SlideShare une entreprise Scribd logo
1  sur  55
SECTIONAL COMPLETION &
PARTIAL POSSESSION BY
EMPLOYER
Partial Possession
○ Premature or early occupation of parts or sections of the works before
practical completion.
○ Reason for such ‘premature’ possession and occupation of part of the
Works before practical completion:
- Business pressure - current demand and price is good so they need to
start business or production
- Commercial reasons - commencement date of Works has delayed so
the need to complete early, thus take partial possession for some
sections
2
Partial Possession By
Employer
With Consent
3
Partial Possession by
Employer (with consent)
○ Under Clause 16.0, the employer must comply with the following to get
partial possession:-
- To give written notice of intention to take partial possession to
contractor, so that the contractor can prepare himself and focus the
part of employer want to occupy.
- The partial possession occurs before practical completion.
- The employer to identify part to be taken over.
- The contractor has given his consent.
4
Partial Possession by
Employer (with consent)
○ Clause 16.1 prohibits the Contractor from unreasonably withholding or
delaying consent. However, the Contractor is not bound to give consent
for partial possession.
○ The Contractor may withhold consent by reasons of:
- When partial possession may give rise to safety and health issues.
- When partial possession may materially disrupt the regular progress
of the remaining works.
- Where there is non-payment issue for work done.
5
Certificate of Partial
Possession
○ Clause 16.1(a) requires the Architect to issue the Certificate of Partial
Completion within 14 days of taking partial possession of the Occupied
Parts.
○ The Certificate of Partial Completion shall state the following:-
(1) Date of partial possession
(2) Must have layout plan to identify or demarcate the occupied part
(3) Estimated value of the occupied part
○ The Architect should also identify relevant works not completed and to
list down schedule of defects for the Occupied Part and time frame of
rectifying the defects.
6
Contractual Effects of Partial
Possession
(a) Practical Completion - Clause 16.1(b)
- The practical completion of the Occupied Part shall be deemed to have
occurred on the date of taking over the Occupied Part.
(b) Defects Liability Period - Clause 16.1(b)
- The DLP is deemed to have commenced on the date of practical
completion of the Occupied Part by the Employer.
7
Contractual Effects of Partial
Possession
(c) Liquidated Damages - Clause 16.1(c)
- Liquidated damages shall be reduced by the ratio of the estimated value
of occupied part to the contract sum.
(d) Retention Sum - Clause 16.1(d)
- Under Clause 16.1(d), the Architect is required to:
i) issue a payment certificate to release the first moiety of the retention
fund in the ratio of the estimated value of the Occupied Part
ii) issue payment certificate within 14 days after the issuance of the
Certificate of Partial Completion
8
Contractual Effects of Partial
Possession
(e) Certificate of Making Good Defects - Clause 16.1(e)
- Under Clause 16.1(e), where all defects in the Occupied Parts have been
made good, the Architect shall issue a CMGD.
(f) Release of Second Moiety of Retention - Clause 16.1(f)
- Under Clause 16.1(f), the Architect shall issue a certificate for the
release of the remaining retention fund (second moiety) for the
Occupied Part within 14 days after the issue of CMGD of the same
Occupied Part.
9
Item Not Affected by Partial
Possession
a) Works Insurance
i) Clause 20.A.1 states that ‘the Contractor shall keep such works so insured
notwithstanding any arrangement for ……. partial possession’.
ii) Clause 20.B.1 and 20.C.1 contain similar provision as for Clause 20.A.1.
iii) The total sum insured of the above provisions is that the parties’
insurance obligations remain unaffected.
iv) The respective parties remain obliged to insure and keep the works
insured to the ‘full value’, there being no reduction for the value of the
Occupied Part.
10
Item Not Affected by Partial
Possession
b) Performance Bond and Final Certificate
i) Clause 37 for Performance Bond does not indicate any deduction or
reduction of the bond value after partial possession.
ii) Clause 30.0 for Final Certificate are not affected by the partial possession
since there is only one Final Certificate issued.
iii) Hence, it can be inferred that both the Performance Bond and the Final
Certificate are to remain unaffected by the issuance of Certificate of Partial
Completion.
11
Partial Possession By
Employer
Without Consent
12
Partial Possession by
Employer (without consent)
○ If the Employer takes partial possession of the Occupied Part without
the Contractor’s consent, the Employer is in culpable breach of
contract.
○ Clause 16.2 is a provision which caters for the common practice where
the Employer does, or is forced to take over parts of the works before
practical completion without the Contractor’s consent.
13
Restrictions on Employer’s
Rights to take partial
possession without
consent
○ Employer has no absolute rights
Employer has no absolute right to take possession of Occupied Part.
The contract placed certain restrictions on the Employer’s rights to do.
Pursuant to Clause 16.2(a) may take partial possession provided
three pre-conditions are met:
14
Restrictions on Employer’s
Rights to take partial
possession without
consent
○ Employer has no absolute rights
i) The completion of Works have been delayed, and
ii) A Certificate of Non-Completion has been issued by
Architect under Clause 22.2, and
iii) Such entry and partial possession of the Occupied Part do not
unreasonably disturb the regular progress of the Contractor’s
remaining works or adversely affect the safety and health issues.
15
Restrictions on Employer’s
Rights to take partial
possession without
consent
○ Employer has no absolute rights
For Clause 16.2(a) to be applicable, it may be implied that the
Certificate of Non-Completion (CNC) is still operative and the
Contractor is liable for liquidated damages.
16
Restrictions on Employer’s
Rights to take partial
possession without
consent
○ Employer’s Rights limited by the Contract
i) Clause 16.2 uses the phrase ‘without prejudice to any other rights
and remedies which he may possess under the contract’.
This limits the Employer’s right to those under the contract only and
in the process excludes his common law right.
ii) Clause 16.2 makes it clear that the procedural and contractual effect
of Clause 16.2 are equally applicable as those under Clauses 16.1(a)
to (f).
17
Restrictions on Employer’s
Rights to take partial
possession without
consent
○ Procedures following Partial Possession (with or without consent)
The provision of Clause 16.3 govern the Contractor’s duties following
partial possession by the Employer, whether with or without
Contractor’s consent.
i) Contractor to remove his site facilities, equipments, plants, materials,
etc from Occupied Part upon receipt of Architect’s written
instruction.
18
Restrictions on Employer’s
Rights to take partial
possession without
consent
○ Procedures following Partial Possession (with or without consent)
ii) It is implied that the Architect must prescribe a definite time for
removal from the Occupied Part and this should be a reasonable
time frame.
iii) However, the contract is silent on consequences of non-compliance
by contractor with Architect’s written instruction to remove such
items.
19
Restrictions on Employer’s
Rights to take partial
possession without
consent
○ Procedures following Partial Possession (with or without consent)
iv) It is also silent on remedies available to employer for such
Non-compliance by the Contractor.
20
Sectional
Commencement Dates
and Sectional
Completion Dates
21
Different
Commencement Dates
○ The Date of Commencement under Clause 21.1 assume that the whole
of the Site be handed over to the Contractor on such date.
○ If this is not possible, the Employer may want to plan for different
sections of the Site or phases to be handed over on different dates.
In this case, this information must be properly documented and made
known to the Contractor in the Contract so that he can price
accordingly.
22
Different
Commencement Dates
○ The details of the different commencement dates must be recorded in
the Appendix to PAM contract as Sectional Commencement Date
under Clause 21.2, together with the demarcation layout showing the
different sections.
23
Different
Commencement Dates
○ This clause is useful where the site is big or where piling works are
carried out under a separate contract. Completed piling areas can be
handed over to the building contractor to start work.
○ Sectional Commencement has the following advantages:
i) Save time as it allows over-lapping of construction activities being
carried out by different contractors on the same site, i.e. building
contractor are given parts of the completed parts of piling works to
commence while piling works continue in other parts.
24
Different
Commencement Dates
○ Sectional Commencement has the following advantages:
ii) Improve cash-flow, Build according to sales and demand.
25
Different
Completion Dates
The Sectional Completion Dates under Clause 21.3 can arise regardless of
whether the Site was handed over to the Contractor as a whole or in
sections. Employer may planned for completion of certain sections for
business or commercial reasons, such as phase completion of apartments to
improve cash-flow.
The details of the different completion dates must be recorded in the
Appendix to PAM contract, together with the demarcation layout showing
the different sections.
26
Different
Completion Dates
Scenario 1: Date of Commencement (Single) => Completion Date (Single).
Scenario 2: Date of Commencement (Single) => Sectional Completion
Dates.
Scenario 3: Sectional Commencement Dates => Completion Date (Single).
Scenario 4: Sectional Commencement Dates => Sectional Completion
Dates.
27
Different
Completion Dates
The contractual effect of Sectional Completion is the same as in Partial
Completion, when all the provisions in the Contract with regards to
Practical Completion and Defects Liability Period (clause 15.0); extension of
time (clause 23.0); Liquidated Damages (clause 22.2); release of Retention
Sum (clause 30.6); will apply to each section of the work as though it is a
separate and distinct contract.
28
Different
Completion Dates
One common practice is for the Employer to state milestone dates or key
dates for works to be done in stages or phases (but not handed over) in the
Contract document but not as Sectional Completion in the Appendix.
29
Different
Completion Dates
Disputes often arise if there is a failure to meet such dates and the question
being if liquidated damages can be imposed. The Employer may contend
that the milestone dates or key dates is on the same footing as Sectional
Completion dates and have the same effect.
On the other hand, Contractor may argue that the milestone dates are
merely part of the Contractor’s work programme and therefore doubtful
that it will be accorded the same contractual treatment as sectional
completion and may not be contractually effective.
30
DISCUSSION
Coursework No. 1
31
Explain the differences
between Sectional
Completion and Partial
Possession in PAM
2006.
Question 1
Answer
33
Sectional Completion Partial Possession
Clause 21.3 Clause 16.1
Contract agreed date No contract agreed date
Decided before the signage of
contract
Decided during construction
Architect to issue a Certificate of
Sectional Completion when the
sections of the Works are
Practically Completed.
Architect to issue a Certificate of
Partial Completion within fourteen
(14) Days from the date on which
the Employer has taken possession
of the Occupied Part.
Under what circumstance can
the Employer take partial
possession of the site?
Please explain for both partial
possession with and without
consent from the Contractor.
Question 2
Answer
Employer can take partial possession of the site under several
circumstances, where the reasons for such possession could be of
i) Business pressure
Current demand and price is good so they need to start business or
production.
ii) Commercial reasons
Commencement date of Works has been delayed so with the need
to complete early, Employer to take partial possession for some sections.
35
Answer
iii) Under Clause 16.2, delayed of Completion of works by the
Contractor and issuance of Certificate of Non-Completion by the
Architect under Clause 22.1, and
iv) The entry and partial possession of the Occupied Part do not
unreasonably disturb the regular progress of the works or affect the
safety and health issues.
36
Answer
Provided the Employer has comply with the following stated in Clause 16.0
i) To give written notice of intention to take partial possession to
contractor, so that contractor can prepare himself and focus the part of
employer want to occupy.
ii) The partial possession occurs before practical completion.
iii) The employer to identify part to be taken over.
iv) That the contractor has given his consent.
37
Answer
Partial possession with consent from the Contractor:
Clause 16.1 prohibits the Contractor from unreasonably withholding or
delaying consent.
However, the Contractor is not bound to give consent for partial
possession.
38
Answer
The Contractor may withhold consent by reasons of:
i) When partial possession may give rise to safety and health issues, or
ii) When partial possession may materially disrupt the regular progress
of the remaining works, or
iii) Where there is non-payment issue for work done.
39
Answer
Partial possession without consent from the Contractor:
Under Clause 16.2, the Employer may take partial possession provided that
i) The completion of Works have been delayed, and
ii) A Certificate of Non-Completion has been issued by Architect under
clause 22.1, and
iii) Such entry and partial possession of the Occupied Part do not
unreasonably disturb the regular progress of the Contractor’s remaining
works or adversely affect the safety and health issues.
40
Explain the contractual
implications of partial
possession and the items
not affected by it.
Question 3
Answer
(a) Practical Completion - Clause 16.1(b)
- The practical completion of the Occupied Part shall be deemed to have
occurred on the date of taking over the Occupied Part.
(b) Defects Liability Period - Clause 16.1(b)
- The DLP is deemed to have commenced on the date of practical
completion of the Occupied Part by the Employer.
42
Answer
(c) Liquidated Damages - Clause 16.1(c)
- Liquidated damages shall be reduced by the ratio of the estimated value
of occupied part to the contract sum.
(d) Retention Sum - Clause 16.1(d)
- Under Clause 16.1(d), the Architect is required to:
i) issue a payment certificate to release the first moiety of the retention
fund in the ratio of the estimated value of the Occupied Part
ii) issue payment certificate within 14 days after the issuance of the
Certificate of Partial Completion
43
Answer
(e) Certificate of Making Good Defects - Clause 16.1(e)
- Under Clause 16.1(e), where all defects in the Occupied Parts have been
made good, the Architect shall issue a CMGD.
(f) Release of Second Moiety of Retention - Clause 16.1(f)
- Under Clause 16.1(f), the Architect shall issue a certificate for the
release of the remaining retention fund (second moiety) for the
Occupied Part within 14 days after the issue of CMGD of the same
Occupied Part.
44
Item Not Affected by Partial
Possession
a) Works Insurance
- Clause 20.A.1, Clause 20.B.1 and 20.C.1
- The total sum of the insurance must be remain unaffected and being no
reduction for the value of the Occupied Part.
b) Performance Bond and Final Certificate
- Clause 37 for Performance Bond does not indicate any deduction or
reduction of the bond value after partial possession.
- Clause 30.0 for Final Certificate are not affected by the partial
possession since there is only one Final Certificate issued.
45
Additional
Questions
46
An employer is trying to take partial possession
without the consent of the Contractor under the
following condition:-
i) A Certificate of Non-Completion has been issued
by Architect
ii) Subsequently, the contractor was granted an
EOT due to the delayed caused by relevant event
under Clause 23.8
Can the employer take partial possession without
the consent of the Contractor? Why?
Question 1
Answer
According to Clause 16.2 (a), the employer can take partial possession
without consent provided that the completion of the Works has been
delayed and a Certificate of Non-Completion has been issued by the
Architect under Clause 22.1.
In this case, the employer cannot take partial possession without
contractor’s consent because the delay is caused by the relevant event
under Clause 23.8. The contractor is then entitled to claim for EOT.
For Clause 16.2(a) to be applicable, it may be implied that the Certificate of
Non-Completion is still operative and the contractor is liable for liquidated
damages.
48
In the construction industry
nowadays, most of the contractor
is willing to give consent for the
employer to get partial
possession. Why?
Question 2
Answer
(1) Defect Liability Period reduced - Clause 16.1 (b)
(2) Liquidated Damages reduced - Clause 16.1 (c)
(3) The first moiety of retention sum is released - Clause 16.1 (d)
50
Does the employer have the
rights to take partial possession
without the Contractor's consent
under the common law?
Why and which clause stated so?
Question 3
Answer
No. Clause 16.2 uses the phrase ‘without prejudice to any other rights and
remedies which he may possess under the contract’.
This limits the Employer’s right to those under the contract only and in the
process excludes his common law rights.
52
THANK YOU!
53
Why is the value of the occupied
part had to be estimated?
Question Back up
Answer
The value of the occupied part had to be estimated because the implications
of partial possession affect some of contract values.
- Liquidated damages
- Retention Sum
According to Clause 16.1(c) and 16.1(d), both the liquidated damages and
retention sum shall be reduced by the ratio of the estimated value of the
occupied part to the contract sum.
55

