SlideShare une entreprise Scribd logo
1  sur  29
Télécharger pour lire hors ligne
Project Risk
Management
+
Risk analysis is a systematic process to estimate the
level of risk for identified and approved risks. This
involves estimating the probability of occurrence
and consequence of occurrence and converting the
results to a corresponding risk.
The approach used depends upon the data available
and requirements levied on the project level.
Risk analyses are often based on detailed information
that may come from a variety of techniques, including
but not limited to:
Analysis of plans and related documents
Experience and interviewing
Relevant lessons-learned studies
Results from tests
…cont’d
There are two methods of risk analysis
Qualitative approach and
Quantitative approaches
Qualitative approach use the probability of occurrence and
consequence of occurrence scales together with a risk mapping
matrix to convert the values to risk levels.
When a qualitative risk analysis is performed, risk ratings can
be used as an indication of the potential importance of risks on
the program and often expressed as low, medium, and high (or
possibly low, medium low, medium, medium high, and high).
Quantitative approaches use the technique such as expected
value ,decision tree analysis, payoff matrices, and modeling
and simulation.
Project problems can be reduced as much
as 90% by using risk analysis
Positives:
More info available during planning
Improved probability of success/optimum
project
Negatives:
Project cut due to risk level
Risks have been thoroughly examined and included in project
plans, resulting in risk reduction. Information about possible risks
is available throughout the project, resulting in a better decision-
making process
Project objectives might be affected by certain risks, allowing the
objectives to be improved
Many of the project weaknesses have been identified in advance
and are incorporated into the project plan.
Decrease the number of changes made to the project plan during
project execution, resulting in higher chances of project success
Risk Management Process
Risk
management
plan and control
Document risk
management
plan
Define
objectives
Identify risk
Quantify
risk
Develop
response
Benefits of Risk Assessment
 Protects project investments
 Proactive management – early warning
 Achieve project objectives
 High Risk: Substantial impact on cost, technical
performance, or schedule. Substantial action required to
alleviate issue. High-priority management attention is
required.
 Medium Risk: Some impact on cost, technical
performance, or schedule. Special action may be required
to alleviate issue. Additional management attention may be
needed.
 Low Risk: Minimal impact on cost, technical
performance, or schedule. Normal management oversight
is sufficient.
Quantitative risk analysis outputs are
1. Prioritized risk lists,
2. Probabilistic cost estimates at completion per project phase
and probabilistic schedule estimates for key milestones to
help the project manager allocate reserve accordingly,
3. Probabilistic estimates of meeting desired technical
performance parameters and validating technical
performance of key components
4. Estimates of the probability of meeting cost, technical
performance, and schedule objectives (e.g., determining the
probability of achieving the planned estimate at completion)
 Updated Risk Register
 Probabilistic analysis for project success (time and cost)
 Updated priority of risk events
 Trends in risk analysis
….cont’d
Interviewing
Decision Tree
Analysis
Monte Carlo
Simulation
The Monte Carlo process is an attempt to create a series of
probability distributions for potential risks, randomly sample the
distributions, and transform the numbers into useful information
that reflects quantification of the associated cost, technical
performance or schedule risks.
 Monte Carlo simulations used to
