5. 1- Forecast Sets
Using Material Planner Res.
Make Sure to Set Only One Category for Each item (Planning)
Else Forecast Will Duplicate at Supply and demand
ForecastSets forecast
(Addinit itemsyouneedto
forecast)
Inventory Planning
Forecast Sets
OpenSets ContainerforGroupof Forecastas below
6. OpenForecasteditems(toListall Forecasteditems)
Enter ForecastedQuantityforeachitemwithBucketType Even“Days,Weeks, Period”
*ConsumptionOption*
To Control ConsumptionPercentage 100
ال تستهلك ممكن المبيعات ان معناها
Forecast
بنسبه
100
ش ال حاله فى مشكله يسببلى ممكن ودا
abnormal SalesDemand
ال قيمه يخلى ممكن اللى
ForecastbyZero or Negative “OverConsumption”
7.
8. In case I needto Generate Forecastbasedonhistorical data“Statistical Method”basedonForecastingRule
Generate Forecasting
SelectForecastName ,and rule (Basedonit define pastbucketandhistorytype andforecast Method)
SelectionSelectSpecificitem,orall itemsor Specificcategory
Startingdate- to Date Horizonfor forecast
9. SpecifySourcesof DemandYoucan drive the planwith:
• Salesorderdemand
• Forecastdemand
• A combination:Inthiscase,the salesorderdemandreduces(consumes) the forecastdemandtoavoidover-
demanding.
The forecastdemandcomesfrom:
DemandfromOracle MRP
Create a newor use an existingmasterdemandscheduleUse the masterdemandschedulesource listto
associate individual forecastswithyourMDSLoad the adjusted(unconstrained) forecastsintoamasterdemand
schedule.Youcanloadindividual forecasts,forexample,forcustomersandsalesregions,intoasingle master
demandschedule andplanthemall atonce.See Oracle MRP User's Guide
DemandfromOracle DemandPlanning
You do nothave to run collections.
See Oracle DemandPlanningImplementationandUser'sGuide
1- Run CollectionsRuncollectionstobringplanningdatafromthe source instance tothe planningserver,where
the data will be accessible toOracle ASCP.
2- Create a PlanAfteran MDS has beendefined,aProduction,Manufacturing,orDistributionplan/schedule canbe
created
3- Launch the PlanAfteryouhave createdyour MRP, MPS,or MPP plan/scheduleandsavedit,choose the plan
from[Production,Manufacturing,orDistributionPlan] >NamesandselectLaunchPlan
10. MRP
Starting the PlanningManager
The PlanningManagercontrolsa continuousbackgroundprocessthatperiodicallyactivatesforall organizations.It
differsfromanormal processinthat you needtostart it onlyonce.Thisprocessisactivatedbasedonthe processing
interval youdefine.Once activated,the PlanningManagerexecutesseveral maintenance tasks.Forexample,the
PlanningManagerperformsforecastconsumption,MDSshipmentrelief,MPSschedule relief,andforecastandmaster
schedule imports.Note:Youshouldactivate the PlanningManagerandleave itrunning.The PlanningManagerperforms
maintenance tasksvital tothe properoperationof Oracle MRP.
DefiningPlanners
CreatingDemandClasses:
You can group similarcustomersorsalesordersbycreatingdemandclasses.Demandclassesare ameansof grouping
differentsourcesof demandseparately forconsumptionpurposes.
Master Scheduling:
Master schedulingisusedfor:
demand management “Demand”
schedulingproduction “Supply”
You use the schedulesgeneratedbymasterschedulingasinputtoothermanufacturingfunctions,suchas
material requirementsplanningandrough-cutcapacityplanning.
Master Demand Schedule: “الطلب مصادر كل فيه وبيجمع الطلب ”حاله “Demand”
The MDS is a statementof demandandcontainsdetailsof the anticipatedshipmentschedule.Youcan
consolidate all sourcesof demandintoamasterdemandschedule torepresentastatementof total
anticipatedshipments
Some of the demandtypesthatthe MDS considersare:
• itemforecasts
• sparesdemand
• salesorders
• internal requisitions
Master Production Schedule (MPS) “Supply”
The MPS isa statementof supply requiredtomeetthe demand forthe itemscontainedinthe MDS.
