SlideShare une entreprise Scribd logo
1  sur  16
Télécharger pour lire hors ligne
The Lesedi PV plant_ and Letsatsi PV plants are two of the
three largest PV plants on the African continent.
 Age’s scope of supply included:
The proposed system consisting of the following elements were requested:
1. INFRARED DOMES in the access and at strategic points.
2. THERMAL CAMERAS in the perimeter and in the principal internal roads.
3. VIDEO MONITORS & VIDEO ANALYZER
5. Access Control with Biometric Readers
6. Control Centre in the O&M Building
7. IR Detector, in the inverters buildings and in the O&M buildings.
8. Guard Tour System.
9. Complete manual to operation and maintenance
Product used in the project
 Scope of work to be done
 Fiber Network
 Installation of fiber cable
 Installation of splice boxes
 Installation of patch leads
 Complete manual for operation and maintenance of the system
 Training
 Total value of the project upon
completion
 1.9 million
 Duration of the project
 3 months
Enclosure Built
8x Floor Standing PLC Enclosures
2x Network Enclosures for Control
and PLC room
13x Power Distribution Enclosures
23x Junction Boxes
33x Instrument Solenoid Bank Enclosures
PLC Inputs and Outputs
288x Analogue Inputs
224x Analogue Outputs
896x Digital Inputs
384x Digital Outputs
Drives Control Engineered
58x Variable Speed Drives
1x Direct Online Starter
2x Soft starters
Project Value
Supply and Engineering R4.2M
Completion
Hardware Supply Complete
Software Engineering Complete
Commissioning July 2014
Foskor is a proudly South African producer of phosphates
and phosphoric acid with international exposure. Foskor
unlocks shareholder value through the profitable,
responsible and sustainable beneficiation of phosphate
rock into either phosphoric acid or phosphate-based
granular fertilisers sold globally.
Founded in 1951, Foskor’s Mining Division in Phalaborwa
mines phosphate rock, from which Foskor’s Acid Division
in Richards Bay produces phosphoric acid and phosphate-
based granular fertilisers for local and international
markets. The opencast mine in Phalaborwa has the
capacity to produce 3 million tonnes per annum of
phosphate rock concentrate from 35 million tonnes of
ore mined per annum. Once crushed, milled,
concentrated and dried, most of the phosphate rock
concentrate is railed to Foskor’s processing plant in
Richards Bay, 800 km away on the KwaZulu-Natal coast.
The D Stream Flotation Plant Replacement (DSF) project
originates from the Foskor’s infrastructure replacement
strategy.
This project will ensure that the installed flotation
capacity remains at a level which makes it possible to
produce circa 3 million tons of concentrate per annum
(mtpa), therefore protecting the production strategy of
the Phalaborwa operations. The project consists of new
600 tph flotation plant.
AGE Technologies JHB was awarded the Supply,
Engineering and Commissioning of the complete PLC and
Scada Control System. The Control System consists of
Schneider’s Quantum PLC and Adroit Scada System
communicating through Hirschman switches. The project
also consisted of the supply and manufacture of the
Festo instrument solenoid bank enclosures.
As Tharisa Mine is the largest known single chrome resource deposit in the world,
the Group is well positioned to benefit from the projected growth in demand for
chrome, which is primarily used in stainless steel manufacturing.
MDM Engineering contracted AGE Technologies to supply in all the requirements
of the Tharisa Expansion
project.
 Age’s scope of supply included:
 Supply of all Siemens PLC hardware (S7-300 & S7-400)
 Supply of all Siemens SCADA software (WinCC)
 RIO Panel supply & manufacturing (34 panels)
 Ethernet & Profibus fiber network installation, splicing, testing, certification
and drawings (Est. 6000m fiber and 900 splices)
 Supply, installation, configuration and commissioning of 4x Wireless
Ethernet radios that links to 4x pump stations (4IPNET Radios)
 2x Commissioning engineers to assist with I/O testing & process
commissioning (I/O count 1546)
 General supply of cable, junction boxes & any other equipment needed
throughout the project
 Configuration of all networks running through OLM’s and the setup of the
OLM’s
 Product used in the project
 Multi core Instrument cable to the value of R400,000.00
 Siemens OLM
 Outdoor Fibre cable (total of 18.7kms)
 Network Switches (3 port & 6 port)
 All fiber equipment inc. adapters, connectors, pigtails & cable
 Scope of work to be done
 Fiber Network
 Installation of fiber cable.
 Installation of splice boxes.
 Installation of patch leads
 Supply IPDB’s
 Installation of a Profibus over fiber network
 Total value of the project upon completion
 5.9 million
 Duration of the project
 8 months
Solution provided to company
The physical structure was constructed by FAMAK in Poland and
shipped to Mozambique. The electrical design and construction
(wiring, cabling, PLC software and MCC cabinets) took place in South
Africa. It was assembled in Beira, and the electrical and
instrumentation installation commenced after. AGE Technologies did
PLC and SCADA software development and will be responsible for
commissioning.
 Products used in the project
PLC control system: Siemens S7-300 PLC with ET200S
Distributed IO
Motor control: Siemens SIMOCODE's and Siemens
Micromaster VSD's
Instruments: majority is supplied from Schneider but
includes Siemens, Rockwell and Weidmuller
All Cabling used on the Stacker predominantly from Jaycor
and Africa Cables
 Relevant information
MCC's were constructed by Raise and Lower
AGE provided 3 containers, operator cabin with all equipment inside,
all PLC and networking equipment, all electrical cables, equipment,
drives, relays, circuit breakers & switchgear
One 630 kVA, 6.6kV/400V transformer
People involved in the project
 Norman Jackson – Project Manager -
Design
 Paul van Rooyen – Project Manager -
Electrical Design and hardware
 Gabriel van der Merwe –
Project Technician - SCADA,
Instrumentation Design, Hardware
 Karlin Gomo- PLC Programming and
Functional Design Specification
Project Scope & Objectives
AGE Technologies was responsible for the
design manufacturer of the entire electrical
and instrumentation requirements of the
Stacker Machine that was installed at the new
coal terminal in Beira Harbour, Mozambique.
AGE Technologies provided the PLC and
electrical control systems.
AGE Technologies JHB (Ltd) together with Instrumentation &
Electrical Consultants had to supply King Shaka International
Airport with Equipment & Design of an Redundant Fibre Profibus
and Profinet Networks with Siemens S7-400 Hot Standby PLC in
SIL3 Safety and Standard I/O.
 Duration of the project
Started 1 May 2010 and ran for the duration of 5-7 months.
 The problem was
to provide Siemens Equipment that could be integrated into a
reliable fail-safe system for the Fuel Storage System at the
Airport.
 Solution Provided
We provided them with a Siemens S7-400 Hot Standby PLC with
Redundant networks and Dual Redundant WinCC SCADA.
 Products in the project
Siemens S7-400 Hot Standby PLC, SIL3 Safety ET 200 IO Stations,
Standard ET200 IO Stations, Redundant WinCC SCADA, Dual
Redundant Profibus Networks, Dual Redundant Profinet
Networks
 Scope of work
AGE was responsible for assisting with the design of the
PLC/SCADA system, to make sure that a working system was
offered to the end user, and to supply the actual PLC hardware
and SCADA software packages.
IEC did the actual system integration and wrote most of the
application software. Some software for leak-detection was
written in Germany.