Estimate risk in the design of service centers;
Measure time to complete key milestones in a project;
Estimate the cost of developing, fabricating, & maintaining
an item.
Uses of Monte Carlo simulation
 A common method/tool to determine whether a risk
is considered low, moderate, or high by combining
the two dimensions of a risk:
 its probability of occurrence, and
 its impact on objectives if it occurs.
2x2 Impact/Probability Matrix
Green: Low Risk (Passive Acceptance – workarounds)
Yellow: Moderate Risk (Active Acceptance –
contingency)
Red: High Risk (Risk Response Planning)
Impact
Probability
HighLow
Low High
Likelihood Class
Likelihood of Occurrence
(events/year)
Not Likely (NL)
<0.01% chance of
occurrence
Low (L)
0.01 - 0.1% chance of
occurrence
Moderate (M)
0.1 - 1% chance of
occurrence
High (H)
1 - 10% chance of
occurrence
Expected (E)
>10% chance of
occurrence
Consequen
ce Health and Safety
Extreme
Fatality or multiple fatalities
expected
High
Severe injury or disability likely;
or some potential for fatality
Moderate
Lost time or injury likely; or
some potential for serious
injuries; or small risk of
fatality
Low
First aid required; or small risk
of serious injury
Negligible No concern
 The process of numerically analyzing the
effect of identified risks on the project’s
objectives In particular, the project schedule
and the project costs.
 Quantify possible outcomes for the project
 Assess probability of achieving specific project
objectives
 Identify risks requiring most attention
 Identify realistic and achievable cost, schedule,
or scope targets, given project risks
 Determine best management decision when
conditions or outcomes are uncertain
 Risks during the Project/idea Initiation phase:
–Unavailable subject matter experts
–Poor definition of problem or project
–No feasibility study
–No or unclear objectives
Taking….cont’d
 Risks during the Project Planning phase:
No risk management plan
Spotty planning
Underdeveloped requirements and
specifications
Unclear statement of work
No management or stakeholder support
Poor role definition
Inexperienced team
Lack of skills
 Risks during the Project Execution phase
 Changes in schedule
 No control systems in place
 Unskilled labour
 Material availability or poor quality material
 Unreliable suppliers
 Unexpected price increase (not budget for it)
 Strikes
 Weather
 Regulatory requirements
….cont’d
Risks during the Project Close-out /
termination phase:
Unacceptable to customer
Poor quality product/project
Budget problems
Penalties to be paid for exceeding the time
parameter of the project
The basics of risk management
Identify the risk
Analyse the probability the risk will occur and the
potential impact of the risk
Determine the overall severity of the risk
Determine which risks are the most important for
further action
Document a response plan for the risk
– Accept the risk
– Avoid the risk
– Monitor the risk
– Transfer the risk
Project standards for risk management
Risk Management Plan
Procurement
Contingency Reserves
Alternative Strategies
Insurance
Management Reserves
◦ Created for unpredictable risks
Contingency Reserves
◦ Created for predictable risks
 Approaches used for developing contingency allowances:
Budgeting a standard allowance for contingencies and applying it to
all projects.
Identifying a percentage of additional cost or time needed, based on
past experience.
Pinpointing the most likely risks for a project, assessing the
probability that they will occur, identifying the possible
consequences, and then allotting contingencies based on these
results.
◦ Exploit
◦ Share
◦ Enhance
◦ Acceptance
)
◦ Avoid
◦ Transfer
◦ Mitigate
◦ Acceptance
Questions the project team should
ask when determining a risk:-
Why should the risk be accepted?
What are the potential benefits?
Are the potential benefits worth the
risk?
What are the potential losses?
What is the possibility of failure?

