• It is common in project management that
additional resources are used to either speed up
some activities to get the project back on
schedule or to reduce the project completion
time.
• Crashing an activity refers to the speeding up or
shortening of the duration of an activity by using
additional resources. These include overtime,
hiring temporary staff, renting more efficient
equipment, and other measures.
Project crashingProject crashing
• Project crashing refers to the process of
shortening the duration of the project by
crashing the duration of a number of activities.
• Since it generally results in an increase of the
overall project costs, the challenge faced by the
project manager is to identify the activities to
crash and the duration reduction for each
activity such that as the project crashing is done
in the least expensive manner possible.
Project crashingProject crashing
• The normal time refers to the estimated activity
duration used with CPM or PERT in the
computation of earliest (latest) start or finish
times.
• The normal cost refers to the activity cost under
the normal activity time.
•
Project crashingProject crashing
• The crash time refers to the shortest possible time to
complete an activity with additional resources.
• The crashing cost refers to the activity cost under the
crashing activity time. This relationship is assumed to
be linear. Hence, for each activity a crash cost per
period (e.g.,per week) can be derived as follows:
• crash cost per period = (Crash cost - Normal Cost)/
(Normal time - Crash time)
Project crashingProject crashing
• the cost to crash per period assumes that the
relationship between adding more money to
the activity and reducing the time is linear.
Spend half of the money, and get half the time
reduction, spend _ of the money and get _
time reduction. This is not always true in
practice, but works alright for a rough
planning technique
THE GENERAL RELATIONSHIP OF TIMETHE GENERAL RELATIONSHIP OF TIME
AND COSTAND COST
• Crashing costs increase as project durationCrashing costs increase as project duration
decreases.decreases.
• Indirect costs increase as productionIndirect costs increase as production
duration increases.duration increases.
• Reduce project length as long as crashingReduce project length as long as crashing
costs are less than indirect costs.costs are less than indirect costs.
Conti….Conti….
Conti….Conti….
• The objective of crashing was to reduce theThe objective of crashing was to reduce the
scheduled completion time to reap thescheduled completion time to reap the
results of the projects sooner.results of the projects sooner.
• However, there may be other reasons forHowever, there may be other reasons for
reducing project time.reducing project time.
• There also may be direct financial penaltiesThere also may be direct financial penalties
for not completing a project on time.for not completing a project on time.
What criteria should it be based onWhat criteria should it be based on
when deciding to crashing criticalwhen deciding to crashing critical
times?times?
The critical path is 1-2-3, the completion time =11The critical path is 1-2-3, the completion time =11
How? Path: 1-2-3 = 5+6=11 weeksHow? Path: 1-2-3 = 5+6=11 weeks
Path: 1-3 = 5 weeksPath: 1-3 = 5 weeks
Now, how many days can we “crash” it?Now, how many days can we “crash” it?
1
3
25 (1) 6(3)
Conti…Conti…
• The maximum time that can be crashed for:The maximum time that can be crashed for:
Path 1-2-3 = 1 + 3 = 4Path 1-2-3 = 1 + 3 = 4
Path 1-3 = 0Path 1-3 = 0
• ShouldShould we use up all these 4 weeks?we use up all these 4 weeks?
1
3
25 (1) 6(3)
5(0)
• If we used all 4 days, then path 1-2-3 has
(5-1) + (6-3) = 7 completion weeks
Now, we need to check if the completion time for path 1-3
has lesser than 7 weeks (why?)
Now, path 1-3 has (5-0) = 5 weeks
Since path 1-3 still shorter than 7 weeks, we used up all 4
crashed weeks
• Question: What if path 1-3 has, say 8 weeks completion
time?
1
3
2
5 (1)
6(3)
5(0)
4(0) 3(0)
• Now, we cannot use all 4 days (Why?)
Because path 1-2-3 will not be critical path anymore
path 1-3 would now has longest hour to finish
• Rule: When a path is a critical path, it will not stay as
a critical path
• So, we can only reduce the path 1-2-3 completion
time to the same time
• as path 1-3. (HOW?)
1 3
25 (1) 6(3)
8(0)
• We can only reduce total time for path 1-2-3 =We can only reduce total time for path 1-2-3 =
path 1-path 1-33,,
that is 8 weeksthat is 8 weeks
If the cost for path 1-2 and path 2-3 is the sameIf the cost for path 1-2 and path 2-3 is the same
thenthen
We can random pick them to crash so that itsWe can random pick them to crash so that its
completioncompletion
Time is 8 weeksTime is 8 weeks
1
3
25 (1) 6(3)
8(0)
1
3
25 (1)5 (1) 6(3)6(3)
8(0)8(0)
1
2
3
5 (1)5 (1)
6(3)6(3)
8(0)8(0)
OR
4(0)4(0) 4(1)4(1)
3(0)3(0)