Age Technologies JHB- a member of the Age of Africa Technologies
Group - were commissioned by ESKOM to come up with a simple
yet intelligent design for the ash conveyor protection system at
their Kendal Power Station in Mpumalanga.
 Design
Owing to the length of the ash handling conveyor, the
protection system had to incorporate enhanced fault finding
and accurate trip site location .
This unique design in long-line conveyor protection is a world
first. All of ESKOM's criteria were met and incorporated all
the other aspects of conveyor related alarms such as belt rip,
misalignment, and blocked chute detection, yet there are no
electronics in the field.
 Duration
The system, which took six months and comprised 66 man
months from conception to completion, is so efficient and
easy to maintain that AGE are pleased to report their client is
extremely pleased with the reliability of the plant.
 Scope
AGE's brief included the overall project management, PLC
engineering using a Siemens Su110 PLC, equipment supply,
installation and commissioning.
 The project, which was repeat business for AEG with ESKOM,
was completed on time and within budget.
 In line with their philosophy of client
relationship marketing, AGE Engineering
undertook this project at Fry's metals of
Wadeville during their annual end-of-year
shutdown. Although small in size the process
to be automated was quite sophisticated
from the point of view of all the different
processes that had to be brought together.
 Lead reclamation has it's own characteristics
and AGE Engineering had to firstly familiarise
themselves with the reclamation process.
Once that was done they had to write the
process software for the ingot pouring,
handling and stacking system.
 In addition to the InTouch SCADA package,
ControlWize made use of a Microsoft SQL
Server with an Access data base for the train
handling facility at the load-out station.
 The project included management, PLC
engineering, equipment supply, installation
and commissioning and took one man-month
to execute.
 Being a shutdown there was no margin for
error and the automation, using an Allen
Bradley S5 PLC, went off smoothly with no
technical hitches experienced at handover.
 ESKOM identified the need for the replacement
of the coal stacker/ reclaimer control system at
their dry cooled power station near Ellisras in the
Northern province.
 Overview
AEG's construction division were awarded the
project to design, supply and install such a
system to provide plant alarm status, monitoring
and reporting. This was repeat business for AEG
who also executed the station MV switchgear
project and the overland Ash Handling conveyor
systems.
The project was carried out during the transition
period from AEG to AGE Engineering and was
completed ahead of the prescribed contract
period.
 Duration of project
The 12-month contract, which comprised 64
man-months effort, included the full project
management, PLC engineering using a Modicon
'A' series PLC, full equipment supply, installation
and commissioning.
 Significant feature
of this project was the design, by one of AGE's
engineers, of unique connection terminals -
housed in the PLC cabinet - which comprised full
lightning protection on all inputs and outputs.
This type of terminal has now become a standard
in the electrical industry
 Zimplats was established by Delta Gold Limited (Delta) in 1998 to take over its
platinum interests. In May 1999 the company purchased BHP’s interests in the
Hartley Platinum and the Mhondoro Platinum Joint Ventures which included a
concentrator and smelter.
 AGE’s Scope of work to be done –
– Capturing of Plant wide process Data and Historizing for minimum period of twelve
months
– Alarm & Fault Logging which will detail the precise reason for Plant Stoppage to enable
the Technician to rectify the fault with minimum down time
– Up to date PLC and SCADA software
– New Plant Computers and Servers with web reports available for Plant Managers.
– The enhancement of the electrode slipping system enables it to measure the actual state
of the electrode slipping system. The new program functions just as the existing program
with the additional benefits:
– Shorter slipping times
– Any given movement, de-clamping, raising, clamping or lowering takes only as long as
required.
– Reliability of the electrode slipping system is improved. Error conditions are alarmed on
the SCADA
 Significant Features of the project –
AGE Technologies offered the following enhancements and benefits to their
current system
– Plant wide Server/Client topology which centralizes their Data for easier Alarming, Data
Retrieval and Reporting and Backup.
– First Up Alarming programmed into their PLCs, with clear Alarm and Fault messaging at
their SCADA Clients
– Fixed format Daily Reports for the Smelter Plant and the Concentrator Plant
– Device Status and Interlock Display Dash boards to assist operators.
– Upgraded two obsolete TSX17 PLCs to Modicon M340 under Unity Software.
– Conversion of Concept PLC programs to Unity by upgrading PLC firmware
– Removed redundant MB+ network that was no longer required.
– Auto-save Change Management Software, that automatically keeps all their PLCs and
SCADA software backed up and tracks any software changes that is being implemented.
– Archestra System Platform Software and Unity PLC Software Training for
Engineers/Technicians
– New latest Dell Computers (Severs and Work Stations) for their entire Plant Operations.
– Onsite System Commissioning
 Duration of the project –
 ± 8 months
 Budget –
 R 2 ,495 024.00
Set amongst the beautiful rolling hills and valleys
of the KwaZulu-Natal midlands, the largest
waterworks in KZ Natal and most modern in the
country, Umgeni Water's Midmar Dam
Waterworks, was successfully commissioned, on
schedule, in October 1996.
 Built on the site of the old Mill Falls
waterworks outside Howick, the first phase
of 250 Ml/day will be augmented to an
ultimate capacity of 1000 Ml/day by 2005,
when predicted water demand is expected
to be around 450 million cubic metres per
year.
 AEG were originally awarded the
subcontract to main contractor Aquazur but
owing to the disruptions within AEG at the
time, leading up to their ultimate sale, AGE
was contracted to complete the contract. In
order to minimise disruptions to the
contract AGE Engineering made use of all
the existing AEG personnel, some of whom
were sent for training in Germany in order
to commission the MCC's bus system.
 Duration
The multi-million rand project was 14
months in duration and comprised 130
man-months effort. AGE Engineering's
scope included Project management, PLC
engineering, equipment supply - including
the sophisticated Motor Control Centres,
installation and commissioning
 Background
The brewery has ten Cellars. Each cellar is
divided into different tanks, in which the
fermentation takes place. Glycine is passed
through tubes wound round the tanks to control
the temperature during the brewing process.
A solenoid valve is used to open and close flow
of glycine. Pt100 at the top and bottom of each
tank are used to monitor the temperature. The
temperature is either monitored using the Top/
Bottom PT100 or both PT100s. should any of the
PT100 fail the PLC will switch the control
completely to the healthy one.
Each of the tanks can be in one of the following
modes: Ready, Filling, Fermentation, Chill or
Cleaning in Progress (CIP)
 AGE’s Scope of work to be done –
The plant is divided into three Control systems,
i.e. Cellar 1&2, Cellar 3-8 and Cellar 9&10.
A SCADA (Supervisory Control And Data
