Information kiosks lead to
probable misguidance in terms of direction and choice of facility to
be availed by the people while coming out of the Rourkela railway
station.
• Since the maximum portion of the vehicular inlet/outlet happen at the
main entrance of the railway station, this contrasting distribution
leads to more chances of accidents in that zone.
PARKING MANAGEMENT (Inside Railway Station)
• As observed, the major concerns to be
facilitated here are
• Parking spaces for cars and
auto rickshaws, and
• An organized Drop off bay for
passengers who are coming to
the station.

The additional development strategies
and proposals will include the following:
• Auto Rickshaw Pre paid Stand
• Tourist information Facilitation
Centre
• Taxis prepaid counter
• Bus interchange facilitation
Centre
• Feeder pickup/drop point and
feeder user shaded seating

Plan of the Proposed Parking, Zoning and Circulation at the Railway
Station

PROPOSALS

1
.
2
.
3
.
4
.
5
.
6
.
7
.

Parking for 24 four wheelers – 10 m wide road
Parking for 56 four wheelers – 10 m wide road
Parking for 170 two wheelers – 5 m wide road
Parking for 170 two wheelers – 5 m wide road
Parking for 170 two wheelers – 5 m wide road
Parking for 50 autos and 80 cycles – 7 m wide road
Feeder Parking for 30-35 feeders and prepaid taxi booth

Contenu connexe

Tendances

Inter state bus terminal - Litrature study
Inter state bus terminal - Litrature studyInter state bus terminal - Litrature study
Inter state bus terminal - Litrature studyAkshey Sharma
 
Bus terminal+commercial complex+isbt+india ppt show
Bus terminal+commercial complex+isbt+india ppt showBus terminal+commercial complex+isbt+india ppt show
Bus terminal+commercial complex+isbt+india ppt showkiranightly
 
Ved tranzcube plaza, Vadodara
Ved tranzcube plaza, VadodaraVed tranzcube plaza, Vadodara
Ved tranzcube plaza, VadodaraPalak Khandelwal
 
Multi-modal transportation, dissertation brief
Multi-modal transportation, dissertation brief Multi-modal transportation, dissertation brief
Multi-modal transportation, dissertation brief Piyush KumAr
 
Literature study- koyembedu chennai
Literature study- koyembedu chennaiLiterature study- koyembedu chennai
Literature study- koyembedu chennaiAbinaya Ramakrishnan
 
Navi mumbai development
Navi mumbai developmentNavi mumbai development
Navi mumbai developmentsmritigupta24
 
UJJAIN DEVELOPMENT PLAN (Transportation Proposals)
UJJAIN DEVELOPMENT PLAN (Transportation Proposals) UJJAIN DEVELOPMENT PLAN (Transportation Proposals)
UJJAIN DEVELOPMENT PLAN (Transportation Proposals) shrikrishna kesharwani
 
Data Collection-Standards- Bus Terminal- Multi-Modal Hub
Data Collection-Standards- Bus Terminal- Multi-Modal HubData Collection-Standards- Bus Terminal- Multi-Modal Hub
Data Collection-Standards- Bus Terminal- Multi-Modal Hubhrudai11
 
Transit Oriented Development - TOD - Human Settlement Planning - Architecture
Transit Oriented Development - TOD - Human Settlement Planning - Architecture Transit Oriented Development - TOD - Human Settlement Planning - Architecture
Transit Oriented Development - TOD - Human Settlement Planning - Architecture YuktaYogeesh1
 
Neighbourhood Concept
Neighbourhood ConceptNeighbourhood Concept
Neighbourhood ConceptAnshul Abbasi
 
Isbt, kashmiri gate, delhi_a case study
Isbt, kashmiri gate, delhi_a case studyIsbt, kashmiri gate, delhi_a case study
Isbt, kashmiri gate, delhi_a case studyMridul Bhandari
 
Integrated multi modal transportation system
Integrated multi modal transportation system Integrated multi modal transportation system
Integrated multi modal transportation system Aditya Gupta
 
Aim, objective and methodology of transit oriented development (TOD)
Aim, objective and methodology of transit oriented development (TOD)Aim, objective and methodology of transit oriented development (TOD)
Aim, objective and methodology of transit oriented development (TOD)padamatikona swapnika
 
Kashmere gate isbt
Kashmere gate isbtKashmere gate isbt
Kashmere gate isbtSneha Lata
 
cognitive, behaviour and activity mapping
cognitive, behaviour and activity mappingcognitive, behaviour and activity mapping
cognitive, behaviour and activity mappingpadamatikona swapnika
 
Waterfront Development Principles
Waterfront Development PrinciplesWaterfront Development Principles
Waterfront Development PrinciplesNicholas Socrates
 
Bus Terminal Pre Design Study.pdf
Bus Terminal Pre Design Study.pdfBus Terminal Pre Design Study.pdf
Bus Terminal Pre Design Study.pdfKeerthireddyNussi
 
Mattuthavani bus terminal case study
Mattuthavani bus terminal  case studyMattuthavani bus terminal  case study
Mattuthavani bus terminal case studyAbinaya Ramakrishnan
 

Tendances (20)

Inter state bus terminal - Litrature study
Inter state bus terminal - Litrature studyInter state bus terminal - Litrature study
Inter state bus terminal - Litrature study
 
Isbt kashmere gate 2
Isbt kashmere gate 2Isbt kashmere gate 2
Isbt kashmere gate 2
 
Bus terminal+commercial complex+isbt+india ppt show
Bus terminal+commercial complex+isbt+india ppt showBus terminal+commercial complex+isbt+india ppt show
Bus terminal+commercial complex+isbt+india ppt show
 
Ved tranzcube plaza, Vadodara
Ved tranzcube plaza, VadodaraVed tranzcube plaza, Vadodara
Ved tranzcube plaza, Vadodara
 
Multi-modal transportation, dissertation brief
Multi-modal transportation, dissertation brief Multi-modal transportation, dissertation brief
Multi-modal transportation, dissertation brief
 
Literature study- koyembedu chennai
Literature study- koyembedu chennaiLiterature study- koyembedu chennai
Literature study- koyembedu chennai
 
Navi mumbai development
Navi mumbai developmentNavi mumbai development
Navi mumbai development
 
UJJAIN DEVELOPMENT PLAN (Transportation Proposals)
UJJAIN DEVELOPMENT PLAN (Transportation Proposals) UJJAIN DEVELOPMENT PLAN (Transportation Proposals)
UJJAIN DEVELOPMENT PLAN (Transportation Proposals)
 
Data Collection-Standards- Bus Terminal- Multi-Modal Hub
Data Collection-Standards- Bus Terminal- Multi-Modal HubData Collection-Standards- Bus Terminal- Multi-Modal Hub
Data Collection-Standards- Bus Terminal- Multi-Modal Hub
 
Transit Oriented Development - TOD - Human Settlement Planning - Architecture
Transit Oriented Development - TOD - Human Settlement Planning - Architecture Transit Oriented Development - TOD - Human Settlement Planning - Architecture
Transit Oriented Development - TOD - Human Settlement Planning - Architecture
 
Neighbourhood Concept
Neighbourhood ConceptNeighbourhood Concept
Neighbourhood Concept
 
Isbt, kashmiri gate, delhi_a case study
Isbt, kashmiri gate, delhi_a case studyIsbt, kashmiri gate, delhi_a case study
Isbt, kashmiri gate, delhi_a case study
 
Integrated multi modal transportation system
Integrated multi modal transportation system Integrated multi modal transportation system
Integrated multi modal transportation system
 
Aim, objective and methodology of transit oriented development (TOD)
Aim, objective and methodology of transit oriented development (TOD)Aim, objective and methodology of transit oriented development (TOD)
Aim, objective and methodology of transit oriented development (TOD)
 
Kashmere gate isbt
Kashmere gate isbtKashmere gate isbt
Kashmere gate isbt
 
metro station planning ar.ravi sankar alumni(auce architecture)
metro station planning ar.ravi sankar alumni(auce architecture)metro station planning ar.ravi sankar alumni(auce architecture)
metro station planning ar.ravi sankar alumni(auce architecture)
 
cognitive, behaviour and activity mapping
cognitive, behaviour and activity mappingcognitive, behaviour and activity mapping
cognitive, behaviour and activity mapping
 
Waterfront Development Principles
Waterfront Development PrinciplesWaterfront Development Principles
Waterfront Development Principles
 