Defininga Schedule Name
And Load on it Forecast
11. Material RequirementsPlanning MRP
Material requirementsplanning(MRP) calculatesnetrequirementsfromgrossrequirementsbyevaluating:
• The masterschedule •Billsof material • Scheduledreceipts•On-handinventorybalances•Leadtimes•
Ordermodifiers
It thenplansreplenishmentsbycreatingasetof recommendationstoreleaseorrescheduleordersfor
material basedonnetmaterial requirements.
Oracle MRP assumesinfinitecapacityisavailabletomeetthe material requirementsplan.However,youcan
use capacityplanningtoverifythatsufficientcapacityexiststosupportyourmaterial plan.
****************************
MRP PlanningMethodsinOracle Inventory
You can define anMRP planningmethodforanitemwhenyoudefine aniteminOracle
Inventory.Itemsthatare consideredbythe planningprocessmusthave one of the followingMRPplanning
methods:
• MPS Planning
• MRP Planning
MPS Planning
SelectMPSplanningforitemsthatyouwant to masterschedule andmaintainpersonalcontrol.MPS
planningismosteffective for:•planningitemswithindependentdemand•itemsthatare critical to the
business•itemsthatcontrol critical resources
MRP PlanningIf yourdemandissmoothor predictable,youmaynotrequire masterproductionscheduling.
SelectMRP Planningforthese itemsanduse the masterdemandschedule todrive the material
requirementsplan
OverviewOracle Supply Chain Planning
isa powerful tool thatintegratesmanufacturinganddistributionintoasingle planningprocess. WithOracle
SupplyChainPlanning,youcangenerate plansthatinclude the entire supplychain.Inasingle stepyoucan
schedule andplanmaterial anddistributionrequirementsformultiple organizations,orcentrallyplanthe
entire enterprise
SettingUp the SupplyChain
Sourcingrulesandbillsof distributionbothspecifydate-effective sourcingstrategies,combining
replenishmentsourceswithsplitallocationpercentagesandrankings.A replenishmentsource is:•Aninter-
organizationtransfer(TransferFrom) • The replenishedorganizationmanufacturesthe item(Make At) •An
external supplier(BuyFrom) • Anorganizationrepairsthe item(Repairat)
12. 1- Create Forecast
2- Create SourcingRule (Include all Make items)
3- CollectData
4- Create Plan
5- Include forecastatPlanOptionat Demand“OrganizationTab”
6- Launch Planand CheckSupply/demand(ForMake andBuyitems)
7- Simulate
8- Release PlannedOrderRecommendations
9- ConvertPlannedOrdertoBatches
2-Sourcing Rules
“الكل ع او فقط واحده على سواء المخزنيه للمنظومه ملء اعاده بيها بعمل اللي الطريقه”
Sourcingrulesdefine inventoryreplenishmentmethodsforeitherasingle organizationorall organizations
inyour enterprise.Time-phasinginasourcingrule determineswheneachgroupof shippingmethod - ship
org combinationsisineffect
Current Project Only Single Org
Open Advanced Supply Chain Planner Res.
SelectSourcingRule toCreate NewSourcingRule
13. We are Creating Rule for Sourcing all itemproducedor Make at GP Org, allocation Percentage 100%
Sourcing Types:
To add itemsto this Sourcing Rule AssignSourcing Rule
14. To find itemat assignedto this Set Click on Detail Linesthen find
*We Must Assign All Make Items even intermediate items to Sourcing Rule if not
assigned will not be able to Drill Down to end item pegging *
15. Above image shownoPeggingforMake item
At thisCase thisitemeven1- not addedto SourcingRule
2- No ApprovedRecipe,formulaforthisItem
3- Ingredientsitemsare notPlanneditem
4- ValidityRule Expired
To solve thisIssue Checkabove addtoSourcing Rule or checkits Validations
Billsof Distribution:
Billsof distributiondefine the sourcingstrategiesof several organizations.Inotherwords,abill of distributionislibrary
of sourcingstrategies.Forinstance,the sourcingstrategydescribed inSR–C01couldapplyto differentorganizationsat
differentperiods.Youcannotdo thiswithsourcingrulesbecause youhave toapplythe strategytoone organizationor
all organizations.