Acquisition) system will provide a graphical
overview of the whole control system. An
Ethernet TCP/IP network will link the three
Systems and the SCADA.
 Significant Features of the project –
 HMI will provide the operator with status of each
Cellar and Tank
 SCADA system will provide a graphical overview
of the plant, with the status of each tank.
 A graph of all temperatures and operator
inputted information will be available.
 The fermentation manager will be able to change
the operating mode of a tank, and with a login
password he can also change the temperature
set points.
 A historical log will also be kept of all tank
batches that have been brewed
 Keeping data for each batch is important
for quality purposes.
 The Mode of operation of each tank will
be colour coded - determined by its
background Colour in the overview page.
 A Siren and alarm lamp will be installed at
each control system to warn the operator
of an alarm condition
 Products used –
 Modicon TSX Premium from Schneider
Electric
 PLC software - PL7 Pro for TSX Premium
PLC
 HMI - is an EZTOUCH, Modbus/TCP 8” Slim
panel
 SCADA System - Intouch version 9, with
1000 tag licence
 Spider, 5 port 10/100 Ethernet switches for
each Control system
 Duration of the project –
6 months
 Total Value –
R 605,906.34
 Background
Botswana Ash (Pty) Ltd began operating in April 1991. The mine is located at Sua Pan,
which is approximately 180 kilometres from Francistown in northern Botswana. The
Company produces Soda Ash and Salt. All the activities of the mine are undertaken at
Sua Pan – from production through to marketing and sales and administration. The
primary market for Soda Ash is South Africa, where most of the products are used in
the glass industry. They also produce fine and coarse salt. Like Soda Ash, the Salt
products are sold within the continent. Production capacity is 650 000 tonnes per
annum.
 AGE’s Scope of work to be done
To upgrade of old absolute TSX-17-20 Telemecanique
PLC’s to the newest Schneider M340 PLC with UnityPro Software for the Soda Ash
Stacker as well as the Salt Reclaimer. AGE Technologies also replaced all panels on
site. In the Salt Reclaimer the panels was replaced by stainless steel panels to help
prevent rust.
The upgrade included –
Supply of all Hardware
Software Engineering & Installation and Commissioning
 Products used
Schneider M340 PLC with UNITYPRO Software
CPU340‐20 MODBUS ETHERNET
Radio telemetry System
PLC, Termister Relays & Output Devices Supply Breakers
Emergency Bypass Keyswitch
New Panel Electrical Drawings plus Field
PLC Application Software Development according to the FDS documents
HMI Application Software development
PLC/HMI Onsite PLC software Commissioning
 Duration of the project
6 weeks
Total Value
Soda Ash Stacker – R 420 000
Salt Reclaimer – R 350 000
Xstrata are one of the world's largest global diversified natural resource
companies and a major producer and marketer of more than 90 commodities.
Their presence at each stage of the commodities chain provides us with superior market
insight and access to opportunities. They have a strong footprint in both established and
emerging regions for natural resources.
SCOPE OF WORK:
Product Included:
IMPALA PLANT - Supply and Install an Enermax plus Meter with Modem for remote metering outside 400v Substation in
Metering box.
 Supply 400V, 3 phase 4 wire 5Amp Enermax Plus meter with external memory.
 Supply cell modem for meter and sim card.
 Supply 3 x 1500/5 metering current transformers.
2. WONDERKOP PLANT - Supply and Install an Enermax Plus Meter with Modem for remote on 11KV Incomer panel.
 Supply 110V, 3 Phase 4 wire 5Amp Enermax Plus meter with external memory.
 Supply cell modem for meter and sim card.
 Supply 3 x 5/5 metering interposing current transformers
3. EPL PLANT - Supply and Install an Enermax Plus Meter with Modem for remote on 11kV Incomer panel.
 Supply 110V, 3 Phase 4 wire 5Amp Enermax Plus meter with external memory.
 Supply cell moden for meter and sim card.
 Supply 3 x 5/5 metering interposing current transformer.
K2.5 PLANT - Supply and install an Enermax Plus Meter with Modem for remote on 11kv Fdr panel.
 Supply 110V, 3 Phase 4 wire 5Amp Enermax Plus meter with external memory.
 Supply cell moden for meter and sim card.
 Supply 3 x 5/5 metering interposing current transformer.
5. K4 PLANT - Supply and install an Enermax Plus Meter with Modem for remote on 11kV panel.
 Supply 110V, 3 Phase 4 wire 5Amp Enermax Plus meter with external memory.
 Supply cell moden for meter and sim card.
 Supply 3 x 5/5 metering interposing current transformer.
6. WPL PLANT - Supply and Install an Enermax Plus Meter with Modem for remote on 11kV Incomer panel.
 Supply 110V, 3 Phase 4 wire 5Amp Enermax Plus meter with external memory.
 Supply cell modem for meter and sim card.
 Supply 3 x 5/5 metering interposing current transformer.
7. Remote data base for all remote meters
 Supply 1 x Meter reader that interface with modem, including software
Significant features of the project
 Remote access from anywhere in the country with cellular coverage to all metering data achieved. Software interface
gave the ability to generate electrical bill for energy consumption audit.
Duration of the project – 4 weeks
Total value of the project upon completion – R156,000.00
 AGE Technologies JHB (Pty) Ltd. secured the contract
to assist Arcelor Mittal’s planning department with
the design, project management and commissioning
of the automation system required at the
Vanderbijlpark works Continuous Casting plant.
 Scope of work to be done
Was the equipment supply and product training of
Modicon Quantum PLC's and FactoryLink SCADA.
However, the whole project was to be executed
during a planned shutdown period and required
careful planning in order to minimise disruption at
the changeover.
 Products used
The PLC was programmed in hot stand-by
configuration and it was decided to make use of
standard terminal cabling in order to facilitate a
smoother transition.
 Duration of the project
The project was five months in preparation and
comprised 3 man-months effort in execution.
 In one of the longest ongoing contracts on
AGE Engineering's order book, their contract
to provide automation packages to Pretoria
City Council
pump stations must rate as their longest.
 Started in mid 1995 - whilst still operating as
AEG Construction - their brief was to supply
an automation system to 5 pump stations
within the greater Pretoria metro pole.
 The first one completed was at the Fountains
station, followed by Garsfontein, Elardus
Park, Klapperkop and finally Mooikloof over a
period of four-and-a-half years.
 The project was run out of Pretoria's
department of water environment and
executed as five separate contracts.
 AGE's brief was to provide the project
management, PLC Engineering using Modicon
Compact and Micro PLC's, the equipment
supply, installation and commissioning. What
started out as first-time business for AGE
developed into a long-term relationship and
resulted in repeat business.
 Main contractor CHI Control appointed AGE
Engineering to carry out the PLC engineering,
equipment supply and commissioning of the
man riding and ore belts project at Randgold's
Lorraine Gold Mine in the Free State.
 This project, although only one month in
duration was very sophisticated in that it
called for an interface from the Modbus to
the Allen Bradley soft starters Scan Port.
 The Allen Bradley PLC interfaced to an AFE
SCADA data panel via Modbus an AFE data
panel interfaced to an existing SCADA via
Modbus

