SlideShare une entreprise Scribd logo
1  sur  37
Télécharger pour lire hors ligne
KSU- CCP/CCT Cost Engineering Training 1018 BTA - Dr. Moustafa Ismail 2018 LEC- III 1
Cost Engineering Management
CCT Training Course:
Association for the Advancement of Cost Engineering
King Saud University
March 2018
LECTURE 07
Certified Cost Technician
‫وبركاته‬ ‫هللا‬ ‫ورحمة‬ ‫عليكن‬ ‫السالم‬
2018
KSU- CCP/CCT Cost Engineering Training 1018 BTA - Dr. Moustafa Ismail 2018 LEC- II 2
Contact details
moustafa1_ismail@yahoo.com
00966508297971
0096598922125
https://www.linkedin.com/in/moustafa-ismail-abu-dief-93798a16/
https://twitter.com/moustafaabudief
https://www.slideshare.net/moustafismail
March 2018
DEC. 2017
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5
3
CCP Certificate Section 4 Progress and cost control Ch. 14
SECTION 4 – Progress and cost control
Chapter 14 – Earned Value Overview
DEC. 2017
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5
4
CCP Certificate Section 4 Progress and cost control Ch. 14
Earned Value Overview
 Earned Value (EV) is a process for monitoring a project’s performance against a baseline.
Earned Value Management Systems
 (EVMS) are project progress control systems that integrate scope, schedule, and resources to
enable objective comparison of the earned value to the actual cost and the planned schedule.
 Required elements for establishing an Earned Value System:
1. Organization of Program
2. Work Breakdown Structure (WBS)
3. Organizational Breakdown Structure (OBS) Functional Organizational Structure, matrix,
4. Responsibility Assignment Matrix (RAM)
5. Work Authorization (WA)
6. Planning, Scheduling, and Budgeting
DEC. 2017
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5
5
CCP Certificate Section 4 Progress and cost control Ch. 14
Earned Value Overview
7.Performance Measurement Baseline (PMB)- PMB reflects the approved baseline of project
8. Control Accounts(CA)to decompose scope into work elements to be planned & managed
9. Risk Management
8.Work Package (WP) WP is the point at which work is planned, progress is measured, and earned value is computed.
9. Planning Package (PP) - package not detailed to date.
10. Management Reserve (MR) and Contingency U unknown- Known unknown
11. Earned Value Definitions- (BCWS/PV, BCWP/EV, ACWP/AC)
12. Variance Reporting
13. Change Management- maintain contract/ manage changes against contract.
14. Performance Review
DEC. 2017
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5
6
CCP Certificate Section 4 Progress and cost control Ch. 14
 Performance is measured by determining the budgeted cost of work performed (i.e.,
earned value) and comparing it to the actual cost of work performed (i.e., actual cost).
 Progress is measured by comparing the earned value to the planned value.
 Budget is maintained, hence, when quantity is changed, the unit price will be adjusted to
maintain the price fixed.
 Earned Value EV=Percent complete% x control account budget; Or EV=Units completed x
Unit Rate adjusted
DEC. 2017
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5
7
CCP Certificate Section 4 Progress and cost control Ch. 14
 Earned Value formulas
o BCWS: Budgeted work hours or cost $
o BCWP: Earned work hours or cost $
o ACWP: Actual work hours or cost $
 Variance:
o SV=BCWP-BCWS -ve Behind Schedule
o CV=BCWP-ACWSP -ve Over budget
 Performance Indices:
o SPI = BCWP/BCWS (SPI>1, ahead of schedule) < 1 Behind schedule
o CPI= BCWP/ACWSP (CPI>1, under budget) < 1 over budget
o Cost - Schedule Index (CSI) = CPI X SPI
<1 Over budget and behind schedule >1 Under budget and ahead of Schedule
Productivity
Index (PI) =
(CWH to date) ÷
(actual WH to
date)
DEC. 2017
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5
8
CCP Certificate Section 4 Progress and cost control Ch. 15
Chapter 15
Performance & Productivity Management
DEC. 2017
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5
9
CCP Certificate Section 4 Progress and cost control Ch. 15
Success Index- SI (net profit)/ (total costs)
Numerical evaluation of total organizational performance is possible using (SI) which
my be referred to performance index. It is an expression of organizational
productivity, because it relates form of output (profit or value) to form of input (cost).
• SI. For profit-oriented business. = (net profit)/ (total costs)*
• SI. For service organization, such as a government =
Success Index = (value of services rendered) / (costs of providing services)*
Total cost or cost of providing the service= (essential costs + cost of waste)*
 Waste
 Inefficiencies inherent in the design and operation of the work place
 Individual inefficiencies- Non-contributing (wasted) time by individuals
 Waste of materials, equipment, supplies, and services (misuse, overuse, loss)
 Waste of equipment (abuse, misuse, loss)- Functions that no longer add value
DEC. 2017
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5
10
CCP Certificate Section 4 Progress and cost control Ch. 15
 Special category
 Personnel in some categories, include most support and professional staff—
secretaries, design engineers, managers, etc. Equipment types include word
processors, tower cranes, and administrative vehicles, their productivity are
not properly measured on the basis of output per unit of input.
 Applying productivity measurements in such category may cause quality
compromise and add stress to the resources.
DEC. 2017
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5
11
CCP Certificate Section 4 Progress and cost control Ch. 15
The Overall Performance Issue
The Performance Problem
DEC. 2017
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5
12
CCP Certificate Section 4 Progress and cost control Ch. 15
The Overall Performance Issue- continue
• Losses Through Inefficiency
 Organizational: inconvenient positioning of office reproduction equipment,
shortages of equipment or materials, lack of procedures.
 Individual: failure to plan, refusing to use labor-saving equipment (such as a
word processor), and sloppy/poor filing are typical individual inefficiencies.
• Waste Through Interruptions
 series of interruptions :telephone calls & visitors reduces productivity. ( screen
visitors & use emails instead of calls).
DEC. 2017
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5
13
CCP Certificate Section 4 Progress and cost control Ch. 15
The Overall Performance Issue- continue
• Other Timewasters
 Interruptions are a form of time waste; there is a list of events or situations
that are accepted parts of life in most organizations, including:
o Official meetings and appointments, Telephone calls, Personal breaks and
lunch breaks, Official visitors, A need to interrupt current activity to make a
copy of something, send a fax, or coordinate with another worker, Fire drills,
hazard alarms, or other emergencies, Adverse weather, Power outages,
Equipment breakdowns, Holds for quality checks or coordination, Absentees
whose work must be absorbed by others, Turnover of key personnel—new
ones must be brought up to speed, Higher headquarters or outside agency
inspections, audits, and reviews, clerks delivering mail and messages, etc.
DEC. 2017
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5
14
CCP Certificate Section 4 Progress and cost control Ch. 15
The Overall Performance Issue- continue
• Other Timewasters - continue
 Events and situations, all of them have significant potential for elimination or
reduction through better planning and management, those include:
o Unnecessary and unstructured meetings; People late for meetings; Social visits
or greetings from passing fellow employees; Sales calls without appointments;
 Waiting for engineering and vendor information; Errors or omissions on
engineering drawings; Lack of communication—somebody didn't ―get the
word;‖ Too many people or organizations involved in getting an answer,
approval, or decision; Excessive time taken to make decisions, or
approve/coordinate something; Too few support personnel available (e.g.,
clerical), so professional staff must perform own support; and, Inadequate
support equipment (e.g., copy machines ) causes waiting.
DEC. 2017
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5
15
CCP Certificate Section 4 Progress and cost control Ch. 15
The Overall Performance Issue- continue
• Other Timewasters - continue
 Construction filed timewasters:
these are controllable time-wasters, including:
 Ill-defined scope forces constant reworking of schedule; Contractual disputes;
Labor disputes and adverse union activity; Arbitrary work rules; Personality
problems among key personnel on owner, engineer, and contractor staffs;
Late materials or installed equipment deliveries; Materials and equipment for
installation do not meet specifications or have fabrication errors; Materials
and equipment allowed to deteriorate in storage, so as to not be usable;
Materials and equipment listed on warehouse inventory cannot be found;
Failure to pick up all needed materials the first time; Excessive distances
between work areas and tool rooms, warehouses, and laydown areas; Wrong
or defective tools issued; Waiting for support equipment (e.g., crane), and etc.
DEC. 2017
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5
16
CCP Certificate Section 4 Progress and cost control Ch. 15
The Overall Performance Issue- continue
• Waste Through Rework
 Rework is a special form of waste, it is applied when W is flawed or changed
 Examples of rework in an organization; Management/Supervision Layering—
maintaining excessive levels of supervision—a higher level essentially
repeats the work of the lower level. Materials Management—Double (or
more) handling of materials before use. Reorganizations—Reconfiguring an
organization with no significant change in missions or workload. Physical
Relocations—Moving personnel and equipment to accommodate a new
organizational structure or otherwise. Lack of Electronic Data Links—
Receiving data in hard copy and reentering it into another computer system,
instead of electronically linking computer systems, Computer Illiteracy—A
manager or other professional staff member who is computer averse still does
everything longhand and turns it over to a clerk for entry into a computer.
DEC. 2017
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5
17
CCP Certificate Section 4 Progress and cost control Ch. 15
The Overall Performance Issue- continue
• The Solution
 Plan! Plan! Plan!— This is universal guidance for any operation.
 Establish written policies and procedures—
 Involve users in design decisions.
 Control changes—Changes degrade performance because they delay & demoralize.
 Give priority emphasis to safety and quality.
 Control disturbances and interruptions
 Take advantage of modern technology
DEC. 2017
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5
18
CCP Certificate Section 4 Progress and cost control Ch. 15
The Overall Performance Issue- continue
• The Solution
 Employ partnering and team building.
 Communicate—An essential element within a true team.
 Involve employees in planning—This establishes their commitment.
 Use employee group problem-solving techniques.
 Make your work place a good place to work—it promotes loyalty and stability.
 Promote first-level quality control—This is the best way to minimize rework.
 Train managers, supervisors, and workers to promote professionalism.
 Be selective in hiring—Quality control of personnel cannot be overemphasized.
DEC. 2017
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5
19
CCP Certificate Section 4 Progress and cost control Ch. 15
The Productivity issue:
• The productivity variations
 production is dependent upon some combination of machines and personnel, so
both must be examined when seeking productivity improvements.
 A major point to be made and emphasized is that productivity on the same type
of work varies significantly from location to location within a country and from
country to country. That variation is caused by many factors, which may be
grouped as follows.
DEC. 2017
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5
20
CCP Certificate Section 4 Progress and cost control Ch. 15
The Productivity issue:
 Productivity variation factors
 Variability—Sociological (Area) Factors
 differences in the sociological makeup of the local population, local work ethic,
level of mechanization, the education and training levels of workers, the
climate, the organized labor situation, and urban vs. rural factors,
 Major construction contractors and some owners maintain proprietary data on
area productivity differences to be considered in their cost estimation.
Typically, they will select one area as the base area and give it an index of 1.00.
Other areas are given indices that relate their general productivity to base area.
DEC. 2017