Contenu connexe

Tendances

Introduction-to-project-management
Introduction-to-project-managementIntroduction-to-project-management
Introduction-to-project-managementSavaş Şakar
 
Project management PPT
Project management  PPTProject management  PPT
Project management PPTRaj Sampat
 
10. Project Quality Management
10. Project Quality Management 10. Project Quality Management
10. Project Quality Management BhuWan Khadka
 
The role and responsibilities of the project manager
The role and responsibilities of the project manager The role and responsibilities of the project manager
The role and responsibilities of the project manager ProofHub
 
PROJECT CONTROL PROCESS
PROJECT CONTROL PROCESS PROJECT CONTROL PROCESS
PROJECT CONTROL PROCESS Akash Prasanna
 
Project management & Network analysis
Project management & Network analysisProject management & Network analysis
Project management & Network analysisHarinadh Karimikonda
 
PMP Lecture 3: Project Management Processes
PMP Lecture 3: Project Management ProcessesPMP Lecture 3: Project Management Processes
PMP Lecture 3: Project Management ProcessesMohamed Loey
 
“Construction Risk Management”
“Construction Risk Management”“Construction Risk Management”
“Construction Risk Management”Ary Jamil
 
Project Selection Methods
Project Selection MethodsProject Selection Methods
Project Selection MethodsManikandan M
 
Work breakdown structure ppt
Work breakdown structure pptWork breakdown structure ppt
Work breakdown structure pptnazi2020
 

Tendances (20)

Introduction-to-project-management
Introduction-to-project-managementIntroduction-to-project-management
Introduction-to-project-management
 
Project management PPT
Project management  PPTProject management  PPT
Project management PPT
 
Project life cycle
Project life cycleProject life cycle
Project life cycle
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Project risk analysis
Project risk analysisProject risk analysis
Project risk analysis
 
10. Project Quality Management
10. Project Quality Management 10. Project Quality Management
10. Project Quality Management
 
project management concepts
project management conceptsproject management concepts
project management concepts
 
The role and responsibilities of the project manager
The role and responsibilities of the project manager The role and responsibilities of the project manager
The role and responsibilities of the project manager
 
Project risk management
Project risk managementProject risk management
Project risk management
 
PROJECT CONTROL PROCESS
PROJECT CONTROL PROCESS PROJECT CONTROL PROCESS
PROJECT CONTROL PROCESS
 
Risk management
Risk managementRisk management
Risk management
 
Project management & Network analysis
Project management & Network analysisProject management & Network analysis
Project management & Network analysis
 
Project Management
Project ManagementProject Management
Project Management
 
Risk management
Risk managementRisk management
Risk management
 
PMP Lecture 3: Project Management Processes
PMP Lecture 3: Project Management ProcessesPMP Lecture 3: Project Management Processes
PMP Lecture 3: Project Management Processes
 
“Construction Risk Management”
“Construction Risk Management”“Construction Risk Management”
“Construction Risk Management”
 
Project Selection Methods
Project Selection MethodsProject Selection Methods
Project Selection Methods
 
Project planning
Project planning Project planning
Project planning
 
Work breakdown structure ppt
Work breakdown structure pptWork breakdown structure ppt
Work breakdown structure ppt
 
Project management
Project managementProject management
Project management
 

En vedette

Step by step guide on project risk management
Step by step guide on project risk managementStep by step guide on project risk management
Step by step guide on project risk managementPMC Mentor
 
Basic Risk Identification Techniques
Basic Risk Identification TechniquesBasic Risk Identification Techniques
Basic Risk Identification TechniquesRicardo Viana Vargas
 
Risk identification
Risk identificationRisk identification
Risk identificationmurukkada
 
Powerpoint Risk Assessment
Powerpoint Risk AssessmentPowerpoint Risk Assessment
Powerpoint Risk AssessmentSteve Bishop
 
Project appraisal and Analysis
Project appraisal and AnalysisProject appraisal and Analysis
Project appraisal and AnalysisSuhail Hussain
 
Risk analysis and management
Risk analysis and managementRisk analysis and management
Risk analysis and managementgnitu
 
Hazard Identification, Risk Assessment and Risk Control (HIRARC) Malay version
Hazard Identification, Risk Assessment and Risk Control (HIRARC) Malay versionHazard Identification, Risk Assessment and Risk Control (HIRARC) Malay version
Hazard Identification, Risk Assessment and Risk Control (HIRARC) Malay versionNorrazman Zaiha Zainol
 
Risk assessment presentation
Risk assessment presentationRisk assessment presentation
Risk assessment presentationmmagario
 
OHSAS Hazard identification & Risk assessment
OHSAS Hazard identification & Risk assessmentOHSAS Hazard identification & Risk assessment
OHSAS Hazard identification & Risk assessmentTechnoSysCon
 
Risk assessment principles and guidelines
Risk assessment principles and guidelinesRisk assessment principles and guidelines
Risk assessment principles and guidelinesHaris Tahir
 
Project Management:Life Cycle & Phases.
Project Management:Life Cycle & Phases.Project Management:Life Cycle & Phases.
Project Management:Life Cycle & Phases.Ashutosh Mishra
 
Project life cycle
Project life cycleProject life cycle
Project life cycleMaryam Juma
 