3-Collect Data
16. ***************************************************************************************
Before Running Data Collection Make Sure Configure this Setting
Some time we face some issue atplanningDataCollectionregardingneedingbiggertable spacesforthisrequest
At thisCase we can use anewconcurrentand add neededrequestonitto be usedwithSpecificRequestsasbelow
From systemadminConcurrentManagerDefine
1- Exclude neededrequestfromStandardConcurrentManageras below
2-Create NewConcurrentAsBelowandInclude initneededRequests
17.
18. To set the processor No. for the New Concurrent
**************************************************************************************************
CollectionTypes:Collections Oracle Systems
19. There is 2 Method of collection “Standard,Continues”
Continues عنصر اى من تدخل اى بدون دورى بشكل بيتم
داتا اي بيجمع مش ال لو الداتا بيجمع تعداها لو...ونسب معادالت طريق عن بشرى
Standard شكل من باكتر الداتا اجمع واقدر معين وقت او فتره فى اجدوله اقدر او يدوى بشكل بيتم ودا
We AlwaysUse StandardMethod
Make sure for the first Time to Set Time higher
Collection Types “Complete, Targeted, Net change”
Basedon Purge PreviouslyCollectedData Can SelectSuitable CollectionMethod
If You SelectPurge = Yes
OnlyComplete Refreshwill be applicable
If NO
Thenyou will be Able toSelectEvenTargetor Net
Target You SelectSpecificValuestocollectandAll OtherFieldswell stillasit
Net Will CollectAll ChangestoCollectedData
20. IMPO Notes:
Technically, it retains the old data (doesn't delete from the MSC base tables) and append the new data (which is
being collected for the first time).
Target collections on the contrary will delete all the earlier collected data and collect the ENTIRE data again for
the entity that you are collecting.
Net change collections can be run only for transactional data, but not the setup data. Ex: If you have
added a new supplier, it can be collected only through a complete refresh or target collections.
Coming to the practical use, If your business does too many transactions during a day OR it needs to run
multiple plans based on the transactions done till that point in time, you really do not need to collect the entire
data set. All that you need to collect is the information of the transactions that happened after the last collection.
You use net change collections.
In a scenario where you have created or updated a sourcing rule OR you did a bulk update of some item
attribute or made mass updates to BOMs or Routings.. you really don't need to collect the ENTIRE data for all
entities, all that you need to collect are the entities which have been modified. You choose Target collections.
You may ask, if I have updated just the BOMs, why cant I use net change data collections. Yes, you can very
well use net change collections. But if the quantum of change is more (that's why I used the word MASS
UPDATE), it is suggested to run target collections as net change might take more time.
Hope that answers your query.
Preferred to use Targeted for setup change (Change in BOM, Recipe, and Routing)
Net change for Transactional Data
In Case New Setup for Material Status “Recommend to Run Complete Refresh”
View Collected Date:
23. (
(
If not equal NoRecipe will existatcollectionbecause are notmatchedqty.
AlsoforScalable make sure to SetMax Quantityto highestno.
----------------------------------------------------------------------------------------------------------------------------------------------------------------
++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
----------------------------------------------------------------------------------------------------------------------------------------------------------------
24. 4-Create Plan and Plan Options
AdvancedSupplyChain Planner,SupplychainPlan Names(Name forPlan)
25. If you checkProduction:itmeansplannedorderwill releasedautomaticallyatitsdate
Create Planand SetType PlanType Manufacturing RelatedtoMRP “FG to material”
Production,MasterRelatedtoMPS “FG andAbove *PlanningRecipe,formulastill FG”
26. Master Plan & Production Plan - Starting from R12 these two plan types are one and the same. These types are
used for performing Master Scheduling - Planning of your finished goods and ABOVE (product families,
Planning BOMs etc.) ,Using this plan type, you arrive at a production schedule which you would like to
execute.