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5
21
CCP Certificate Section 4 Progress and cost control Ch. 15
The Productivity issue:
• Variability—Location Factors
 As location varies, so do these factors: Weather patterns, Altitude, Access,
Availability of skills, Availability of logistical support, traffic-ability of site,
Attitude of communities, transportation network, local economy,
• Variability—Project and Contract Characteristics
 Every Project is unique, so differences impact productivity potential, for the
following: project size; single craft size. schedule constraints, adequacy of
scope definition, constructability of design, exposure to hazards, environmental
requirements, height or depth of work, form of contract, budget constraints,
Quality of engineering, degree of congestion or confinement, relationship to
existing facilities, and relationship to other construction.
• Variability—Human Factors
 Overall project performance is a function of the human factors; including;
Management competence, supervisor competence, individual worker skills,
work rules, personal pride, stability of employment, overtime, experience/point
on learning curve, worker attitudes, crew stability/key personnel turnover.
DEC. 2017
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5
22
CCP Certificate Section 4 Progress and cost control Ch. 15
The Productivity issue:
• Variability—Impact of Disturbance on Performance
Factors which are most completely in the hands of management to control:
 Site layout for construction, support equipment availability, project controls
system, quality management program, technology/methodology used,
subcontractor performance, degree of communication, crew balance, materials
availability and quality, tool availability & quality, safety program, adequacy of
support facilities, planning degree, vendor performance, interruptions control.
• Variability―Accounting and Estimates
 Ideally, a contractor will maintain historical data files containing actual
productivity data from past projects. For this on future , several criteria apply:
 A standard chart of accounts for crew tasks must be used for all projects so that
data from one project realistically can be compared to data from another.
 Breakdown of crew tasks for purposes of estimating must be same as that used
for reporting, so that estimated & actual performance can be truly compared.
 In addition to the numerical data collected on each project, the conditions under
which work was performed (e.g. weather, congestion, materials shortages).
 When preparing bids, estimators retrieve the data on similar work performed
under similar conditions. Judgment decisions must be made to adapt data on
hand to the new project, by using range estimates and checklist & work sheets.
DEC. 2017
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5
23
CCP Certificate Section 4 Progress and cost control Ch. 15
The Productivity issue:
• Variability―Accounting and Estimates
 Ideally, a contractor will maintain historical data files containing actual
productivity data from past projects. For this on future , several criteria apply:
 A standard chart of accounts for crew tasks must be used for all projects so that
data from one project realistically can be compared to data from another.
 Breakdown of crew tasks for purposes of estimating must be same as that used
for reporting, so that estimated & actual performance can be truly compared.
 In addition to the numerical data collected on each project, the conditions under
which work was performed (e.g. weather, congestion, materials shortages).
 When preparing bids, estimators retrieve the data on similar work performed
under similar conditions. Judgment decisions must be made to adapt data on
hand to the new project, by using range estimates and checklist & work sheets.
DEC. 2017
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5
24
CCP Certificate Section 4 Progress and cost control Ch. 15
Productivity analysis- Determining percent complete.
1. Units Completed
 Suitable when the total scope of an activity consists of a number of equal or
nearly equal parts, such as; ideally, each unit is of relatively short duration, in
engineering, an application is in writing of a number of specifications of a
given type where all specifications are considered to have equal weight.
 In construction, useful in activities like earthwork, concrete, and wire pulling.
2. Incremental Milestone
 Appropriate for activities of significant duration that are composed of easily
recognized, sequential sub activities. Percentage completion values are
established based on the effort estimated to be required at each milestone point
relative to the total for the activity.
 This method is ideal for control of engineering drawings and procurement.
 Ex. for drawing control is:
 Construction Ex. Vessel installation.
DEC. 2017
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5
25
CCP Certificate Section 4 Progress and cost control Ch. 15
Productivity analysis- Determining percent complete.
3. Start/Finish Percentages
 Applicable to activities that lack readily definable intermediate milestones, and/or
the effort/time required is very difficult to estimate.
 Start = controllers credit 20 to 50%
 Finish 100 %
 In engineering, for work such as planning, designing, manual writing, model
building, and studies. Also for specification writing.
 Construction in any situation if scheduling with detailed multiple short-term tasks.
4. Ratio
 Applicable to tasks as project M, constructability studies, project controls, and
comparable activity that involve a long period of time, no end product).
 used on tasks where start/finish method is appropriate.
 % complete at any time = dividing hours (or dollars) spent to date BY the
current estimate of hours (or dollars) at completion.
5. Supervisor Opinion
 Subjective evaluation of % complete (by the supervisors) and should be used
only absence discrete methods cannot be used.( for small tasks).
 There is tendency to over-estimate % completed for activity in its early stages.
DEC. 2017
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5
26
CCP Certificate Section 4 Progress and cost control Ch. 15
Productivity analysis- Determining percent complete.
6. Weighted or Equivalent Units
 Applicable where the task is a major effort involving a long period of time and
composed of two or more overlapping subtasks, with different unit of
measurement (e.g., each, yd3, LM).
 Subtasks are listed along with their respective units of measure and quantities,
weighted, using relative work hours
 Total of all weights equals 1.00 or 100 %.
 Subtask % is reported using one of the 5 measure. techniques above mentioned.
 S.task Progress% x S.task weighting factor = its contribution to overall task
 Those for all subtasks are summed = overall percent completion of the activity.
Ex1. concrete placement ( yrd3),; broken up into base preparation, forming, re-
steel installation, concrete placement, curing, form stripping, and patching.
DEC. 2017
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5
27
CCP Certificate Section 4 Progress and cost control Ch. 15
Productivity analysis- Determining percent complete.
6. Weighted or Equivalent Units- continue
 Ex2. steel erection(Tons)The process is illustrated in Table 15.1.(SK6- p230)
DEC. 2017
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5
28
CCP Certificate Section 4 Progress and cost control Ch. 15
Productivity analysis- Determining percent complete.
Productivity Measurement of Individual Work Tasks
• Owners & contractors compare actual productivity to estimated/budgeted.
 For single work activity:
Productivity = (number of units completed) ÷ (work-hours consumed)
Productivity Analysis at a Summary Level
Productivity = EV/ Actual WH
Valid at a summary level, if actual Q of work are equal to those budgeted.
• Credit work hours – CWH.
CWH = (budgeted unit rate*) x (units completed to date)
*Budgeted Unit Rate = budgeted hours per unit of work( e.g. h/m3)
DEC. 2017
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5
29
CCP Certificate Section 4 Progress and cost control Ch. 15
Productivity analysis- Determining percent complete.
Productivity Analysis at a Summary Level- continue
For progressing w. package:
CWH = (percent complete) x (budgeted unit rate) e.g. = 50%x 4h/me= 2h/m3…. And,
The Productivity Index (PI) = (CWH to date) ÷ (actual WH to date)
(PI) for a combination of work packages or for a total project:
Productivity Index = (CWH ÷ a c t u a l work hours).
PI< 1 unfavorable
PI ≥ 1 favorable
DEC. 2017
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5
30
CCP Certificate Section 4 Progress and cost control Ch. 15
Productivity analysis- Determining percent complete.
Incentives
1. The incentives increase the productivity & reduce the waste, reduce absenteeism.
2. Improve employee morale and promote teamwork, and identify more cost-effective
work procedures
3. Improve equipment design, Improve quality
4. Share business risks with employees.
DEC. 2017
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5
31
CCP Certificate Section 4 Progress and cost control Ch. 15
The stimuli
a. Possibility of winning that personal satisfaction in achieving a goal, financial gain,
career enhancement, pride as part of the winners, chance to do something different.
b. Fear of losing that potential loss of job, potential loss of promotion, .. etc.
c. Rewards within the winning scenario
d. Intrinsic value such as cash rewards
e. Extrinsic value such as medals, badges (esteem value).
f. A chance to do something different
g. Fear of losing:
 Potential embarrassment
 Potential loss of status, job, potential for promotion, etc.
Best incentive programs are based on the concept of win-win; (i.e., both the employer
and employee are potential winners). Capitalizers on the employee's fear of losing are
more fragile and can be counterproductive.
DEC. 2017
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5
32
CCP Certificate Section 4 Progress and cost control Ch. 15
Q.
Possibility of winning that personal satisfaction in achieving a goal,
financial gain, career enhancement, pride as part of the winners, chance
to do something different.
1- High productivity
2-Stimuli
Q: Potential embarrassment and Potential loss of status, job, potential
for promotion, etc. are consequences o.
1- fear of loose
2- delay in work
3- low KPI’s
4- improper quality metrics.
DEC. 2017
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5
33
CCP Certificate Section 4 Progress and cost control Ch. 15
PRODUCTIVITY INDEX EVALUATION WORKSHEET
Purpose: The table shown below, is intended to facilitate a comparison
of the productivity
 potential of a proposed project with respect to a completed project. For
this purpose, a productivity index of 1.0 is average, a
 productivity index less than 1.0 is less than average (unfavorable), and
a productivity index greater than 1.0 is better than average (favorable).
DEC. 2017
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5
34
CCP Certificate Section 4 Progress and cost control Ch. 15
PRODUCTIVITY INDEX EVALUATION WORKSHEET
DEC. 2017
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5
35
CCP Certificate Section 4 Progress and cost control Ch. 15
PRODUCTIVITY INDEX EVALUATION WORKSHEET continue
DEC. 2017
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5
36
CCP Certificate Section 4 Progress and cost control Ch. 15
PRODUCTIVITY INDEX EVALUATION WORKSHEET continue
Use of Worksheet
• For a reference project, complete evaluation of the 7 categories.
• each category is made up of 2 or more subcategories, evaluation to be
made at the subcategory level to yield the category score. For example,
note that the first category, general area economy, has three sub-elements.
• Assume that the group makes the following analysis of a completed
project:
o Construction volume in the area at the time of the project was somewhat
low compared to previous years when
several major plants were built. Now, most construction activity involves
homes and small commercial projects. This subcategory is given an index of
110.
DEC. 2017
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5
37
CCP Certificate Section 4 Progress and cost control Ch. 15
PRODUCTIVITY INDEX EVALUATION WORKSHEET continue
The unemployment rate was about average for the state, but better than the
national average. There were jobs available, but most were of the minimum
wage category. This subcategory is given an index of 100.
o The local business situation was basically healthy, neither robust nor
depressed. This subcategory is given
an index of 100.
o The resultant score for Category 1, general area economy, is calculated
from the above three index totals.
110 x 4 = 440
100 x 4 = 400
100 x 2 = 200
1,040 ÷ 10 = 104

