80m XHD Webinar Slides
1. 80-meter XHD
INSTALLATION OVERVIEW WEBINAR
Paul Dawson – Global Sales Manager
Larry Jacobs – Marketing Manager
Steve Clark – P.E., Mechanical Engineer & Technical Lead
Emeric Rochford – Mechanical Engineer & Crew Leader
24 March 2011
2. Webinar Objectives
• Provide a high-level overview of the 80m XHD
• Underscore critical installation steps
• Answer your questions
• Share next steps and resources
This webinar DOES NOT
replace a thorough review of
the 80m XHD Manual
3. Webinar Agenda
• Introduction
• 80m XHD tower overview
• Testing and beta program
• Design
• Installation
• Lighting and compliance
• Critical Steps and Safety
• Q&A
• Wrap-up
4. Testing and Beta Program
Laboratory tests of Off-site laboratory
base plate and joints tests on guy wire
(axial and bending) breaking strengths
5. Testing and Beta Program
Three (3) North
Multiple on-site American beta
installs installations for final
testing and feedback
6. 60m vs. 80m Comparison:
Design
Component 60-meter XHD 80-meter XHD
(197.7 ft or 60.3m) (266.7 ft or 81.3m)
Tube diameter (OD) 10 inch (254 mm) 10 inch (254 mm)
8 inch (203.2 mm) 8 inch (203.2 mm)
Tube wall 10 inch 0.109 inch nominal (12 ga) 0.134 inch nominal (10 ga)
thickness
8 inch 0.109 inch nominal (12 ga) 0.134 inch nominal (10 ga)
Tube transition 101 feet, 5 inch (30.9 m) 182 feet, 2 inch (55.8 m)
Shipping weight 4323 lbf (1960.9 kg) 9050 lbf (4105 kg)
(tower and ginpole)
Footprint 50 meters to outermost anchor 55 meters to outermost anchor
Bolted Joints No bolts; flared, lanced joint Flared, lanced and bolted joint
Base plate 0.134 inch (3.4 mm), 10 ga steel 0.188 inch (4.8 mm), 7 ga steel
Guy levels 6 8
Guy wire diameter All levels: 1/4 inch (6.3mm) Levels 1-6: 5/16 inch (7.9mm)
Levels 7-8: 3/8 inch (9.5mm)
7. 60m vs. 80m Comparison:
Installation
Component 60-meter XHD 80-meter XHD
Total erection forces 35.6 kN (8000 lbf) 66.7 kN (15000 lbf)
(tower plus NOW System)
Erection forces 11.9 kN (2667 lbf) 13.3 kN (3000 lbf)
(winch cable force)
Winch rigging 3-part line 5-part line
Wire rope length 300 ft (91.4 m) 750 ft (228.6 m)
Maximum anchor load 5,100 lbf (2313 kg) 12,400 lbf (5625 kg)
Anchor number and type Fifteen 8-inch, single-helix screw- • Sixteen 8-inch, double-helix
in earth anchors power installed screw anchors
• Two 8-inch, single-helix screw-
in earth anchors
8. Installation
Topics Covered
• Resources and Time
• Terrain/slope Requirements
• Anchors and Pull Test
• Joint Assembly
• Ginpole and Jumper-struts
• Winch
9. Installation
Resources and Time
• Site layout / anchor setting: 1 day
• Tube bolting: 3.5 hours
• Laying out guy wires: 3.5 hours
• Ginpole assembly: 1.5 hours
• Lighting installation: 2.5 hours
• Raising & plumbing tower: 3.5 hours
TOTAL: 3-4 days
11. Installation
Anchors and Pull Test 1
• Double Helix Power-Installed
Screw Anchors.
• Maximum anchor load: 12,400
lbf (5625 kgf).
• CRITICAL STEP:
Anchors must be pull-tested
to 15,000 lbf (6804 kgf).
12. Installation
Joint Assembly
1. Hold top fastener up while
tubes are slid together.
2. Using a block of wood and
sledge hammer, pound 2 to 3
times to seat joint.
3. Using a torque wrench, torque
5/8” – 11 nuts to 203 Nm
(150 ft-lbs).
15. Installation
Winch
• 750 ft of 3/8 in diameter 4
cable.
• 3000 lbf (1361 kgf) winch
cable erection force.
• CRITICAL STEP:
Winch base plate must be
secured to winch anchor
using sling provided.
16. Installation Toolkit
Toolkit Includes: 5
• Chicago grip
• Come-along
• Shackles
• CRITICAL STEP:
Mechanical tensioning
is required to tension
guy wires.
18. Lighting Options
Top mounted, L-864 RED LED flashing beacon
Side-mounted L-810 RED LED steady burning side markers
Red light controller (RLC)
PV Power Supply
PV Integrated Lighting & Remote Monitoring System
22. Final Thoughts
• 60m XHD performance at 80m
• More steel means more weight
• Similar installation, new tools
and anchoring required
• Thoroughly review the 80m
XHD Manual