Bus Terminal Pre Design Study.pdf
Bus Terminal Pre Design Study.pdfBus Terminal Pre Design Study.pdf
Bus Terminal Pre Design Study.pdf
 
Mattuthavani bus terminal case study
Mattuthavani bus terminal  case studyMattuthavani bus terminal  case study
Mattuthavani bus terminal case study
 

Similaire à Planning for a Multi-Modal Transportation Hub at Rourkela

Planning principles of Bus Terminals and Logistics Parks
Planning principles of Bus Terminals and Logistics ParksPlanning principles of Bus Terminals and Logistics Parks
Planning principles of Bus Terminals and Logistics ParksYajush Sonar
 
Tod mpd-road map-08nov09
Tod mpd-road map-08nov09Tod mpd-road map-08nov09
Tod mpd-road map-08nov09Paromita Roy
 
DESIGN STANDARDS FOR PLANNING A BUS TERMINUS
DESIGN STANDARDS FOR PLANNING A BUS TERMINUSDESIGN STANDARDS FOR PLANNING A BUS TERMINUS
DESIGN STANDARDS FOR PLANNING A BUS TERMINUSSruthiTummalapalli
 
Understanding Transit Hubs - Karpagam Architecture.pdf
Understanding Transit Hubs - Karpagam Architecture.pdfUnderstanding Transit Hubs - Karpagam Architecture.pdf
Understanding Transit Hubs - Karpagam Architecture.pdfKarpagam Architecture
 
Possibilities For Bus Lane System
Possibilities For Bus Lane SystemPossibilities For Bus Lane System
Possibilities For Bus Lane SystemNaveen Chandra
 
chapter-4 Railway Station.pptx
chapter-4   Railway Station.pptxchapter-4   Railway Station.pptx
chapter-4 Railway Station.pptxMamushLeta
 
A STUDY ON PROVISION OF PARK AND RIDE FACILITY FOR SMART CITY BELAGAVI
A STUDY ON PROVISION OF PARK AND RIDE FACILITY FOR SMART CITY BELAGAVIA STUDY ON PROVISION OF PARK AND RIDE FACILITY FOR SMART CITY BELAGAVI
A STUDY ON PROVISION OF PARK AND RIDE FACILITY FOR SMART CITY BELAGAVIIRJET Journal
 
Basics of transportation planning
Basics of transportation planningBasics of transportation planning
Basics of transportation planningDhwani Shah
 
Planning for system of transportation
Planning for system of transportationPlanning for system of transportation
Planning for system of transportationKU Leuven
 

Similaire à Planning for a Multi-Modal Transportation Hub at Rourkela (20)

Planning principles of Bus Terminals and Logistics Parks
Planning principles of Bus Terminals and Logistics ParksPlanning principles of Bus Terminals and Logistics Parks
Planning principles of Bus Terminals and Logistics Parks
 
Transit oriented development
Transit oriented developmentTransit oriented development
Transit oriented development
 
Tod mpd-road map-08nov09
Tod mpd-road map-08nov09Tod mpd-road map-08nov09
Tod mpd-road map-08nov09
 
DESIGN STANDARDS FOR PLANNING A BUS TERMINUS
DESIGN STANDARDS FOR PLANNING A BUS TERMINUSDESIGN STANDARDS FOR PLANNING A BUS TERMINUS
DESIGN STANDARDS FOR PLANNING A BUS TERMINUS
 
SEM 1 PRESENTATION
SEM 1 PRESENTATIONSEM 1 PRESENTATION
SEM 1 PRESENTATION
 
Mobility or Accessibility?
Mobility or Accessibility?Mobility or Accessibility?
Mobility or Accessibility?
 
Addressing Safety Through Design for Dindoshi Terminal (Draft)
Addressing Safety Through Design for Dindoshi Terminal (Draft)Addressing Safety Through Design for Dindoshi Terminal (Draft)
Addressing Safety Through Design for Dindoshi Terminal (Draft)
 
Understanding Transit Hubs - Karpagam Architecture.pdf
Understanding Transit Hubs - Karpagam Architecture.pdfUnderstanding Transit Hubs - Karpagam Architecture.pdf
Understanding Transit Hubs - Karpagam Architecture.pdf
 
Catalyzing the New Mobility in Cities
Catalyzing the New Mobility in CitiesCatalyzing the New Mobility in Cities
Catalyzing the New Mobility in Cities
 
Possibilities For Bus Lane System
Possibilities For Bus Lane SystemPossibilities For Bus Lane System
Possibilities For Bus Lane System
 
chapter-4 Railway Station.pptx
chapter-4   Railway Station.pptxchapter-4   Railway Station.pptx
chapter-4 Railway Station.pptx
 
A STUDY ON PROVISION OF PARK AND RIDE FACILITY FOR SMART CITY BELAGAVI
A STUDY ON PROVISION OF PARK AND RIDE FACILITY FOR SMART CITY BELAGAVIA STUDY ON PROVISION OF PARK AND RIDE FACILITY FOR SMART CITY BELAGAVI
A STUDY ON PROVISION OF PARK AND RIDE FACILITY FOR SMART CITY BELAGAVI
 
Basics of transportation planning
Basics of transportation planningBasics of transportation planning
Basics of transportation planning
 
Planning for system of transportation
Planning for system of transportationPlanning for system of transportation
Planning for system of transportation
 
SITCE_v10
SITCE_v10SITCE_v10
SITCE_v10
 
BUS STOPS
BUS STOPSBUS STOPS
BUS STOPS
 
Transforming the Urban Space through TOD: The 3V Approach
Transforming the Urban Space through TOD: The 3V ApproachTransforming the Urban Space through TOD: The 3V Approach
Transforming the Urban Space through TOD: The 3V Approach
 
Settlement
Settlement Settlement
Settlement
 
Unit 4_1.pptx
Unit 4_1.pptxUnit 4_1.pptx
Unit 4_1.pptx
 
Upl2015 term project sample
Upl2015 term project sampleUpl2015 term project sample
Upl2015 term project sample
 

Plus de Maitreyi Yellapragada

Plus de Maitreyi Yellapragada (6)

Architecture in Hot and humid climate
Architecture in Hot and humid climateArchitecture in Hot and humid climate
Architecture in Hot and humid climate
 
Earth air tunnels
Earth air tunnelsEarth air tunnels
Earth air tunnels
 
Landuse Mapping
Landuse Mapping Landuse Mapping
Landuse Mapping
 
Critical Analysis of the Planning scenario in Hyderabad City
Critical Analysis of the Planning scenario in Hyderabad CityCritical Analysis of the Planning scenario in Hyderabad City
Critical Analysis of the Planning scenario in Hyderabad City
 
Primacystudies andhra pradesh
Primacystudies andhra pradeshPrimacystudies andhra pradesh
Primacystudies andhra pradesh
 
Gender inclusive planning
Gender inclusive planningGender inclusive planning
Gender inclusive planning
 

Dernier

VIP Russian Call Girls in Saharanpur Deepika 8250192130 Independent Escort Se...
VIP Russian Call Girls in Saharanpur Deepika 8250192130 Independent Escort Se...VIP Russian Call Girls in Saharanpur Deepika 8250192130 Independent Escort Se...
VIP Russian Call Girls in Saharanpur Deepika 8250192130 Independent Escort Se...Suhani Kapoor
 
WAEC Carpentry and Joinery Past Questions
WAEC Carpentry and Joinery Past QuestionsWAEC Carpentry and Joinery Past Questions
WAEC Carpentry and Joinery Past QuestionsCharles Obaleagbon
 
Recommendable # 971589162217 # philippine Young Call Girls in Dubai By Marina...
Recommendable # 971589162217 # philippine Young Call Girls in Dubai By Marina...Recommendable # 971589162217 # philippine Young Call Girls in Dubai By Marina...
Recommendable # 971589162217 # philippine Young Call Girls in Dubai By Marina...home
 
VIP Call Girls Bhiwandi Ananya 8250192130 Independent Escort Service Bhiwandi
VIP Call Girls Bhiwandi Ananya 8250192130 Independent Escort Service BhiwandiVIP Call Girls Bhiwandi Ananya 8250192130 Independent Escort Service Bhiwandi
VIP Call Girls Bhiwandi Ananya 8250192130 Independent Escort Service BhiwandiSuhani Kapoor
 
Design Inspiration for College by Slidesgo.pptx
Design Inspiration for College by Slidesgo.pptxDesign Inspiration for College by Slidesgo.pptx
Design Inspiration for College by Slidesgo.pptxTusharBahuguna2
 