Contenu connexe

Tendances

Professional Practice 2: Group Assignment
Professional Practice 2: Group AssignmentProfessional Practice 2: Group Assignment
Professional Practice 2: Group Assignment마 이환
 
Construction Contract in Malaysia
Construction Contract in MalaysiaConstruction Contract in Malaysia
Construction Contract in MalaysiaDayat Mohamad
 
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMDIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMAnep Botak
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variationVj NiroSh
 
Seminar - Partial Possession by Employer
Seminar - Partial Possession by EmployerSeminar - Partial Possession by Employer
Seminar - Partial Possession by EmployerKai Yun Pang
 
Payments in the construction industry
Payments in the construction industryPayments in the construction industry
Payments in the construction industryKheng Hoe Advocates
 
Construction Law Assignment BQS Taylor's University
Construction Law Assignment BQS Taylor's UniversityConstruction Law Assignment BQS Taylor's University
Construction Law Assignment BQS Taylor's UniversityPang Khai Shuen
 
Pp2 coursework 2 201808
Pp2 coursework 2   201808Pp2 coursework 2   201808
Pp2 coursework 2 201808Arissa Loh
 
Tender evaluation procedure
Tender evaluation procedureTender evaluation procedure
Tender evaluation procedureayushida
 
07 cl-assignment-syafiq-qy-macy-huiyong-deric
07 cl-assignment-syafiq-qy-macy-huiyong-deric07 cl-assignment-syafiq-qy-macy-huiyong-deric
07 cl-assignment-syafiq-qy-macy-huiyong-dericSyafiq Zariful
 
Professional Practice 1 Group Assignment
Professional Practice 1 Group AssignmentProfessional Practice 1 Group Assignment
Professional Practice 1 Group AssignmentHaziq1511
 
Professional practice 1 report
Professional practice 1 reportProfessional practice 1 report
Professional practice 1 reportNgo Jia Haur
 
Provisional sum prime cost sum
Provisional sum  prime cost sumProvisional sum  prime cost sum
Provisional sum prime cost sumEst
 
Certificates and payments
Certificates and paymentsCertificates and payments
Certificates and paymentsHafizul Mukhlis
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2ahmong4
 

Tendances (20)

Professional Practice 2: Group Assignment
Professional Practice 2: Group AssignmentProfessional Practice 2: Group Assignment
Professional Practice 2: Group Assignment
 
Construction Contract in Malaysia
Construction Contract in MalaysiaConstruction Contract in Malaysia
Construction Contract in Malaysia
 
Defects liability
Defects liabilityDefects liability
Defects liability
 
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMDIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
 
Pp2 final report
Pp2 final reportPp2 final report
Pp2 final report
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variation
 
Seminar - Partial Possession by Employer
Seminar - Partial Possession by EmployerSeminar - Partial Possession by Employer
Seminar - Partial Possession by Employer
 
Payments in the construction industry
Payments in the construction industryPayments in the construction industry
Payments in the construction industry
 
Construction Law Assignment BQS Taylor's University
Construction Law Assignment BQS Taylor's UniversityConstruction Law Assignment BQS Taylor's University
Construction Law Assignment BQS Taylor's University
 
PP2 - Assignment
PP2 - Assignment PP2 - Assignment
PP2 - Assignment
 
Pp2 coursework 2 201808
Pp2 coursework 2   201808Pp2 coursework 2   201808
Pp2 coursework 2 201808
 
Tender evaluation procedure
Tender evaluation procedureTender evaluation procedure
Tender evaluation procedure
 
07 cl-assignment-syafiq-qy-macy-huiyong-deric
07 cl-assignment-syafiq-qy-macy-huiyong-deric07 cl-assignment-syafiq-qy-macy-huiyong-deric
07 cl-assignment-syafiq-qy-macy-huiyong-deric
 
Pengurusan kontrak
Pengurusan kontrakPengurusan kontrak
Pengurusan kontrak
 
Professional Practice 1 Group Assignment
Professional Practice 1 Group AssignmentProfessional Practice 1 Group Assignment
Professional Practice 1 Group Assignment
 
Professional practice 1 report
Professional practice 1 reportProfessional practice 1 report
Professional practice 1 report
 
Provisional sum prime cost sum
Provisional sum  prime cost sumProvisional sum  prime cost sum
Provisional sum prime cost sum
 
Certificates and payments
Certificates and paymentsCertificates and payments
Certificates and payments
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
 
