1. STATUS REPORT OF MY HOME ABHRA Tower-”A”As On 23.05.13
1.First Floor Slab :Completed
2.Second Floor Slab: 1 & 2 Flats Shuttering Work Completed Bar Bending work In Progress
2. STATUS REPORT OF MY HOME ABHRA Tower-”B” As On 23.05.13
1.First Floor Slab : Completed
2.Second Floor Slab :Flats No 1 & 2 Completed
3. STATUS REPORT OF MY HOME ABHRA Tower-”C”As On 23.05.13
1.Ground Floor Slab : Completed
2.First Floor Slab : Flat No 01 Shuttering work In Progress
4. STATUS REPORT OF MY HOME ABHRA Tower-”D”As On 23.05.13
1.First Floor Slab: Completed
2.Second Floor Slab : Flat No 1 & 2 flats Completed and 4th and 5th Flats shuttering Completed,3rd flat
Beam Bottom shuttering Work started
5. STATUS REPORT OF MY HOME ABHRA Tower-”E”As On 23.05.13
1.First Floor Slab :Completed
2.Second Floor Slab : Flat no 1 & 2 Shuttering completed
6. STATUS REPORT OF MY HOME ABHRA “TOTAL SITE”As On 23.05.13
1.Total Site Ground Floor slab Completed
2.Total Site First Floor slab Except Tower :C Remain All Completed