Contenu connexe

Tendances

Ss 07 training fidic moustafa ismail 2018 _ lec 7_a
Ss 07 training fidic moustafa ismail  2018 _ lec 7_aSs 07 training fidic moustafa ismail  2018 _ lec 7_a
Ss 07 training fidic moustafa ismail 2018 _ lec 7_aMoustafa Ismail Abu Dief
 
Ss 09 cost engineering management training- nov 2017 moustafa sec 5 part ii...
Ss 09 cost engineering management  training- nov 2017  moustafa sec 5 part ii...Ss 09 cost engineering management  training- nov 2017  moustafa sec 5 part ii...
Ss 09 cost engineering management training- nov 2017 moustafa sec 5 part ii...Moustafa Ismail Abu Dief
 
Ss 06 training fidic moustafa ismail 2018 _ lec 6
Ss 06 training fidic moustafa ismail  2018 _ lec 6Ss 06 training fidic moustafa ismail  2018 _ lec 6
Ss 06 training fidic moustafa ismail 2018 _ lec 6Moustafa Ismail Abu Dief
 
Cfcc certified forensic claims consultant lecture one 2017- dr moustafa ismail
Cfcc certified forensic claims consultant  lecture one  2017- dr moustafa ismailCfcc certified forensic claims consultant  lecture one  2017- dr moustafa ismail
Cfcc certified forensic claims consultant lecture one 2017- dr moustafa ismailMoustafa Ismail Abu Dief
 