Land acquisition
Land acquisitionLand acquisition
Land acquisition
 

Similaire à Sectional completion and partial possession by employer PP2 Coursework 1

Suspension and Termination by Contractor Presentation.pptx
Suspension and Termination by Contractor Presentation.pptxSuspension and Termination by Contractor Presentation.pptx
Suspension and Termination by Contractor Presentation.pptxNathannielGonzales1
 
TE&A's Newsletter, April, 2019
TE&A's Newsletter, April, 2019TE&A's Newsletter, April, 2019
TE&A's Newsletter, April, 2019Cerasela Angelescu
 
PP2 presentation
PP2 presentationPP2 presentation
PP2 presentationYong Sy
 
HM hub and NPD second masterclass seminar 6.11.15.PPT
HM hub and NPD second masterclass seminar 6.11.15.PPTHM hub and NPD second masterclass seminar 6.11.15.PPT
HM hub and NPD second masterclass seminar 6.11.15.PPTEuan Pirie
 
PP2 Seminar Presentation
PP2 Seminar PresentationPP2 Seminar Presentation
PP2 Seminar Presentationashleyyeap
 
Lecture 8-determination-of-own-employment-by
Lecture 8-determination-of-own-employment-byLecture 8-determination-of-own-employment-by
Lecture 8-determination-of-own-employment-byseenyeeyong
 
Techno Engineering & Associates
Techno Engineering & AssociatesTechno Engineering & Associates
Techno Engineering & AssociatesCerasela Angelescu
 
Professional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTProfessional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTYee Len Wan
 
CONTRACTS AND CLAIMS MANAGEMENT PPT.pptx
CONTRACTS AND CLAIMS MANAGEMENT PPT.pptxCONTRACTS AND CLAIMS MANAGEMENT PPT.pptx
CONTRACTS AND CLAIMS MANAGEMENT PPT.pptxssuserb7dd601
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7Farah Sham
 
Bcd4 standard building_contract_(without_quantities)_and_schedule_of_contract...
Bcd4 standard building_contract_(without_quantities)_and_schedule_of_contract...Bcd4 standard building_contract_(without_quantities)_and_schedule_of_contract...
Bcd4 standard building_contract_(without_quantities)_and_schedule_of_contract...tdartnell
 
contract labour act 1970-ppt.pptx
contract labour act 1970-ppt.pptxcontract labour act 1970-ppt.pptx
contract labour act 1970-ppt.pptxNileshNanda1
 

Similaire à Sectional completion and partial possession by employer PP2 Coursework 1 (20)

Pp2 p7
Pp2   p7Pp2   p7
Pp2 p7
 
Suspension and Termination by Contractor Presentation.pptx
Suspension and Termination by Contractor Presentation.pptxSuspension and Termination by Contractor Presentation.pptx
Suspension and Termination by Contractor Presentation.pptx
 
TE&A's Newsletter, April, 2019
TE&A's Newsletter, April, 2019TE&A's Newsletter, April, 2019
TE&A's Newsletter, April, 2019
 
Site Possession
Site PossessionSite Possession
Site Possession
 
PP2 presentation
PP2 presentationPP2 presentation
PP2 presentation
 
HM hub and NPD second masterclass seminar 6.11.15.PPT
HM hub and NPD second masterclass seminar 6.11.15.PPTHM hub and NPD second masterclass seminar 6.11.15.PPT
HM hub and NPD second masterclass seminar 6.11.15.PPT
 
PP2 Seminar Presentation
PP2 Seminar PresentationPP2 Seminar Presentation
PP2 Seminar Presentation
 
Seminar p8x
Seminar p8xSeminar p8x
Seminar p8x
 
Lecture 8-determination-of-own-employment-by
Lecture 8-determination-of-own-employment-byLecture 8-determination-of-own-employment-by
Lecture 8-determination-of-own-employment-by
 
Progress and delay_
Progress and delay_Progress and delay_
Progress and delay_
 
Techno Engineering & Associates
Techno Engineering & AssociatesTechno Engineering & Associates
Techno Engineering & Associates
 
Claims and insolvencies (1)
Claims and insolvencies (1)Claims and insolvencies (1)
Claims and insolvencies (1)
 
PP2 COMPILCATION
PP2 COMPILCATIONPP2 COMPILCATION
PP2 COMPILCATION
 
Professional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTProfessional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOT
 
Cl report final
Cl report finalCl report final
Cl report final
 
CONTRACTS AND CLAIMS MANAGEMENT PPT.pptx
CONTRACTS AND CLAIMS MANAGEMENT PPT.pptxCONTRACTS AND CLAIMS MANAGEMENT PPT.pptx
CONTRACTS AND CLAIMS MANAGEMENT PPT.pptx
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7
 
Pp2 p5
Pp2   p5Pp2   p5
Pp2 p5
 
Bcd4 standard building_contract_(without_quantities)_and_schedule_of_contract...
Bcd4 standard building_contract_(without_quantities)_and_schedule_of_contract...Bcd4 standard building_contract_(without_quantities)_and_schedule_of_contract...
Bcd4 standard building_contract_(without_quantities)_and_schedule_of_contract...
 
contract labour act 1970-ppt.pptx
contract labour act 1970-ppt.pptxcontract labour act 1970-ppt.pptx
contract labour act 1970-ppt.pptx
 

Plus de Arissa Loh

Value Management Group Assignment
Value Management Group AssignmentValue Management Group Assignment
Value Management Group AssignmentArissa Loh
 
Project Management Individual Assignment
Project Management Individual AssignmentProject Management Individual Assignment
Project Management Individual AssignmentArissa Loh
 
Project Management Group Assignment Final Report
Project Management Group Assignment Final ReportProject Management Group Assignment Final Report
Project Management Group Assignment Final ReportArissa Loh
 
Project Management Presentation Slides
Project Management Presentation SlidesProject Management Presentation Slides
Project Management Presentation SlidesArissa Loh
 
Remedies for Breach of Contract
Remedies for Breach of ContractRemedies for Breach of Contract
Remedies for Breach of ContractArissa Loh
 
Be De Workshop Cost Appraisal
Be De Workshop Cost AppraisalBe De Workshop Cost Appraisal
Be De Workshop Cost AppraisalArissa Loh
 
Financial Management Final Report
Financial Management Final ReportFinancial Management Final Report
Financial Management Final ReportArissa Loh
 
CSI Presentation Slides
CSI Presentation SlidesCSI Presentation Slides
CSI Presentation SlidesArissa Loh
 
BE slides presentation
BE slides presentationBE slides presentation
BE slides presentationArissa Loh
 