Peaches App development presentation deck
Peaches App development presentation deckPeaches App development presentation deck
Peaches App development presentation decktbatkhuu1
 
VIP Kolkata Call Girl Gariahat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Gariahat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Gariahat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Gariahat 👉 8250192130 Available With Roomdivyansh0kumar0
 
AMBER GRAIN EMBROIDERY | Growing folklore elements | Root-based materials, w...
AMBER GRAIN EMBROIDERY | Growing folklore elements |  Root-based materials, w...AMBER GRAIN EMBROIDERY | Growing folklore elements |  Root-based materials, w...
AMBER GRAIN EMBROIDERY | Growing folklore elements | Root-based materials, w...BarusRa
 
CALL ON ➥8923113531 🔝Call Girls Aminabad Lucknow best Night Fun service
CALL ON ➥8923113531 🔝Call Girls Aminabad Lucknow best Night Fun serviceCALL ON ➥8923113531 🔝Call Girls Aminabad Lucknow best Night Fun service
CALL ON ➥8923113531 🔝Call Girls Aminabad Lucknow best Night Fun serviceanilsa9823
 
Best VIP Call Girls Noida Sector 44 Call Me: 8448380779
Best VIP Call Girls Noida Sector 44 Call Me: 8448380779Best VIP Call Girls Noida Sector 44 Call Me: 8448380779
Best VIP Call Girls Noida Sector 44 Call Me: 8448380779Delhi Call girls
 
Chapter 19_DDA_TOD Policy_First Draft 2012.pdf
Chapter 19_DDA_TOD Policy_First Draft 2012.pdfChapter 19_DDA_TOD Policy_First Draft 2012.pdf
Chapter 19_DDA_TOD Policy_First Draft 2012.pdfParomita Roy
 
VIP College Call Girls Gorakhpur Bhavna 8250192130 Independent Escort Service...
VIP College Call Girls Gorakhpur Bhavna 8250192130 Independent Escort Service...VIP College Call Girls Gorakhpur Bhavna 8250192130 Independent Escort Service...
VIP College Call Girls Gorakhpur Bhavna 8250192130 Independent Escort Service...Suhani Kapoor
 
SD_The MATATAG Curriculum Training Design.pptx
SD_The MATATAG Curriculum Training Design.pptxSD_The MATATAG Curriculum Training Design.pptx
SD_The MATATAG Curriculum Training Design.pptxjanettecruzeiro1
 
Petrosains Drama Competition (PSDC).pptx
Petrosains Drama Competition (PSDC).pptxPetrosains Drama Competition (PSDC).pptx
Petrosains Drama Competition (PSDC).pptxIgnatiusAbrahamBalin
 
The_Canvas_of_Creative_Mastery_Newsletter_April_2024_Version.pdf
The_Canvas_of_Creative_Mastery_Newsletter_April_2024_Version.pdfThe_Canvas_of_Creative_Mastery_Newsletter_April_2024_Version.pdf
The_Canvas_of_Creative_Mastery_Newsletter_April_2024_Version.pdfAmirYakdi
 
Stark Industries Marketing Plan (1).pptx
Stark Industries Marketing Plan (1).pptxStark Industries Marketing Plan (1).pptx
Stark Industries Marketing Plan (1).pptxjeswinjees
 

Dernier (20)

VIP Russian Call Girls in Saharanpur Deepika 8250192130 Independent Escort Se...
VIP Russian Call Girls in Saharanpur Deepika 8250192130 Independent Escort Se...VIP Russian Call Girls in Saharanpur Deepika 8250192130 Independent Escort Se...
VIP Russian Call Girls in Saharanpur Deepika 8250192130 Independent Escort Se...
 
WAEC Carpentry and Joinery Past Questions
WAEC Carpentry and Joinery Past QuestionsWAEC Carpentry and Joinery Past Questions
WAEC Carpentry and Joinery Past Questions
 
Recommendable # 971589162217 # philippine Young Call Girls in Dubai By Marina...
Recommendable # 971589162217 # philippine Young Call Girls in Dubai By Marina...Recommendable # 971589162217 # philippine Young Call Girls in Dubai By Marina...
Recommendable # 971589162217 # philippine Young Call Girls in Dubai By Marina...
 
VIP Call Girls Bhiwandi Ananya 8250192130 Independent Escort Service Bhiwandi
VIP Call Girls Bhiwandi Ananya 8250192130 Independent Escort Service BhiwandiVIP Call Girls Bhiwandi Ananya 8250192130 Independent Escort Service Bhiwandi
VIP Call Girls Bhiwandi Ananya 8250192130 Independent Escort Service Bhiwandi
 
Design Inspiration for College by Slidesgo.pptx
Design Inspiration for College by Slidesgo.pptxDesign Inspiration for College by Slidesgo.pptx
Design Inspiration for College by Slidesgo.pptx
 
Peaches App development presentation deck
Peaches App development presentation deckPeaches App development presentation deck
Peaches App development presentation deck
 
VIP Kolkata Call Girl Gariahat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Gariahat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Gariahat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Gariahat 👉 8250192130 Available With Room
 
AMBER GRAIN EMBROIDERY | Growing folklore elements | Root-based materials, w...
AMBER GRAIN EMBROIDERY | Growing folklore elements |  Root-based materials, w...AMBER GRAIN EMBROIDERY | Growing folklore elements |  Root-based materials, w...
AMBER GRAIN EMBROIDERY | Growing folklore elements | Root-based materials, w...
 
CALL ON ➥8923113531 🔝Call Girls Aminabad Lucknow best Night Fun service
CALL ON ➥8923113531 🔝Call Girls Aminabad Lucknow best Night Fun serviceCALL ON ➥8923113531 🔝Call Girls Aminabad Lucknow best Night Fun service
CALL ON ➥8923113531 🔝Call Girls Aminabad Lucknow best Night Fun service
 
escort service sasti (*~Call Girls in Prasad Nagar Metro❤️9953056974
escort service sasti (*~Call Girls in Prasad Nagar Metro❤️9953056974escort service sasti (*~Call Girls in Prasad Nagar Metro❤️9953056974
escort service sasti (*~Call Girls in Prasad Nagar Metro❤️9953056974
 
Best VIP Call Girls Noida Sector 44 Call Me: 8448380779
Best VIP Call Girls Noida Sector 44 Call Me: 8448380779Best VIP Call Girls Noida Sector 44 Call Me: 8448380779
Best VIP Call Girls Noida Sector 44 Call Me: 8448380779
 
Chapter 19_DDA_TOD Policy_First Draft 2012.pdf
Chapter 19_DDA_TOD Policy_First Draft 2012.pdfChapter 19_DDA_TOD Policy_First Draft 2012.pdf
Chapter 19_DDA_TOD Policy_First Draft 2012.pdf
 
young call girls in Pandav nagar 🔝 9953056974 🔝 Delhi escort Service
young call girls in Pandav nagar 🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Pandav nagar 🔝 9953056974 🔝 Delhi escort Service
young call girls in Pandav nagar 🔝 9953056974 🔝 Delhi escort Service
 
Call Girls Service Mukherjee Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SER...
Call Girls Service Mukherjee Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SER...Call Girls Service Mukherjee Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SER...
Call Girls Service Mukherjee Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SER...
 
VIP College Call Girls Gorakhpur Bhavna 8250192130 Independent Escort Service...
VIP College Call Girls Gorakhpur Bhavna 8250192130 Independent Escort Service...VIP College Call Girls Gorakhpur Bhavna 8250192130 Independent Escort Service...
VIP College Call Girls Gorakhpur Bhavna 8250192130 Independent Escort Service...
 