Engineering design guildline_general_plant_cost_estimating_rev01web
Engineering design guildline_general_plant_cost_estimating_rev01webEngineering design guildline_general_plant_cost_estimating_rev01web
Engineering design guildline_general_plant_cost_estimating_rev01webGABISA DEMISIE
 
Session M2 - Scream If You Want To Go Faster - The contractual, legal, financ...
Session M2 - Scream If You Want To Go Faster - The contractual, legal, financ...Session M2 - Scream If You Want To Go Faster - The contractual, legal, financ...
Session M2 - Scream If You Want To Go Faster - The contractual, legal, financ...Project Controls Expo
 
Sample cost control training proposal
Sample cost control training proposalSample cost control training proposal
Sample cost control training proposalSadegh Yazdani
 
Green field project making of production plant
Green field project making of production plantGreen field project making of production plant
Green field project making of production plantVikram Bakshi
 
Cost management basics for Construction Engineers
Cost management basics for Construction EngineersCost management basics for Construction Engineers
Cost management basics for Construction EngineersAmit Kumar Senapati, PMP®
 
Suspensions and Delays in Construction Contract
Suspensions and Delays in Construction ContractSuspensions and Delays in Construction Contract
Suspensions and Delays in Construction ContractAvinash Kumar Gupta
 
10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation StepsSHAZEBALIKHAN1
 
Fidic comparison red yellow - silver book
Fidic comparison red   yellow - silver bookFidic comparison red   yellow - silver book
Fidic comparison red yellow - silver bookHani Saad
 
GCCC contracts experience to date 08'03'11
GCCC contracts experience to date 08'03'11GCCC contracts experience to date 08'03'11
GCCC contracts experience to date 08'03'11cmcgoverntobin
 
ESTIEM Lean Six Sigma Green Belt Project at Continental - Scrap Reduction
ESTIEM Lean Six Sigma Green Belt Project at Continental - Scrap ReductionESTIEM Lean Six Sigma Green Belt Project at Continental - Scrap Reduction
ESTIEM Lean Six Sigma Green Belt Project at Continental - Scrap ReductionESTIEM
 

Tendances (18)

Ss 07 training fidic moustafa ismail 2018 _ lec 7_a
Ss 07 training fidic moustafa ismail  2018 _ lec 7_aSs 07 training fidic moustafa ismail  2018 _ lec 7_a
Ss 07 training fidic moustafa ismail 2018 _ lec 7_a
 
Ss 09 cost engineering management training- nov 2017 moustafa sec 5 part ii...
Ss 09 cost engineering management  training- nov 2017  moustafa sec 5 part ii...Ss 09 cost engineering management  training- nov 2017  moustafa sec 5 part ii...
Ss 09 cost engineering management training- nov 2017 moustafa sec 5 part ii...
 
Ss 06 training fidic moustafa ismail 2018 _ lec 6
Ss 06 training fidic moustafa ismail  2018 _ lec 6Ss 06 training fidic moustafa ismail  2018 _ lec 6
Ss 06 training fidic moustafa ismail 2018 _ lec 6
 
Cfcc certified forensic claims consultant lecture one 2017- dr moustafa ismail
Cfcc certified forensic claims consultant  lecture one  2017- dr moustafa ismailCfcc certified forensic claims consultant  lecture one  2017- dr moustafa ismail
Cfcc certified forensic claims consultant lecture one 2017- dr moustafa ismail
 
Ppt on fidic claims
Ppt on fidic claimsPpt on fidic claims
Ppt on fidic claims
 
Engineering design guildline_general_plant_cost_estimating_rev01web
Engineering design guildline_general_plant_cost_estimating_rev01webEngineering design guildline_general_plant_cost_estimating_rev01web
Engineering design guildline_general_plant_cost_estimating_rev01web
 
Session M2 - Scream If You Want To Go Faster - The contractual, legal, financ...
Session M2 - Scream If You Want To Go Faster - The contractual, legal, financ...Session M2 - Scream If You Want To Go Faster - The contractual, legal, financ...
Session M2 - Scream If You Want To Go Faster - The contractual, legal, financ...
 
Sample cost control training proposal
Sample cost control training proposalSample cost control training proposal
Sample cost control training proposal
 
Green field project making of production plant
Green field project making of production plantGreen field project making of production plant
Green field project making of production plant
 
Cost management basics for Construction Engineers
Cost management basics for Construction EngineersCost management basics for Construction Engineers
Cost management basics for Construction Engineers
 
Suspensions and Delays in Construction Contract
Suspensions and Delays in Construction ContractSuspensions and Delays in Construction Contract
Suspensions and Delays in Construction Contract
 
cost-estimation-tutorial
cost-estimation-tutorialcost-estimation-tutorial
cost-estimation-tutorial
 
Questions in notes
Questions in notesQuestions in notes
Questions in notes
 
10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps
 
Fidic comparison red yellow - silver book
Fidic comparison red   yellow - silver bookFidic comparison red   yellow - silver book
Fidic comparison red yellow - silver book
 
062 Logistics & Productivity PART 1
062  Logistics & Productivity PART 1062  Logistics & Productivity PART 1
062 Logistics & Productivity PART 1
 
GCCC contracts experience to date 08'03'11
GCCC contracts experience to date 08'03'11GCCC contracts experience to date 08'03'11
GCCC contracts experience to date 08'03'11
 
ESTIEM Lean Six Sigma Green Belt Project at Continental - Scrap Reduction
ESTIEM Lean Six Sigma Green Belt Project at Continental - Scrap ReductionESTIEM Lean Six Sigma Green Belt Project at Continental - Scrap Reduction
ESTIEM Lean Six Sigma Green Belt Project at Continental - Scrap Reduction
 

Similaire à Ss 07 cost engineering management training- nov 2017 moustafa part ii ch 14 15

Ss 03 CCP- AACE.org cost engineering management training- 2017 - dr. mousta...
Ss 03 CCP- AACE.org  cost engineering management  training- 2017 - dr. mousta...Ss 03 CCP- AACE.org  cost engineering management  training- 2017 - dr. mousta...
Ss 03 CCP- AACE.org cost engineering management training- 2017 - dr. mousta...Moustafa Ismail Abu Dief
 
April 2016 CV_1
April 2016 CV_1April 2016 CV_1
April 2016 CV_15Asdfghjkl
 
Arun Sahu_ Deputy Manager_12 years experience
Arun Sahu_ Deputy Manager_12 years experienceArun Sahu_ Deputy Manager_12 years experience
Arun Sahu_ Deputy Manager_12 years experienceArun Sahu, CIPM/CrtPRM
 
HPAC article_AUG2015_CP Optimization
HPAC article_AUG2015_CP OptimizationHPAC article_AUG2015_CP Optimization
HPAC article_AUG2015_CP OptimizationDavid Yancosky
 
Maintenance engineering
Maintenance engineeringMaintenance engineering
Maintenance engineeringAnirudh Goyal
 
Job description factory services engineer
Job description   factory services engineerJob description   factory services engineer
Job description factory services engineerBabatunde Sofoluwe
 
Lecture-3-Introduction to Maintenance Management.ppt
Lecture-3-Introduction to Maintenance Management.pptLecture-3-Introduction to Maintenance Management.ppt
Lecture-3-Introduction to Maintenance Management.pptThushan9
 
Operation Management
Operation ManagementOperation Management
Operation ManagementPrabu U
 
Refinery Overhauling Introduction
Refinery Overhauling IntroductionRefinery Overhauling Introduction
Refinery Overhauling IntroductionAshar Ahmed
 
D08 Quantify Project Value
D08 Quantify Project ValueD08 Quantify Project Value
D08 Quantify Project ValueLeanleaders.org
 