Manufacturing Plan - This plan type is used for performing the Materials Requirement Planning - Planning of
your finished goods and BELOW (Sub-assemblies and Raw material)
If we Select Production CheckBox it will AutomaticallyRelease it Schedule it Also Needto SetupA Profile Optionto allow Automatic Release
Open Plan Option:
27. Planned Items “What planinclude in it ?”
الخطه جوه هتبقى اللى االصناف هيحدد اساسها على
ال االصناف كل هل
Planned
ال جوه اللى
Forecast
االصناف او
ال جوه تصنيعها بيتم اللى
WIP
/all salesOrders
At thisPlanI UsedDemandSchedule andWIPComponent
If I needonlyforecasted“use DemandSchedule itemsonly”
If neededtoPlanBuyitems“SupplySchedule itemsonly”
Overwrite ALLupdate generatedordersafterEachLaunch
ForecastAllocationandconsumption
-Do notspreadForecast
-CheckonConsume by ForecastBucket“OnlySalesorderat CurrentBucketConsume Forecast”
------------------------------------------------------------------------------------------------------------------------------------------
28. Aggregation RepresentHorizonforPlan,IamPlanningfor3 Future Periods الخطه مدى
Preferred to set it by Day to Show effect of Lead time for Buy items
OrganizationToSelectUsedForecastonit
If I needtoinclude SalesOrdertoconsume ForecastCheckonitat organization
29. If I needtoPlan forSafetyStockCheck onit at Organization
You can also set Nettable (Sub-inventories Contained at Planning)
SometimesitneedComplete RefreshCollectiontoeffect
Constrains
To specifyif there isCapacityorMaterial Constrains
36. Can AlsoShowThe SupplyandDemandforComponent
From Component SelectitemandOpenSupplyandDemand
Lead-time and the Planning Time Fence:
Lead-times are portions of the span of time from recognizing the need for an order to receivingthe goods to inventory
The planningtime fence defines a time period within which theplanningengine may not create planned orders.Use
planningtime fence control for schedule stability duringtheinitial periods of a plan.
The more realistic that your lead-times are,the more accuratetheplan matches what will actually occur duringexecution
Safety Stock:
Safety Stock Must Collected by Targeted Collection
Safety stock is a quantity of stock you plan toremain in inventory toprotect against fluctuations in demand
Safety stock is sometimes referred to as over planning.
Safety stock level can be made up of different types of safety stock levels:
Non-transient safety stocklevels arelevels that you hold from their point of origination to the end of the
planninghorizon. They are safety stock levels without ending effectivity dates
37. Transient safety stock levels arelevels that you hold for only a certain time duringthe planning horizon.They
are safety stock levels with ending effectivity dates.
• MRP Planned %: The planningengine calculates safety stock level for the item
• Non MRP Planned: The planningengine receives safety stock level for the item
from Oracle Inventory.
You Specify Safety Stock Levels
Navigateto the item attributes (Inventory > Items > Master Items or Inventory > Items >
Organization Items > tab General Planning > region Safety Stock > field Method.
Navigateto form Enter Item Safety Stocks (Inventory > Planning> Safety Stocks).
Enter Item, Quantity,and Effective Date.
If you specify only one safety stock level for an item, the planningengine considers the safety stock level as non -transient.
If you enter more than one safety stock level for an item, the planning engine generally considers the safety stock level as
transient.
38. Safety Stock Planning
Enabling Safety Stock Planning (Supply Chain Planning > Supply Chain Plan > Options)
In region Organizations,select field Plan Safety Stock for the organizations that you want.You can default this settingin
the Plan Parameters form (Supply Chain Planning> Setup > Parameters > Execution Defaults
SetProfile Option: MSC:PlanItemswithSafetyStockinDemandSchedule =YES
AndProfile Option:MSC:Include SafetyStocksinPriorityBasedPeggingtoYES
Forecast Consumption:
Forecast consumption replaces forecasted demand with actual sales order demand
Each time you createa sales order line, you createactual demand. If the actual demand is already forecasted, the forecast
demand must be decremented by the sales order quantity toavoid counting the same demand twice.
39. Forecast Control
You control forecast consumption against each component by settingits organization item attributeForecast control:
• Consume: Sales orders for this item consume forecasts for this item in the same.
• Consume and derive: Sales orders for this item consume forecasts for this item in the sameorganization.Select this
option if you will also do forecast explosion against the item; see Forecast Explosion, page 5-103.
• None: Sales orders for this item do not consume forecasts for this item.
Backward and Forward Consumption Days
Use consumption days if:
• You do not always havean exact match between the sales order line schedule dates and forecast entry dates.