SD_The MATATAG Curriculum Training Design.pptx
SD_The MATATAG Curriculum Training Design.pptxSD_The MATATAG Curriculum Training Design.pptx
SD_The MATATAG Curriculum Training Design.pptx
 
young call girls in Vivek Vihar🔝 9953056974 🔝 Delhi escort Service
young call girls in Vivek Vihar🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Vivek Vihar🔝 9953056974 🔝 Delhi escort Service
young call girls in Vivek Vihar🔝 9953056974 🔝 Delhi escort Service
 
Petrosains Drama Competition (PSDC).pptx
Petrosains Drama Competition (PSDC).pptxPetrosains Drama Competition (PSDC).pptx
Petrosains Drama Competition (PSDC).pptx
 
The_Canvas_of_Creative_Mastery_Newsletter_April_2024_Version.pdf
The_Canvas_of_Creative_Mastery_Newsletter_April_2024_Version.pdfThe_Canvas_of_Creative_Mastery_Newsletter_April_2024_Version.pdf
The_Canvas_of_Creative_Mastery_Newsletter_April_2024_Version.pdf
 
Stark Industries Marketing Plan (1).pptx
Stark Industries Marketing Plan (1).pptxStark Industries Marketing Plan (1).pptx
Stark Industries Marketing Plan (1).pptx
 