D08 Quantify Project Value
D08 Quantify Project ValueD08 Quantify Project Value
D08 Quantify Project ValueLeanleaders.org
 
SOLVED SMU MBA ASSIGNMENTS AVAILABLE....
SOLVED SMU MBA ASSIGNMENTS AVAILABLE....SOLVED SMU MBA ASSIGNMENTS AVAILABLE....
SOLVED SMU MBA ASSIGNMENTS AVAILABLE....Naveen Kumar
 
Manual%204%20 kobetsu kaizen
Manual%204%20 kobetsu kaizenManual%204%20 kobetsu kaizen
Manual%204%20 kobetsu kaizenvikymail
 
Storyboard_SPS_Payroll
Storyboard_SPS_PayrollStoryboard_SPS_Payroll
Storyboard_SPS_PayrollBalaguru SP
 
Smsvn pmp training_slides_chapter_7
Smsvn pmp training_slides_chapter_7Smsvn pmp training_slides_chapter_7
Smsvn pmp training_slides_chapter_7Nam Trung
 

Similaire à Ss 07 cost engineering management training- nov 2017 moustafa part ii ch 14 15 (20)

Ss 03 CCP- AACE.org cost engineering management training- 2017 - dr. mousta...
Ss 03 CCP- AACE.org  cost engineering management  training- 2017 - dr. mousta...Ss 03 CCP- AACE.org  cost engineering management  training- 2017 - dr. mousta...
Ss 03 CCP- AACE.org cost engineering management training- 2017 - dr. mousta...
 
Viresh Jugali CV
Viresh Jugali CVViresh Jugali CV
Viresh Jugali CV
 
GNB LATEST
GNB LATESTGNB LATEST
GNB LATEST
 
GNB LATEST
GNB LATESTGNB LATEST
GNB LATEST
 
April 2016 CV_1
April 2016 CV_1April 2016 CV_1
April 2016 CV_1
 
Arun Sahu_ Deputy Manager_12 years experience
Arun Sahu_ Deputy Manager_12 years experienceArun Sahu_ Deputy Manager_12 years experience
Arun Sahu_ Deputy Manager_12 years experience
 
HPAC article_AUG2015_CP Optimization
HPAC article_AUG2015_CP OptimizationHPAC article_AUG2015_CP Optimization
HPAC article_AUG2015_CP Optimization
 
Maintenance engineering
Maintenance engineeringMaintenance engineering
Maintenance engineering
 
Job description factory services engineer
Job description   factory services engineerJob description   factory services engineer
Job description factory services engineer
 
Lecture-3-Introduction to Maintenance Management.ppt
Lecture-3-Introduction to Maintenance Management.pptLecture-3-Introduction to Maintenance Management.ppt
Lecture-3-Introduction to Maintenance Management.ppt
 
Operation Management
Operation ManagementOperation Management
Operation Management
 
Refinery Overhauling Introduction
Refinery Overhauling IntroductionRefinery Overhauling Introduction
Refinery Overhauling Introduction
 
D08 Quantify Project Value
D08 Quantify Project ValueD08 Quantify Project Value
D08 Quantify Project Value
 
D08 Quantify Project Value
D08 Quantify Project ValueD08 Quantify Project Value
D08 Quantify Project Value
 
Report for COOP PUPR without fusion
Report for COOP PUPR without fusionReport for COOP PUPR without fusion
Report for COOP PUPR without fusion
 
SOLVED SMU MBA ASSIGNMENTS AVAILABLE....
SOLVED SMU MBA ASSIGNMENTS AVAILABLE....SOLVED SMU MBA ASSIGNMENTS AVAILABLE....
SOLVED SMU MBA ASSIGNMENTS AVAILABLE....
 
Manual%204%20 kobetsu kaizen
Manual%204%20 kobetsu kaizenManual%204%20 kobetsu kaizen
Manual%204%20 kobetsu kaizen
 
Storyboard_SPS_Payroll
Storyboard_SPS_PayrollStoryboard_SPS_Payroll
Storyboard_SPS_Payroll
 
SURESH MANICKAM
SURESH MANICKAMSURESH MANICKAM
SURESH MANICKAM
 
Smsvn pmp training_slides_chapter_7
Smsvn pmp training_slides_chapter_7Smsvn pmp training_slides_chapter_7
Smsvn pmp training_slides_chapter_7
 

Plus de Moustafa Ismail Abu Dief

Presentation eci dr moustafa ismail 20 july 2020
Presentation eci dr moustafa ismail 20 july 2020Presentation eci dr moustafa ismail 20 july 2020
Presentation eci dr moustafa ismail 20 july 2020Moustafa Ismail Abu Dief
 
Ss 07 training fidic moustafa ismail 2018 _ lec 7_a
Ss 07 training fidic moustafa ismail  2018 _ lec 7_aSs 07 training fidic moustafa ismail  2018 _ lec 7_a
Ss 07 training fidic moustafa ismail 2018 _ lec 7_aMoustafa Ismail Abu Dief
 
Training fidic moustafa ismail 2018 _ lec 8
Training fidic moustafa ismail  2018 _ lec 8Training fidic moustafa ismail  2018 _ lec 8
Training fidic moustafa ismail 2018 _ lec 8Moustafa Ismail Abu Dief
 
Ss 07 training fidic moustafa ismail 2018__ lec 7B
Ss 07 training fidic moustafa ismail  2018__ lec 7BSs 07 training fidic moustafa ismail  2018__ lec 7B
Ss 07 training fidic moustafa ismail 2018__ lec 7BMoustafa Ismail Abu Dief
 
SCE 1 2018 claims management-in-construction-projects-seminar-.-2017 dr mous...
SCE 1 2018 claims management-in-construction-projects-seminar-.-2017  dr mous...SCE 1 2018 claims management-in-construction-projects-seminar-.-2017  dr mous...
SCE 1 2018 claims management-in-construction-projects-seminar-.-2017 dr mous...Moustafa Ismail Abu Dief
 
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5Moustafa Ismail Abu Dief
 
Training fidic moustafa ismail 2017 _ lec 4
Training fidic moustafa ismail  2017 _  lec 4Training fidic moustafa ismail  2017 _  lec 4
Training fidic moustafa ismail 2017 _ lec 4Moustafa Ismail Abu Dief
 
Ss training fidic moustafa ismail 2017 _ lec. 1
Ss training fidic moustafa ismail  2017 _ lec. 1Ss training fidic moustafa ismail  2017 _ lec. 1
Ss training fidic moustafa ismail 2017 _ lec. 1Moustafa Ismail Abu Dief
 

Plus de Moustafa Ismail Abu Dief (14)

Bim arabia red fidic
Bim arabia red fidicBim arabia red fidic
Bim arabia red fidic
 
Fidic 2017 engineering
Fidic 2017 engineeringFidic 2017 engineering
Fidic 2017 engineering
 
Presentation eci dr moustafa ismail 20 july 2020
Presentation eci dr moustafa ismail 20 july 2020Presentation eci dr moustafa ismail 20 july 2020
Presentation eci dr moustafa ismail 20 july 2020
 
Yellow book session bimarabia
Yellow book session bimarabiaYellow book session bimarabia
Yellow book session bimarabia
 
CMC certification
CMC certificationCMC certification
CMC certification
 
Ss 07 training fidic moustafa ismail 2018 _ lec 7_a
Ss 07 training fidic moustafa ismail  2018 _ lec 7_aSs 07 training fidic moustafa ismail  2018 _ lec 7_a
Ss 07 training fidic moustafa ismail 2018 _ lec 7_a
 
Construction Claims Training Course 2019
Construction Claims Training Course 2019Construction Claims Training Course 2019
Construction Claims Training Course 2019
 
Construction Claims Training Course 2019
Construction Claims Training Course 2019Construction Claims Training Course 2019
Construction Claims Training Course 2019
 
Training fidic moustafa ismail 2018 _ lec 8
Training fidic moustafa ismail  2018 _ lec 8Training fidic moustafa ismail  2018 _ lec 8
Training fidic moustafa ismail 2018 _ lec 8
 
Ss 07 training fidic moustafa ismail 2018__ lec 7B
Ss 07 training fidic moustafa ismail  2018__ lec 7BSs 07 training fidic moustafa ismail  2018__ lec 7B
Ss 07 training fidic moustafa ismail 2018__ lec 7B
 
SCE 1 2018 claims management-in-construction-projects-seminar-.-2017 dr mous...
SCE 1 2018 claims management-in-construction-projects-seminar-.-2017  dr mous...SCE 1 2018 claims management-in-construction-projects-seminar-.-2017  dr mous...
SCE 1 2018 claims management-in-construction-projects-seminar-.-2017 dr mous...
 