• Your forecast entry quantity is not always sufficient to cover thesales order quantities.
Forecast consumption works as follows:
• It searches backward from the sales order line schedule date, workday by workday, for forecast quantities to consume.
• If that search is not successful in consuming theentire sales order line quantity,it searches forward from the sales order
line schedule date, workday by workday,for forecast quantities to consume.
• If that search is not successful in consuming theentire sales order line quantity,it creates an overconsumption (negative
demand) entry on thesales order line schedule date.
1- At standard planning Collection Make Sure to Include Sales order at collection
The collection program requires the following
visible_demand_flag = Y
schedule ship date is not null
shipped quantity is null
deliver_to_org_id, sold_from_org_id and invoice_to_org_id is not null
2- OutlierUpdate Percent
Material Planner At Forecast Set
40. This controls theeffects of abnormal demand with a maximum percent of the original quantity forecast that a single sales
order can consume
التوقع من معينه نسبه اال ميستهلكش انه طبيعي الغير طلب ال فى اتحكم عشان نسبه
Daily Forecast at 2nd day and 9th day With 20 unit
There is Sales order at 9th Day With 50 unit
For Specified forecast we Set outlier percent 50% SO Will only Consume 50% of forecast at 9th day with Will be 10 unit
And Remaining unit (40) Will be over Consumption
41. IN Case Day bucket for consumption is 3 Day backward
It will Consume 20 and over-consumption with 5
Consumption with Weekly Buckets
At this scenario I plan weekly so no forward or backward days use and Sales order consumed With in Week
42. Consumption Rule
Current Week, then Previous Week “Backward”, Then Next Week “Forward”
Consumption with PeriodicBuckets
OnlyConsume at the Current Period and remainsconvert to overconsumption
No Backward at period
Collection for Sales Order
To collect past due sales order demand, set the profile option MSC: Sales Orders Offset Days
43. Collectpast due Sales order for 60 day before running Collection
The collection enginecollectsshipped salesorder linesstarting from 5 days before today. The default for this option is
99999.
The collection enginecollectspartially-ornon-shipped salesorders regardlessof this profileoption.
Consumption Setup
1- On Item Master Level
2- Set up the following in thePlan Options level
At org level “IncludeSalesorders”tobe consideredatplanLaunch
44. If you are using forecasts collected directly from Oracle Demand Planning, specify Forecast Consumption
Backward Days and Forecast Consumption Forward Days.
The planningengine applies this window to all Oracle Demand Planningforecasts drivingthe plan
The forecast consumption process occurs in the snapshot phase.When you launch a plan,
IF you want to Consume Forecast on itsPeriod Make sure To select
45. Viewing Forecast Consumption:
Planner Workbench
Select order type“Forecast ”on Forecast name Consumption Details
To show all Collected Sales order:
View collected Data Demand filter by below Data
When the plan setup is Schedule By - Schedule Ship Date - then we will consume forecast based on that value
on the sales order.
There are no other option to exclude sales orders.
46. If Schedule By = Request Ship Date, then if that date is in the past, it will not consume current forecast as
long as the Request Date + Forward Days < Forecast bucket date
++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Notes for Sales orders with ASCP
System Collect All Sales Orders but Only consume “Shipped” from Forecast
Other not Shipped Qty. Consume on-hand.