PP2 final report
PP2 final reportPP2 final report
PP2 final reportArissa Loh
 
Professional Practice 1 Presentation Slides
Professional Practice 1 Presentation SlidesProfessional Practice 1 Presentation Slides
Professional Practice 1 Presentation SlidesArissa Loh
 
Professional Practice 1 Proposal Report
Professional Practice 1 Proposal ReportProfessional Practice 1 Proposal Report
Professional Practice 1 Proposal ReportArissa Loh
 
Measurement 4 presentation slides
Measurement 4 presentation slidesMeasurement 4 presentation slides
Measurement 4 presentation slidesArissa Loh
 
Pp1 group presentation
Pp1 group presentation  Pp1 group presentation
Pp1 group presentation Arissa Loh
 
Tender Presentation
Tender PresentationTender Presentation
Tender PresentationArissa Loh
 
Int. ceiling finishes
Int. ceiling finishesInt. ceiling finishes
Int. ceiling finishesArissa Loh
 
Software Presentation Slides
Software Presentation SlidesSoftware Presentation Slides
Software Presentation SlidesArissa Loh
 
Elemental cost analysis Presentation Slides
Elemental cost analysis Presentation SlidesElemental cost analysis Presentation Slides
Elemental cost analysis Presentation SlidesArissa Loh
 

Plus de Arissa Loh (20)

Value Management Group Assignment
Value Management Group AssignmentValue Management Group Assignment
Value Management Group Assignment
 
Project Management Individual Assignment
Project Management Individual AssignmentProject Management Individual Assignment
Project Management Individual Assignment
 
Project Management Group Assignment Final Report
Project Management Group Assignment Final ReportProject Management Group Assignment Final Report
Project Management Group Assignment Final Report
 
Project Management Presentation Slides
Project Management Presentation SlidesProject Management Presentation Slides
Project Management Presentation Slides
 
Remedies for Breach of Contract
Remedies for Breach of ContractRemedies for Breach of Contract
Remedies for Breach of Contract
 
Be De Workshop Cost Appraisal
Be De Workshop Cost AppraisalBe De Workshop Cost Appraisal
Be De Workshop Cost Appraisal
 
Financial Management Final Report
Financial Management Final ReportFinancial Management Final Report
Financial Management Final Report
 
CSI Presentation Slides
CSI Presentation SlidesCSI Presentation Slides
CSI Presentation Slides
 
BE slides presentation
BE slides presentationBE slides presentation
BE slides presentation
 
PP2 final report
PP2 final reportPP2 final report
PP2 final report
 
Professional Practice 1 Presentation Slides
Professional Practice 1 Presentation SlidesProfessional Practice 1 Presentation Slides
Professional Practice 1 Presentation Slides
 
Professional Practice 1 Proposal Report
Professional Practice 1 Proposal ReportProfessional Practice 1 Proposal Report
Professional Practice 1 Proposal Report
 
Measurement 4 presentation slides
Measurement 4 presentation slidesMeasurement 4 presentation slides
Measurement 4 presentation slides
 
Pp1 group presentation
Pp1 group presentation  Pp1 group presentation
Pp1 group presentation
 
Tender Presentation
Tender PresentationTender Presentation
Tender Presentation
 
Int. ceiling finishes
Int. ceiling finishesInt. ceiling finishes
Int. ceiling finishes
 
Software Presentation Slides
Software Presentation SlidesSoftware Presentation Slides
Software Presentation Slides
 
Software Report
Software ReportSoftware Report
Software Report
 
Elemental cost analysis Presentation Slides
Elemental cost analysis Presentation SlidesElemental cost analysis Presentation Slides
Elemental cost analysis Presentation Slides
 
ECA form
ECA formECA form
ECA form
 

Dernier

Mohammad_Alnahdi_Oral_Presentation_Assignment.pptx
Mohammad_Alnahdi_Oral_Presentation_Assignment.pptxMohammad_Alnahdi_Oral_Presentation_Assignment.pptx
Mohammad_Alnahdi_Oral_Presentation_Assignment.pptxmohammadalnahdi22
 
George Lever - eCommerce Day Chile 2024
George Lever -  eCommerce Day Chile 2024George Lever -  eCommerce Day Chile 2024
George Lever - eCommerce Day Chile 2024eCommerce Institute
 
Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...
Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...
Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...Pooja Nehwal
 
Presentation on Engagement in Book Clubs
Presentation on Engagement in Book ClubsPresentation on Engagement in Book Clubs
Presentation on Engagement in Book Clubssamaasim06
 
Microsoft Copilot AI for Everyone - created by AI
Microsoft Copilot AI for Everyone - created by AIMicrosoft Copilot AI for Everyone - created by AI
Microsoft Copilot AI for Everyone - created by AITatiana Gurgel
 
Thirunelveli call girls Tamil escorts 7877702510
Thirunelveli call girls Tamil escorts 7877702510Thirunelveli call girls Tamil escorts 7877702510
Thirunelveli call girls Tamil escorts 7877702510Vipesco
 
ANCHORING SCRIPT FOR A CULTURAL EVENT.docx
ANCHORING SCRIPT FOR A CULTURAL EVENT.docxANCHORING SCRIPT FOR A CULTURAL EVENT.docx
ANCHORING SCRIPT FOR A CULTURAL EVENT.docxNikitaBankoti2
 
Mathematics of Finance Presentation.pptx
Mathematics of Finance Presentation.pptxMathematics of Finance Presentation.pptx
Mathematics of Finance Presentation.pptxMoumonDas2
 
SaaStr Workshop Wednesday w/ Lucas Price, Yardstick
SaaStr Workshop Wednesday w/ Lucas Price, YardstickSaaStr Workshop Wednesday w/ Lucas Price, Yardstick
SaaStr Workshop Wednesday w/ Lucas Price, Yardsticksaastr
 
WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )
WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )
WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )Pooja Nehwal
 
Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...
Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...
Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...Hasting Chen
 
Governance and Nation-Building in Nigeria: Some Reflections on Options for Po...
Governance and Nation-Building in Nigeria: Some Reflections on Options for Po...Governance and Nation-Building in Nigeria: Some Reflections on Options for Po...
Governance and Nation-Building in Nigeria: Some Reflections on Options for Po...Kayode Fayemi
 
BDSM⚡Call Girls in Sector 93 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 93 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 93 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 93 Noida Escorts >༒8448380779 Escort ServiceDelhi Call girls
 
Introduction to Prompt Engineering (Focusing on ChatGPT)
Introduction to Prompt Engineering (Focusing on ChatGPT)Introduction to Prompt Engineering (Focusing on ChatGPT)
Introduction to Prompt Engineering (Focusing on ChatGPT)Chameera Dedduwage
 