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
 
Training fidic moustafa ismail 2017 _ lec 4
Training fidic moustafa ismail  2017 _  lec 4Training fidic moustafa ismail  2017 _  lec 4
Training fidic moustafa ismail 2017 _ lec 4
 
Ss training fidic moustafa ismail 2017 _ lec. 1
Ss training fidic moustafa ismail  2017 _ lec. 1Ss training fidic moustafa ismail  2017 _ lec. 1
Ss training fidic moustafa ismail 2017 _ lec. 1
 

Dernier

Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 

Dernier (20)

Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 

Ss 07 cost engineering management training- nov 2017 moustafa part ii ch 14 15

  • 1. KSU- CCP/CCT Cost Engineering Training 1018 BTA - Dr. Moustafa Ismail 2018 LEC- III 1 Cost Engineering Management CCT Training Course: Association for the Advancement of Cost Engineering King Saud University March 2018 LECTURE 07 Certified Cost Technician ‫وبركاته‬ ‫هللا‬ ‫ورحمة‬ ‫عليكن‬ ‫السالم‬ 2018
  • 2. KSU- CCP/CCT Cost Engineering Training 1018 BTA - Dr. Moustafa Ismail 2018 LEC- II 2 Contact details moustafa1_ismail@yahoo.com 00966508297971 0096598922125 https://www.linkedin.com/in/moustafa-ismail-abu-dief-93798a16/ https://twitter.com/moustafaabudief https://www.slideshare.net/moustafismail March 2018
  • 3. DEC. 2017 AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5 3 CCP Certificate Section 4 Progress and cost control Ch. 14 SECTION 4 – Progress and cost control Chapter 14 – Earned Value Overview
  • 4. DEC. 2017 AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5 4 CCP Certificate Section 4 Progress and cost control Ch. 14 Earned Value Overview  Earned Value (EV) is a process for monitoring a project’s performance against a baseline. Earned Value Management Systems  (EVMS) are project progress control systems that integrate scope, schedule, and resources to enable objective comparison of the earned value to the actual cost and the planned schedule.  Required elements for establishing an Earned Value System: 1. Organization of Program 2. Work Breakdown Structure (WBS) 3. Organizational Breakdown Structure (OBS) Functional Organizational Structure, matrix, 4. Responsibility Assignment Matrix (RAM) 5. Work Authorization (WA) 6. Planning, Scheduling, and Budgeting
  • 5. DEC. 2017 AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5 5 CCP Certificate Section 4 Progress and cost control Ch. 14 Earned Value Overview 7.Performance Measurement Baseline (PMB)- PMB reflects the approved baseline of project 8. Control Accounts(CA)to decompose scope into work elements to be planned & managed 9. Risk Management 8.Work Package (WP) WP is the point at which work is planned, progress is measured, and earned value is computed. 9. Planning Package (PP) - package not detailed to date. 10. Management Reserve (MR) and Contingency U unknown- Known unknown 11. Earned Value Definitions- (BCWS/PV, BCWP/EV, ACWP/AC) 12. Variance Reporting 13. Change Management- maintain contract/ manage changes against contract. 14. Performance Review
  • 6. DEC. 2017 AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5 6 CCP Certificate Section 4 Progress and cost control Ch. 14  Performance is measured by determining the budgeted cost of work performed (i.e., earned value) and comparing it to the actual cost of work performed (i.e., actual cost).  Progress is measured by comparing the earned value to the planned value.  Budget is maintained, hence, when quantity is changed, the unit price will be adjusted to maintain the price fixed.  Earned Value EV=Percent complete% x control account budget; Or EV=Units completed x Unit Rate adjusted
  • 7. DEC. 2017 AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5 7 CCP Certificate Section 4 Progress and cost control Ch. 14  Earned Value formulas o BCWS: Budgeted work hours or cost $ o BCWP: Earned work hours or cost $ o ACWP: Actual work hours or cost $  Variance: o SV=BCWP-BCWS -ve Behind Schedule o CV=BCWP-ACWSP -ve Over budget  Performance Indices: o SPI = BCWP/BCWS (SPI>1, ahead of schedule) < 1 Behind schedule o CPI= BCWP/ACWSP (CPI>1, under budget) < 1 over budget o Cost - Schedule Index (CSI) = CPI X SPI <1 Over budget and behind schedule >1 Under budget and ahead of Schedule Productivity Index (PI) = (CWH to date) ÷ (actual WH to date)
  • 8. DEC. 2017 AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5 8 CCP Certificate Section 4 Progress and cost control Ch. 15 Chapter 15 Performance & Productivity Management
  • 9. DEC. 2017 AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5 9 CCP Certificate Section 4 Progress and cost control Ch. 15 Success Index- SI (net profit)/ (total costs) Numerical evaluation of total organizational performance is possible using (SI) which my be referred to performance index. It is an expression of organizational productivity, because it relates form of output (profit or value) to form of input (cost). • SI. For profit-oriented business. = (net profit)/ (total costs)* • SI. For service organization, such as a government = Success Index = (value of services rendered) / (costs of providing services)* Total cost or cost of providing the service= (essential costs + cost of waste)*  Waste  Inefficiencies inherent in the design and operation of the work place  Individual inefficiencies- Non-contributing (wasted) time by individuals  Waste of materials, equipment, supplies, and services (misuse, overuse, loss)  Waste of equipment (abuse, misuse, loss)- Functions that no longer add value
  • 10. DEC. 2017 AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5 10 CCP Certificate Section 4 Progress and cost control Ch. 15  Special category  Personnel in some categories, include most support and professional staff— secretaries, design engineers, managers, etc. Equipment types include word processors, tower cranes, and administrative vehicles, their productivity are not properly measured on the basis of output per unit of input.  Applying productivity measurements in such category may cause quality compromise and add stress to the resources.
  • 11. DEC. 2017 AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5 11 CCP Certificate Section 4 Progress and cost control Ch. 15 The Overall Performance Issue The Performance Problem
  • 12. DEC. 2017 AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5 12 CCP Certificate Section 4 Progress and cost control Ch. 15 The Overall Performance Issue- continue • Losses Through Inefficiency  Organizational: inconvenient positioning of office reproduction equipment, shortages of equipment or materials, lack of procedures.  Individual: failure to plan, refusing to use labor-saving equipment (such as a word processor), and sloppy/poor filing are typical individual inefficiencies. • Waste Through Interruptions  series of interruptions :telephone calls & visitors reduces productivity. ( screen visitors & use emails instead of calls).
  • 13. DEC. 2017 AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5 13 CCP Certificate Section 4 Progress and cost control Ch. 15 The Overall Performance Issue- continue • Other Timewasters  Interruptions are a form of time waste; there is a list of events or situations that are accepted parts of life in most organizations, including: o Official meetings and appointments, Telephone calls, Personal breaks and lunch breaks, Official visitors, A need to interrupt current activity to make a copy of something, send a fax, or coordinate with another worker, Fire drills, hazard alarms, or other emergencies, Adverse weather, Power outages, Equipment breakdowns, Holds for quality checks or coordination, Absentees whose work must be absorbed by others, Turnover of key personnel—new ones must be brought up to speed, Higher headquarters or outside agency inspections, audits, and reviews, clerks delivering mail and messages, etc.
  • 14. DEC. 2017 AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5 14 CCP Certificate Section 4 Progress and cost control Ch. 15 The Overall Performance Issue- continue • Other Timewasters - continue  Events and situations, all of them have significant potential for elimination or reduction through better planning and management, those include: o Unnecessary and unstructured meetings; People late for meetings; Social visits or greetings from passing fellow employees; Sales calls without appointments;  Waiting for engineering and vendor information; Errors or omissions on engineering drawings; Lack of communication—somebody didn't ―get the word;‖ Too many people or organizations involved in getting an answer, approval, or decision; Excessive time taken to make decisions, or approve/coordinate something; Too few support personnel available (e.g., clerical), so professional staff must perform own support; and, Inadequate support equipment (e.g., copy machines ) causes waiting.
