M. C. Sharma
Associate Professor
Department of Commerce
Shaheed Bhagat Singh Evening College
(University of Delhi)
Delhi
Updated on 29/03/2020
1
Learning Objectives
 Concept of Activity Based Costing (ABC)
 Significant Terms: Cost Objectives, Activities, Cost Pool
and Cost Drivers
 Steps Involved in ABC
 Use of Activity Based Information
 Activity Based Costing Vs. Trading Costing
 Solved Practical Problem
 Practice Questions with Answer
2
Traditional Method of Absorption
 In traditional method of overhead absorption, a
general or blanket rate is used, which is volume based.
For example:
 Factory overheads as a percentage on direct
material/direct labour or prime cost,
 Labour hour rate or machine hour rate.
3
Concept of Activity Based Costing (ABC)
 According to Cooper and Kalpan, “ABC (Activity based
costing) system calculate the costs of individual activities
and assign costs to cost objects such as products and
services on the basis of activities undertaken to produce
each product or service.”
 Activity based costing (ABC) is a method of assigning (or
absorbing) overheads to end products and services on the
basis of benefits received by the products and services from
indirect activities, instead of using a blanket rate of
absorption. Production activities are divided into major
activities, which are used as a cost centers. Overheads cost
are pooled at these center and then overhead rates are
calculated per activity. And then these rates are applied to
charge overheads to end products.
4
Significant Terms
 Cost Objects: Generally the products are cost objects, but
Customers, services or locations may also be the cost
objects.
 Activities: Activities are of two types: (a) Production
activities, like manual and mechanical process, assembly
and (b) Support Activities, like, purchase, storage, repairs
and maintenance, etc.
 Cost Pool: Cost pool is an activity cost center at which
costs are pooled.
 Cost Drivers: Cost driver may be defined as a factor or
cause for incurrence of overhead costs. For example:
machine our, number of purchase orders, number of set-
ups, etc.
5
Examples of Activity Cost Drivers
 For purchase of materials: number of purchase
orders, number of receipts of materials, number of
inspections.
 For setting-up of machines: number of set-ups or
number of set-up hours.
 For production activity: machine hours or labour
hours.
 For repairs and maintenance activity: Number of
service calls, time spent in repairs and maintenance.
6
Steps Involved in ABC
 Identify significant activities
 Calculate the total cost of each activity (i.e. cost pool)
 Determine the appropriate activity cost driver for each
activity
 Calculate the activity cost driver rate:
𝐴𝑐𝑡𝑖𝑣𝑖𝑡𝑦 𝑐𝑜𝑠𝑡 𝑑𝑟𝑖𝑣𝑒𝑟 𝑟𝑎𝑡𝑒
=
𝑇𝑜𝑡𝑎𝑙 𝐶𝑜𝑠𝑡 𝑜𝑓 𝑎𝑛 𝑎𝑐𝑡𝑖𝑣𝑖𝑡𝑦
𝐴𝑐𝑡𝑖𝑣𝑖𝑡𝑦 𝑐𝑜𝑠𝑡 𝑑𝑟𝑖𝑣𝑒𝑟 𝑣𝑜𝑙𝑢𝑚𝑒
 Charge activity cost to end products, jobs or services:
Activity cost to be charged= Activity consumed ×
𝐴𝑐𝑡𝑖𝑣𝑖𝑡𝑦 𝑐𝑜𝑠𝑡 𝑑𝑟𝑖𝑣𝑒𝑟 𝑟𝑎𝑡𝑒
7
Use of Activity Based Information
 Focus on the factors or causes of the cost
 Helps in ascertaining accurate product cost due to
understanding the cost behavior
 Focus on value-added activities
 Provides strategic cost information, which helps in
long-term pricing and profitability decisions
 Improved cost basis
8
Activity Based Costing Vs Traditional Costing
 Effectiveness of purpose: ABC method serves the
objectives of product costing and pricing decisions
more effectively.
 Basis of identification: Activites Vs Department:
Under traditional costing method overheads are
attributed to a department while under ABC system,
overheads are attributed to major activities performed
in the department.
 Terms used: Under ABC system, ‘cost drivers’ are used
for major activities for overhead absorption, while
traditional method uses a blanket rate.
9
DU B. Com. (H) 2006 &2013
A Company manufacturing two products furnishes the following data for a year:
The annual overheads are as under:
 Volume related activity cost Rs. 5,50,000
 Setup related cost Rs. 8,20,000
 Purchase order related cost Rs. 6,18,000
You are required to calculate the cost per unit of each product A and B based on (i)
traditional method of charging overheads and (ii) activity based costing method.
10
Products annual output
(units)
total machine
hours
total number of
purchase orders
total number of
set-ups
A 5,000 20,000 160 20
B 60,000 1,20,000 384 44
 Solution:
Total Overheads = Rs. 5,50,000 + Rs. 8,20,000 + Rs.
6,18,000 = Rs. 19,88,000
Total Machine Hours = 20,000 + 120,000 = 1,40,000
Total Number of Purchase Orders = 160 + 384 = 544
Total Number of Set-ups = 20 + 44 = 64
1. Traditional Method of charging Overheads
Machine Hour Rate (General) =
𝑇𝑜𝑡𝑎𝑙 𝐴𝑛𝑛𝑢𝑎𝑙 𝑂𝑣𝑒𝑟ℎ𝑒𝑎𝑑𝑠
𝑇𝑜𝑡𝑎𝑙 𝑀𝑎𝑐ℎ𝑖𝑛𝑒 𝐻𝑜𝑢𝑟𝑠
=
19,88,000
1,40,000
= Rs. 14.20 per hour
11
 Solution:
Total Overheads = Rs. 5,50,000 + Rs. 8,20,000 + Rs. 6,18,000 = Rs. 19,88,000
Total Machine Hours = 20,000 + 120,000 = 1,40,000
Total Number of Purchase Orders = 160 + 384 = 544
Total Number of Set-ups = 20 + 44 = 64
1. Traditional Method of charging Overheads
Machine Hour Rate (General) =
𝑇𝑜𝑡𝑎𝑙 𝐴𝑛𝑛𝑢𝑎𝑙 𝑂𝑣𝑒𝑟ℎ𝑒𝑎𝑑𝑠
𝑇𝑜𝑡𝑎𝑙 𝑀𝑎𝑐ℎ𝑖𝑛𝑒 𝐻𝑜𝑢𝑟𝑠
=
19,88,000
1,40,000
=
Rs. 14.20 per hour
2. Activity Based Costing
(a) For Volume related Costs, Machine Hour Rate
=
𝑇𝑜𝑡𝑎𝑙 𝐴𝑛𝑛𝑢𝑎𝑙 𝑂𝑣𝑒𝑟ℎ𝑒𝑎𝑑𝑠 𝑓𝑜𝑟 𝑣𝑜𝑙𝑢𝑚𝑒 𝑟𝑒𝑙𝑎𝑡𝑒𝑑 𝑐𝑜𝑠𝑡𝑠
𝑇𝑜𝑡𝑎𝑙 𝑀𝑎𝑐ℎ𝑖𝑛𝑒 𝐻𝑜𝑢𝑟𝑠
=
5,50,000
1,40,000
= Rs. 3.93 per hour
(b) For set-up related Costs, Set-up Rate
=
𝑇𝑜𝑡𝑎𝑙 𝐴𝑛𝑛𝑢𝑎𝑙 𝑂𝑣𝑒𝑟ℎ𝑒𝑎𝑑𝑠 𝑓𝑜𝑟 𝑠𝑒𝑡−𝑢𝑝 𝑟𝑒𝑙𝑎𝑡𝑒𝑑 𝑐𝑜𝑠𝑡𝑠
𝑇𝑜𝑡𝑎𝑙 𝑛𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑠𝑒𝑡−𝑢𝑝𝑠
=
8,20,000
64
=
Rs. 12,850.50 per set-up
12
(c) For purchase related Costs, Overheads per purchase order
=
𝑇𝑜𝑡𝑎𝑙 𝐴𝑛𝑛𝑢𝑎𝑙 𝑂𝑣𝑒𝑟ℎ𝑒𝑎𝑑𝑠 𝑓𝑜𝑟 𝑝𝑢𝑟𝑐ℎ𝑎𝑠𝑒 𝑟𝑒𝑙𝑎𝑡𝑒𝑑 𝑐𝑜𝑠𝑡𝑠
𝑇𝑜𝑡𝑎𝑙 𝑛𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑝𝑢𝑟𝑐ℎ𝑎𝑠𝑒 𝑜𝑟𝑑𝑒𝑟𝑠
=
6,18,000
544
= Rs. 1,136.03 per order
A) Statement of Overhead Cost Per Unit (Traditional Method)
13
Products Annual
Output
Total machine
Hours
Overhead Costs Overhead Cost
per unit
A 5,000 20,000 20,000 x 14.20
= 2,84,000
2,84,000/5,000
= 56.80
B 60,000 1,20,000 1,20,000 x 14.20
= 17,04,000
17,04,000/60,000
= 28.40
B) Statement of Overhead Cost Per Unit (Activity Based Costing Method)
14
Product and
Annual Output
Overheads Costs Overhead cost
per unit
A (5,000 units) Cost related to Volume
activities
20,000 x 3.93
= 78,600
Cost related to Purchases 160 x 1,136.03
= 1,81,765
Cost related to set-ups 20 x 12,812.5
= 2,56,250
Total Overheads Costs 5,16,615 5,16,615/5,000
= 103.32
B (60,000 units) Cost related to Volume
activities
1,20,000 x 3.93
= 4,71,600
Cost related to Purchases 384 x 1,136.03
= 4,36,236
Cost related to set-ups 44 x 12,812.5
= 5,63,750
Total Overheads Costs 14,71,586 14,71,586/60,000
= 24.53
DU B. Com. (H) 2012
A company manufactures two products A and B using common
facilities. the following cost data for a month are presented to you:
 Machine activity expenses Rs. 3,00,000
 Setup related expenses Rs. 30,000
 Expenses related to orders Rs. 35,000