Contenu connexe

Tendances

2016 CV Torey Walsh LinkedIn
2016 CV Torey Walsh LinkedIn2016 CV Torey Walsh LinkedIn
2016 CV Torey Walsh LinkedInTorey Walsh
 
Performix System - High Performance 300mm EFEM
Performix System - High Performance 300mm EFEMPerformix System - High Performance 300mm EFEM
Performix System - High Performance 300mm EFEMkensington labs
 
Railway Data Communication in Harsh Environments
Railway Data Communication in Harsh EnvironmentsRailway Data Communication in Harsh Environments
Railway Data Communication in Harsh EnvironmentsIbrahim Al-Hudhaif
 
PLC Based Annunciation System
PLC Based Annunciation SystemPLC Based Annunciation System
PLC Based Annunciation SystemFasih Ahmed
 
Vodaworld - As-built documentation
Vodaworld - As-built documentationVodaworld - As-built documentation
Vodaworld - As-built documentationhannese
 
PLC Based Annunciation System Report
PLC Based Annunciation System ReportPLC Based Annunciation System Report
PLC Based Annunciation System ReportFasih Ahmed
 
Electronics Division Linked In
Electronics Division   Linked InElectronics Division   Linked In
Electronics Division Linked Injpguy
 
DesignCon 2019 112-Gbps Electrical Interfaces: An OIF Update on CEI-112G
DesignCon 2019 112-Gbps Electrical Interfaces: An OIF Update on CEI-112GDesignCon 2019 112-Gbps Electrical Interfaces: An OIF Update on CEI-112G
DesignCon 2019 112-Gbps Electrical Interfaces: An OIF Update on CEI-112GLeah Wilkinson
 
Yazan Al-Najjar MAJOR PROJECTS
Yazan Al-Najjar MAJOR PROJECTSYazan Al-Najjar MAJOR PROJECTS
Yazan Al-Najjar MAJOR PROJECTSYazan Al-Najjar
 
Aditech industrial networking
Aditech industrial networkingAditech industrial networking
Aditech industrial networkingVilas Fulsundar
 
OIF CEI-112G at OFC 2020 Presentation
OIF CEI-112G at OFC 2020 PresentationOIF CEI-112G at OFC 2020 Presentation
OIF CEI-112G at OFC 2020 PresentationLeah Wilkinson
 
Fieldbus Presentation
Fieldbus PresentationFieldbus Presentation
Fieldbus PresentationSachin Rasane
 
Leon Chacon Resume_Sept2016R
Leon Chacon Resume_Sept2016RLeon Chacon Resume_Sept2016R
Leon Chacon Resume_Sept2016RLeon Chacon
 
ICG-2510W-LTE Industrial 4G LTE Cellular Wireless Gateway
 ICG-2510W-LTE  Industrial 4G LTE Cellular Wireless Gateway  ICG-2510W-LTE  Industrial 4G LTE Cellular Wireless Gateway
ICG-2510W-LTE Industrial 4G LTE Cellular Wireless Gateway BluBoxx Communication Pvt. ltd
 
VEGA Pressure & Level Measurement – Shipbuilding Industry Applications
VEGA Pressure & Level Measurement – Shipbuilding Industry ApplicationsVEGA Pressure & Level Measurement – Shipbuilding Industry Applications
VEGA Pressure & Level Measurement – Shipbuilding Industry ApplicationsThorne & Derrick UK
 

Tendances (20)

2016 CV Torey Walsh LinkedIn
2016 CV Torey Walsh LinkedIn2016 CV Torey Walsh LinkedIn
2016 CV Torey Walsh LinkedIn
 
Mohamed Zakaria 01-2017
Mohamed Zakaria 01-2017Mohamed Zakaria 01-2017
Mohamed Zakaria 01-2017
 
Performix System - High Performance 300mm EFEM
Performix System - High Performance 300mm EFEMPerformix System - High Performance 300mm EFEM
Performix System - High Performance 300mm EFEM
 
Railway Data Communication in Harsh Environments
Railway Data Communication in Harsh EnvironmentsRailway Data Communication in Harsh Environments
Railway Data Communication in Harsh Environments
 
PLC Based Annunciation System
PLC Based Annunciation SystemPLC Based Annunciation System
PLC Based Annunciation System
 
Vodaworld - As-built documentation
Vodaworld - As-built documentationVodaworld - As-built documentation
Vodaworld - As-built documentation
 
PLC Based Annunciation System Report
PLC Based Annunciation System ReportPLC Based Annunciation System Report
PLC Based Annunciation System Report
 
CV_AD1
CV_AD1CV_AD1
CV_AD1
 
Cv sivam oct.doc 1
Cv sivam oct.doc 1Cv sivam oct.doc 1
Cv sivam oct.doc 1
 
WV CV_Eng_2016
WV CV_Eng_2016WV CV_Eng_2016
WV CV_Eng_2016
 
Electronics Division Linked In
Electronics Division   Linked InElectronics Division   Linked In
Electronics Division Linked In
 
DesignCon 2019 112-Gbps Electrical Interfaces: An OIF Update on CEI-112G
DesignCon 2019 112-Gbps Electrical Interfaces: An OIF Update on CEI-112GDesignCon 2019 112-Gbps Electrical Interfaces: An OIF Update on CEI-112G
DesignCon 2019 112-Gbps Electrical Interfaces: An OIF Update on CEI-112G
 
Yazan Al-Najjar MAJOR PROJECTS
Yazan Al-Najjar MAJOR PROJECTSYazan Al-Najjar MAJOR PROJECTS
Yazan Al-Najjar MAJOR PROJECTS
 
Ahmed Fahmy_CV
Ahmed Fahmy_CVAhmed Fahmy_CV
Ahmed Fahmy_CV
 
Aditech industrial networking
Aditech industrial networkingAditech industrial networking
Aditech industrial networking
 
OIF CEI-112G at OFC 2020 Presentation
OIF CEI-112G at OFC 2020 PresentationOIF CEI-112G at OFC 2020 Presentation
OIF CEI-112G at OFC 2020 Presentation
 
Fieldbus Presentation
Fieldbus PresentationFieldbus Presentation
Fieldbus Presentation
 
Leon Chacon Resume_Sept2016R
Leon Chacon Resume_Sept2016RLeon Chacon Resume_Sept2016R
Leon Chacon Resume_Sept2016R
 
ICG-2510W-LTE Industrial 4G LTE Cellular Wireless Gateway
 ICG-2510W-LTE  Industrial 4G LTE Cellular Wireless Gateway  ICG-2510W-LTE  Industrial 4G LTE Cellular Wireless Gateway
ICG-2510W-LTE Industrial 4G LTE Cellular Wireless Gateway
 
VEGA Pressure & Level Measurement – Shipbuilding Industry Applications
VEGA Pressure & Level Measurement – Shipbuilding Industry ApplicationsVEGA Pressure & Level Measurement – Shipbuilding Industry Applications
VEGA Pressure & Level Measurement – Shipbuilding Industry Applications
 

En vedette

Methane and Water Contamination Associated with Shale Gas Development and Hyd...
Methane and Water Contamination Associated with Shale Gas Development and Hyd...Methane and Water Contamination Associated with Shale Gas Development and Hyd...
Methane and Water Contamination Associated with Shale Gas Development and Hyd...Cary Institute of Ecosystem Studies
 
PROCESO MONTAJE 03
PROCESO MONTAJE 03PROCESO MONTAJE 03
PROCESO MONTAJE 03cecilia
 
Implementing a solar system on your mine - AGE Technologies
Implementing a solar system on your mine - AGE TechnologiesImplementing a solar system on your mine - AGE Technologies
Implementing a solar system on your mine - AGE TechnologiesAGE Technologies
 
Kgalagadi breweries fermentation plant
Kgalagadi breweries fermentation plantKgalagadi breweries fermentation plant
Kgalagadi breweries fermentation plantAGE Technologies
 
Technology in the Kingdom, Society, and Your Life
Technology in the Kingdom, Society, and Your LifeTechnology in the Kingdom, Society, and Your Life
Technology in the Kingdom, Society, and Your LifeJohn Dyer
 