En vedette (20)

Risk Analysis
Risk AnalysisRisk Analysis
Risk Analysis
 
Step by step guide on project risk management
Step by step guide on project risk managementStep by step guide on project risk management
Step by step guide on project risk management
 
Basic Risk Identification Techniques
Basic Risk Identification TechniquesBasic Risk Identification Techniques
Basic Risk Identification Techniques
 
Risk identification
Risk identificationRisk identification
Risk identification
 
Project quality management.ppt msm
Project quality management.ppt msmProject quality management.ppt msm
Project quality management.ppt msm
 
Spm unit 1
Spm unit 1Spm unit 1
Spm unit 1
 
Powerpoint Risk Assessment
Powerpoint Risk AssessmentPowerpoint Risk Assessment
Powerpoint Risk Assessment
 
Bond
BondBond
Bond
 
Project appraisal and Analysis
Project appraisal and AnalysisProject appraisal and Analysis
Project appraisal and Analysis
 
Risk analysis and management
Risk analysis and managementRisk analysis and management
Risk analysis and management
 
Risk analysis
Risk analysisRisk analysis
Risk analysis
 
Web Security
Web SecurityWeb Security
Web Security
 
Hazard Identification, Risk Assessment and Risk Control (HIRARC) Malay version
Hazard Identification, Risk Assessment and Risk Control (HIRARC) Malay versionHazard Identification, Risk Assessment and Risk Control (HIRARC) Malay version
Hazard Identification, Risk Assessment and Risk Control (HIRARC) Malay version
 
Risk assessment presentation
Risk assessment presentationRisk assessment presentation
Risk assessment presentation
 
OHSAS Hazard identification & Risk assessment
OHSAS Hazard identification & Risk assessmentOHSAS Hazard identification & Risk assessment
OHSAS Hazard identification & Risk assessment
 
Risk assessment principles and guidelines
Risk assessment principles and guidelinesRisk assessment principles and guidelines
Risk assessment principles and guidelines
 
Spm unit 5
Spm unit 5Spm unit 5
Spm unit 5
 
Spm unit2
Spm unit2Spm unit2
Spm unit2
 
Project Management:Life Cycle & Phases.
Project Management:Life Cycle & Phases.Project Management:Life Cycle & Phases.
Project Management:Life Cycle & Phases.
 
Project life cycle
Project life cycleProject life cycle
Project life cycle
 

Similaire à Project Risk Management

Risk management overview
Risk management overviewRisk management overview
Risk management overviewHossam Maghrabi
 
Beyond PMP: Risk Management
Beyond PMP: Risk ManagementBeyond PMP: Risk Management
Beyond PMP: Risk Managementabhinayverma
 
Project Risk Management
 Project Risk Management Project Risk Management
Project Risk ManagementHayat Denzi
 
Project Risk Management (10)
 Project Risk Management (10) Project Risk Management (10)
Project Risk Management (10)Serdar Temiz
 
PMP Training - 11 project risk management
PMP Training - 11 project risk managementPMP Training - 11 project risk management
PMP Training - 11 project risk managementejlp12
 
Control only.pdf
Control only.pdfControl only.pdf
Control only.pdfNmnKmr2
 
Risk Analysis In IT Projects - TNS09
Risk Analysis In IT Projects - TNS09Risk Analysis In IT Projects - TNS09
Risk Analysis In IT Projects - TNS09Thomas Danford
 
05-risk_assesment.ppt
05-risk_assesment.ppt05-risk_assesment.ppt
05-risk_assesment.pptKareemRasmy1
 
Episode 25 : Project Risk Management
Episode 25 :  Project Risk ManagementEpisode 25 :  Project Risk Management
Episode 25 : Project Risk ManagementSAJJAD KHUDHUR ABBAS
 
Lecture 6 Managing risk.pptx
Lecture 6 Managing risk.pptxLecture 6 Managing risk.pptx
Lecture 6 Managing risk.pptxMehediHasan636262
 