Planning for a Multi-Modal Transportation Hub at Rourkela

  • 1. MULTI MODAL INTERCHANGE HUB at Rourkela… Action Area Plan : TRANSPORTATION
  • 2. A I M : To promote the utility of the area under consideration for the purpose of functioning as a multimodal interchange hub for transit oriented development of the area. OBJECTIVES: The major objectives of the study are:  To strengthen the link between various modes of transport present in close proximity , thus achieving the ultimate goal of a multi-modal interchange that combines various modes and their associated functions in order to achieve a better degree of transport network.  Encourage integrated development of traffic movement & networks, transportation facilities & their linkages and associated functions/ activities prompting landuse modifications to suit the context of the development. MULTIMODAL INTERCHANGE HUB: A PROLOGUE . . . SCOPE:  Development of transit facilities as per user rate, multiple mode linking and passenger comfort and affordability.  Holistic approach to commercial bases and their delineation along avenues of relevantly related freight movement and logistics.  Promotion of single landuse zones to facilitate correlativity between the various activities that are related to transport and traffic networking. LIMITATIONS:  The area under consideration is the stretch of road between Madhusudan Chowk and Rourkela railway station’s main entrance (longitudinal) and the stretch of road from the other entrance of the Rourkela railway station to the bus depot (traversal) – as because this part experiences maximum traffic congestion and which is to be addressed to promote better transport network for the area. MULTI MODAL INTERCHANGE : Aim, Need, Methodology, Scope and
  • 3. Need: SURVEYS & ANALYSIS The need to develop the area under consideration was defined by three basic necessities to be addressed: VISUAL SURVEY    MULTIMODAL INTERCHANGE HUB: A PROLOGUE . . . The LANDUSE ANALYSIS location:  The multiple modes of transport concentrated within USER PERCEPTION SURVEY the same area;  CONNECTIVITY ANALYSIS of the daily market in the vicinity. Strategic location INTERSECTION VOLUME SURVEY The trip generation factor: FACILITIES ANALYSIS  The high O-D data generated to and fro in this area – due to location of varied typology including the huge base of hospitality sector and commercial sector;  Also location of the major railway station for the city – DESIGNING major source for translocation of passengers and goods – major issue: traffic congestion and mismanagement. ACCESS FOR FOOTPATHS DISABLED The importance of Rourkela on the industrial and commercial scenario of India:  Steel industry based development, major INTER. V/C RATIOS transshipment ofVOLUME and materials – both in goods processed and unprocessed states – requires railway services and railway stations in the vicinity helps curb STREETSCAPE transportation charges agglutinating to the production cost / market price. Also passengers consists majorly of entrepreneurs, business based STREET DESIGN companies and individuals.  The Bus stand may act as a major source for easy movement of labor and can prompt affordable rates for travel for the workforce that travels long distances daily – to and fro – within or outside the urban M O D I F I C A T I O N S I N . . . agglomeration. PLANNING PEDESTRIAN MGMT. TRANSPORT VEHICULAR MGMT. SAFETY/ SECURITY COMM. / KIOSKS DRAINAGE STREET LIGHTING SOCIAL INFRA. PHY. INFRA. FREIGHT PARKING CAFETERIA FACILITIES TOILETS WAITING ROOM LANDUSE MULTI MODAL INTERCHANGE : Aim, Need ,Methodology, Scope and
  • 4. INTRODUCTION A Multi modal Interchange hub is one in which co-ordination and integration of different modes of transport takes place to decongest road, reduce journey time, enhance environment, provide greater convenience for commuters, efficiency and cost effectiveness. The act of changing between modes – The place where one changes the modes – A purpose built facility to improve interchange quality – Interchange Interchange Zone Interchange facility Source: The Intermodal Transport Interchange For London: Best Practice Guidelines MULTI MODAL INTERCHANGE :
  • 5. DECISION SPACES Areas where passenger decisions take priority. Examples include decision points such as entrances, ticket offices or corridor junctions. At these locations there should be good sight lines/clear signing or transport information. There should be no nonessential physical infrastructure or visual distractions such as advertising/ retail or other land uses that would serve to distract or confuse passengers. INTRODUCTION OPPORTUNITY SPACES Opportunity spaces include those areas of the interchange zone outside the core corridors of movement or decisions. They can accommodate cafés, retail entrances, retail display, seating or landscaping. Street furniture, advertising or other fixed or temporary infrastructure located in these zones must be managed so as not to protrude or interfere with the requirements of decision or movement spaces in adjacent areas. MOVEMENT SPACES Movement spaces connect decision spaces. Typically these include corridors and paths specially reserved for passenger movement and connections to/ from/ between transport modes or the surrounding area. These spaces should provide clear, unobstructed routes matched to desire lines. Street furniture, plantings, advertising, information displays, retail boards or any other fixed items should not protrude into these zones but may be located adjacent to them. MULTI MODAL INTERCHANGE :
  • 6. INTRODUCTION Example of an Multi modal Interchange Four interchange themes which should be considered at transport hubs: Efficiency: moving sustainability Operations, around, Usability: Accessibility, safety and preventing accidents, personal security, protection Understanding: Legibility, permeability, way-finding, information Quality: Perception, design, spaces, sense of place MULTI MODAL INTERCHANGE :
  • 7. Access to Transit Station by Non-Motorized Transport MULTI MODAL TRANSPORT SYSTEM, DELHI INFERENCES 1. Pedestrian access - Provisions for pedestrians and their safe movement are an essential access consideration. - Direct and safe approach for pedestrians • • • Pedestrian access-ways that reduce distances to bus services on the adjacent higher order bus streets. Continuous and direct footpath networks that permeate neighborhoods. Safe, convenient and/or controlled road crossing points should be provided to stops with high passenger usage. 2. Bicycle access • Can increase the service area of transit stations. • Bicycle parking facilities located to provide protection from weather, theft and conflicts with other modes. Parking areas i.e. active areas with high pedestrian activity, or under the observation of station attendants preferred. • Well Lit and designated by signages. Accessibility by Intermediate Para Transit (IPT) • • Various modes of IPT such as auto, taxi, phatphat, etc are considered as feeder modes to bring passengers from various parts of the neighborhood to the multi modal transit station. IPT zone is desirable. IPT area must be covered and seating may be provided. MULTI MODAL INTERCHANGE :
  • 8. Accessibility by Public Transport • • MULTI MODAL TRANSPORT SYSTEM, DELHI INFERENCES Bus stop design capacity for a station is based on the individual requirements for each station either as a single station, interchange station or integration point. The following designs may be used for various types of bus loading zones, depending on specific conditions: i. Recessed Bus Bay: It is used where more mixed traffics are on the road. The bus loading zone is recessed from the through traffic lane. A recessed bus bay is designed parallel to close enough to the curb so that passengers may enter and leave any door by an easy step to the curb. Upon leaving, the merging lane enables the bus an easy re-entry into the through traffic lane. ii. Parallel- to-curb Bus Bays It should have 3 mt wide lanes and an overall length of 73.2 mt. This layout for bus loading area provides the minimum roadway width but requires the longest length for a bus loading zone. The critical movement in this layout is moving into position ahead of the parked bus. This leaves the rear door of the bus offset from the platform curb by approximately 0.45 mt. iii. Sawtooth Bus Bays Sawtooth bus bays reduces the length of loading zone and therefore reduces walking distances but increases the width of the roadway. MULTI MODAL INTERCHANGE :
  • 9. Accessibility by Private Modes • • • • MULTI MODAL TRANSPORT SYSTEM, DELHI INFERENCES Parking space for car, two wheelers at the station. Entry and exit points should be at mid block. Parking aisles should be lined perpendicular to the station entrance/exit are to minimize the no. of potential conflicts between pedestrians and automobiles. Collapsible posts or signs should be used to delineate drives and pedestrian. Major pedestrian walkways should be raised 0.15 mt above the parking pavement. Right angle parking should be used because it allows better circulation, more orderly parking, and in most cases has lower average area requirement per space. Accessibility to Transit Station/Stops: Current Practices in Delhi • • “Cycle-for-Hire Scheme” Encourage people to use bicycles for short distances at Delhi University Metro station and near by areas. The charge of a bicycle on rent is Rs 10/= for 4 hours. Pedestrian way to the BRT Corridor in Delhi: To provide safe and comfortable sidewalk to access public transport. • • • • Continuity of the sidewalks. Wide and well surfaced sidewalks and is disable friendly. Sidewalks are easily negotiable by women, children, senior citizens, as the height is close to 15 cm. Width of sidewalks varies from 1.5 mt (min) to 4.5 mt (max) along the corridor. Sidewalks are well lit. Crossings are easily accessible with kerbed ramps and there is a holding area for people to want at the side and at the pedestrian refuge islands. Pedestrian path on the BRT corridor has the least permanent and temporary obstructions on the sidewalks MULTI MODAL INTERCHANGE :