Brochure - Slim Boring 2016
Brochure - Slim Boring 2016Brochure - Slim Boring 2016
Brochure - Slim Boring 2016Master Drilling
 
Floor Plan Presentation
Floor Plan PresentationFloor Plan Presentation
Floor Plan Presentationmqazi
 
Menager bosc2010 mobyle
Menager bosc2010 mobyleMenager bosc2010 mobyle
Menager bosc2010 mobyleBOSC 2010
 
Trip attraction rates of shopping centers in dhanmondi area of dhaka city final
Trip attraction rates of shopping centers in dhanmondi area of dhaka city finalTrip attraction rates of shopping centers in dhanmondi area of dhaka city final
Trip attraction rates of shopping centers in dhanmondi area of dhaka city finalTeletalk Bangladesh Ltd
 
Русская бизнес-профессионалов
Русская бизнес-профессионаловРусская бизнес-профессионалов
Русская бизнес-профессионаловDavid Dugas
 
Texto sustitutorio final informe btr
Texto sustitutorio final   informe btrTexto sustitutorio final   informe btr
Texto sustitutorio final informe btrrppc
 
Tharisa platinum mine expansion project 2012
Tharisa platinum mine expansion project 2012Tharisa platinum mine expansion project 2012
Tharisa platinum mine expansion project 2012AGE Technologies
 

En vedette (20)

Methane and Water Contamination Associated with Shale Gas Development and Hyd...
Methane and Water Contamination Associated with Shale Gas Development and Hyd...Methane and Water Contamination Associated with Shale Gas Development and Hyd...
Methane and Water Contamination Associated with Shale Gas Development and Hyd...
 
PROCESO MONTAJE 03
PROCESO MONTAJE 03PROCESO MONTAJE 03
PROCESO MONTAJE 03
 
Age Catalogue Feb'14
Age Catalogue Feb'14Age Catalogue Feb'14
Age Catalogue Feb'14
 
Implementing a solar system on your mine - AGE Technologies
Implementing a solar system on your mine - AGE TechnologiesImplementing a solar system on your mine - AGE Technologies
Implementing a solar system on your mine - AGE Technologies
 
Kendal power station
Kendal power station Kendal power station
Kendal power station
 
Kgalagadi breweries fermentation plant
Kgalagadi breweries fermentation plantKgalagadi breweries fermentation plant
Kgalagadi breweries fermentation plant
 
Technology in the Kingdom, Society, and Your Life
Technology in the Kingdom, Society, and Your LifeTechnology in the Kingdom, Society, and Your Life
Technology in the Kingdom, Society, and Your Life
 
Brochure - Slim Boring 2016
Brochure - Slim Boring 2016Brochure - Slim Boring 2016
Brochure - Slim Boring 2016
 
Alliance overview3.18.10
Alliance overview3.18.10Alliance overview3.18.10
Alliance overview3.18.10
 
Floor Plan Presentation
Floor Plan PresentationFloor Plan Presentation
Floor Plan Presentation
 
Menager bosc2010 mobyle
Menager bosc2010 mobyleMenager bosc2010 mobyle
Menager bosc2010 mobyle
 
United Way of Greater Toledo SEM Presentation
United Way of Greater Toledo SEM PresentationUnited Way of Greater Toledo SEM Presentation
United Way of Greater Toledo SEM Presentation
 
Portfolio Michelle Merritt
Portfolio Michelle MerrittPortfolio Michelle Merritt
Portfolio Michelle Merritt
 
Trip attraction rates of shopping centers in dhanmondi area of dhaka city final
Trip attraction rates of shopping centers in dhanmondi area of dhaka city finalTrip attraction rates of shopping centers in dhanmondi area of dhaka city final
Trip attraction rates of shopping centers in dhanmondi area of dhaka city final
 
Coventry
CoventryCoventry
Coventry
 
Mobile Levers for Retail
Mobile Levers for RetailMobile Levers for Retail
Mobile Levers for Retail
 
Русская бизнес-профессионалов
Русская бизнес-профессионаловРусская бизнес-профессионалов
Русская бизнес-профессионалов
 
Alfabeto español
Alfabeto españolAlfabeto español
Alfabeto español
 
Texto sustitutorio final informe btr
Texto sustitutorio final   informe btrTexto sustitutorio final   informe btr
Texto sustitutorio final informe btr
 
Tharisa platinum mine expansion project 2012
Tharisa platinum mine expansion project 2012Tharisa platinum mine expansion project 2012
Tharisa platinum mine expansion project 2012
 

Similaire à AGE TECHNOLOGIES_2014 project briefs

EPIC Engineering/Valero Case Study
EPIC Engineering/Valero Case StudyEPIC Engineering/Valero Case Study
EPIC Engineering/Valero Case StudyMichael Gauthier
 
MoreauMulumeCV_Profile07012015
MoreauMulumeCV_Profile07012015MoreauMulumeCV_Profile07012015
MoreauMulumeCV_Profile07012015Moreau Mulume
 
IESA: Automation for Oil & Gas Industry
IESA: Automation for Oil & Gas IndustryIESA: Automation for Oil & Gas Industry
IESA: Automation for Oil & Gas IndustryVincent BOYER
 
Robert Williams Work Experience
Robert Williams Work ExperienceRobert Williams Work Experience
Robert Williams Work ExperienceRobert Williams
 
Ahmed Elsayed Salem CV
Ahmed Elsayed Salem CVAhmed Elsayed Salem CV
Ahmed Elsayed Salem CVAhmed Salem
 
I tron automation's experience
I tron automation's experienceI tron automation's experience
I tron automation's experiencehugo_mx
 
I tron automation's experience
I tron automation's experienceI tron automation's experience
I tron automation's experiencehugo_mx
 
I tron automation's experience
I tron automation's experienceI tron automation's experience
I tron automation's experiencehugo_mx
 
FInal_CV_08_4_2016
FInal_CV_08_4_2016FInal_CV_08_4_2016
FInal_CV_08_4_2016PANKAJ PAL
 
KP Controls CV 1.4
KP Controls CV 1.4KP Controls CV 1.4
KP Controls CV 1.4kevin pratt
 
Company_IPP_Profile_Template
Company_IPP_Profile_TemplateCompany_IPP_Profile_Template
Company_IPP_Profile_TemplateAlan Simon
 
PAUL_OWEN_CV
PAUL_OWEN_CVPAUL_OWEN_CV
PAUL_OWEN_CVPaul Owen
 

Similaire à AGE TECHNOLOGIES_2014 project briefs (20)

CV_Sandeep Anugade
CV_Sandeep AnugadeCV_Sandeep Anugade
CV_Sandeep Anugade
 
Resume
ResumeResume
Resume
 
EPIC Engineering/Valero Case Study
EPIC Engineering/Valero Case StudyEPIC Engineering/Valero Case Study
EPIC Engineering/Valero Case Study
 
MoreauMulumeCV_Profile07012015
MoreauMulumeCV_Profile07012015MoreauMulumeCV_Profile07012015
MoreauMulumeCV_Profile07012015
 
Abdallah Al Sagheir Cv
Abdallah Al Sagheir CvAbdallah Al Sagheir Cv
Abdallah Al Sagheir Cv
 
IESA: Automation for Oil & Gas Industry
IESA: Automation for Oil & Gas IndustryIESA: Automation for Oil & Gas Industry
IESA: Automation for Oil & Gas Industry
 