NCV 4 Project Management Hands-On Support Slide Show - Module5
NCV 4 Project Management Hands-On Support Slide Show - Module5NCV 4 Project Management Hands-On Support Slide Show - Module5
NCV 4 Project Management Hands-On Support Slide Show - Module5Future Managers
 

Similaire à Project Risk Management (20)

Risk management
Risk management Risk management
Risk management
 
Chap007
Chap007Chap007
Chap007
 
Risk management overview
Risk management overviewRisk management overview
Risk management overview
 
Beyond PMP: Risk Management
Beyond PMP: Risk ManagementBeyond PMP: Risk Management
Beyond PMP: Risk Management
 
Risk Management
Risk ManagementRisk Management
Risk Management
 
Project Risk Management
 Project Risk Management Project Risk Management
Project Risk Management
 
Project Risk Management (10)
 Project Risk Management (10) Project Risk Management (10)
Project Risk Management (10)
 
PMP Training - 11 project risk management
PMP Training - 11 project risk managementPMP Training - 11 project risk management
PMP Training - 11 project risk management
 
Risk Management
Risk ManagementRisk Management
Risk Management
 
Control only.pdf
Control only.pdfControl only.pdf
Control only.pdf
 
Risk based thinking
Risk based thinkingRisk based thinking
Risk based thinking
 
Risk Analysis In IT Projects - TNS09
Risk Analysis In IT Projects - TNS09Risk Analysis In IT Projects - TNS09
Risk Analysis In IT Projects - TNS09
 
Session 18 4th edition PMP
Session 18 4th edition PMPSession 18 4th edition PMP
Session 18 4th edition PMP
 
Project mngmnt risks3.2
Project mngmnt risks3.2Project mngmnt risks3.2
Project mngmnt risks3.2
 
05-risk_assesment.ppt
05-risk_assesment.ppt05-risk_assesment.ppt
05-risk_assesment.ppt
 
Risk management
Risk managementRisk management
Risk management
 
Episode 25 : Project Risk Management
Episode 25 :  Project Risk ManagementEpisode 25 :  Project Risk Management
Episode 25 : Project Risk Management
 
Lecture 6 Managing risk.pptx
Lecture 6 Managing risk.pptxLecture 6 Managing risk.pptx
Lecture 6 Managing risk.pptx
 
Risk project mgt, infra
Risk project mgt, infraRisk project mgt, infra
Risk project mgt, infra
 
NCV 4 Project Management Hands-On Support Slide Show - Module5
NCV 4 Project Management Hands-On Support Slide Show - Module5NCV 4 Project Management Hands-On Support Slide Show - Module5
NCV 4 Project Management Hands-On Support Slide Show - Module5
 

Plus de Markos Mulat G

ERP and CRM Integration for Quality Service Delivery
ERP and CRM Integration for Quality Service DeliveryERP and CRM Integration for Quality Service Delivery
ERP and CRM Integration for Quality Service DeliveryMarkos Mulat G
 
A Review of FDRE Civil Society Proclamation No.621/2009
A Review of FDRE Civil Society Proclamation No.621/2009A Review of FDRE Civil Society Proclamation No.621/2009
A Review of FDRE Civil Society Proclamation No.621/2009Markos Mulat G
 
Traffic and Transportation Problems in Ethiopia: Manifestations and the Way out
Traffic and Transportation Problems in Ethiopia:  Manifestations and the Way outTraffic and Transportation Problems in Ethiopia:  Manifestations and the Way out
Traffic and Transportation Problems in Ethiopia: Manifestations and the Way outMarkos Mulat G
 
Human Resource Information System Applications
Human Resource Information System Applications Human Resource Information System Applications
Human Resource Information System Applications Markos Mulat G
 
Human Resource Information System [HRIS] MBA defence
Human Resource Information System [HRIS] MBA defence Human Resource Information System [HRIS] MBA defence
Human Resource Information System [HRIS] MBA defence Markos Mulat G
 
Performance Appraisal
Performance Appraisal Performance Appraisal
Performance Appraisal Markos Mulat G
 
