- 1. Table 3. Alexandria Water & Wastewater PSP Study
Updated Project Implementation Schedule
- - 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41
March April May June July August September October November
TASK 1 (Policy Statement)
Initial Trip to Egypt (3/18-3/29)
Data collection and validation (local team)
Considerations for main policy decision making
* Report 1
Policy Statement
* Report (2)
* Team in Egypt - Policy - discussion
* Workshop (1)
TASK 2 (SOW adjustment - Service Contracts)
* Report (Needs Assessment merged into FS report)
TASK 3 (Feasibility Study)
* Team in Egypt - Service Contract for M/B+C
* Consultant in Egypt - Service Contract for Septage Mgt
* Briefings to USAID - AWGA - AGOSD
* Reports 3 & 4 - Feasibility M/B+C and Options Septage Mgt
* Team in Egypt -Service Contracts / Transaction Plan
* Workshop (2) - Service Contract Definitions
TASK 4 (Transaction & Implementation Plan)
* Report (5) - Transaction Implementation Plan - AWGA
* Report (6) - Steps Toward Transaction Implementation - AGOSD
* Final report (7)
* Final Presentation USAID/GOE
Religious holidays (Ramadan) -Oct 16 - Nov 14 (approx)
Notes: 1. Weeks start on Sundays, from March 21/04