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...henrik385807
 
VVIP Call Girls Nalasopara : 9892124323, Call Girls in Nalasopara Services
VVIP Call Girls Nalasopara : 9892124323, Call Girls in Nalasopara ServicesVVIP Call Girls Nalasopara : 9892124323, Call Girls in Nalasopara Services
VVIP Call Girls Nalasopara : 9892124323, Call Girls in Nalasopara ServicesPooja Nehwal
 
Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024
Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024
Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024eCommerce Institute
 
If this Giant Must Walk: A Manifesto for a New Nigeria
If this Giant Must Walk: A Manifesto for a New NigeriaIf this Giant Must Walk: A Manifesto for a New Nigeria
If this Giant Must Walk: A Manifesto for a New NigeriaKayode Fayemi
 
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdfCTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdfhenrik385807
 
Call Girl Number in Khar Mumbai📲 9892124323 💞 Full Night Enjoy
Call Girl Number in Khar Mumbai📲 9892124323 💞 Full Night EnjoyCall Girl Number in Khar Mumbai📲 9892124323 💞 Full Night Enjoy
Call Girl Number in Khar Mumbai📲 9892124323 💞 Full Night EnjoyPooja Nehwal
 

Dernier (20)

Mohammad_Alnahdi_Oral_Presentation_Assignment.pptx
Mohammad_Alnahdi_Oral_Presentation_Assignment.pptxMohammad_Alnahdi_Oral_Presentation_Assignment.pptx
Mohammad_Alnahdi_Oral_Presentation_Assignment.pptx
 
George Lever - eCommerce Day Chile 2024
George Lever -  eCommerce Day Chile 2024George Lever -  eCommerce Day Chile 2024
George Lever - eCommerce Day Chile 2024
 
Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...
Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...
Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...
 
Presentation on Engagement in Book Clubs
Presentation on Engagement in Book ClubsPresentation on Engagement in Book Clubs
Presentation on Engagement in Book Clubs
 
Microsoft Copilot AI for Everyone - created by AI
Microsoft Copilot AI for Everyone - created by AIMicrosoft Copilot AI for Everyone - created by AI
Microsoft Copilot AI for Everyone - created by AI
 
Thirunelveli call girls Tamil escorts 7877702510
Thirunelveli call girls Tamil escorts 7877702510Thirunelveli call girls Tamil escorts 7877702510
Thirunelveli call girls Tamil escorts 7877702510
 
ANCHORING SCRIPT FOR A CULTURAL EVENT.docx
ANCHORING SCRIPT FOR A CULTURAL EVENT.docxANCHORING SCRIPT FOR A CULTURAL EVENT.docx
ANCHORING SCRIPT FOR A CULTURAL EVENT.docx
 
Mathematics of Finance Presentation.pptx
Mathematics of Finance Presentation.pptxMathematics of Finance Presentation.pptx
Mathematics of Finance Presentation.pptx
 
SaaStr Workshop Wednesday w/ Lucas Price, Yardstick
SaaStr Workshop Wednesday w/ Lucas Price, YardstickSaaStr Workshop Wednesday w/ Lucas Price, Yardstick
SaaStr Workshop Wednesday w/ Lucas Price, Yardstick
 
WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )
WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )
WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )
 
Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...
Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...
Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...
 
Governance and Nation-Building in Nigeria: Some Reflections on Options for Po...
Governance and Nation-Building in Nigeria: Some Reflections on Options for Po...Governance and Nation-Building in Nigeria: Some Reflections on Options for Po...
Governance and Nation-Building in Nigeria: Some Reflections on Options for Po...
 
BDSM⚡Call Girls in Sector 93 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 93 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 93 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 93 Noida Escorts >༒8448380779 Escort Service
 
Introduction to Prompt Engineering (Focusing on ChatGPT)
Introduction to Prompt Engineering (Focusing on ChatGPT)Introduction to Prompt Engineering (Focusing on ChatGPT)
Introduction to Prompt Engineering (Focusing on ChatGPT)
 
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...
 
VVIP Call Girls Nalasopara : 9892124323, Call Girls in Nalasopara Services
VVIP Call Girls Nalasopara : 9892124323, Call Girls in Nalasopara ServicesVVIP Call Girls Nalasopara : 9892124323, Call Girls in Nalasopara Services
VVIP Call Girls Nalasopara : 9892124323, Call Girls in Nalasopara Services
 
Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024
Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024
Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024
 
If this Giant Must Walk: A Manifesto for a New Nigeria
If this Giant Must Walk: A Manifesto for a New NigeriaIf this Giant Must Walk: A Manifesto for a New Nigeria
If this Giant Must Walk: A Manifesto for a New Nigeria
 
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdfCTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
 
Call Girl Number in Khar Mumbai📲 9892124323 💞 Full Night Enjoy
Call Girl Number in Khar Mumbai📲 9892124323 💞 Full Night EnjoyCall Girl Number in Khar Mumbai📲 9892124323 💞 Full Night Enjoy
Call Girl Number in Khar Mumbai📲 9892124323 💞 Full Night Enjoy
 