HR Audit with checklist
HR Audit with checklistHR Audit with checklist
HR Audit with checklistMarkos Mulat G
 

Plus de Markos Mulat G (10)

ERP and CRM Integration for Quality Service Delivery
ERP and CRM Integration for Quality Service DeliveryERP and CRM Integration for Quality Service Delivery
ERP and CRM Integration for Quality Service Delivery
 
A Review of FDRE Civil Society Proclamation No.621/2009
A Review of FDRE Civil Society Proclamation No.621/2009A Review of FDRE Civil Society Proclamation No.621/2009
A Review of FDRE Civil Society Proclamation No.621/2009
 
Traffic and Transportation Problems in Ethiopia: Manifestations and the Way out
Traffic and Transportation Problems in Ethiopia:  Manifestations and the Way outTraffic and Transportation Problems in Ethiopia:  Manifestations and the Way out
Traffic and Transportation Problems in Ethiopia: Manifestations and the Way out
 
Continuous Assessment
Continuous AssessmentContinuous Assessment
Continuous Assessment
 
Human Resource Information System Applications
Human Resource Information System Applications Human Resource Information System Applications
Human Resource Information System Applications
 
Human Resource Information System [HRIS] MBA defence
Human Resource Information System [HRIS] MBA defence Human Resource Information System [HRIS] MBA defence
Human Resource Information System [HRIS] MBA defence
 
Performance Appraisal
Performance Appraisal Performance Appraisal
Performance Appraisal
 
HR Audit with checklist
HR Audit with checklistHR Audit with checklist
HR Audit with checklist
 
HR Audit in EIC
HR Audit in EIC HR Audit in EIC
HR Audit in EIC
 
Pricing in Practice
Pricing in PracticePricing in Practice
Pricing in Practice
 

Dernier

Falcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business PotentialFalcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business PotentialFalcon investment
 
Falcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting
 
Structuring and Writing DRL Mckinsey (1).pdf
Structuring and Writing DRL Mckinsey (1).pdfStructuring and Writing DRL Mckinsey (1).pdf
Structuring and Writing DRL Mckinsey (1).pdflaloo_007
 
Cannabis Legalization World Map: 2024 Updated
Cannabis Legalization World Map: 2024 UpdatedCannabis Legalization World Map: 2024 Updated
Cannabis Legalization World Map: 2024 UpdatedCannaBusinessPlans
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityEric T. Tung
 
Cracking the 'Career Pathing' Slideshare
Cracking the 'Career Pathing' SlideshareCracking the 'Career Pathing' Slideshare
Cracking the 'Career Pathing' SlideshareWorkforce Group
 
Falcon Invoice Discounting: Aviate Your Cash Flow Challenges
Falcon Invoice Discounting: Aviate Your Cash Flow ChallengesFalcon Invoice Discounting: Aviate Your Cash Flow Challenges
Falcon Invoice Discounting: Aviate Your Cash Flow Challengeshemanthkumar470700
 
Uneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration PresentationUneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration Presentationuneakwhite
 
Pre Engineered Building Manufacturers Hyderabad.pptx
Pre Engineered  Building Manufacturers Hyderabad.pptxPre Engineered  Building Manufacturers Hyderabad.pptx
Pre Engineered Building Manufacturers Hyderabad.pptxRoofing Contractor
 
Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...
Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...
Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...meghakumariji156
 
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al MizharAl Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizharallensay1
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxCynthia Clay
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfAdmir Softic
 
PHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation FinalPHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation FinalPanhandleOilandGas
 
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAIGetting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAITim Wilson
 
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All TimeCall 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Timegargpaaro
 
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...ssuserf63bd7
 
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)Adnet Communications
 
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan CytotecJual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan CytotecZurliaSoop
 

Dernier (20)

Falcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business PotentialFalcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business Potential
 
Falcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investors
 
Structuring and Writing DRL Mckinsey (1).pdf
Structuring and Writing DRL Mckinsey (1).pdfStructuring and Writing DRL Mckinsey (1).pdf
Structuring and Writing DRL Mckinsey (1).pdf
 
