Fidic flow charts final
1. FIDIC Tendering Procedures International Federation of Consulting Engineers
2.
3.
4.
5.
6.
7. Section Employer/Engineer Contractors 3.2 ISSUE OF TENDER DOCUMENTS ISSUE TENDER DOCUMENTS TO CONTRACTORS ON LIST OF TENDERERS ACKNOWLEDGEMENT RECEIPT 3.3 VISIT TO SITE BY TENDERERS ARRANGE DATE AND TIME FOR VISIT TO SITE APPLY FOR VISIT TO SITE IF REQUIRED VISIT(S) TO SITE BY TENDERERS ACCOMPANIED BY EMPLOYER/ENGINEER
8.
9. Section Employer/Engineer Contractors 3.5 ADDENDA TO TENDER DOCUMENTS ISSUE ADDENDA INCLUDING REPLIES TO QUERIES TO ALL TENDERERS ACKNOWLEDGE RECEIPT RECORD DATE AND TIME OF RECEIPT SUBMIT TENDERS 3.6 SUBMISSION AND RECEIPT OF TENDERS ACKNOWLEDGE RECEIPT OR RETURN UNOPENED TENDERS RECEIVED LATE
10.
11.
12.
13. Section Employer/Engineer Contractors 6.0 AWARD OF CONTRACT DECIDE ON CONTRACT AWARD, IF NECESSARY AFTER PRE-AWARD DISCUSSIONS 6.1 ISSUE LETTER OF ACCEPTANCE 6.2 PERFORMANCE SECURITY ATTEND PRE-AWARD DISCUSSIONS, IF REQUIRED ISSUE LETTER OF ACCEPTANCE PROVIDE PERFORMANCE SECURITY 6.3 PREPARATION OF CONTRACT AGREEMENT 6.4 NOTIFICATION OF UNSUCCESSFUL TENDERERS OBTAIN PERFORMANCE SECURITY FROM CONTRACTOR PREPARE CONTRACT DOCUMENTS SIGNING OF CONTRACT ADVISE UNSUCCESSFUL TENDERERS AND RETURN TENDER SECURITY (IF PROVIDED) ACKNOWLEDGEMENT RECEIPT SIGNING OF CONTRACT UNSUCCESSFUL TENDERERS ACKNOWLEDGE RECEIPT
14.
15.
16.
17.
18. Main Types of Contracts in Construction according to Pricing Method Lump Sum Fixed Price Unit Price Schedule of Rates Cost Plus Fixed Price with escalation Target Cost Cost Plus Percentage Cost Plus Fixed Fee Guaranteed Maximum Guaranteed Maximum with Incentive Fee