  • 10. Attributes to enhance the accessibility to transit station: • • • • • MULTI MODAL TRANSIT ORIENTED DESIGN People Place: Transit station area is a place for people/commuters. Hence, it must be well used, safe, comfortable, and attractive; and need to be distinctive and offer variety, choice and fun. Streetscape Design: M2OD should promote and enrich the qualities of existing urban places at neighborhood and street level. It is important to develop streetscape design elements for each of the transport corridor by incorporating various architectural elements. Urban Form: Transit station is considered as a part of urban design and sky line. It is blended with different building forms, colors, materials, textures, forms, etc. Such areas should be integrated physically and visually with its surroundings having better access by foot, bicycles, bus, cars, metro, etc. Amenities that are stimulating, enjoyable and convenient should be offered to a wide range of possible users. Transit in Landscape: These areas should provide balance between the natural and the manmade environment and utilize each locations intrinsic resource – the climate, land form, landscape, and ecology – to maximize the experience. Design must put such built environment in proper land scape environment. Design in Flexibility: New development near and around transit station take very little time. New development needs to be flexible enough to respond to future change in use, lifestyle, and demographics. Flexibility must be evident in the use of property, public spaces, and infrastructure. Integration of any new modes with the station area requires more space for loading, unloading, transfer, integration, parking, traffic management, etc. MULTI MODAL INTERCHANGE :
  • 11. CONNECTIVITY: CITY LEVEL RAILWAY STATION BUS TERMINAL DAILY MARKET CONNECTIVITY
  • 12. NODE AND NETWORK PHYSICAL ACCESSIBILITY
  • 14. ROURKELA RAILWAY STATION ROURKELA RAILWAY STATION BUS STAND SCHEMATIC LAYOUT OF RAILWAY STATION RICKSHAWS 5- PLATFORMS 3- SIDINGS 11 TRACKS BROAD GAUGE 2 FOOT OVER BRIDGES. BOOKING OFFICE CONCOURSE CYCLE PARKING NO. OF USERS PER DAY NO. OF PASSENGER TRAINS CAR PARKING 2-WHEELER PARKING THE EXISTING SITUATION 6000 52 NO. OF GOODS TRAINS 38 MONTHLY TICKET SALE (OFF PEAK) 2 LAKHS MONTHLY TICKET SALE (PEAK) 2.45 LAKHS
  • 15. ROURKELA RAILWAY STATION FACILITY WAITING HALL (1ST CLASS) 1ST FLOOR WAITING HALL (2ND CLASS) PLATFORM 1 PAY AND USE TOILET AT BOTH ENDS OF STATION TRAIN INDICATION BOARD CONCOURSE AND PLATFORM FACILITATION CENTRE FACING CONCOURSE AND PLATFORM 1 STD BOOTH CONCOURSE AND PLATFORM 1 WATER COOLERS PLATFORM 4 & 5 TOUCH SCREEN CONCOURSE AREA RESERVATION AND REFUND COUNTERS BOOKING OFFICE ATM CONCOURSE DORMITORY 1ST FLOOR RETIRING ROOMS 1ST FLOOR CLOAK ROOM GROUND FLOOR POLICE STATION ON FRONT SIDE OF STATION POST OFFICE ON FRONT SIDE OF STATION CAFETERIA 1ST FLOOR BOOKSTALL PLATFORM 1 SNACKS SHOPS(6-7) OBSERVATIONS: •Ramps/ elevators/ lifts are not available at the station •Provision of seating is less •No provision of proper drop off bay at the entrance for arriving vehicles LOCATION ALL PLATFORMS THE EXISTING SITUATION
  • 16. FACILITY CONDITION WAITING HALL ABSENT PAY AND USE TOILET PRESENT Poorly maintained. Requirement of additional toilets for increase in demand SIGNAGES ABSENT Required FACILITATION CENTRE PRESENT PRESENT - DRINKING WATER PRESENT Unhygienic RESERVATION AND REFUND COUNTERS PRESENT Unhygienic ATM ABSENT Required CLOAK ROOM PRESENT - POLICE STATION/ POST ABSENT Unsafe Environment CAFETERIA PRESENT Sufficient BOOKSTALL PRESENT - COMMERCIAL ZONE PRESENT Meant for Hardware (Auto Spare parts etc) ROURKELA RAILWAY STATION Located in a corner. Difficult to locate STD BOOTH ROURKELA BUS STAND THE EXISTING SITUATION BUS STAND NO. OF USERS PER DAY 2000 NO. OF DAILY BUSES 300 TIMINGS 7 PM TO 10 PM 6 AM TO 10 AM (Departure) (Arrival)
  • 17. railway station PARKING 800 600 400 200 0 BICYCLE 2W CARS GOODS VEHICLES 43 877 62 3 railway station Unauthorized parking at railway station: Bicycles: 13 Two wheelers: 60 Cars: 11 (parked in wrong location despite space being available in authorized parking) Rickshaw parking: Space given for 35 rickshaws Around 20 rickshaws were observed Auto rickshaw parking: Space for 30 autos 18 autos observed Parking lot Peak timing Railway station 7:30-9 am 6:30pm-8pm Possibility rejection 2w- no 4w- yes 6-8pm no Bus stand (pvt) of THE EXISTING SITUATION Bus stand no of vehicles no of vehicles 1000 35 30 25 20 15 10 5 0 BICYCLE Bus stand 2W CARS GOODS VEHICLES 18 30 14 0
  • 18. ON-STREET PARKING Unauthorized on street parking Auto rickshaw stand THE EXISTING SITUATION •OBSERVATIONS: •Unauthorized parking along the streets is leading to congestion along the main roads •Trucks have been illegally parked near the Fakir Mohan market hence compromising on the space available to commuters.
  • 19. NO. OF AUTOS PRESENT 80 DAILY TRIPS ~ 20 FACILITY ISSUES Toilet Facility Absent Drinking Water facility Absent Shelter for Auto Drivers Absent Cleanliness Garbage Disposed along the stretch PARA – TRANSIT STAND ROURKELA RAILWAY STATION BUS STAND PARA-TRANSIT Routes taken by Autos from the Railway Station: Station Road to Sectors Station Road to Panposh Station Road to Bandamunda Station Road to Fertilizer colony Station Road to Civil township Station Road to Vedvyas Station Road to Kaswal Rajganjpur Station Road to Kwarmunda Station Road to Birmitrapur Data obtained from Primary Survey Under - Construction Para-transit Stand THE EXISTING SITUATION
  • 20. LENGTH OF ROAD WIDTH OF THE ROAD ROAD STRETCH 400 m Effective width 4.5 m to 7.5 m B A B THE EXISTING SITUATION
  • 21. NODE AND NETWORK PHYSICAL ACCESSIBILITY
  • 24. Mixed use 767 Authorized parking 3350 vacant land (railways) 17465 vacant land (Govt) 2681 Public-semi public area 5069 hospitality zone 2267 Railway station/bus station 45702 commercial Mixed use 1% 10% 1% Authorized parking 2% 11% 3% vacant land (railways) 1% 26% 14879 Informal Commercial LANDUSE vacant land (Govt) Public-semi public area hospitality zone 29% 1000 6% Railway station/bus station commercial 9% Informal Commercial Residential 9986 Informal residential 41582 Open Ground 15700 Residential 1% Informal residential Open Ground EXISTING ISSUES Presence of discordant activities such as schools and gurudwaras along the stretch Might lead to chaos due to irrelevance in terms of activities Informal market along the stretch Unorganised traffic movement and creation of bottlenecks Hospitality + Residential (Mixed Zones) present along the road leading to Panposh road Diametrically opposite to the proposed multi modal interchange concept Existing economic activities caters to auto service/ spare parts etc which is incompatible with the proposed idea Might lead to chaos due to irrelevance in terms of activities THE EXISTING SITUATION
  • 26. 45.0 40.0 35.0 30.0 25.0 20.0 15.0 10.0 5.0 0.0 FACILITY ANALYSIS : User Profile Mode used to reach station < than once /month Series1 once a/month 2 times/mont h 1-2 times/ week 5-6 times/week 5.6 38.9 16.7 11.1 45.0 40.0 35.0 30.0 25.0 20.0 15.0 10.0 5.0 0.0 % of respondents % of respondents Frequency of using the station 27.8 auto % of respondents Trip purpose 50.0 45.0 40.0 35.0 30.0 25.0 20.0 15.0 10.0 5.0 0.0 Series1 Series1 work education shopping other 38.9 5.6 11.1 44.4 USER – PERCEPTION SURVEY bus car two wheeler walk 38.9 22.2 27.8 5.6 5.6 Observations: •Most respondents use the station once every month. •Daily users amount to around 28 %. •Work and other (including family engagements) are the main reasons for making trips. •Almost 40% respondents use auto rickshaw to reach the station indicating importance of the mode. Requirement: •Parking space for cars and auto rickshaws •Drop off bay for passengers who are coming to station .
  • 27. 120.0 FACILITY ANALYSIS :Accessibility 100.0 100.0 90.0 80.0 66.7 55.6 60.0 83.3 80.0 70.0 44.4 33.3 40.0 50.0 20.0 0.0 willing to use feeder services 44.4 38.9 40.0 0.0 Buses conjested? 61.1 55.6 60.0 Do you think bus /auto stops are too far? 30.0 16.7 20.0 10.0 yes % no% 0.0 parking enough? 120.0 Direct entrance from road More no. of entrances to to platform station 100.0 100.0 88.9 80.0 60.0 yes % 72.2 55.6 50.0 50.0 44.4 40.0 27.8 11.1 20.0 0.0 0.0 Do you prefer surface walkways over subway? Are the walkways safe?` Do you want escalator? yes % Do you want ramp? travelator necessary? no% USER – PERCEPTION SURVEY no% Observations: •All respondents willing to opt for feeder services •Almost 2/3rd of the respondents feel that bus/auto stops are too far from the station . •An overwhelming majority in favor of provision of ramps and escalators at the station. •Safety of walkways a major concern. Requirements: •Feeder services •Accessible interchange facilities •Ramps/escalators for easy barrier free access •Well lit secure walkways
  • 28. 100.0 88.9 90.0 80.0 77.8 72.2 FACILITY ANALYSIS : Facilities 77.8 70.0 Recreational facilities desired 60.0 120 50.0 27.8 30.0 22.2 100 22.2 20.0 11.1 10.0 0.0 Integrated ticket system ticket vending machines? yes % internet booking? do you have a monthly pass? % of respondents 40.0 80 60 40 20 no% 0 90.0 80.0 70.0 60.0 50.0 40.0 30.0 20.0 10.0 0.0 83.3 77.8 Series1 61.1 50.0 50.0 38.9 22.2 waiting areas be air conditioned? 16.7 Do you use dorm Are seating areas Do you want facilities? enough? covered platform for entire length? yes % no% USER – PERCEPTION SURVEY tv magazine stands audio 100 50 44.4 Observations: •High demand for ticket vending machines. •Maximum people are using internet booking options. •Air conditioned waiting areas desired •Dorm facilities not required •More seating required for the general public Requirements: •Ticket vending machines •Internet kiosks for bookings •More seating •Recreational facilities: TV in the waiting areas •Magazine stands required.
  • 29. FACILITY ANALYSIS : Facilities Requirement of more shops yes % no% 22% 120.0 100.0 100.0 88.9 94.4 88.9 80.0 60.0 78% 40.0 44.4 38.9 20.0 0.0 Willingness to pay for extra facilities yes % no% Type of shop that you want 44% 56% Requirements: •snacks/juice bar •fruits/veg shops •books/magazine shops •medicine shops USER – PERCEPTION SURVEY 44.4 33.3