Sectional completion and partial possession by employer PP2 Coursework 1

  • 1. SECTIONAL COMPLETION & PARTIAL POSSESSION BY EMPLOYER
  • 2. Partial Possession ○ Premature or early occupation of parts or sections of the works before practical completion. ○ Reason for such ‘premature’ possession and occupation of part of the Works before practical completion: - Business pressure - current demand and price is good so they need to start business or production - Commercial reasons - commencement date of Works has delayed so the need to complete early, thus take partial possession for some sections 2
  • 4. Partial Possession by Employer (with consent) ○ Under Clause 16.0, the employer must comply with the following to get partial possession:- - To give written notice of intention to take partial possession to contractor, so that the contractor can prepare himself and focus the part of employer want to occupy. - The partial possession occurs before practical completion. - The employer to identify part to be taken over. - The contractor has given his consent. 4
  • 5. Partial Possession by Employer (with consent) ○ Clause 16.1 prohibits the Contractor from unreasonably withholding or delaying consent. However, the Contractor is not bound to give consent for partial possession. ○ The Contractor may withhold consent by reasons of: - When partial possession may give rise to safety and health issues. - When partial possession may materially disrupt the regular progress of the remaining works. - Where there is non-payment issue for work done. 5
  • 6. Certificate of Partial Possession ○ Clause 16.1(a) requires the Architect to issue the Certificate of Partial Completion within 14 days of taking partial possession of the Occupied Parts. ○ The Certificate of Partial Completion shall state the following:- (1) Date of partial possession (2) Must have layout plan to identify or demarcate the occupied part (3) Estimated value of the occupied part ○ The Architect should also identify relevant works not completed and to list down schedule of defects for the Occupied Part and time frame of rectifying the defects. 6
  • 7. Contractual Effects of Partial Possession (a) Practical Completion - Clause 16.1(b) - The practical completion of the Occupied Part shall be deemed to have occurred on the date of taking over the Occupied Part. (b) Defects Liability Period - Clause 16.1(b) - The DLP is deemed to have commenced on the date of practical completion of the Occupied Part by the Employer. 7
  • 8. Contractual Effects of Partial Possession (c) Liquidated Damages - Clause 16.1(c) - Liquidated damages shall be reduced by the ratio of the estimated value of occupied part to the contract sum. (d) Retention Sum - Clause 16.1(d) - Under Clause 16.1(d), the Architect is required to: i) issue a payment certificate to release the first moiety of the retention fund in the ratio of the estimated value of the Occupied Part ii) issue payment certificate within 14 days after the issuance of the Certificate of Partial Completion 8
  • 9. Contractual Effects of Partial Possession (e) Certificate of Making Good Defects - Clause 16.1(e) - Under Clause 16.1(e), where all defects in the Occupied Parts have been made good, the Architect shall issue a CMGD. (f) Release of Second Moiety of Retention - Clause 16.1(f) - Under Clause 16.1(f), the Architect shall issue a certificate for the release of the remaining retention fund (second moiety) for the Occupied Part within 14 days after the issue of CMGD of the same Occupied Part. 9
  • 10. Item Not Affected by Partial Possession a) Works Insurance i) Clause 20.A.1 states that ‘the Contractor shall keep such works so insured notwithstanding any arrangement for ……. partial possession’. ii) Clause 20.B.1 and 20.C.1 contain similar provision as for Clause 20.A.1. iii) The total sum insured of the above provisions is that the parties’ insurance obligations remain unaffected. iv) The respective parties remain obliged to insure and keep the works insured to the ‘full value’, there being no reduction for the value of the Occupied Part. 10
  • 11. Item Not Affected by Partial Possession b) Performance Bond and Final Certificate i) Clause 37 for Performance Bond does not indicate any deduction or reduction of the bond value after partial possession. ii) Clause 30.0 for Final Certificate are not affected by the partial possession since there is only one Final Certificate issued. iii) Hence, it can be inferred that both the Performance Bond and the Final Certificate are to remain unaffected by the issuance of Certificate of Partial Completion. 11
  • 13. Partial Possession by Employer (without consent) ○ If the Employer takes partial possession of the Occupied Part without the Contractor’s consent, the Employer is in culpable breach of contract. ○ Clause 16.2 is a provision which caters for the common practice where the Employer does, or is forced to take over parts of the works before practical completion without the Contractor’s consent. 13
  • 14. Restrictions on Employer’s Rights to take partial possession without consent ○ Employer has no absolute rights Employer has no absolute right to take possession of Occupied Part. The contract placed certain restrictions on the Employer’s rights to do. Pursuant to Clause 16.2(a) may take partial possession provided three pre-conditions are met: 14
  • 15. Restrictions on Employer’s Rights to take partial possession without consent ○ Employer has no absolute rights i) The completion of Works have been delayed, and ii) A Certificate of Non-Completion has been issued by Architect under Clause 22.2, and iii) Such entry and partial possession of the Occupied Part do not unreasonably disturb the regular progress of the Contractor’s remaining works or adversely affect the safety and health issues. 15
  • 16. Restrictions on Employer’s Rights to take partial possession without consent ○ Employer has no absolute rights For Clause 16.2(a) to be applicable, it may be implied that the Certificate of Non-Completion (CNC) is still operative and the Contractor is liable for liquidated damages. 16
  • 17. Restrictions on Employer’s Rights to take partial possession without consent ○ Employer’s Rights limited by the Contract i) Clause 16.2 uses the phrase ‘without prejudice to any other rights and remedies which he may possess under the contract’. This limits the Employer’s right to those under the contract only and in the process excludes his common law right. ii) Clause 16.2 makes it clear that the procedural and contractual effect of Clause 16.2 are equally applicable as those under Clauses 16.1(a) to (f). 17
  • 18. Restrictions on Employer’s Rights to take partial possession without consent ○ Procedures following Partial Possession (with or without consent) The provision of Clause 16.3 govern the Contractor’s duties following partial possession by the Employer, whether with or without Contractor’s consent. i) Contractor to remove his site facilities, equipments, plants, materials, etc from Occupied Part upon receipt of Architect’s written instruction. 18
  • 19. Restrictions on Employer’s Rights to take partial possession without consent ○ Procedures following Partial Possession (with or without consent) ii) It is implied that the Architect must prescribe a definite time for removal from the Occupied Part and this should be a reasonable time frame. iii) However, the contract is silent on consequences of non-compliance by contractor with Architect’s written instruction to remove such items. 19
  • 20. Restrictions on Employer’s Rights to take partial possession without consent ○ Procedures following Partial Possession (with or without consent) iv) It is also silent on remedies available to employer for such Non-compliance by the Contractor. 20
  • 22. Different Commencement Dates ○ The Date of Commencement under Clause 21.1 assume that the whole of the Site be handed over to the Contractor on such date. ○ If this is not possible, the Employer may want to plan for different sections of the Site or phases to be handed over on different dates. In this case, this information must be properly documented and made known to the Contractor in the Contract so that he can price accordingly. 22
  • 23. Different Commencement Dates ○ The details of the different commencement dates must be recorded in the Appendix to PAM contract as Sectional Commencement Date under Clause 21.2, together with the demarcation layout showing the different sections. 23
  • 24. Different Commencement Dates ○ This clause is useful where the site is big or where piling works are carried out under a separate contract. Completed piling areas can be handed over to the building contractor to start work. ○ Sectional Commencement has the following advantages: i) Save time as it allows over-lapping of construction activities being carried out by different contractors on the same site, i.e. building contractor are given parts of the completed parts of piling works to commence while piling works continue in other parts. 24
  • 25. Different Commencement Dates ○ Sectional Commencement has the following advantages: ii) Improve cash-flow, Build according to sales and demand. 25