Calculate the overheads per unit absorbed using activity based costing
approach.
15
Product Units
produced
Direct
Labour
Hours per
unit
Machine
Hours per
unit
Set-ups of
machines
Orders
A 1,000 2 6 15 18
B 2,000 3 1.5 50 70
DU B. Com. (H) 2012 – Detailed Answer
(a) For machine related Costs, Machine Hour Rate
=
𝑇𝑜𝑡𝑎𝑙 𝑂𝑣𝑒𝑟ℎ𝑒𝑎𝑑𝑠 𝑓𝑜𝑟 𝑚𝑎𝑐ℎ𝑖𝑛𝑒 𝑟𝑒𝑙𝑎𝑡𝑒𝑑 𝑐𝑜𝑠𝑡𝑠
𝑇𝑜𝑡𝑎𝑙 𝑀𝑎𝑐ℎ𝑖𝑛𝑒 𝐻𝑜𝑢𝑟𝑠
=
3,00,000
9,000
= Rs. 33.33 per hour
(b) For set-up related Costs, Set-up Rate
=
𝑇𝑜𝑡𝑎𝑙 𝑂𝑣𝑒𝑟ℎ𝑒𝑎𝑑𝑠 𝑓𝑜𝑟 𝑠𝑒𝑡−𝑢𝑝 𝑟𝑒𝑙𝑎𝑡𝑒𝑑 𝑐𝑜𝑠𝑡𝑠
𝑇𝑜𝑡𝑎𝑙 𝑛𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑠𝑒𝑡−𝑢𝑝𝑠
=
30,000
65
= Rs. 461.54 per set-up
(c) For order related Costs, Overheads per order
=
𝑇𝑜𝑡𝑎𝑙 𝑂𝑣𝑒𝑟ℎ𝑒𝑎𝑑𝑠 𝑓𝑜𝑟 𝑜𝑟𝑑𝑒𝑟 𝑟𝑒𝑙𝑎𝑡𝑒𝑑 𝑐𝑜𝑠𝑡𝑠
𝑇𝑜𝑡𝑎𝑙 𝑛𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑜𝑟𝑑𝑒𝑟𝑠
=
35,000
88
= Rs. 397.73 per order
(d) Overhead cost per unit (Product A) = 214.08 (200+6.92+7.16)
(e) Overhead cost per unit (Product B) = 75.46 (50+11.54+13.92)
16
DU B. Com. (H) 2011
Major Limited manufactures two products a and b. the product is low volume
atom and its sales are only 5,000 units per annum. the product B is a high
volume item and sales are 20,000 units per annum. both products required to
direct labour hours for completion. the company works 50,000 direct labour
hours each year as given below:
 Poduct A : 5000 units x 2 hours = 10,000 hours
 Product B: 20,000 x 2 hours = 40,000 hours
Details of cost for material and labour for each product (per unit) are given
below:
 Direct materials: Product A – Rs. 25 and Product B – Rs. 15
 Direct labour @ Rs. 5 per hour : Product A – Rs. 10 and Product B – Rs. 10
The company's total manufacturing overhead costs are Rs. 8,75,000 per
annum. The company has analysed its operations and has determined the five
activities act as cost drivers in the incurrence of overhead costs. Data relating
to the five activities are as follows:
17
DU B. Com. (H) 2011 (Continued)
A company manufactures two products A and B using common facilities. the
following cost data for a month are presented to you:
You are required to computer per unit cost for each product using (i) direct
labour hour rate method for absorption of overhead cost and (ii) activity based
costing technique for absorption of overhead cost comment on your results.
18
Activity Traceable
costs (Rs.)
Number of events or transactions
Total Product A Product B
Machine set-ups 2,30,000 5,000 3,000 2,000
Quality Inspections 1,60,000 8,000 5,000 3,000
Production Orders 81,000 600 200 400
Machine hours worked 3,14,000 40,000 12,000 28,000
Materials Receipts 90,000 750 150 600
Total 8,75,000
DU B. Com. (H) 2011 – Detailed Answer
(1) Computation of product cost using direct labour hour rate
=
𝑇𝑜𝑡𝑎𝑙 𝑚𝑎𝑛𝑢𝑓𝑎𝑐𝑡𝑢𝑟𝑖𝑛𝑔 𝑂𝑣𝑒𝑟ℎ𝑒𝑎𝑑𝑠
𝑇𝑜𝑡𝑎𝑙 𝐷𝑖𝑟𝑒𝑐𝑡 𝐿𝑎𝑏𝑜𝑢𝑟 𝐻𝑜𝑢𝑟𝑠
=
8,75,000
50,000
= Rs. 17.50 per hour
Product cost per unit (Product A) = 70 (DM 25+DL 10 + Overheads 35)
Product cost per unit (Product B) = 60 (DM 15+DL 10 + Overheads 35)
(2) Computation of product cost using ABC
(i) Cost per set-up = Rs. 46
(ii) Cost per inspection = Rs. 20
(iii) Cost per production order = Rs. 135
(iv) Cost per machine hour worked = Rs. 7.85
(v) Cost per material receipt = Rs. 120
Overhead cost per Unit = Product A – Rs. 75.44 and Product B – Rs. 24.89
Product cost per unit (A) = 110.44 (DM 25+DL 10 + Overheads 75.44)
Product cost per unit (B) = 49.89 (DM 15+DL 10 + Overheads 24.89)
19
THANKS
Please inform
your feedback, doubts and suggestions to me.
Email: m_c_Sharma@yahoo.com
20