  • 30. 9 FACILITY ANALYSIS :Time 8.5 7.6 8 Observations 7 6 5.4 5.16 5 4.5 4.5 Average 3.7 4 Maximum 3 Desired 3 2 1.5 •Average present waiting time at the bus stop was found to be 5.16 minutes which is more than the desired ( 4.5 minutes) 1 0 Waiting time at autostop Waiting time at bus stop Ticketing time 20 •Average present ticketing time at railway station was found to be 4.5minutes which is more than the desired (1.5minutes) 17.5 18 16 14 12 10 10 8.5 Average 8.5 Maximum 8 5 6 4 •Average present waiting time at the auto stop was found to be 3.7minutes which is more than the desired ( 3 minutes) Desired •Average time spent walking was found to be 8.5minutes which is more than the desired (2.5minutes) and which is equal to the maximum . 2.5 2 0 Average time spent walking Average waiting time at platform USER – PERCEPTION SURVEY •Average waiting time at platform was found to be 4.5minutes which is more than the desired (5minutes) and even more than the maximum which is 10 minutes.
  • 31. IMPORTANCE SATISFACTION ANALYSIS Bus Stop 4.5 4 3.5 3 2.5 2 1.5 1 0.5 0 Interchange importance satisfaction bus stop performance frequency of bus service 6 5 4 3 2 1 0 importance satisfaction feeder service Paratransit 3.5 3 2.5 2 1.5 importance 1 satisfaction 0.5 0 paratransit stop performance frequency of auto service safety of stand distance from building USER – PERCEPTION SURVEY
  • 32. IMPORTANCE SATISFACTION ANALYSIS Railway Station 6 5 4 3 2 1 importance satisfaction 0 USER – PERCEPTION SURVEY
  • 33. 100% 90% 80% 70% 60% 50% No 40% Yes 30% 20% 10% 0% Students 100% LIG MIG 90% 80% 70% 60% 50% No 40% Yes 30% 20% 10% 0% LIG MIG APPROPRIATENESS No Yes Primary HIG Willingness to pay for extra services v/s income group Students 100% 90% 80% 70% 60% 50% 40% 30% 20% 10% 0% 100% 90% 80% 70% 60% 50% 40% 30% 20% 10% 0% HIG Willingness to have more shopping area v/s income levels USER – PERCEPTION SURVEY Class XII Graduate Willingness to use internet booking v/s level of education level No Yes <18 yrs 18-40 yrs 40-60 Willingness to use ramps v/s age group 60<
  • 34. Facilities at para transit stop importance satisfaction paratransit stop performance 1 3 frequency of auto service 2 2 1 3 safety of stand ANALYSIS IMPORTANCE SATISFACTION ANALYSIS SATISFACTIO N 5 4 3 2 IMPORTANCE distance from building 2 2 importance satisfaction 1 4 Facilities at bus stop bus stop performance 1 2 3 4 frequency of bus service 3 2 4 importance feeder service 1 satisfaction 1 4 1 4 1 5 2 3 1 3 1 4 1 4 1 5 2 4 2 3 Miscellaneous parking areas pedestrian pathways disable access level changes Surveillance Toilet facilities Cleanliness Organised areas in the interchange weather protection in interchange areas Safety 5 Observations USER – PERCEPTION SURVEY The most critical aspects which are to be taken care of - Feeder service - Parking areas - Pedestrian pathways - Disable access - Toilet facilities - Cleanliness - Weather protection Second most critical aspects -Safety of para transit stop -frequency of bus service - level changes in the railway station -Safety 1
  • 35. Facilities at railway station importance building entrances accessible location of entrances walking distance to ticket counter queuing time Queuing space No. of ticket counters Location of ticket counters Real time information Information system placement Walking distance (from ticket counter to platform) Alignment of platform and the entrance location Goods loading/unloading area on platform Safety or surveillance of platform Waiting area in platform Railway station performance satisfaction ANALYSIS IMPORTANCE SATISFACTION ANALYSIS 2 2 2 2 2 2 2 3 2 3 2 3 2 2 1 3 Second most critical aspects 2 3 2 3 2 3 2 5 -Queuing time - Queuing space – No. of ticket counters – Real time information –Information system –Waiting area in plat form 2 3 1 3 2 4 USER – PERCEPTION SURVEY Observations The most critical aspects which are to be taken care of -Goods loading and unloading area -Total railway station performance Third most critical aspects - Building entrances - location of entrances - walking distance to ticket counter - Location of ticket counters
  • 37. TRAFFIC ANALYSIS Traffic Volume Count LINK NAME PEDESTRIANS PCU V/C PAVEMEN T ENCROACHMENT OF PAVEMENT ENCROACHMEN T OF ROAD ON STREET PARKING PROMINENT MODE ALONG THE LINK Railway Station to Panposh Road, via Hotel Aastha 108 6.3% 130.8 0.12 Absent NA Very Less Very Less Two-Wheeler Railway Station to Madhusudhan Marg 456 26.6% 450.6 0.41 Absent NA Informal Sector near the ParaTransit Stand Present along the Commercial Stretch Non Specific Towards the Railway Station 586 34.1% 156.6 0.14 Absent NA Nil Nil Non Specific Towards the Bus Stand 438 25.5% 180 0.16 Absent NA Informal shops situated along the stretch at certain locations Truck Parking in front of Fakir Mohan market. Otherwise negligible Pedestrians Cyclists Along Alternative Entrance/ Exit 126 7.5% 51.6 - Absent NA Very Less Nil Pedestrians Two Wheelers TOTAL 1714 918 -
  • 38. TRAFFIC ANALYSIS Traffic Volume Count -Traffic Count at Railway Station is 918 PCU’s in 1 hour time period. ( 5pm to 6pm) - A large Volume of pedestrian movement was observed along the main entrance, towards the stretch to the Bus Stand and Para Transit Stand present at Madhusudhan Chowk. - The Traffic Volume Count at madhusudhan chowk at peak time is 3426.6 PCU which has to be considered into the proposals. 4% Mode Availability and Usage of Mode -Pedestrians constitute most of the traffic, and no provisions are made for their circulation. Cycle 23% 11% - Two wheelers ranks the highest in modal choice followed by four wheelers and auto rickshaw. 5% 0% Cycle rickshaw 2 Wheelers 57% Auto Rickshaw Car/jeep Lcv Parameters Probable Solutions for Implementation Responsive to street congestion • Dedicated Corridors for Pedestrian and Motorized Modes of transport • Road Widening of roads at strategic locations • Strategic Relocation of Encroachments Responsive to travel costs • Pedestrianisation of corridors to the possible extent Reduction of unnecessary travel movements Responsive to Availability of Public transport • Explore scope of Para-Transit/ Feeder Service Responsive to the OBSERVATIONS growth of the Surroundings • Incorporation of ancillary activities along the stretch
  • 39. Mapping Pedestrian Routes & Demand RAILWAY STATION TRAFFIC ANALYSIS 438 Pedestrians 586 Pedestrians BUS STAND PARA-TRANSIT 456 Pedestrians CONFLICT POINTS MAX. DEMAND
  • 41. ELECTRIC LINES CROSSING OVER THE ROAD NO STREET LIGHTING ON THE ROAD NO PEDESTRAIN ON THE ROAD NO PEDESTRAIN PATHWAY ON THE ROAD STREET LIGHT ON THE 1 SIDE OF ROAD ONLY NO PEDSTRAIN PATHWAY ON THE ROAD ROAD LINKING THE RAILWAY STATION AND BUS STAND ROAD IN FRONT OF RAILWAY STATION OPEN DRAINS IN SOME AREA ROAD IN FRONT OF BUS STAND NO PEDESTRAIN AREA
  • 42. EXISTING STREET LIGHTING , ELECTRICTY DISTRIBUTION LINES CCTV LOCATIONS TRANSFORMER FLOOD LIGHTS Improper street lighting Crossing of the electric lanes over the road STREET LIGHT ELECTRIC LINE NO Segregation of pedestrian and vehiclular movement STREET LIGHT WIRE No Defined pedestrain path NO Flood lights at the MADHUSUDAN chowk Existing road section of the road linking bus stand to railway station
  • 43. EXISTING DRAINAGE AND SOLIDWATSE SITUATION Major problems of drainage and solid waste This area is highly polluted due to the presence of vendor Drains are not well maintained as in some area are these are open . OPEN ROADSIDE DUMPING CLOSED DRAINS OPEN DRAINS OPENING TO DRAINS No proper waste disposal area / collection area.. Existing section through the road in front of the railway station Existing section through road in front of BUS STAND
  • 44. PROPOSALS FOR THE ELECTRIC LANES AND STREET LIGHTING TRANSFORMER FLOOD LIGHTS STREET LIGHT UNDERGROUND ELECTRIC LINE STREET LIGHT WIRE Proposals •Underground electric lane •Flood lighting at junctions. UNDERGROUND ELECTRIC LANES PITS •Solar panel street lighting . •Lighting also provided along the pedestrian movement .
  • 45. SOLAR PANEL STREET LIGHTING • • Solar street lights require much less maintenance compared to conventional street lights. • Since external wires are eliminated, risk of accidents is minimized. PROPOSALS FOR THE ELECTRIC LANES AND STREET LIGHTING Solar street lights are independent of the utility grid. Hence, the operation costs are minimized. • This is a non polluting source of electricity Separate parts of solar system can be easily carried to the remote areas DX3 Solar Street Light Uses standard size/connection Uses standard size/connection 90 W high pressure sodium 30W Ultra High Efficient Array 5500 Lumens (3850 effective) • Regular Street Light 3400 Lumens 30-50 Lumen / Watt 120+ Lumen / Watt Photo-sensor or wire control Photo-sensor, wire or solar panel No Back Up Power Source Internal Battery, fully integrated into Street Light Head (Approx. 3 nights autonomous operation/battery reserve) No solar array Integrated solar array Requires electricity Solar powered Works only when grid is energized Works during power outages Cable requires expensive trenching No trenching Additional wiring in the ground No wire in ground Wire in the pole No wire in pole Significant resources to install Simple install Special crews for safe installation & commission Safe to install (12V) Attracts insects Does not attract insect
  • 46. Municipal waste B. Recyclables A. Organic • • • • Food waste vegetables waste Garden trimmings dry leaves • • • • • • • • Paper Plastics/polyethenes Rubber, leather Glass & ceramics Textile/cottons Earthen wares Metal Coconut shells 63.00 For B i o – degradable wastes For Re-cyclable wastes Solid waste management C. Inert • Dirt • Sand • Dust • soil
  • 47. Calculations  The stretch will be mostly used by the floating population which depends on the transits  Bins for Commercial Establishments/Shops : It is assumed that one bin will serve 25 shops.  Organic waste will be collected daily & recyclable waste will be collected once in a week.  Providing 100L capacity fibre glass bins for bio degradable waste and 500L capacity bins for recyclable wastes. Waste density for bio degradable waste = 300 kg/cubic metre Waste density for bio degradable waste = 150 kg/cubic metre Total no. of people using the stretch from railway station to Madhusudan chowk per day= around 5000 waste generated per day per pedestrians= 5000X.05kg=250 kg waste generated by the shops=0.5X84=42kg Total waste generated = 292 kg Total no. of people using the stretch from railway station to bus stand, per day= around 4500 Total waste generated per day= 4500X.05kg=225 kg waste generated by the shops=0.5X80=40kg Total waste generated = 265 kg assuming that 1/4th of the total waste is organic Amount of organic waste = 70 kg Amount of recyclable waste= 222 kg assuming that 1/4th of the total waste is organic Amount of organic waste =70 kg Amount of recyclable waste= 195kg Bio degradable waste N=70/(300X0.1X1X1)=3 Bio degradable waste N=70/(300X0.1X1X1)=3 Recyclable waste N=190/(150X.5X1X1.6)=2 Recyclable waste N=195/(150X.5X1X1.6)=2 N=W/(DXSXF1XCF)Where N = Number of collection bins W = Total quantity of waste generated per day in Kg D = Density of waste in Kg/m Solid waste management: Calculations S= Size of bins in m3 F1= Average filling rate of bin. (Generally 80 %) CF = Collection Frequency