Entered will show as Demand but not Consume forecast , but will consume On-hand Qty., if available Quantity
not cover Demand , Will Suggest Planned Order to Supply Required Demand of SO
+++++++++++++++++++++++++++++++++++++++++++++++++++++++
Planner Activity:
Main Points:
A-For MakeItem (FG)
1-Validate safetyStock
2-Validate Lead time
3-ValidateSales Order Consumption
4-Used Recipes/ formulas
5-Planned Orders Quantities
6-Simulation
B- For Buy item (MRP)
1-Validate Safety Stock “If Exist”
2-Lead Time
3-Planned Orders
47. Code Description
GN7701F4/01 Ambezim - G Tablet. (3blisters/box) FG
GN19401F2/01 Cobal F Tablets ( 3blisters/box ) FG Pack Mediseal
GN5601F3/01 Cobal Tablets Pack (3blisters/box) FG Mediseal
ET0401F2/01 Coughsed Children {2strips/box( 6 Supp. each)} FG
ET0301F2/01 Coughsed Infantile {2strips/box( 6 Supp. each)} FG
GN18301F2/01 Napifit 100mg Tabs. Pack {2blisters/box (2 tabs. on each)/box} FG CAM
GN2201F1/01 Napizole Cap. 1 Jar Pack
GN0201F7/01 Sinopril 10mg Tabs. {3Blisters/box (10Tabs. in each)} FG
GN0201F5/01 Sinopril 10mg Tabs. {3Blisters/box (10Tabs. in each)} UPA
GN0101F1/01 Sinopril 5mg Tabs. (2 Blisters/ Pack) FG
GN0101F3/01 Sinopril 5mg Tabs. (2Blisters/ box) UPA
GN8701F3/01 Sinopril CoTabs. Pack. (3Blister/Box )
GN8701F4/01 Sinopril CoTabs. Pack. (3Blister/Box ) UPA
GN7701F4/01
Min Order Qty. Max order Qty. Safety Stock
Fixed order
Qty.
33,333 9,999,999 623,945 33,333
Validate Make item
Batch Size = Fixed Order Qty
73. OPM Planning:
After Launch Plan and Validate Planned Order Even (Make or Buy)
Then Release + Firm Planned Order
ASCP to OPM Flow
The flow between ASCP and OPM is as follows:
1. Static and dynamic production planningdata transfers from OPM to ASCP.
2. ASCP makes selected suggestion based on the data to meet the demands.
3. Through OPM you can reschedule, add, and cancel batches and firmed planned orders.
Defining Firmed Batches:
To Prevent ASCP Rescheduling or Cancel you have to Define Batch as firmed
Then collect data and Launch Plan
Analysis of Suggestions:
ASCP suggestions for production batches consist of the following:
• Create a new batch
• Reschedule an existing batch
• Cancel an existingbatch
74. Implementing Planning Suggestions
Sending feedback from Advanced Supply Chain Planning(ASCP) to OPM includes implementing ASCP suggestions in
OPM. ASCP calculates the following types of planning suggestions based on the data collected from OPM: create
production and purchaseorders; reschedule production orders; and cancel production and purchaseorders. You can
release individual ASCP suggestions or release them in mass.
Manual Release and Implementation of Planning Suggestions
You can manually release ASCP suggestions in Advanced Planning Scheduling (APS) and manually accept some, all,
or none of the ASCP suggestions in OPM.
While Release Suggested Planned Orders (Even Production or Purchasing)they Send Automatically to even
Purchasing module or Production module
But it need first to Review (Accept, Reschedule, and Cancel) Sug.
Order
• Create new productions orders through the APS New Batch window
• Reschedule existing productions orders through the Reschedule Update
window
• Cancel existing productions orders through the Batch Cancellations
window
OPM Supply Chain Planner Res Production Updates: APS New
Batch
75. Set Organization Access
For application Process Manufacturing Process Planning
Then from Advanced Supply Chain Planner
Give Permission to Res. To use Planned Organization
79. Fully Automatic Release and Implementation of Production Planning Suggestions
You can automatically releaseASCP production order planningsuggestions in Advanced Planning Scheduling (APS) and
automatically accept all of theASCP production order planningsuggestions in OPM without intervention.
Recommendation for Automatic Release and Approve
80. Simulation:
ASCP Provide you by Tool to simulate Changes at input and its effect on Planning Result (Output)
Simulations can be run by changing plan inputs and parameters rerunningthenew, simulated plan. The new simulated
plan can be saved as a new plan and compared to the original (baseline) plan
Simulation Scenarios:
You can simulate changing in Material and Capacity and Changing Planned Orders
Simulation Modes:
Planner Workbench to simulateand evaluatechanges to specific orders
Additions to demand and supplies can alsobe simulated
Net change re-plan simulation is a powerful What If analysis feature
, that lets you update a material plan by planningonly the items you have changed in the Planner Workbench.
Net Change Re-plan
Net change re-plan generates only thoseplan outputs that havechanged compared to a baseline plan. When you make
minor changes to a plan, it evaluates it in a time that depends on the plan size and complexity.