Contenu connexe

Tendances

importance of cost accounting
importance of cost accountingimportance of cost accounting
importance of cost accounting
annajacobanu
 
Material control and its techniques
Material control and its techniquesMaterial control and its techniques
Material control and its techniques
nidhikathakur
 
Activity base costing.pptx presentation
Activity base costing.pptx presentationActivity base costing.pptx presentation
Activity base costing.pptx presentation
Tanweer Sudhan
 

Tendances (20)

importance of cost accounting
importance of cost accountingimportance of cost accounting
importance of cost accounting
 
Target Costing
Target CostingTarget Costing
Target Costing
 
Gordon's model
Gordon's modelGordon's model
Gordon's model
 
Overheads
OverheadsOverheads
Overheads
 
Own or Lease.ppt
Own or Lease.pptOwn or Lease.ppt
Own or Lease.ppt
 
Contract costing
Contract costingContract costing
Contract costing
 
Cost Accounting
Cost AccountingCost Accounting
Cost Accounting
 
Indian Accounting standards
Indian Accounting standardsIndian Accounting standards
Indian Accounting standards
 
Material control and its techniques
Material control and its techniquesMaterial control and its techniques
Material control and its techniques
 
Target costing Prepared By Melwin Mathew
Target costing Prepared By Melwin MathewTarget costing Prepared By Melwin Mathew
Target costing Prepared By Melwin Mathew
 
Target costing
Target costingTarget costing
Target costing
 
Working capital
Working capitalWorking capital
Working capital
 
Marginal Costing
Marginal CostingMarginal Costing
Marginal Costing
 
Absorption Costing Concept
Absorption Costing ConceptAbsorption Costing Concept
Absorption Costing Concept
 
Cost of capital ppt
Cost of capital pptCost of capital ppt
Cost of capital ppt
 
marginal and absorption costing
marginal and absorption costingmarginal and absorption costing
marginal and absorption costing
 
Standard costing
Standard costingStandard costing
Standard costing
 
Activity base costing.pptx presentation
Activity base costing.pptx presentationActivity base costing.pptx presentation
Activity base costing.pptx presentation
 
Cost of capital
Cost of capitalCost of capital
Cost of capital
 
Activity based costing(prabha)
Activity based costing(prabha)Activity based costing(prabha)
Activity based costing(prabha)
 

Similaire à Activity based costing

Activity based costing
Activity based costingActivity based costing
Activity based costing
Rahul Kumar
 
Cost and Management Accounting I Chapter 3 (2)(2)-1 (1).pptx
Cost and Management Accounting I Chapter 3 (2)(2)-1 (1).pptxCost and Management Accounting I Chapter 3 (2)(2)-1 (1).pptx
Cost and Management Accounting I Chapter 3 (2)(2)-1 (1).pptx
ObsaKamil
 
Management AccountingActivity Based Costing vs Absorption Cost.docx
Management AccountingActivity Based Costing vs Absorption Cost.docxManagement AccountingActivity Based Costing vs Absorption Cost.docx
Management AccountingActivity Based Costing vs Absorption Cost.docx
infantsuk
 
CA Ch.4-Job Costing-part 1-Nureni.pdf
CA Ch.4-Job Costing-part 1-Nureni.pdfCA Ch.4-Job Costing-part 1-Nureni.pdf
CA Ch.4-Job Costing-part 1-Nureni.pdf
sandiibrahim3
 
Activity Based Costing.pptx
Activity Based Costing.pptxActivity Based Costing.pptx
Activity Based Costing.pptx
1986anu
 

Similaire à Activity based costing (20)

Activity Based costing
Activity Based costingActivity Based costing
Activity Based costing
 
Activity based costing
Activity based costingActivity based costing
Activity based costing
 
PPT on PM_Unit 1 .pptx.
PPT                  on PM_Unit 1 .pptx.PPT                  on PM_Unit 1 .pptx.
PPT on PM_Unit 1 .pptx.
 
Absorption costing
Absorption costingAbsorption costing
Absorption costing
 
Acc mgt noreen03 systems design activity based costing
Acc mgt noreen03 systems design activity based costingAcc mgt noreen03 systems design activity based costing
Acc mgt noreen03 systems design activity based costing
 
Abc costing
Abc costingAbc costing
Abc costing
 
Acct 326 week 4 midterm exam new 2016
Acct 326 week 4 midterm exam new 2016Acct 326 week 4 midterm exam new 2016
Acct 326 week 4 midterm exam new 2016
 
16-02-2023 accounting presentation.pptx
16-02-2023 accounting presentation.pptx16-02-2023 accounting presentation.pptx
16-02-2023 accounting presentation.pptx
 
Garrison18e_PPTch02A_ppt_Accessible.pptx
Garrison18e_PPTch02A_ppt_Accessible.pptxGarrison18e_PPTch02A_ppt_Accessible.pptx
Garrison18e_PPTch02A_ppt_Accessible.pptx
 
Cost and Management Accounting I Chapter 3 (2)(2)-1 (1).pptx
Cost and Management Accounting I Chapter 3 (2)(2)-1 (1).pptxCost and Management Accounting I Chapter 3 (2)(2)-1 (1).pptx
Cost and Management Accounting I Chapter 3 (2)(2)-1 (1).pptx
 
Management AccountingActivity Based Costing vs Absorption Cost.docx
Management AccountingActivity Based Costing vs Absorption Cost.docxManagement AccountingActivity Based Costing vs Absorption Cost.docx
Management AccountingActivity Based Costing vs Absorption Cost.docx
 
CA Ch.4-Job Costing-part 1-Nureni.pdf
CA Ch.4-Job Costing-part 1-Nureni.pdfCA Ch.4-Job Costing-part 1-Nureni.pdf
CA Ch.4-Job Costing-part 1-Nureni.pdf
 
Chap005 abc
Chap005 abcChap005 abc
Chap005 abc
 
Activity Based Costing
Activity Based CostingActivity Based Costing
Activity Based Costing
 
APC costing
APC costingAPC costing
APC costing
 
| Managerial Accounting | Chapter 7 | Systems Design: Activity-Based Costing ...
| Managerial Accounting | Chapter 7 | Systems Design: Activity-Based Costing ...| Managerial Accounting | Chapter 7 | Systems Design: Activity-Based Costing ...
| Managerial Accounting | Chapter 7 | Systems Design: Activity-Based Costing ...
 