  • 48. At railway station At Bus stand Total no. of people using railway station per day = 6000 Waste generated per person = 100g Total waste generated= 600kg assuming that 1/4th of the total waste is organic Amount of organic waste = 150 kg Amount of recyclable waste= 450 kg Total no. of people using railway station per day = 1000 Waste generated per person = 100g Total waste generated= 100kg assuming that 1/4th of the total waste is organic Amount of organic waste = 25 kg Amount of recyclable waste= 75 kg Bio degradable wastes N=70/(300X0.1X1X1)=5 Bio degradable wastes N=25/(300X0.1X1X1)=1 Recyclable wastes N=190/(150X.5X1X1.6)=4 Recyclable wastes N=75/(150X.5X1X1.6)=1 Bins for Institutions It is assumed that two trash bin will be placed in each institution. Both Organic waste & recyclable waste will be collected daily. Bins for Hotel and Restaurant 2000 litres capacity will be placed at each hotels and restaurant for collection of bulk generation of organic waste. Street sweeping The width of t he roads are different. Considering 2 0% of road length having 12 Mt. width, 40% of the road length having 22 Mt. width & 40% of road length having 6 Mt. width, the length of the roads of different width are as follows 12 Mt. width road = 260km; 22 Mt. width road = 520km; 6Mt. width road = 520km Considering one sweeper can sweep 2500 Sqmt. of road/day and also be allotted the duty for primary collection of waste from road side to dumper placer container. The no of sweeper required For 12Mt.width road = (12x260)/2500 = 2nos. For 22Mt.width road = (22X520)/2500 = 5nos. For 6Mt.width road = (6X520)/2500 = nos. Total = 2 nos. Total no. of workers=2+4+2=9 Solid waste management: calculations
  • 49. 100L capacity fibre glass green colour bins for bio degradable waste Two types of bins will be placed together 500L capacity fibe glass black colourbins for recyclable waste Solid waste management: positions of bins
  • 51. VISUAL CONNECTIVITY Observations: •There street connecting railway station and madhusudan chowk acts as a view corridor. •The statue in the madhusudhan chowk is a focal point in the view corridor. •No visual connection between railway station and bus stand. View corridor View corridor Statue in the madhusudhan chowk URBAN DESIGN Ratio of enclosure in view corridor (6m-9m height , 21m road width
  • 52. VISUAL POLLUTION 5 1 3 2 4 URBAN DESIGN Observations: 1.Billboards of various sizes cause visual pollution by making a disturbance to view of street. 2.In some area electric cable is causing visual pollution, it may create accidents also. Condition of road is not good. 3.Irregular parking in the roadside reduces the visual quality of street. 4.Billboards in front of railway station also create visual disturbance. 5.Advertisements in building walls also cause visual pollution. Condition of road is not good. 6.Informal shops in the beginning of road to bus stand from railway station also reduce visual quality of street. Requirement: •Defined parking area. •Good condition road •Control over bill boards and advertisements. •Removal of big billboards over buildings. •Proper maintenance of electric cables. •New location for informal shops
  • 53. STREETSCAPE Observations: •Signage: signage boards are absent (no signage board from railway station to bus stand). •Side walks: well designed pedestrian pathways are absent. •Cross walks: cross walks are absent, people move randomly, create chaos in the junction. Requirement: • There should be a proper designed signage. As a general rule, it is suggested that the letter height should be at least 1% of the distance at which the message will usually be read boards showing connection to each roads. •Enhance the pedestrian linkage by: 1.Ensuring the continuity of sidewalks, lighting and paving material.2Providing adequate width for both pedestrians and Areas required signage bicyclists.3Maintaining and enhancing accessibility for boards differently-abled individuals. Areas required cross walks •Proper cross walks should be marked. Areas required continues pedestrian connectivity 1 URBAN DESIGN
  • 54. STREETSCAPE Observations: •Screenings: Screening provides a visual buffer between pedestrian and vehicular spaces and separation of public areas from parking and circulation areas, as well as grade Areas required landscape changes. There are no such screenings present. in road divider •Landscape : trees and plants are less. Area lacking street lighting •utility: no trash receptacles, people drop plastic waste on road side. Areas that can be treated with •Street lighting is not adequate in road connecting railway vegetation station to bus stand. Requirement: •There should be screenings between public parking area and the street. •The road divider can be treated with some small plants. •Trash receptacles are required. •There should be adequate street lighting 1 URBAN DESIGN
  • 56. Issue identification & broad proposals
  • 57. LANDUSE Proposed Truck parking = 862 sq m on the land available near informal sector. The area can accommodate 15 trucks. Area for 1 truck = 50 sqm . Therefore for 15 trucks = 750 sqm Expansion of existing parking near commercial area = 2681 sqm No. of cars parked = 50 , No. of Two wheelers = 400, No of autos = 15 Proposal = 500 two wheelers, 60 cars and 20 autos Area = (500* 2.5) + (60 * 15) + (20 *8) = 2310 sq m Accquired railway land = 4700 sq m Relocation of informal shops = 1000 sq m Formal Commercial = 430 sq m Plaza = 2200 sq m Feeder Paking = 850 sq m Toilets = 220 sq m Effective road width of bus stand strech is 4.5 m Encroached area = 1.5m Encroachments removed and converted to pedestrian pathway PROPOSALS
  • 59. COMPARISON OF EXISTING AND PROPOSED LANDUSE 50000 45000 40000 35000 30000 25000 20000 Existing 15000 Proposed 10000 5000 0 PROPOSALS
  • 60. TRAFFIC MANAGEMENT PLAN • The vehicular movement along the stretch of the road is guided by the main principle to decongest the intersection in front of the railway station and put the alternate entrance to maximum use. • The introduction of a feeder service is looked upon as a viable option to make the link between the railway station and the bus stand more accessible. The link being almost 400 m long, cannot be accessed easily by pedestrians. • The entry and exit for the feeder service is separated from the main entrance and exit Traffic Management Plan Indicating The Movement Of Vehicular Traffic PROPOSALS
  • 61. TRAFFIC MANAGEMENT PLAN • The pedestrian movement which was otherwise chaotic at the intersection is improved by provision of pavements along one side of stretch 1 and along both the sides of stretch 2. • The pavement along stretch 1 is integrated with facilities such as eateries, fruit and vegetable vendors, groceries, etc and a plaza which doubles as a recreational zone. Traffic Management Plan Indicating The Movement Of Pedestrian Traffic PROPOSALS
  • 62. PARKING MANAGEMENT (Inside Railway Station) • As observed with the help of the survey data, most of the respondents use the station almost once in every month and 28 % of the total users surveyed use the station on a daily basis, the reasons for the regular trips being work and other personal (including family engagements). • Almost 40% respondents use auto rickshaw to reach the station indicating importance of this particular mode. A large portion of the respondents feel that the bus stand and auto stands are too far to travel by foot. • The safety along the walkways to the same mentioned facilities is a major concern here. • Hence as observed, the major concerns to be looked upon here are: • Parking spaces for cars and auto rickshaws, and • The unorganized Drop off/Drop in system for passengers who are coming/leaving to/from the station. • Inconvenient accessibility to public modes of travel. PROPOSALS Views of the Existing Parking and Circulation at the Railway Station • The above illustrates the haphazard parking of the auto rickshaws, taxis and private vehicles. • Also there is no specific pathway demarcated for Pedestrians especially with luggage. The station can be accessed by two entry/exit gates which serve as a major reason for this unorganized vehicular and pedestrian circulation. • Absence of Facilitation centres and Information kiosks lead to probable misguidance in terms of direction and choice of facility to be availed by the people while coming out of the Rourkela railway station. • Since the maximum portion of the vehicular inlet/outlet happen at the main entrance of the railway station, this contrasting distribution leads to more chances of accidents in that zone.
  • 63. PARKING MANAGEMENT (Inside Railway Station) • As observed, the major concerns to be facilitated here are • Parking spaces for cars and auto rickshaws, and • An organized Drop off bay for passengers who are coming to the station. The additional development strategies and proposals will include the following: • Auto Rickshaw Pre paid Stand • Tourist information Facilitation Centre • Taxis prepaid counter • Bus interchange facilitation Centre • Feeder pickup/drop point and feeder user shaded seating Plan of the Proposed Parking, Zoning and Circulation at the Railway Station PROPOSALS 1 . 2 . 3 . 4 . 5 . 6 . 7 . Parking for 24 four wheelers – 10 m wide road Parking for 56 four wheelers – 10 m wide road Parking for 170 two wheelers – 5 m wide road Parking for 170 two wheelers – 5 m wide road Parking for 170 two wheelers – 5 m wide road Parking for 50 autos and 80 cycles – 7 m wide road Feeder Parking for 30-35 feeders and prepaid taxi booth