  • 15. DEC. 2017 AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5 15 CCP Certificate Section 4 Progress and cost control Ch. 15 The Overall Performance Issue- continue • Other Timewasters - continue  Construction filed timewasters: these are controllable time-wasters, including:  Ill-defined scope forces constant reworking of schedule; Contractual disputes; Labor disputes and adverse union activity; Arbitrary work rules; Personality problems among key personnel on owner, engineer, and contractor staffs; Late materials or installed equipment deliveries; Materials and equipment for installation do not meet specifications or have fabrication errors; Materials and equipment allowed to deteriorate in storage, so as to not be usable; Materials and equipment listed on warehouse inventory cannot be found; Failure to pick up all needed materials the first time; Excessive distances between work areas and tool rooms, warehouses, and laydown areas; Wrong or defective tools issued; Waiting for support equipment (e.g., crane), and etc.
  • 16. DEC. 2017 AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5 16 CCP Certificate Section 4 Progress and cost control Ch. 15 The Overall Performance Issue- continue • Waste Through Rework  Rework is a special form of waste, it is applied when W is flawed or changed  Examples of rework in an organization; Management/Supervision Layering— maintaining excessive levels of supervision—a higher level essentially repeats the work of the lower level. Materials Management—Double (or more) handling of materials before use. Reorganizations—Reconfiguring an organization with no significant change in missions or workload. Physical Relocations—Moving personnel and equipment to accommodate a new organizational structure or otherwise. Lack of Electronic Data Links— Receiving data in hard copy and reentering it into another computer system, instead of electronically linking computer systems, Computer Illiteracy—A manager or other professional staff member who is computer averse still does everything longhand and turns it over to a clerk for entry into a computer.
  • 17. DEC. 2017 AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5 17 CCP Certificate Section 4 Progress and cost control Ch. 15 The Overall Performance Issue- continue • The Solution  Plan! Plan! Plan!— This is universal guidance for any operation.  Establish written policies and procedures—  Involve users in design decisions.  Control changes—Changes degrade performance because they delay & demoralize.  Give priority emphasis to safety and quality.  Control disturbances and interruptions  Take advantage of modern technology
  • 18. DEC. 2017 AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5 18 CCP Certificate Section 4 Progress and cost control Ch. 15 The Overall Performance Issue- continue • The Solution  Employ partnering and team building.  Communicate—An essential element within a true team.  Involve employees in planning—This establishes their commitment.  Use employee group problem-solving techniques.  Make your work place a good place to work—it promotes loyalty and stability.  Promote first-level quality control—This is the best way to minimize rework.  Train managers, supervisors, and workers to promote professionalism.  Be selective in hiring—Quality control of personnel cannot be overemphasized.
  • 19. DEC. 2017 AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5 19 CCP Certificate Section 4 Progress and cost control Ch. 15 The Productivity issue: • The productivity variations  production is dependent upon some combination of machines and personnel, so both must be examined when seeking productivity improvements.  A major point to be made and emphasized is that productivity on the same type of work varies significantly from location to location within a country and from country to country. That variation is caused by many factors, which may be grouped as follows.
  • 20. DEC. 2017 AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5 20 CCP Certificate Section 4 Progress and cost control Ch. 15 The Productivity issue:  Productivity variation factors  Variability—Sociological (Area) Factors  differences in the sociological makeup of the local population, local work ethic, level of mechanization, the education and training levels of workers, the climate, the organized labor situation, and urban vs. rural factors,  Major construction contractors and some owners maintain proprietary data on area productivity differences to be considered in their cost estimation. Typically, they will select one area as the base area and give it an index of 1.00. Other areas are given indices that relate their general productivity to base area.
  • 21. DEC. 2017 AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5 21 CCP Certificate Section 4 Progress and cost control Ch. 15 The Productivity issue: • Variability—Location Factors  As location varies, so do these factors: Weather patterns, Altitude, Access, Availability of skills, Availability of logistical support, traffic-ability of site, Attitude of communities, transportation network, local economy, • Variability—Project and Contract Characteristics  Every Project is unique, so differences impact productivity potential, for the following: project size; single craft size. schedule constraints, adequacy of scope definition, constructability of design, exposure to hazards, environmental requirements, height or depth of work, form of contract, budget constraints, Quality of engineering, degree of congestion or confinement, relationship to existing facilities, and relationship to other construction. • Variability—Human Factors  Overall project performance is a function of the human factors; including; Management competence, supervisor competence, individual worker skills, work rules, personal pride, stability of employment, overtime, experience/point on learning curve, worker attitudes, crew stability/key personnel turnover.
  • 22. DEC. 2017 AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5 22 CCP Certificate Section 4 Progress and cost control Ch. 15 The Productivity issue: • Variability—Impact of Disturbance on Performance Factors which are most completely in the hands of management to control:  Site layout for construction, support equipment availability, project controls system, quality management program, technology/methodology used, subcontractor performance, degree of communication, crew balance, materials availability and quality, tool availability & quality, safety program, adequacy of support facilities, planning degree, vendor performance, interruptions control. • Variability―Accounting and Estimates  Ideally, a contractor will maintain historical data files containing actual productivity data from past projects. For this on future , several criteria apply:  A standard chart of accounts for crew tasks must be used for all projects so that data from one project realistically can be compared to data from another.  Breakdown of crew tasks for purposes of estimating must be same as that used for reporting, so that estimated & actual performance can be truly compared.  In addition to the numerical data collected on each project, the conditions under which work was performed (e.g. weather, congestion, materials shortages).  When preparing bids, estimators retrieve the data on similar work performed under similar conditions. Judgment decisions must be made to adapt data on hand to the new project, by using range estimates and checklist & work sheets.
  • 23. DEC. 2017 AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5 23 CCP Certificate Section 4 Progress and cost control Ch. 15 The Productivity issue: • Variability―Accounting and Estimates  Ideally, a contractor will maintain historical data files containing actual productivity data from past projects. For this on future , several criteria apply:  A standard chart of accounts for crew tasks must be used for all projects so that data from one project realistically can be compared to data from another.  Breakdown of crew tasks for purposes of estimating must be same as that used for reporting, so that estimated & actual performance can be truly compared.  In addition to the numerical data collected on each project, the conditions under which work was performed (e.g. weather, congestion, materials shortages).  When preparing bids, estimators retrieve the data on similar work performed under similar conditions. Judgment decisions must be made to adapt data on hand to the new project, by using range estimates and checklist & work sheets.