Activity Based Costing.pptx
Activity Based Costing.pptxActivity Based Costing.pptx
Activity Based Costing.pptx
 
Ch04 m 06_09_10
Ch04 m 06_09_10Ch04 m 06_09_10
Ch04 m 06_09_10
 
abc COSTING
abc COSTINGabc COSTING
abc COSTING
 
Management and Cost Accounting 7th Edition Drury Solutions Manual
Management and Cost Accounting 7th Edition Drury Solutions ManualManagement and Cost Accounting 7th Edition Drury Solutions Manual
Management and Cost Accounting 7th Edition Drury Solutions Manual
 

Plus de Mahesh Chandra Sharma

Plus de Mahesh Chandra Sharma (20)

Straddle strategy for option trading
Straddle strategy for option tradingStraddle strategy for option trading
Straddle strategy for option trading
 
Integrated & non integral accounts part ii
Integrated & non integral accounts part iiIntegrated & non integral accounts part ii
Integrated & non integral accounts part ii
 
Integrated and non integrated accounts part i
Integrated and non integrated accounts part iIntegrated and non integrated accounts part i
Integrated and non integrated accounts part i
 
Contract costing
Contract costingContract costing
Contract costing
 
Reconciliation of cost and financial accounts
Reconciliation of cost and financial accountsReconciliation of cost and financial accounts
Reconciliation of cost and financial accounts
 
Accounting for depreciation 1
Accounting for depreciation 1Accounting for depreciation 1
Accounting for depreciation 1
 
Financial statements of sole trader with adjustments 2
Financial statements of sole trader with adjustments 2Financial statements of sole trader with adjustments 2
Financial statements of sole trader with adjustments 2
 
Financial statements of sole trader with adjustments 1
Financial statements of sole trader with adjustments 1Financial statements of sole trader with adjustments 1
Financial statements of sole trader with adjustments 1
 
Financial statements of sole trader without adjustments
Financial statements of sole trader without adjustmentsFinancial statements of sole trader without adjustments
Financial statements of sole trader without adjustments
 
Accounting principles
Accounting principlesAccounting principles
Accounting principles
 
Hire purchase system calculation of interest
Hire purchase system   calculation of interestHire purchase system   calculation of interest
Hire purchase system calculation of interest
 
Issue of bonus shares in india
Issue of bonus shares in indiaIssue of bonus shares in india
Issue of bonus shares in india
 
Redemption of preference shares and bonus issue
Redemption of preference shares and bonus issueRedemption of preference shares and bonus issue
Redemption of preference shares and bonus issue
 
Accounting for share capital
Accounting for share capitalAccounting for share capital
Accounting for share capital
 
Branch accounting stock and debtors method
Branch accounting   stock and debtors methodBranch accounting   stock and debtors method
Branch accounting stock and debtors method
 
Branch accounting debtors method
Branch accounting   debtors methodBranch accounting   debtors method
Branch accounting debtors method
 
Hire purchase system default and repossession
Hire purchase system   default and repossessionHire purchase system   default and repossession
Hire purchase system default and repossession
 
Hire purchase system stock and debtors method
Hire purchase system   stock and debtors methodHire purchase system   stock and debtors method
Hire purchase system stock and debtors method
 
Accounting an introduction
Accounting   an introductionAccounting   an introduction
Accounting an introduction
 
Buy back of shares - introduction and accounting
Buy back of shares - introduction and accountingBuy back of shares - introduction and accounting
Buy back of shares - introduction and accounting
 

Dernier

Mckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for ViewingMckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for Viewing
Nauman Safdar
 
Mifepristone Available in Muscat +918761049707^^ €€ Buy Abortion Pills in Oman
Mifepristone Available in Muscat +918761049707^^ €€ Buy Abortion Pills in OmanMifepristone Available in Muscat +918761049707^^ €€ Buy Abortion Pills in Oman
Mifepristone Available in Muscat +918761049707^^ €€ Buy Abortion Pills in Oman
instagramfab782445
 
!~+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUD...
!~+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUD...!~+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUD...
!~+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUD...
DUBAI (+971)581248768 BUY ABORTION PILLS IN ABU dhabi...Qatar
 
Mifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pills
Mifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pillsMifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pills
Mifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pills
Abortion pills in Kuwait Cytotec pills in Kuwait
 

Dernier (20)

Cracking the 'Career Pathing' Slideshare
Cracking the 'Career Pathing' SlideshareCracking the 'Career Pathing' Slideshare
Cracking the 'Career Pathing' Slideshare
 
Buy Verified TransferWise Accounts From Seosmmearth
Buy Verified TransferWise Accounts From SeosmmearthBuy Verified TransferWise Accounts From Seosmmearth
Buy Verified TransferWise Accounts From Seosmmearth
 
Rice Manufacturers in India | Shree Krishna Exports
Rice Manufacturers in India | Shree Krishna ExportsRice Manufacturers in India | Shree Krishna Exports
Rice Manufacturers in India | Shree Krishna Exports
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
 
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
 
New 2024 Cannabis Edibles Investor Pitch Deck Template
New 2024 Cannabis Edibles Investor Pitch Deck TemplateNew 2024 Cannabis Edibles Investor Pitch Deck Template
New 2024 Cannabis Edibles Investor Pitch Deck Template
 
Power point presentation on enterprise performance management
Power point presentation on enterprise performance managementPower point presentation on enterprise performance management
Power point presentation on enterprise performance management
 
Arti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdfArti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdf
 
Mckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for ViewingMckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for Viewing
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with Culture
 
HomeRoots Pitch Deck | Investor Insights | April 2024
HomeRoots Pitch Deck | Investor Insights | April 2024HomeRoots Pitch Deck | Investor Insights | April 2024
HomeRoots Pitch Deck | Investor Insights | April 2024
 