Cannabis Legalization World Map: 2024 Updated
Cannabis Legalization World Map: 2024 UpdatedCannabis Legalization World Map: 2024 Updated
Cannabis Legalization World Map: 2024 Updated
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League City
 
Cracking the 'Career Pathing' Slideshare
Cracking the 'Career Pathing' SlideshareCracking the 'Career Pathing' Slideshare
Cracking the 'Career Pathing' Slideshare
 
Falcon Invoice Discounting: Aviate Your Cash Flow Challenges
Falcon Invoice Discounting: Aviate Your Cash Flow ChallengesFalcon Invoice Discounting: Aviate Your Cash Flow Challenges
Falcon Invoice Discounting: Aviate Your Cash Flow Challenges
 
Uneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration PresentationUneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration Presentation
 
Pre Engineered Building Manufacturers Hyderabad.pptx
Pre Engineered  Building Manufacturers Hyderabad.pptxPre Engineered  Building Manufacturers Hyderabad.pptx
Pre Engineered Building Manufacturers Hyderabad.pptx
 
Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...
Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...
Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...
 
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al MizharAl Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
 
Buy gmail accounts.pdf buy Old Gmail Accounts
Buy gmail accounts.pdf buy Old Gmail AccountsBuy gmail accounts.pdf buy Old Gmail Accounts
Buy gmail accounts.pdf buy Old Gmail Accounts
 
PHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation FinalPHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation Final
 
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAIGetting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
 
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All TimeCall 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
 
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
 
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
 
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan CytotecJual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
 