Batch Mode Planner
Batch mode lets you communicatedirectly with thedatabasewhilemaking and re-planningyour changes.
While frequent re-planningcan place an excessive load on system resources,batch mode gives other users
access to theplan whileyou are performing simulations.
Batch mode is particularly useful when you want tocomplete a single re-planningcycle
Online Planner
Let you simulateand re-plan manual changes to supply and demand records without increasingdatabase
traffic
1- Plan Loaded to Memory
2- Make Needed Change on the Plan
3- Re-plan the Change to see the effect on Result
4- You can re-plan and release your change or re-plan many time as you need
Running Net Change Re-plan Simulations
You havetwooptions for runningnet change re-plan simulations:
• Batch plan
• Online re-plan
NOTE:
Run the online planner or batch re-plan process after making changes tosupplies and demands in Planner Workbench,
for example, adding new supplies and demands, changing supply dates and quantities.If you do not run these, your next
complete regeneration may fail, especially if you set plan option OverwritetoNone or Outside PlanningTime Fence.
81. Running Online Re-plan:
1. Select a plan in the Planner Workbench Window.
2. Choose Plan > Start OnlinePlanner.
3. Make a note of theconcurrent request ID and choose OK.
4. When thestatus window informs you that thesession is ready for planning, close the window to return tothe Planner
Workbench.Your online planner session is now active.
5. Make the desired changes to your plan.
6. Save the plan.
7. Choose Plan > Online Re-plan.
82.
83. You can simulate changing in Material and Capacity and Changing Planned Orders
To stop an onlineplannersession
1. Choose Plan > Stop Online Planner
2. Click OK to confirm your choice.
Note: Do not stop the online planner until all simulations arecomplete.
To compare scenarios quantitatively
1. Navigateto the Planner Workbench.
2. Select the baselineplan.
3. While holding the shift key, select the simulated plan.
KPIs for both plans show side by side.
84. To ShowCorrect Qty.at Horizontal Plan
Make sure to be on the firstitem
At detailsrightclickandOpenHorizontal Plan
85. Lead time:
Lead-times are portions of the span of time from recognizing the need for an order to receivingthe goods to inventory.
Setting Lead-times
Set lead-timevalues for the planning engine to use in the following source system forms:
• Oracle Inventory > Organization items form > Item attributes > Lead-timetabbed region
• Oracle Purchasing> Approved Supplier List form
The planningengine does not use sub-inventory lead-times from Oracle Inventory.
These values are for the Oracle Inventory Min-Max planningprocess.
Lead-time ItemAttributes Definition:
For Buy item I Need to Define 3 Fields:
Pre-processing: Refer to time taken by paperwork “Preparing PO”
Processing:Time fromissuingPOtill Receive Materials
Post-Processing:Time fromReceivingMaterial andinspecttill be Readyforuse
For Make items
Fixed:fixedperiodforitemtobe totallymanufacturedwithoutconsideringQty
Variable:basedonManufactured Qty.
Lead-times and Order Dates
The lead-times define dates that are associated with planned orders and scheduled receipts for these items:
• Order date: The beginning of Preprocessing thedate you should begin the
processing to release theorder.
• Start date: The end of Preprocessingand beginning of Processing; the date you,
your supplier, or your ship from facility should begin work on the order.
• Dock date: The end of Processing and the beginning of Postprocessing;the date that
the material should be on your receiving dock.
• Due date: The end of Postprocessing and the date that thematerial should be in
your inventory.For make orders,put the on-hand on hold to account for the post
processing lead time.
Example on Lead Time:
86.
87.
88. To produce correct Dates you haveto set the Plan with Daily bucket at aggregation
Plan Output for Planned order with make item
For Buy item
89. Need Date = Due Date =1/Nov
Dock Date = Due – Post Processing 1/Nov - 5 Days = 27-Oct
Suggest start= Due-(processing+ Post) = 1/Nov – (20+5) = 07/Oct
Suggest Order=Due-(Pre + Processing+ Post) =1/Nov – (20+5+5)= 1/Oct
Notes
1- Make Sure to Add All Make item at Sourcing Rule to Be shown at end item
Pegging
2- Make Sure to Set Fixed order Qty. for Make Item to Shown on S/D
------------------------------------------------------