Mifepristone Available in Muscat +918761049707^^ €€ Buy Abortion Pills in Oman
Mifepristone Available in Muscat +918761049707^^ €€ Buy Abortion Pills in OmanMifepristone Available in Muscat +918761049707^^ €€ Buy Abortion Pills in Oman
Mifepristone Available in Muscat +918761049707^^ €€ Buy Abortion Pills in Oman
 
Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1
 
CROSS CULTURAL NEGOTIATION BY PANMISEM NS
CROSS CULTURAL NEGOTIATION BY PANMISEM NSCROSS CULTURAL NEGOTIATION BY PANMISEM NS
CROSS CULTURAL NEGOTIATION BY PANMISEM NS
 
Uneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration PresentationUneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration Presentation
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League City
 
Falcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business PotentialFalcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business Potential
 
!~+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUD...
!~+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUD...!~+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUD...
!~+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUD...
 
Mifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pills
Mifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pillsMifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pills
Mifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pills
 
Falcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to ProsperityFalcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to Prosperity
 

Activity based costing

  • 1. M. C. Sharma Associate Professor Department of Commerce Shaheed Bhagat Singh Evening College (University of Delhi) Delhi Updated on 29/03/2020 1
  • 2. Learning Objectives  Concept of Activity Based Costing (ABC)  Significant Terms: Cost Objectives, Activities, Cost Pool and Cost Drivers  Steps Involved in ABC  Use of Activity Based Information  Activity Based Costing Vs. Trading Costing  Solved Practical Problem  Practice Questions with Answer 2
  • 3. Traditional Method of Absorption  In traditional method of overhead absorption, a general or blanket rate is used, which is volume based. For example:  Factory overheads as a percentage on direct material/direct labour or prime cost,  Labour hour rate or machine hour rate. 3
  • 4. Concept of Activity Based Costing (ABC)  According to Cooper and Kalpan, “ABC (Activity based costing) system calculate the costs of individual activities and assign costs to cost objects such as products and services on the basis of activities undertaken to produce each product or service.”  Activity based costing (ABC) is a method of assigning (or absorbing) overheads to end products and services on the basis of benefits received by the products and services from indirect activities, instead of using a blanket rate of absorption. Production activities are divided into major activities, which are used as a cost centers. Overheads cost are pooled at these center and then overhead rates are calculated per activity. And then these rates are applied to charge overheads to end products. 4
  • 5. Significant Terms  Cost Objects: Generally the products are cost objects, but Customers, services or locations may also be the cost objects.  Activities: Activities are of two types: (a) Production activities, like manual and mechanical process, assembly and (b) Support Activities, like, purchase, storage, repairs and maintenance, etc.  Cost Pool: Cost pool is an activity cost center at which costs are pooled.  Cost Drivers: Cost driver may be defined as a factor or cause for incurrence of overhead costs. For example: machine our, number of purchase orders, number of set- ups, etc. 5
  • 6. Examples of Activity Cost Drivers  For purchase of materials: number of purchase orders, number of receipts of materials, number of inspections.  For setting-up of machines: number of set-ups or number of set-up hours.  For production activity: machine hours or labour hours.  For repairs and maintenance activity: Number of service calls, time spent in repairs and maintenance. 6