Contenu connexe

Tendances

Tendances (20)

time cost trade off
 time cost trade off time cost trade off
time cost trade off
 
09. Project Cost Management
09. Project Cost Management09. Project Cost Management
09. Project Cost Management
 
Per tand project crashing
Per tand project crashingPer tand project crashing
Per tand project crashing
 
Difference between PERT and CPM
Difference between PERT and CPMDifference between PERT and CPM
Difference between PERT and CPM
 
Critical path method(cpm)
Critical path method(cpm)Critical path method(cpm)
Critical path method(cpm)
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
Pert and CPM
Pert and CPMPert and CPM
Pert and CPM
 
Module :-5 project scheduling and resource levelling
Module :-5 project scheduling and resource levellingModule :-5 project scheduling and resource levelling
Module :-5 project scheduling and resource levelling
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
Critical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksCritical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/Slacks
 
Project cost control
Project cost controlProject cost control
Project cost control
 
Project Cost Management - PMBOK6
Project Cost Management - PMBOK6Project Cost Management - PMBOK6
Project Cost Management - PMBOK6
 
Triple constraint
Triple constraintTriple constraint
Triple constraint
 
Project Management - Critical path method
Project Management - Critical path methodProject Management - Critical path method
Project Management - Critical path method
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniques
 
Estimating Cost & Time.ppt
Estimating Cost & Time.pptEstimating Cost & Time.ppt
Estimating Cost & Time.ppt
 
Work breakdown structure ppt
Work breakdown structure pptWork breakdown structure ppt
Work breakdown structure ppt
 
Pert
PertPert
Pert
 
Project organization
Project organizationProject organization
Project organization
 
Pert cpm
Pert cpmPert cpm
Pert cpm
 

Similaire à crashing of project

Resource-Allocation.ppt
Resource-Allocation.pptResource-Allocation.ppt
Resource-Allocation.pptTecnicoItca
 
Software Project Scheduling Diagrams
Software Project Scheduling DiagramsSoftware Project Scheduling Diagrams
Software Project Scheduling DiagramsSaqib Raza
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..pptPedadaSaikumar
 
Criticalchainprojectmanagement
CriticalchainprojectmanagementCriticalchainprojectmanagement
Criticalchainprojectmanagementkaton808
 
chapter 6.ppt
chapter 6.pptchapter 6.ppt
chapter 6.pptDejeneDay
 
Mba ii pmom_unit-4.1 project management a
Mba ii pmom_unit-4.1 project management aMba ii pmom_unit-4.1 project management a
Mba ii pmom_unit-4.1 project management aRai University
 
Pert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gertPert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gertRaj J Das
 
PERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTPERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTsalsa moyara
 
Time cost trade off
Time cost trade offTime cost trade off
Time cost trade offzollatrix
 
Reducing Project Duration_Jagat Prasad Upadhyay.pptx
Reducing Project Duration_Jagat Prasad Upadhyay.pptxReducing Project Duration_Jagat Prasad Upadhyay.pptx
Reducing Project Duration_Jagat Prasad Upadhyay.pptxJagat Upadhyay
 
Project crashing and job sequencing
Project crashing and job sequencingProject crashing and job sequencing
Project crashing and job sequencingBuha Payal
 
Allocating Resources To The Project
Allocating Resources To The ProjectAllocating Resources To The Project
Allocating Resources To The ProjectJeff Brooks
 
06 project time management
06  project time management06  project time management
06 project time managementAla Ibrahim
 