Nagy_CV_Docx
Nagy_CV_DocxNagy_CV_Docx
Nagy_CV_Docx
 
Nagy_CV_Docx
Nagy_CV_DocxNagy_CV_Docx
Nagy_CV_Docx
 
Robert Williams Work Experience
Robert Williams Work ExperienceRobert Williams Work Experience
Robert Williams Work Experience
 
Ahmed Elsayed Salem CV
Ahmed Elsayed Salem CVAhmed Elsayed Salem CV
Ahmed Elsayed Salem CV
 
I tron automation's experience
I tron automation's experienceI tron automation's experience
I tron automation's experience
 
I tron automation's experience
I tron automation's experienceI tron automation's experience
I tron automation's experience
 
I tron automation's experience
I tron automation's experienceI tron automation's experience
I tron automation's experience
 
FInal_CV_08_4_2016
FInal_CV_08_4_2016FInal_CV_08_4_2016
FInal_CV_08_4_2016
 
iab-suc-prosafe-en
iab-suc-prosafe-eniab-suc-prosafe-en
iab-suc-prosafe-en
 
KP Controls CV 1.4
KP Controls CV 1.4KP Controls CV 1.4
KP Controls CV 1.4
 
Company_IPP_Profile_Template
Company_IPP_Profile_TemplateCompany_IPP_Profile_Template
Company_IPP_Profile_Template
 
PAUL_OWEN_CV
PAUL_OWEN_CVPAUL_OWEN_CV
PAUL_OWEN_CV
 
dmb Portfolio
dmb Portfoliodmb Portfolio
dmb Portfolio
 
Khlau Rev0 150701
Khlau Rev0 150701Khlau Rev0 150701
Khlau Rev0 150701
 

Dernier

Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdfKamal Acharya
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...ranjana rawat
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 

Dernier (20)

DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 

AGE TECHNOLOGIES_2014 project briefs

  • 1. The Lesedi PV plant_ and Letsatsi PV plants are two of the three largest PV plants on the African continent.  Age’s scope of supply included: The proposed system consisting of the following elements were requested: 1. INFRARED DOMES in the access and at strategic points. 2. THERMAL CAMERAS in the perimeter and in the principal internal roads. 3. VIDEO MONITORS & VIDEO ANALYZER 5. Access Control with Biometric Readers 6. Control Centre in the O&M Building 7. IR Detector, in the inverters buildings and in the O&M buildings. 8. Guard Tour System. 9. Complete manual to operation and maintenance Product used in the project  Scope of work to be done  Fiber Network  Installation of fiber cable  Installation of splice boxes  Installation of patch leads  Complete manual for operation and maintenance of the system  Training  Total value of the project upon completion  1.9 million  Duration of the project  3 months
  • 2. Enclosure Built 8x Floor Standing PLC Enclosures 2x Network Enclosures for Control and PLC room 13x Power Distribution Enclosures 23x Junction Boxes 33x Instrument Solenoid Bank Enclosures PLC Inputs and Outputs 288x Analogue Inputs 224x Analogue Outputs 896x Digital Inputs 384x Digital Outputs Drives Control Engineered 58x Variable Speed Drives 1x Direct Online Starter 2x Soft starters Project Value Supply and Engineering R4.2M Completion Hardware Supply Complete Software Engineering Complete Commissioning July 2014 Foskor is a proudly South African producer of phosphates and phosphoric acid with international exposure. Foskor unlocks shareholder value through the profitable, responsible and sustainable beneficiation of phosphate rock into either phosphoric acid or phosphate-based granular fertilisers sold globally. Founded in 1951, Foskor’s Mining Division in Phalaborwa mines phosphate rock, from which Foskor’s Acid Division in Richards Bay produces phosphoric acid and phosphate- based granular fertilisers for local and international markets. The opencast mine in Phalaborwa has the capacity to produce 3 million tonnes per annum of phosphate rock concentrate from 35 million tonnes of ore mined per annum. Once crushed, milled, concentrated and dried, most of the phosphate rock concentrate is railed to Foskor’s processing plant in Richards Bay, 800 km away on the KwaZulu-Natal coast. The D Stream Flotation Plant Replacement (DSF) project originates from the Foskor’s infrastructure replacement strategy. This project will ensure that the installed flotation capacity remains at a level which makes it possible to produce circa 3 million tons of concentrate per annum (mtpa), therefore protecting the production strategy of the Phalaborwa operations. The project consists of new 600 tph flotation plant. AGE Technologies JHB was awarded the Supply, Engineering and Commissioning of the complete PLC and Scada Control System. The Control System consists of Schneider’s Quantum PLC and Adroit Scada System communicating through Hirschman switches. The project also consisted of the supply and manufacture of the Festo instrument solenoid bank enclosures.
  • 3. As Tharisa Mine is the largest known single chrome resource deposit in the world, the Group is well positioned to benefit from the projected growth in demand for chrome, which is primarily used in stainless steel manufacturing. MDM Engineering contracted AGE Technologies to supply in all the requirements of the Tharisa Expansion project.  Age’s scope of supply included:  Supply of all Siemens PLC hardware (S7-300 & S7-400)  Supply of all Siemens SCADA software (WinCC)  RIO Panel supply & manufacturing (34 panels)  Ethernet & Profibus fiber network installation, splicing, testing, certification and drawings (Est. 6000m fiber and 900 splices)  Supply, installation, configuration and commissioning of 4x Wireless Ethernet radios that links to 4x pump stations (4IPNET Radios)  2x Commissioning engineers to assist with I/O testing & process commissioning (I/O count 1546)  General supply of cable, junction boxes & any other equipment needed throughout the project  Configuration of all networks running through OLM’s and the setup of the OLM’s  Product used in the project  Multi core Instrument cable to the value of R400,000.00  Siemens OLM  Outdoor Fibre cable (total of 18.7kms)  Network Switches (3 port & 6 port)  All fiber equipment inc. adapters, connectors, pigtails & cable  Scope of work to be done  Fiber Network  Installation of fiber cable.  Installation of splice boxes.  Installation of patch leads  Supply IPDB’s  Installation of a Profibus over fiber network  Total value of the project upon completion  5.9 million  Duration of the project  8 months
  • 4. Solution provided to company The physical structure was constructed by FAMAK in Poland and shipped to Mozambique. The electrical design and construction (wiring, cabling, PLC software and MCC cabinets) took place in South Africa. It was assembled in Beira, and the electrical and instrumentation installation commenced after. AGE Technologies did PLC and SCADA software development and will be responsible for commissioning.  Products used in the project PLC control system: Siemens S7-300 PLC with ET200S Distributed IO Motor control: Siemens SIMOCODE's and Siemens Micromaster VSD's Instruments: majority is supplied from Schneider but includes Siemens, Rockwell and Weidmuller All Cabling used on the Stacker predominantly from Jaycor and Africa Cables  Relevant information MCC's were constructed by Raise and Lower AGE provided 3 containers, operator cabin with all equipment inside, all PLC and networking equipment, all electrical cables, equipment, drives, relays, circuit breakers & switchgear One 630 kVA, 6.6kV/400V transformer People involved in the project  Norman Jackson – Project Manager - Design  Paul van Rooyen – Project Manager - Electrical Design and hardware  Gabriel van der Merwe – Project Technician - SCADA, Instrumentation Design, Hardware  Karlin Gomo- PLC Programming and Functional Design Specification Project Scope & Objectives AGE Technologies was responsible for the design manufacturer of the entire electrical and instrumentation requirements of the Stacker Machine that was installed at the new coal terminal in Beira Harbour, Mozambique. AGE Technologies provided the PLC and electrical control systems.
  • 5. AGE Technologies JHB (Ltd) together with Instrumentation & Electrical Consultants had to supply King Shaka International Airport with Equipment & Design of an Redundant Fibre Profibus and Profinet Networks with Siemens S7-400 Hot Standby PLC in SIL3 Safety and Standard I/O.  Duration of the project Started 1 May 2010 and ran for the duration of 5-7 months.  The problem was to provide Siemens Equipment that could be integrated into a reliable fail-safe system for the Fuel Storage System at the Airport.  Solution Provided We provided them with a Siemens S7-400 Hot Standby PLC with Redundant networks and Dual Redundant WinCC SCADA.  Products in the project Siemens S7-400 Hot Standby PLC, SIL3 Safety ET 200 IO Stations, Standard ET200 IO Stations, Redundant WinCC SCADA, Dual Redundant Profibus Networks, Dual Redundant Profinet Networks  Scope of work AGE was responsible for assisting with the design of the PLC/SCADA system, to make sure that a working system was offered to the end user, and to supply the actual PLC hardware and SCADA software packages. IEC did the actual system integration and wrote most of the application software. Some software for leak-detection was written in Germany.
  • 6. Age Technologies JHB- a member of the Age of Africa Technologies Group - were commissioned by ESKOM to come up with a simple yet intelligent design for the ash conveyor protection system at their Kendal Power Station in Mpumalanga.  Design Owing to the length of the ash handling conveyor, the protection system had to incorporate enhanced fault finding and accurate trip site location . This unique design in long-line conveyor protection is a world first. All of ESKOM's criteria were met and incorporated all the other aspects of conveyor related alarms such as belt rip, misalignment, and blocked chute detection, yet there are no electronics in the field.  Duration The system, which took six months and comprised 66 man months from conception to completion, is so efficient and easy to maintain that AGE are pleased to report their client is extremely pleased with the reliability of the plant.  Scope AGE's brief included the overall project management, PLC engineering using a Siemens Su110 PLC, equipment supply, installation and commissioning.  The project, which was repeat business for AEG with ESKOM, was completed on time and within budget.
  • 7.  In line with their philosophy of client relationship marketing, AGE Engineering undertook this project at Fry's metals of Wadeville during their annual end-of-year shutdown. Although small in size the process to be automated was quite sophisticated from the point of view of all the different processes that had to be brought together.  Lead reclamation has it's own characteristics and AGE Engineering had to firstly familiarise themselves with the reclamation process. Once that was done they had to write the process software for the ingot pouring, handling and stacking system.  In addition to the InTouch SCADA package, ControlWize made use of a Microsoft SQL Server with an Access data base for the train handling facility at the load-out station.  The project included management, PLC engineering, equipment supply, installation and commissioning and took one man-month to execute.  Being a shutdown there was no margin for error and the automation, using an Allen Bradley S5 PLC, went off smoothly with no technical hitches experienced at handover.
  • 8.  ESKOM identified the need for the replacement of the coal stacker/ reclaimer control system at their dry cooled power station near Ellisras in the Northern province.  Overview AEG's construction division were awarded the project to design, supply and install such a system to provide plant alarm status, monitoring and reporting. This was repeat business for AEG who also executed the station MV switchgear project and the overland Ash Handling conveyor systems. The project was carried out during the transition period from AEG to AGE Engineering and was completed ahead of the prescribed contract period.  Duration of project The 12-month contract, which comprised 64 man-months effort, included the full project management, PLC engineering using a Modicon 'A' series PLC, full equipment supply, installation and commissioning.  Significant feature of this project was the design, by one of AGE's engineers, of unique connection terminals - housed in the PLC cabinet - which comprised full lightning protection on all inputs and outputs. This type of terminal has now become a standard in the electrical industry