  • 7. Steps Involved in ABC  Identify significant activities  Calculate the total cost of each activity (i.e. cost pool)  Determine the appropriate activity cost driver for each activity  Calculate the activity cost driver rate: 𝐴𝑐𝑡𝑖𝑣𝑖𝑡𝑦 𝑐𝑜𝑠𝑡 𝑑𝑟𝑖𝑣𝑒𝑟 𝑟𝑎𝑡𝑒 = 𝑇𝑜𝑡𝑎𝑙 𝐶𝑜𝑠𝑡 𝑜𝑓 𝑎𝑛 𝑎𝑐𝑡𝑖𝑣𝑖𝑡𝑦 𝐴𝑐𝑡𝑖𝑣𝑖𝑡𝑦 𝑐𝑜𝑠𝑡 𝑑𝑟𝑖𝑣𝑒𝑟 𝑣𝑜𝑙𝑢𝑚𝑒  Charge activity cost to end products, jobs or services: Activity cost to be charged= Activity consumed × 𝐴𝑐𝑡𝑖𝑣𝑖𝑡𝑦 𝑐𝑜𝑠𝑡 𝑑𝑟𝑖𝑣𝑒𝑟 𝑟𝑎𝑡𝑒 7
  • 8. Use of Activity Based Information  Focus on the factors or causes of the cost  Helps in ascertaining accurate product cost due to understanding the cost behavior  Focus on value-added activities  Provides strategic cost information, which helps in long-term pricing and profitability decisions  Improved cost basis 8
  • 9. Activity Based Costing Vs Traditional Costing  Effectiveness of purpose: ABC method serves the objectives of product costing and pricing decisions more effectively.  Basis of identification: Activites Vs Department: Under traditional costing method overheads are attributed to a department while under ABC system, overheads are attributed to major activities performed in the department.  Terms used: Under ABC system, ‘cost drivers’ are used for major activities for overhead absorption, while traditional method uses a blanket rate. 9
  • 10. DU B. Com. (H) 2006 &2013 A Company manufacturing two products furnishes the following data for a year: The annual overheads are as under:  Volume related activity cost Rs. 5,50,000  Setup related cost Rs. 8,20,000  Purchase order related cost Rs. 6,18,000 You are required to calculate the cost per unit of each product A and B based on (i) traditional method of charging overheads and (ii) activity based costing method. 10 Products annual output (units) total machine hours total number of purchase orders total number of set-ups A 5,000 20,000 160 20 B 60,000 1,20,000 384 44
  • 11.  Solution: Total Overheads = Rs. 5,50,000 + Rs. 8,20,000 + Rs. 6,18,000 = Rs. 19,88,000 Total Machine Hours = 20,000 + 120,000 = 1,40,000 Total Number of Purchase Orders = 160 + 384 = 544 Total Number of Set-ups = 20 + 44 = 64 1. Traditional Method of charging Overheads Machine Hour Rate (General) = 𝑇𝑜𝑡𝑎𝑙 𝐴𝑛𝑛𝑢𝑎𝑙 𝑂𝑣𝑒𝑟ℎ𝑒𝑎𝑑𝑠 𝑇𝑜𝑡𝑎𝑙 𝑀𝑎𝑐ℎ𝑖𝑛𝑒 𝐻𝑜𝑢𝑟𝑠 = 19,88,000 1,40,000 = Rs. 14.20 per hour 11
  • 12.  Solution: Total Overheads = Rs. 5,50,000 + Rs. 8,20,000 + Rs. 6,18,000 = Rs. 19,88,000 Total Machine Hours = 20,000 + 120,000 = 1,40,000 Total Number of Purchase Orders = 160 + 384 = 544 Total Number of Set-ups = 20 + 44 = 64 1. Traditional Method of charging Overheads Machine Hour Rate (General) = 𝑇𝑜𝑡𝑎𝑙 𝐴𝑛𝑛𝑢𝑎𝑙 𝑂𝑣𝑒𝑟ℎ𝑒𝑎𝑑𝑠 𝑇𝑜𝑡𝑎𝑙 𝑀𝑎𝑐ℎ𝑖𝑛𝑒 𝐻𝑜𝑢𝑟𝑠 = 19,88,000 1,40,000 = Rs. 14.20 per hour 2. Activity Based Costing (a) For Volume related Costs, Machine Hour Rate = 𝑇𝑜𝑡𝑎𝑙 𝐴𝑛𝑛𝑢𝑎𝑙 𝑂𝑣𝑒𝑟ℎ𝑒𝑎𝑑𝑠 𝑓𝑜𝑟 𝑣𝑜𝑙𝑢𝑚𝑒 𝑟𝑒𝑙𝑎𝑡𝑒𝑑 𝑐𝑜𝑠𝑡𝑠 𝑇𝑜𝑡𝑎𝑙 𝑀𝑎𝑐ℎ𝑖𝑛𝑒 𝐻𝑜𝑢𝑟𝑠 = 5,50,000 1,40,000 = Rs. 3.93 per hour (b) For set-up related Costs, Set-up Rate = 𝑇𝑜𝑡𝑎𝑙 𝐴𝑛𝑛𝑢𝑎𝑙 𝑂𝑣𝑒𝑟ℎ𝑒𝑎𝑑𝑠 𝑓𝑜𝑟 𝑠𝑒𝑡−𝑢𝑝 𝑟𝑒𝑙𝑎𝑡𝑒𝑑 𝑐𝑜𝑠𝑡𝑠 𝑇𝑜𝑡𝑎𝑙 𝑛𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑠𝑒𝑡−𝑢𝑝𝑠 = 8,20,000 64 = Rs. 12,850.50 per set-up 12
  • 13. (c) For purchase related Costs, Overheads per purchase order = 𝑇𝑜𝑡𝑎𝑙 𝐴𝑛𝑛𝑢𝑎𝑙 𝑂𝑣𝑒𝑟ℎ𝑒𝑎𝑑𝑠 𝑓𝑜𝑟 𝑝𝑢𝑟𝑐ℎ𝑎𝑠𝑒 𝑟𝑒𝑙𝑎𝑡𝑒𝑑 𝑐𝑜𝑠𝑡𝑠 𝑇𝑜𝑡𝑎𝑙 𝑛𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑝𝑢𝑟𝑐ℎ𝑎𝑠𝑒 𝑜𝑟𝑑𝑒𝑟𝑠 = 6,18,000 544 = Rs. 1,136.03 per order A) Statement of Overhead Cost Per Unit (Traditional Method) 13 Products Annual Output Total machine Hours Overhead Costs Overhead Cost per unit A 5,000 20,000 20,000 x 14.20 = 2,84,000 2,84,000/5,000 = 56.80 B 60,000 1,20,000 1,20,000 x 14.20 = 17,04,000 17,04,000/60,000 = 28.40
  • 14. B) Statement of Overhead Cost Per Unit (Activity Based Costing Method) 14 Product and Annual Output Overheads Costs Overhead cost per unit A (5,000 units) Cost related to Volume activities 20,000 x 3.93 = 78,600 Cost related to Purchases 160 x 1,136.03 = 1,81,765 Cost related to set-ups 20 x 12,812.5 = 2,56,250 Total Overheads Costs 5,16,615 5,16,615/5,000 = 103.32 B (60,000 units) Cost related to Volume activities 1,20,000 x 3.93 = 4,71,600 Cost related to Purchases 384 x 1,136.03 = 4,36,236 Cost related to set-ups 44 x 12,812.5 = 5,63,750 Total Overheads Costs 14,71,586 14,71,586/60,000 = 24.53