Project Risk Management

  • 2. + Risk analysis is a systematic process to estimate the level of risk for identified and approved risks. This involves estimating the probability of occurrence and consequence of occurrence and converting the results to a corresponding risk. The approach used depends upon the data available and requirements levied on the project level.
  • 3. Risk analyses are often based on detailed information that may come from a variety of techniques, including but not limited to: Analysis of plans and related documents Experience and interviewing Relevant lessons-learned studies Results from tests
  • 4. …cont’d There are two methods of risk analysis Qualitative approach and Quantitative approaches Qualitative approach use the probability of occurrence and consequence of occurrence scales together with a risk mapping matrix to convert the values to risk levels. When a qualitative risk analysis is performed, risk ratings can be used as an indication of the potential importance of risks on the program and often expressed as low, medium, and high (or possibly low, medium low, medium, medium high, and high). Quantitative approaches use the technique such as expected value ,decision tree analysis, payoff matrices, and modeling and simulation.
  • 5. Project problems can be reduced as much as 90% by using risk analysis Positives: More info available during planning Improved probability of success/optimum project Negatives: Project cut due to risk level
  • 6. Risks have been thoroughly examined and included in project plans, resulting in risk reduction. Information about possible risks is available throughout the project, resulting in a better decision- making process Project objectives might be affected by certain risks, allowing the objectives to be improved Many of the project weaknesses have been identified in advance and are incorporated into the project plan. Decrease the number of changes made to the project plan during project execution, resulting in higher chances of project success
  • 7. Risk Management Process Risk management plan and control Document risk management plan Define objectives Identify risk Quantify risk Develop response
  • 8. Benefits of Risk Assessment  Protects project investments  Proactive management – early warning  Achieve project objectives
  • 9.  High Risk: Substantial impact on cost, technical performance, or schedule. Substantial action required to alleviate issue. High-priority management attention is required.  Medium Risk: Some impact on cost, technical performance, or schedule. Special action may be required to alleviate issue. Additional management attention may be needed.  Low Risk: Minimal impact on cost, technical performance, or schedule. Normal management oversight is sufficient.
  • 10. Quantitative risk analysis outputs are 1. Prioritized risk lists, 2. Probabilistic cost estimates at completion per project phase and probabilistic schedule estimates for key milestones to help the project manager allocate reserve accordingly, 3. Probabilistic estimates of meeting desired technical performance parameters and validating technical performance of key components
  • 11. 4. Estimates of the probability of meeting cost, technical performance, and schedule objectives (e.g., determining the probability of achieving the planned estimate at completion)  Updated Risk Register  Probabilistic analysis for project success (time and cost)  Updated priority of risk events  Trends in risk analysis ….cont’d
  • 13. The Monte Carlo process is an attempt to create a series of probability distributions for potential risks, randomly sample the distributions, and transform the numbers into useful information that reflects quantification of the associated cost, technical performance or schedule risks.
  • 14.
  • 15.  Monte Carlo simulations used to Estimate risk in the design of service centers; Measure time to complete key milestones in a project; Estimate the cost of developing, fabricating, & maintaining an item. Uses of Monte Carlo simulation
  • 16.  A common method/tool to determine whether a risk is considered low, moderate, or high by combining the two dimensions of a risk:  its probability of occurrence, and  its impact on objectives if it occurs.
  • 17. 2x2 Impact/Probability Matrix Green: Low Risk (Passive Acceptance – workarounds) Yellow: Moderate Risk (Active Acceptance – contingency) Red: High Risk (Risk Response Planning) Impact Probability HighLow Low High
  • 18. Likelihood Class Likelihood of Occurrence (events/year) Not Likely (NL) <0.01% chance of occurrence Low (L) 0.01 - 0.1% chance of occurrence Moderate (M) 0.1 - 1% chance of occurrence High (H) 1 - 10% chance of occurrence Expected (E) >10% chance of occurrence Consequen ce Health and Safety Extreme Fatality or multiple fatalities expected High Severe injury or disability likely; or some potential for fatality Moderate Lost time or injury likely; or some potential for serious injuries; or small risk of fatality Low First aid required; or small risk of serious injury Negligible No concern
  • 19.  The process of numerically analyzing the effect of identified risks on the project’s objectives In particular, the project schedule and the project costs.
  • 20.  Quantify possible outcomes for the project  Assess probability of achieving specific project objectives  Identify risks requiring most attention  Identify realistic and achievable cost, schedule, or scope targets, given project risks  Determine best management decision when conditions or outcomes are uncertain
  • 21.  Risks during the Project/idea Initiation phase: –Unavailable subject matter experts –Poor definition of problem or project –No feasibility study –No or unclear objectives
  • 22. Taking….cont’d  Risks during the Project Planning phase: No risk management plan Spotty planning Underdeveloped requirements and specifications Unclear statement of work No management or stakeholder support Poor role definition Inexperienced team Lack of skills
  • 23.  Risks during the Project Execution phase  Changes in schedule  No control systems in place  Unskilled labour  Material availability or poor quality material  Unreliable suppliers  Unexpected price increase (not budget for it)  Strikes  Weather  Regulatory requirements
  • 24. ….cont’d Risks during the Project Close-out / termination phase: Unacceptable to customer Poor quality product/project Budget problems Penalties to be paid for exceeding the time parameter of the project
  • 25. The basics of risk management Identify the risk Analyse the probability the risk will occur and the potential impact of the risk Determine the overall severity of the risk Determine which risks are the most important for further action Document a response plan for the risk – Accept the risk – Avoid the risk – Monitor the risk – Transfer the risk
  • 26. Project standards for risk management Risk Management Plan Procurement Contingency Reserves Alternative Strategies Insurance
  • 27. Management Reserves ◦ Created for unpredictable risks Contingency Reserves ◦ Created for predictable risks  Approaches used for developing contingency allowances: Budgeting a standard allowance for contingencies and applying it to all projects. Identifying a percentage of additional cost or time needed, based on past experience. Pinpointing the most likely risks for a project, assessing the probability that they will occur, identifying the possible consequences, and then allotting contingencies based on these results.
  • 28. ◦ Exploit ◦ Share ◦ Enhance ◦ Acceptance ) ◦ Avoid ◦ Transfer ◦ Mitigate ◦ Acceptance
  • 29. Questions the project team should ask when determining a risk:- Why should the risk be accepted? What are the potential benefits? Are the potential benefits worth the risk? What are the potential losses? What is the possibility of failure?