  • 9.  Zimplats was established by Delta Gold Limited (Delta) in 1998 to take over its platinum interests. In May 1999 the company purchased BHP’s interests in the Hartley Platinum and the Mhondoro Platinum Joint Ventures which included a concentrator and smelter.  AGE’s Scope of work to be done – – Capturing of Plant wide process Data and Historizing for minimum period of twelve months – Alarm & Fault Logging which will detail the precise reason for Plant Stoppage to enable the Technician to rectify the fault with minimum down time – Up to date PLC and SCADA software – New Plant Computers and Servers with web reports available for Plant Managers. – The enhancement of the electrode slipping system enables it to measure the actual state of the electrode slipping system. The new program functions just as the existing program with the additional benefits: – Shorter slipping times – Any given movement, de-clamping, raising, clamping or lowering takes only as long as required. – Reliability of the electrode slipping system is improved. Error conditions are alarmed on the SCADA  Significant Features of the project – AGE Technologies offered the following enhancements and benefits to their current system – Plant wide Server/Client topology which centralizes their Data for easier Alarming, Data Retrieval and Reporting and Backup. – First Up Alarming programmed into their PLCs, with clear Alarm and Fault messaging at their SCADA Clients – Fixed format Daily Reports for the Smelter Plant and the Concentrator Plant – Device Status and Interlock Display Dash boards to assist operators. – Upgraded two obsolete TSX17 PLCs to Modicon M340 under Unity Software. – Conversion of Concept PLC programs to Unity by upgrading PLC firmware – Removed redundant MB+ network that was no longer required. – Auto-save Change Management Software, that automatically keeps all their PLCs and SCADA software backed up and tracks any software changes that is being implemented. – Archestra System Platform Software and Unity PLC Software Training for Engineers/Technicians – New latest Dell Computers (Severs and Work Stations) for their entire Plant Operations. – Onsite System Commissioning  Duration of the project –  ± 8 months  Budget –  R 2 ,495 024.00
  • 10. Set amongst the beautiful rolling hills and valleys of the KwaZulu-Natal midlands, the largest waterworks in KZ Natal and most modern in the country, Umgeni Water's Midmar Dam Waterworks, was successfully commissioned, on schedule, in October 1996.  Built on the site of the old Mill Falls waterworks outside Howick, the first phase of 250 Ml/day will be augmented to an ultimate capacity of 1000 Ml/day by 2005, when predicted water demand is expected to be around 450 million cubic metres per year.  AEG were originally awarded the subcontract to main contractor Aquazur but owing to the disruptions within AEG at the time, leading up to their ultimate sale, AGE was contracted to complete the contract. In order to minimise disruptions to the contract AGE Engineering made use of all the existing AEG personnel, some of whom were sent for training in Germany in order to commission the MCC's bus system.  Duration The multi-million rand project was 14 months in duration and comprised 130 man-months effort. AGE Engineering's scope included Project management, PLC engineering, equipment supply - including the sophisticated Motor Control Centres, installation and commissioning
  • 11.  Background The brewery has ten Cellars. Each cellar is divided into different tanks, in which the fermentation takes place. Glycine is passed through tubes wound round the tanks to control the temperature during the brewing process. A solenoid valve is used to open and close flow of glycine. Pt100 at the top and bottom of each tank are used to monitor the temperature. The temperature is either monitored using the Top/ Bottom PT100 or both PT100s. should any of the PT100 fail the PLC will switch the control completely to the healthy one. Each of the tanks can be in one of the following modes: Ready, Filling, Fermentation, Chill or Cleaning in Progress (CIP)  AGE’s Scope of work to be done – The plant is divided into three Control systems, i.e. Cellar 1&2, Cellar 3-8 and Cellar 9&10. A SCADA (Supervisory Control And Data Acquisition) system will provide a graphical overview of the whole control system. An Ethernet TCP/IP network will link the three Systems and the SCADA.  Significant Features of the project –  HMI will provide the operator with status of each Cellar and Tank  SCADA system will provide a graphical overview of the plant, with the status of each tank.  A graph of all temperatures and operator inputted information will be available.  The fermentation manager will be able to change the operating mode of a tank, and with a login password he can also change the temperature set points.  A historical log will also be kept of all tank batches that have been brewed  Keeping data for each batch is important for quality purposes.  The Mode of operation of each tank will be colour coded - determined by its background Colour in the overview page.  A Siren and alarm lamp will be installed at each control system to warn the operator of an alarm condition  Products used –  Modicon TSX Premium from Schneider Electric  PLC software - PL7 Pro for TSX Premium PLC  HMI - is an EZTOUCH, Modbus/TCP 8” Slim panel  SCADA System - Intouch version 9, with 1000 tag licence  Spider, 5 port 10/100 Ethernet switches for each Control system  Duration of the project – 6 months  Total Value – R 605,906.34
  • 12.  Background Botswana Ash (Pty) Ltd began operating in April 1991. The mine is located at Sua Pan, which is approximately 180 kilometres from Francistown in northern Botswana. The Company produces Soda Ash and Salt. All the activities of the mine are undertaken at Sua Pan – from production through to marketing and sales and administration. The primary market for Soda Ash is South Africa, where most of the products are used in the glass industry. They also produce fine and coarse salt. Like Soda Ash, the Salt products are sold within the continent. Production capacity is 650 000 tonnes per annum.  AGE’s Scope of work to be done To upgrade of old absolute TSX-17-20 Telemecanique PLC’s to the newest Schneider M340 PLC with UnityPro Software for the Soda Ash Stacker as well as the Salt Reclaimer. AGE Technologies also replaced all panels on site. In the Salt Reclaimer the panels was replaced by stainless steel panels to help prevent rust. The upgrade included – Supply of all Hardware Software Engineering & Installation and Commissioning  Products used Schneider M340 PLC with UNITYPRO Software CPU340‐20 MODBUS ETHERNET Radio telemetry System PLC, Termister Relays & Output Devices Supply Breakers Emergency Bypass Keyswitch New Panel Electrical Drawings plus Field PLC Application Software Development according to the FDS documents HMI Application Software development PLC/HMI Onsite PLC software Commissioning  Duration of the project 6 weeks Total Value Soda Ash Stacker – R 420 000 Salt Reclaimer – R 350 000
  • 13. Xstrata are one of the world's largest global diversified natural resource companies and a major producer and marketer of more than 90 commodities. Their presence at each stage of the commodities chain provides us with superior market insight and access to opportunities. They have a strong footprint in both established and emerging regions for natural resources. SCOPE OF WORK: Product Included: IMPALA PLANT - Supply and Install an Enermax plus Meter with Modem for remote metering outside 400v Substation in Metering box.  Supply 400V, 3 phase 4 wire 5Amp Enermax Plus meter with external memory.  Supply cell modem for meter and sim card.  Supply 3 x 1500/5 metering current transformers. 2. WONDERKOP PLANT - Supply and Install an Enermax Plus Meter with Modem for remote on 11KV Incomer panel.  Supply 110V, 3 Phase 4 wire 5Amp Enermax Plus meter with external memory.  Supply cell modem for meter and sim card.  Supply 3 x 5/5 metering interposing current transformers 3. EPL PLANT - Supply and Install an Enermax Plus Meter with Modem for remote on 11kV Incomer panel.  Supply 110V, 3 Phase 4 wire 5Amp Enermax Plus meter with external memory.  Supply cell moden for meter and sim card.  Supply 3 x 5/5 metering interposing current transformer. K2.5 PLANT - Supply and install an Enermax Plus Meter with Modem for remote on 11kv Fdr panel.  Supply 110V, 3 Phase 4 wire 5Amp Enermax Plus meter with external memory.  Supply cell moden for meter and sim card.  Supply 3 x 5/5 metering interposing current transformer. 5. K4 PLANT - Supply and install an Enermax Plus Meter with Modem for remote on 11kV panel.  Supply 110V, 3 Phase 4 wire 5Amp Enermax Plus meter with external memory.  Supply cell moden for meter and sim card.  Supply 3 x 5/5 metering interposing current transformer. 6. WPL PLANT - Supply and Install an Enermax Plus Meter with Modem for remote on 11kV Incomer panel.  Supply 110V, 3 Phase 4 wire 5Amp Enermax Plus meter with external memory.  Supply cell modem for meter and sim card.  Supply 3 x 5/5 metering interposing current transformer. 7. Remote data base for all remote meters  Supply 1 x Meter reader that interface with modem, including software Significant features of the project  Remote access from anywhere in the country with cellular coverage to all metering data achieved. Software interface gave the ability to generate electrical bill for energy consumption audit. Duration of the project – 4 weeks Total value of the project upon completion – R156,000.00
  • 14.  AGE Technologies JHB (Pty) Ltd. secured the contract to assist Arcelor Mittal’s planning department with the design, project management and commissioning of the automation system required at the Vanderbijlpark works Continuous Casting plant.  Scope of work to be done Was the equipment supply and product training of Modicon Quantum PLC's and FactoryLink SCADA. However, the whole project was to be executed during a planned shutdown period and required careful planning in order to minimise disruption at the changeover.  Products used The PLC was programmed in hot stand-by configuration and it was decided to make use of standard terminal cabling in order to facilitate a smoother transition.  Duration of the project The project was five months in preparation and comprised 3 man-months effort in execution.
  • 15.  In one of the longest ongoing contracts on AGE Engineering's order book, their contract to provide automation packages to Pretoria City Council pump stations must rate as their longest.  Started in mid 1995 - whilst still operating as AEG Construction - their brief was to supply an automation system to 5 pump stations within the greater Pretoria metro pole.  The first one completed was at the Fountains station, followed by Garsfontein, Elardus Park, Klapperkop and finally Mooikloof over a period of four-and-a-half years.  The project was run out of Pretoria's department of water environment and executed as five separate contracts.  AGE's brief was to provide the project management, PLC Engineering using Modicon Compact and Micro PLC's, the equipment supply, installation and commissioning. What started out as first-time business for AGE developed into a long-term relationship and resulted in repeat business.
  • 16.  Main contractor CHI Control appointed AGE Engineering to carry out the PLC engineering, equipment supply and commissioning of the man riding and ore belts project at Randgold's Lorraine Gold Mine in the Free State.  This project, although only one month in duration was very sophisticated in that it called for an interface from the Modbus to the Allen Bradley soft starters Scan Port.  The Allen Bradley PLC interfaced to an AFE SCADA data panel via Modbus an AFE data panel interfaced to an existing SCADA via Modbus