  • 15. DU B. Com. (H) 2012 A company manufactures two products A and B using common facilities. the following cost data for a month are presented to you:  Machine activity expenses Rs. 3,00,000  Setup related expenses Rs. 30,000  Expenses related to orders Rs. 35,000 Calculate the overheads per unit absorbed using activity based costing approach. 15 Product Units produced Direct Labour Hours per unit Machine Hours per unit Set-ups of machines Orders A 1,000 2 6 15 18 B 2,000 3 1.5 50 70
  • 16. DU B. Com. (H) 2012 – Detailed Answer (a) For machine related Costs, Machine Hour Rate = 𝑇𝑜𝑡𝑎𝑙 𝑂𝑣𝑒𝑟ℎ𝑒𝑎𝑑𝑠 𝑓𝑜𝑟 𝑚𝑎𝑐ℎ𝑖𝑛𝑒 𝑟𝑒𝑙𝑎𝑡𝑒𝑑 𝑐𝑜𝑠𝑡𝑠 𝑇𝑜𝑡𝑎𝑙 𝑀𝑎𝑐ℎ𝑖𝑛𝑒 𝐻𝑜𝑢𝑟𝑠 = 3,00,000 9,000 = Rs. 33.33 per hour (b) For set-up related Costs, Set-up Rate = 𝑇𝑜𝑡𝑎𝑙 𝑂𝑣𝑒𝑟ℎ𝑒𝑎𝑑𝑠 𝑓𝑜𝑟 𝑠𝑒𝑡−𝑢𝑝 𝑟𝑒𝑙𝑎𝑡𝑒𝑑 𝑐𝑜𝑠𝑡𝑠 𝑇𝑜𝑡𝑎𝑙 𝑛𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑠𝑒𝑡−𝑢𝑝𝑠 = 30,000 65 = Rs. 461.54 per set-up (c) For order related Costs, Overheads per order = 𝑇𝑜𝑡𝑎𝑙 𝑂𝑣𝑒𝑟ℎ𝑒𝑎𝑑𝑠 𝑓𝑜𝑟 𝑜𝑟𝑑𝑒𝑟 𝑟𝑒𝑙𝑎𝑡𝑒𝑑 𝑐𝑜𝑠𝑡𝑠 𝑇𝑜𝑡𝑎𝑙 𝑛𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑜𝑟𝑑𝑒𝑟𝑠 = 35,000 88 = Rs. 397.73 per order (d) Overhead cost per unit (Product A) = 214.08 (200+6.92+7.16) (e) Overhead cost per unit (Product B) = 75.46 (50+11.54+13.92) 16
  • 17. DU B. Com. (H) 2011 Major Limited manufactures two products a and b. the product is low volume atom and its sales are only 5,000 units per annum. the product B is a high volume item and sales are 20,000 units per annum. both products required to direct labour hours for completion. the company works 50,000 direct labour hours each year as given below:  Poduct A : 5000 units x 2 hours = 10,000 hours  Product B: 20,000 x 2 hours = 40,000 hours Details of cost for material and labour for each product (per unit) are given below:  Direct materials: Product A – Rs. 25 and Product B – Rs. 15  Direct labour @ Rs. 5 per hour : Product A – Rs. 10 and Product B – Rs. 10 The company's total manufacturing overhead costs are Rs. 8,75,000 per annum. The company has analysed its operations and has determined the five activities act as cost drivers in the incurrence of overhead costs. Data relating to the five activities are as follows: 17
  • 18. DU B. Com. (H) 2011 (Continued) A company manufactures two products A and B using common facilities. the following cost data for a month are presented to you: You are required to computer per unit cost for each product using (i) direct labour hour rate method for absorption of overhead cost and (ii) activity based costing technique for absorption of overhead cost comment on your results. 18 Activity Traceable costs (Rs.) Number of events or transactions Total Product A Product B Machine set-ups 2,30,000 5,000 3,000 2,000 Quality Inspections 1,60,000 8,000 5,000 3,000 Production Orders 81,000 600 200 400 Machine hours worked 3,14,000 40,000 12,000 28,000 Materials Receipts 90,000 750 150 600 Total 8,75,000
  • 19. DU B. Com. (H) 2011 – Detailed Answer (1) Computation of product cost using direct labour hour rate = 𝑇𝑜𝑡𝑎𝑙 𝑚𝑎𝑛𝑢𝑓𝑎𝑐𝑡𝑢𝑟𝑖𝑛𝑔 𝑂𝑣𝑒𝑟ℎ𝑒𝑎𝑑𝑠 𝑇𝑜𝑡𝑎𝑙 𝐷𝑖𝑟𝑒𝑐𝑡 𝐿𝑎𝑏𝑜𝑢𝑟 𝐻𝑜𝑢𝑟𝑠 = 8,75,000 50,000 = Rs. 17.50 per hour Product cost per unit (Product A) = 70 (DM 25+DL 10 + Overheads 35) Product cost per unit (Product B) = 60 (DM 15+DL 10 + Overheads 35) (2) Computation of product cost using ABC (i) Cost per set-up = Rs. 46 (ii) Cost per inspection = Rs. 20 (iii) Cost per production order = Rs. 135 (iv) Cost per machine hour worked = Rs. 7.85 (v) Cost per material receipt = Rs. 120 Overhead cost per Unit = Product A – Rs. 75.44 and Product B – Rs. 24.89 Product cost per unit (A) = 110.44 (DM 25+DL 10 + Overheads 75.44) Product cost per unit (B) = 49.89 (DM 15+DL 10 + Overheads 24.89) 19
  • 20. THANKS Please inform your feedback, doubts and suggestions to me. Email: m_c_Sharma@yahoo.com 20