  • 24. DEC. 2017 AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5 24 CCP Certificate Section 4 Progress and cost control Ch. 15 Productivity analysis- Determining percent complete. 1. Units Completed  Suitable when the total scope of an activity consists of a number of equal or nearly equal parts, such as; ideally, each unit is of relatively short duration, in engineering, an application is in writing of a number of specifications of a given type where all specifications are considered to have equal weight.  In construction, useful in activities like earthwork, concrete, and wire pulling. 2. Incremental Milestone  Appropriate for activities of significant duration that are composed of easily recognized, sequential sub activities. Percentage completion values are established based on the effort estimated to be required at each milestone point relative to the total for the activity.  This method is ideal for control of engineering drawings and procurement.  Ex. for drawing control is:  Construction Ex. Vessel installation.
  • 25. DEC. 2017 AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5 25 CCP Certificate Section 4 Progress and cost control Ch. 15 Productivity analysis- Determining percent complete. 3. Start/Finish Percentages  Applicable to activities that lack readily definable intermediate milestones, and/or the effort/time required is very difficult to estimate.  Start = controllers credit 20 to 50%  Finish 100 %  In engineering, for work such as planning, designing, manual writing, model building, and studies. Also for specification writing.  Construction in any situation if scheduling with detailed multiple short-term tasks. 4. Ratio  Applicable to tasks as project M, constructability studies, project controls, and comparable activity that involve a long period of time, no end product).  used on tasks where start/finish method is appropriate.  % complete at any time = dividing hours (or dollars) spent to date BY the current estimate of hours (or dollars) at completion. 5. Supervisor Opinion  Subjective evaluation of % complete (by the supervisors) and should be used only absence discrete methods cannot be used.( for small tasks).  There is tendency to over-estimate % completed for activity in its early stages.
  • 26. DEC. 2017 AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5 26 CCP Certificate Section 4 Progress and cost control Ch. 15 Productivity analysis- Determining percent complete. 6. Weighted or Equivalent Units  Applicable where the task is a major effort involving a long period of time and composed of two or more overlapping subtasks, with different unit of measurement (e.g., each, yd3, LM).  Subtasks are listed along with their respective units of measure and quantities, weighted, using relative work hours  Total of all weights equals 1.00 or 100 %.  Subtask % is reported using one of the 5 measure. techniques above mentioned.  S.task Progress% x S.task weighting factor = its contribution to overall task  Those for all subtasks are summed = overall percent completion of the activity. Ex1. concrete placement ( yrd3),; broken up into base preparation, forming, re- steel installation, concrete placement, curing, form stripping, and patching.
  • 27. DEC. 2017 AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5 27 CCP Certificate Section 4 Progress and cost control Ch. 15 Productivity analysis- Determining percent complete. 6. Weighted or Equivalent Units- continue  Ex2. steel erection(Tons)The process is illustrated in Table 15.1.(SK6- p230)
  • 28. DEC. 2017 AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5 28 CCP Certificate Section 4 Progress and cost control Ch. 15 Productivity analysis- Determining percent complete. Productivity Measurement of Individual Work Tasks • Owners & contractors compare actual productivity to estimated/budgeted.  For single work activity: Productivity = (number of units completed) ÷ (work-hours consumed) Productivity Analysis at a Summary Level Productivity = EV/ Actual WH Valid at a summary level, if actual Q of work are equal to those budgeted. • Credit work hours – CWH. CWH = (budgeted unit rate*) x (units completed to date) *Budgeted Unit Rate = budgeted hours per unit of work( e.g. h/m3)
  • 29. DEC. 2017 AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5 29 CCP Certificate Section 4 Progress and cost control Ch. 15 Productivity analysis- Determining percent complete. Productivity Analysis at a Summary Level- continue For progressing w. package: CWH = (percent complete) x (budgeted unit rate) e.g. = 50%x 4h/me= 2h/m3…. And, The Productivity Index (PI) = (CWH to date) ÷ (actual WH to date) (PI) for a combination of work packages or for a total project: Productivity Index = (CWH ÷ a c t u a l work hours). PI< 1 unfavorable PI ≥ 1 favorable
  • 30. DEC. 2017 AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5 30 CCP Certificate Section 4 Progress and cost control Ch. 15 Productivity analysis- Determining percent complete. Incentives 1. The incentives increase the productivity & reduce the waste, reduce absenteeism. 2. Improve employee morale and promote teamwork, and identify more cost-effective work procedures 3. Improve equipment design, Improve quality 4. Share business risks with employees.
  • 31. DEC. 2017 AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5 31 CCP Certificate Section 4 Progress and cost control Ch. 15 The stimuli a. Possibility of winning that personal satisfaction in achieving a goal, financial gain, career enhancement, pride as part of the winners, chance to do something different. b. Fear of losing that potential loss of job, potential loss of promotion, .. etc. c. Rewards within the winning scenario d. Intrinsic value such as cash rewards e. Extrinsic value such as medals, badges (esteem value). f. A chance to do something different g. Fear of losing:  Potential embarrassment  Potential loss of status, job, potential for promotion, etc. Best incentive programs are based on the concept of win-win; (i.e., both the employer and employee are potential winners). Capitalizers on the employee's fear of losing are more fragile and can be counterproductive.
  • 32. DEC. 2017 AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5 32 CCP Certificate Section 4 Progress and cost control Ch. 15 Q. Possibility of winning that personal satisfaction in achieving a goal, financial gain, career enhancement, pride as part of the winners, chance to do something different. 1- High productivity 2-Stimuli Q: Potential embarrassment and Potential loss of status, job, potential for promotion, etc. are consequences o. 1- fear of loose 2- delay in work 3- low KPI’s 4- improper quality metrics.
  • 33. DEC. 2017 AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5 33 CCP Certificate Section 4 Progress and cost control Ch. 15 PRODUCTIVITY INDEX EVALUATION WORKSHEET Purpose: The table shown below, is intended to facilitate a comparison of the productivity  potential of a proposed project with respect to a completed project. For this purpose, a productivity index of 1.0 is average, a  productivity index less than 1.0 is less than average (unfavorable), and a productivity index greater than 1.0 is better than average (favorable).
  • 34. DEC. 2017 AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5 34 CCP Certificate Section 4 Progress and cost control Ch. 15 PRODUCTIVITY INDEX EVALUATION WORKSHEET
  • 35. DEC. 2017 AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5 35 CCP Certificate Section 4 Progress and cost control Ch. 15 PRODUCTIVITY INDEX EVALUATION WORKSHEET continue
  • 36. DEC. 2017 AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5 36 CCP Certificate Section 4 Progress and cost control Ch. 15 PRODUCTIVITY INDEX EVALUATION WORKSHEET continue Use of Worksheet • For a reference project, complete evaluation of the 7 categories. • each category is made up of 2 or more subcategories, evaluation to be made at the subcategory level to yield the category score. For example, note that the first category, general area economy, has three sub-elements. • Assume that the group makes the following analysis of a completed project: o Construction volume in the area at the time of the project was somewhat low compared to previous years when several major plants were built. Now, most construction activity involves homes and small commercial projects. This subcategory is given an index of 110.
  • 37. DEC. 2017 AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 5 37 CCP Certificate Section 4 Progress and cost control Ch. 15 PRODUCTIVITY INDEX EVALUATION WORKSHEET continue The unemployment rate was about average for the state, but better than the national average. There were jobs available, but most were of the minimum wage category. This subcategory is given an index of 100. o The local business situation was basically healthy, neither robust nor depressed. This subcategory is given an index of 100. o The resultant score for Category 1, general area economy, is calculated from the above three index totals. 110 x 4 = 440 100 x 4 = 400 100 x 2 = 200 1,040 ÷ 10 = 104