  • 26. Different Completion Dates The Sectional Completion Dates under Clause 21.3 can arise regardless of whether the Site was handed over to the Contractor as a whole or in sections. Employer may planned for completion of certain sections for business or commercial reasons, such as phase completion of apartments to improve cash-flow. The details of the different completion dates must be recorded in the Appendix to PAM contract, together with the demarcation layout showing the different sections. 26
  • 27. Different Completion Dates Scenario 1: Date of Commencement (Single) => Completion Date (Single). Scenario 2: Date of Commencement (Single) => Sectional Completion Dates. Scenario 3: Sectional Commencement Dates => Completion Date (Single). Scenario 4: Sectional Commencement Dates => Sectional Completion Dates. 27
  • 28. Different Completion Dates The contractual effect of Sectional Completion is the same as in Partial Completion, when all the provisions in the Contract with regards to Practical Completion and Defects Liability Period (clause 15.0); extension of time (clause 23.0); Liquidated Damages (clause 22.2); release of Retention Sum (clause 30.6); will apply to each section of the work as though it is a separate and distinct contract. 28
  • 29. Different Completion Dates One common practice is for the Employer to state milestone dates or key dates for works to be done in stages or phases (but not handed over) in the Contract document but not as Sectional Completion in the Appendix. 29
  • 30. Different Completion Dates Disputes often arise if there is a failure to meet such dates and the question being if liquidated damages can be imposed. The Employer may contend that the milestone dates or key dates is on the same footing as Sectional Completion dates and have the same effect. On the other hand, Contractor may argue that the milestone dates are merely part of the Contractor’s work programme and therefore doubtful that it will be accorded the same contractual treatment as sectional completion and may not be contractually effective. 30
  • 32. Explain the differences between Sectional Completion and Partial Possession in PAM 2006. Question 1
  • 33. Answer 33 Sectional Completion Partial Possession Clause 21.3 Clause 16.1 Contract agreed date No contract agreed date Decided before the signage of contract Decided during construction Architect to issue a Certificate of Sectional Completion when the sections of the Works are Practically Completed. Architect to issue a Certificate of Partial Completion within fourteen (14) Days from the date on which the Employer has taken possession of the Occupied Part.
  • 34. Under what circumstance can the Employer take partial possession of the site? Please explain for both partial possession with and without consent from the Contractor. Question 2
  • 35. Answer Employer can take partial possession of the site under several circumstances, where the reasons for such possession could be of i) Business pressure Current demand and price is good so they need to start business or production. ii) Commercial reasons Commencement date of Works has been delayed so with the need to complete early, Employer to take partial possession for some sections. 35
  • 36. Answer iii) Under Clause 16.2, delayed of Completion of works by the Contractor and issuance of Certificate of Non-Completion by the Architect under Clause 22.1, and iv) The entry and partial possession of the Occupied Part do not unreasonably disturb the regular progress of the works or affect the safety and health issues. 36
  • 37. Answer Provided the Employer has comply with the following stated in Clause 16.0 i) To give written notice of intention to take partial possession to contractor, so that contractor can prepare himself and focus the part of employer want to occupy. ii) The partial possession occurs before practical completion. iii) The employer to identify part to be taken over. iv) That the contractor has given his consent. 37
  • 38. Answer Partial possession with consent from the Contractor: Clause 16.1 prohibits the Contractor from unreasonably withholding or delaying consent. However, the Contractor is not bound to give consent for partial possession. 38
  • 39. Answer The Contractor may withhold consent by reasons of: i) When partial possession may give rise to safety and health issues, or ii) When partial possession may materially disrupt the regular progress of the remaining works, or iii) Where there is non-payment issue for work done. 39
  • 40. Answer Partial possession without consent from the Contractor: Under Clause 16.2, the Employer may take partial possession provided that i) The completion of Works have been delayed, and ii) A Certificate of Non-Completion has been issued by Architect under clause 22.1, and iii) Such entry and partial possession of the Occupied Part do not unreasonably disturb the regular progress of the Contractor’s remaining works or adversely affect the safety and health issues. 40
  • 41. Explain the contractual implications of partial possession and the items not affected by it. Question 3
  • 42. Answer (a) Practical Completion - Clause 16.1(b) - The practical completion of the Occupied Part shall be deemed to have occurred on the date of taking over the Occupied Part. (b) Defects Liability Period - Clause 16.1(b) - The DLP is deemed to have commenced on the date of practical completion of the Occupied Part by the Employer. 42
  • 43. Answer (c) Liquidated Damages - Clause 16.1(c) - Liquidated damages shall be reduced by the ratio of the estimated value of occupied part to the contract sum. (d) Retention Sum - Clause 16.1(d) - Under Clause 16.1(d), the Architect is required to: i) issue a payment certificate to release the first moiety of the retention fund in the ratio of the estimated value of the Occupied Part ii) issue payment certificate within 14 days after the issuance of the Certificate of Partial Completion 43
  • 44. Answer (e) Certificate of Making Good Defects - Clause 16.1(e) - Under Clause 16.1(e), where all defects in the Occupied Parts have been made good, the Architect shall issue a CMGD. (f) Release of Second Moiety of Retention - Clause 16.1(f) - Under Clause 16.1(f), the Architect shall issue a certificate for the release of the remaining retention fund (second moiety) for the Occupied Part within 14 days after the issue of CMGD of the same Occupied Part. 44
  • 45. Item Not Affected by Partial Possession a) Works Insurance - Clause 20.A.1, Clause 20.B.1 and 20.C.1 - The total sum of the insurance must be remain unaffected and being no reduction for the value of the Occupied Part. b) Performance Bond and Final Certificate - Clause 37 for Performance Bond does not indicate any deduction or reduction of the bond value after partial possession. - Clause 30.0 for Final Certificate are not affected by the partial possession since there is only one Final Certificate issued. 45
  • 47. An employer is trying to take partial possession without the consent of the Contractor under the following condition:- i) A Certificate of Non-Completion has been issued by Architect ii) Subsequently, the contractor was granted an EOT due to the delayed caused by relevant event under Clause 23.8 Can the employer take partial possession without the consent of the Contractor? Why? Question 1
  • 48. Answer According to Clause 16.2 (a), the employer can take partial possession without consent provided that the completion of the Works has been delayed and a Certificate of Non-Completion has been issued by the Architect under Clause 22.1. In this case, the employer cannot take partial possession without contractor’s consent because the delay is caused by the relevant event under Clause 23.8. The contractor is then entitled to claim for EOT. For Clause 16.2(a) to be applicable, it may be implied that the Certificate of Non-Completion is still operative and the contractor is liable for liquidated damages. 48
  • 49. In the construction industry nowadays, most of the contractor is willing to give consent for the employer to get partial possession. Why? Question 2
  • 50. Answer (1) Defect Liability Period reduced - Clause 16.1 (b) (2) Liquidated Damages reduced - Clause 16.1 (c) (3) The first moiety of retention sum is released - Clause 16.1 (d) 50
  • 51. Does the employer have the rights to take partial possession without the Contractor's consent under the common law? Why and which clause stated so? Question 3
  • 52. Answer No. Clause 16.2 uses the phrase ‘without prejudice to any other rights and remedies which he may possess under the contract’. This limits the Employer’s right to those under the contract only and in the process excludes his common law rights. 52
  • 54. Why is the value of the occupied part had to be estimated? Question Back up
  • 55. Answer The value of the occupied part had to be estimated because the implications of partial possession affect some of contract values. - Liquidated damages - Retention Sum According to Clause 16.1(c) and 16.1(d), both the liquidated damages and retention sum shall be reduced by the ratio of the estimated value of the occupied part to the contract sum. 55