Similaire à crashing of project (20)

Resource-Allocation.ppt
Resource-Allocation.pptResource-Allocation.ppt
Resource-Allocation.ppt
 
ch09s.ppt
ch09s.pptch09s.ppt
ch09s.ppt
 
Software Project Scheduling Diagrams
Software Project Scheduling DiagramsSoftware Project Scheduling Diagrams
Software Project Scheduling Diagrams
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt
 
Criticalchainprojectmanagement
CriticalchainprojectmanagementCriticalchainprojectmanagement
Criticalchainprojectmanagement
 
chapter 6.ppt
chapter 6.pptchapter 6.ppt
chapter 6.ppt
 
Mba ii pmom_unit-4.1 project management a
Mba ii pmom_unit-4.1 project management aMba ii pmom_unit-4.1 project management a
Mba ii pmom_unit-4.1 project management a
 
Pert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gertPert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gert
 
Chapter 07
Chapter 07Chapter 07
Chapter 07
 
Project time management
Project time managementProject time management
Project time management
 
EpM
EpMEpM
EpM
 
Ch09 (1).pptx
Ch09 (1).pptxCh09 (1).pptx
Ch09 (1).pptx
 
Project management techniques
Project management techniquesProject management techniques
Project management techniques
 
PERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTPERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENT
 
Time cost trade off
Time cost trade offTime cost trade off
Time cost trade off
 
Reducing Project Duration_Jagat Prasad Upadhyay.pptx
Reducing Project Duration_Jagat Prasad Upadhyay.pptxReducing Project Duration_Jagat Prasad Upadhyay.pptx
Reducing Project Duration_Jagat Prasad Upadhyay.pptx
 
pm--basic.pptx
pm--basic.pptxpm--basic.pptx
pm--basic.pptx
 
Project crashing and job sequencing
Project crashing and job sequencingProject crashing and job sequencing
Project crashing and job sequencing
 
Allocating Resources To The Project
Allocating Resources To The ProjectAllocating Resources To The Project
Allocating Resources To The Project
 
06 project time management
06  project time management06  project time management
06 project time management
 

Plus de Mir Zafarullah

Introduction to Irrigation System of Pakistan
Introduction to Irrigation System of PakistanIntroduction to Irrigation System of Pakistan
Introduction to Irrigation System of PakistanMir Zafarullah
 
Transition curve and Superelevation
Transition curve and SuperelevationTransition curve and Superelevation
Transition curve and SuperelevationMir Zafarullah
 
Obstaclesinchaining 170811123641
Obstaclesinchaining 170811123641Obstaclesinchaining 170811123641
Obstaclesinchaining 170811123641Mir Zafarullah
 
Errorsandmistakesinchaining 170810071200
Errorsandmistakesinchaining 170810071200Errorsandmistakesinchaining 170810071200
Errorsandmistakesinchaining 170810071200Mir Zafarullah
 
Types of flow in open channel
Types of flow in open channelTypes of flow in open channel
Types of flow in open channelMir Zafarullah
 
Types of beam & types of supports
Types of beam & types of supportsTypes of beam & types of supports
Types of beam & types of supportsMir Zafarullah
 
Hydrographics surveying
Hydrographics surveyingHydrographics surveying
Hydrographics surveyingMir Zafarullah
 
Levelling, terms related to levelling, methods of levelling
Levelling, terms related to levelling, methods of levellingLevelling, terms related to levelling, methods of levelling
Levelling, terms related to levelling, methods of levellingMir Zafarullah
 
Water pollution and source
Water pollution and sourceWater pollution and source
Water pollution and sourceMir Zafarullah
 
Self purification of river water
Self purification of river waterSelf purification of river water
Self purification of river waterMir Zafarullah
 
Water sampling , procedure, purpose , techniques and equipments
Water sampling , procedure, purpose , techniques and equipmentsWater sampling , procedure, purpose , techniques and equipments
Water sampling , procedure, purpose , techniques and equipmentsMir Zafarullah
 
Environmental Pollution and its causess
Environmental Pollution and its causessEnvironmental Pollution and its causess
Environmental Pollution and its causessMir Zafarullah
 
Water Filtration by sand filtration
Water Filtration by sand filtrationWater Filtration by sand filtration
Water Filtration by sand filtrationMir Zafarullah
 
coagulation and flocculation
coagulation and flocculation coagulation and flocculation
coagulation and flocculation Mir Zafarullah
 
sedimentation and its types
sedimentation and its typessedimentation and its types
sedimentation and its typesMir Zafarullah
 
Water purification and methods
Water purification and methodsWater purification and methods
Water purification and methodsMir Zafarullah
 

Plus de Mir Zafarullah (20)

Introduction to Irrigation System of Pakistan
Introduction to Irrigation System of PakistanIntroduction to Irrigation System of Pakistan
Introduction to Irrigation System of Pakistan
 
Transition curve and Superelevation
Transition curve and SuperelevationTransition curve and Superelevation
Transition curve and Superelevation
 
Ranging 170811123447
Ranging 170811123447Ranging 170811123447
Ranging 170811123447
 
Obstaclesinchaining 170811123641
Obstaclesinchaining 170811123641Obstaclesinchaining 170811123641
Obstaclesinchaining 170811123641
 
Errorsandmistakesinchaining 170810071200
Errorsandmistakesinchaining 170810071200Errorsandmistakesinchaining 170810071200
Errorsandmistakesinchaining 170810071200
 
Friction factor
Friction factorFriction factor
Friction factor
 
Types of flow in open channel
Types of flow in open channelTypes of flow in open channel
Types of flow in open channel
 
Types of beam & types of supports
Types of beam & types of supportsTypes of beam & types of supports
Types of beam & types of supports
 
Hydrographics surveying
Hydrographics surveyingHydrographics surveying
Hydrographics surveying
 
Levelling, terms related to levelling, methods of levelling
Levelling, terms related to levelling, methods of levellingLevelling, terms related to levelling, methods of levelling
Levelling, terms related to levelling, methods of levelling
 
Water pollution and source
Water pollution and sourceWater pollution and source
Water pollution and source
 
Self purification of river water
Self purification of river waterSelf purification of river water
Self purification of river water
 
Water sampling , procedure, purpose , techniques and equipments
Water sampling , procedure, purpose , techniques and equipmentsWater sampling , procedure, purpose , techniques and equipments
Water sampling , procedure, purpose , techniques and equipments
 
Reverse osmosis
Reverse osmosisReverse osmosis
Reverse osmosis
 
Environmental Pollution and its causess
Environmental Pollution and its causessEnvironmental Pollution and its causess
Environmental Pollution and its causess
 
Hard and soft water
Hard and soft water Hard and soft water
Hard and soft water
 
Water Filtration by sand filtration
Water Filtration by sand filtrationWater Filtration by sand filtration
Water Filtration by sand filtration
 
coagulation and flocculation
coagulation and flocculation coagulation and flocculation
coagulation and flocculation
 
sedimentation and its types
sedimentation and its typessedimentation and its types
sedimentation and its types
 
Water purification and methods
Water purification and methodsWater purification and methods
Water purification and methods
 

Dernier

Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...tanu pandey
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueBhangaleSonal
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxfenichawla
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01KreezheaRecto
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptMsecMca
 
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdfSuman Jyoti
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756dollysharma2066
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfRagavanV2
 
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 

Dernier (20)

NFPA 5000 2024 standard .
NFPA 5000 2024 standard                                  .NFPA 5000 2024 standard                                  .
NFPA 5000 2024 standard .
 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
 
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
 
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 

crashing of project

  • 2. Project crashingProject crashing • It is common in project management that additional resources are used to either speed up some activities to get the project back on schedule or to reduce the project completion time. • Crashing an activity refers to the speeding up or shortening of the duration of an activity by using additional resources. These include overtime, hiring temporary staff, renting more efficient equipment, and other measures.
  • 3. Project crashingProject crashing • Project crashing refers to the process of shortening the duration of the project by crashing the duration of a number of activities. • Since it generally results in an increase of the overall project costs, the challenge faced by the project manager is to identify the activities to crash and the duration reduction for each activity such that as the project crashing is done in the least expensive manner possible.
  • 4. Project crashingProject crashing • The normal time refers to the estimated activity duration used with CPM or PERT in the computation of earliest (latest) start or finish times. • The normal cost refers to the activity cost under the normal activity time. •
  • 5. Project crashingProject crashing • The crash time refers to the shortest possible time to complete an activity with additional resources. • The crashing cost refers to the activity cost under the crashing activity time. This relationship is assumed to be linear. Hence, for each activity a crash cost per period (e.g.,per week) can be derived as follows: • crash cost per period = (Crash cost - Normal Cost)/ (Normal time - Crash time)
  • 6. Project crashingProject crashing • the cost to crash per period assumes that the relationship between adding more money to the activity and reducing the time is linear. Spend half of the money, and get half the time reduction, spend _ of the money and get _ time reduction. This is not always true in practice, but works alright for a rough planning technique
  • 7. THE GENERAL RELATIONSHIP OF TIMETHE GENERAL RELATIONSHIP OF TIME AND COSTAND COST • Crashing costs increase as project durationCrashing costs increase as project duration decreases.decreases. • Indirect costs increase as productionIndirect costs increase as production duration increases.duration increases. • Reduce project length as long as crashingReduce project length as long as crashing costs are less than indirect costs.costs are less than indirect costs.
  • 9. Conti….Conti…. • The objective of crashing was to reduce theThe objective of crashing was to reduce the scheduled completion time to reap thescheduled completion time to reap the results of the projects sooner.results of the projects sooner. • However, there may be other reasons forHowever, there may be other reasons for reducing project time.reducing project time. • There also may be direct financial penaltiesThere also may be direct financial penalties for not completing a project on time.for not completing a project on time.
  • 10. What criteria should it be based onWhat criteria should it be based on when deciding to crashing criticalwhen deciding to crashing critical times?times? The critical path is 1-2-3, the completion time =11The critical path is 1-2-3, the completion time =11 How? Path: 1-2-3 = 5+6=11 weeksHow? Path: 1-2-3 = 5+6=11 weeks Path: 1-3 = 5 weeksPath: 1-3 = 5 weeks Now, how many days can we “crash” it?Now, how many days can we “crash” it? 1 3 25 (1) 6(3)
  • 11. Conti…Conti… • The maximum time that can be crashed for:The maximum time that can be crashed for: Path 1-2-3 = 1 + 3 = 4Path 1-2-3 = 1 + 3 = 4 Path 1-3 = 0Path 1-3 = 0 • ShouldShould we use up all these 4 weeks?we use up all these 4 weeks? 1 3 25 (1) 6(3) 5(0)
  • 12. • If we used all 4 days, then path 1-2-3 has (5-1) + (6-3) = 7 completion weeks Now, we need to check if the completion time for path 1-3 has lesser than 7 weeks (why?) Now, path 1-3 has (5-0) = 5 weeks Since path 1-3 still shorter than 7 weeks, we used up all 4 crashed weeks • Question: What if path 1-3 has, say 8 weeks completion time? 1 3 2 5 (1) 6(3) 5(0) 4(0) 3(0)
  • 13. • Now, we cannot use all 4 days (Why?) Because path 1-2-3 will not be critical path anymore path 1-3 would now has longest hour to finish • Rule: When a path is a critical path, it will not stay as a critical path • So, we can only reduce the path 1-2-3 completion time to the same time • as path 1-3. (HOW?) 1 3 25 (1) 6(3) 8(0)
  • 14. • We can only reduce total time for path 1-2-3 =We can only reduce total time for path 1-2-3 = path 1-path 1-33,, that is 8 weeksthat is 8 weeks If the cost for path 1-2 and path 2-3 is the sameIf the cost for path 1-2 and path 2-3 is the same thenthen We can random pick them to crash so that itsWe can random pick them to crash so that its completioncompletion Time is 8 weeksTime is 8 weeks 1 3 25 (1) 6(3) 8(0)
  • 15. 1 3 25 (1)5 (1) 6(3)6(3) 8(0)8(0) 1 2 3 5 (1)5 (1) 6(3)6(3) 8(0)8(0) OR 4(0)4(0) 4(1)4(1) 3(0)3(0)