2. IT
Rwanda Vision For Science & Technology – Focus on ICT
• Step 1: Enabling Environment already in place that allows investment in
sector: Policies, Ins<tu<ons, Regulatory Environment
• Step 2: Infrastructure Challenge being addressed
– See next Diagram (NBB, KMN, WiBro, Rwandatel and MTN fiber
Networks and Several ISP Wimax Solu<ons now exist)
• Step 3: Developing IT driven Service Sector [Ongoing, needs accelerated
development]
– Efficient Banking Systems, Tourism and Public Service Delivery
– Financing of Development
• Step 4: Needs concerted efforts in building a cri<cal mass of highly skilled
2
5. The Projects
1. NBB: National Backbone Fibre-Optic
Network
2. KMN: Kigali Metropolitan Network
3. WiBro: Wireless Broadband Network
IT Broadband Connec,vity Infrastructure Projects
6. National Backbone Network
About the Project
• A high-speed 2,300 Km fiber-optic network that
will interconnect all the districts and border posts
of the Country
• This network shall also provide converged IP/MPLS
services to 226 identified located in the districts
• Sites to be connected: district headquarters,
schools, universities, hospitals, health centers,
social security fund offices, RRA & Customs offices,
police offices, immigration offices, utilities, army
camps/barracks, BNR branches, Judiciary Offices,
ORTPN sites, etc…
• Border post connectivity for regional and
international traffic
IT Broadband Connec,vity Infrastructure Projects
9. The Projects
1. NBB: National Backbone Fibre-Optic
Network
2. KMN: Kigali Metropolitan Network
3. WiBro: Wireless Broadband Network
IT Broadband Connec,vity Infrastructure Projects
10. Kigali Metropolitan Network
About the Project
• Construction of a high-speed Fiber-optic network
in the Kigali metropolitan area;
• Deployment of Network Equipments (MPLS) to
provide IP data, voice and video services to all
government agencies in Kigali City;
• Construction of a Network Operations Control
Center (NOC) for central network management and
operation;
• Network capacity: 10Gbps ring (STM-64),
max1Gbps network equipment for each
government site
• Interconnection with the National Backbone
Network (all the 30 districts and border posts)
IT Broadband Connec,vity Infrastructure Projects
11. Kigali Metropolitan Network
Completed Activities
• Phase 1:
– Installation of underground fibre-optic cables (57 Km, 54
government buildings, 63 agencies)
– Deployment of IP/MPLS Network Equipments to (46
Routers, 105 Switches, 53 Optical Fiber Distribution Frame
(ODF), 72 Network racks, 73 UPS) Installation and
configuration completed for 46 government agencies
– Construction of Network Operation Center (NOC) at
Telecom House
– 3040 VoIP phones delivered (1725 phones configured)
– Configuration of VoIP System & Data Connectivity
– Network Migration: 10th of December 2009
IT Broadband Connec,vity Infrastructure Projects
12. Kigali Metropolitan Network
Network Operation Center (NOC) at Telecom House for
Real-time Network Control & Monitoring
IT Broadband Connec,vity Infrastructure Projects
13. The Projects
1. NBB: National Backbone Fibre-Optic
Network
2. KMN: Kigali Metropolitan Network
3. WiBro: Wireless Broadband Network
IT Broadband Connec,vity Infrastructure Projects
14. WiBro Network
About the Project
• WIBRO stands for Wireless Broadband; it is a Korean Mobile
WiMax Technology which provide superior broadband
services for data, voice , video
• The network consists of a core fibre-optic transmission
network , wibro radio equipments, antennas and masts
installed at various locations in the city
• Project implementation started in June 2008. First trial-run
succesfully conducted in Dec 2009
• The project is divided into 2 phases.
– The first phase is coverage of Kigali City
– Second phase is coverage of 5 towns: Rwamagana, Huye,
Rusizi, Ruhengeri and Gisenyi.
IT Broadband Connec,vity Infrastructure Projects
15. WiBro Network
IT Broadband Connec,vity Infrastructure Projects
16. WiBro Network
Topology
Internet Backbone
Centenary House
City Plaza BCDI
AAA
APEX
AAA Biryogo Gitega
Nyarugenge
Nyakabanda
RWT Switch Nyamirambo
Kinamba
Kabuga ACR-
Telecom Nyarutamara Golf Club
Okapi Hotel KL House
House
Kibagabaga
Kimihurura 1 Mininfra
RITA Covibar
Inind House
Kacyiru 1
Samantha House Kicukiro
Gisozi
Kacyiru 2 Kanombe
Stadium Giporoso
Mburabuturo Kimironko 2
Gorilla Hotel
Kimihurura 2 Giporoso Minijust
Kissementi
KIST 2
KIST 3
Gicondo 1 Gicondo 2
IT Broadband Connec,vity Infrastructure Projects
17. WiBro Network
Project Status
Civil works for fibre-optic cables installation – 95% completed
Site acquisition – 100% completed
Power Installation – 80% completed
Telecommunication Tower construction – 90% completed
Equipment installation(Antennas, Base station, repeaters...) –
95 % completed – Total of 40 Sites (Towers & Rooftop)
WIBRO Network Operating Center – 90% completed
Kigali WiBro Network scheduled to go live on December 10th, 2009
– Trial Run Phase (Dec 2009 to February)
– Commercial Services requires a company set-up (Regulatory
Requirement) WiBro network should be owned and managed by
a Commercial Entity
IT Broadband Connec,vity Infrastructure Projects
18. WiBro Network
Tower Construction &
Installation
RDB-IT has constructed 40 Sites (Towers and Rooftop types) in Kigali City
IT Broadband Connec,vity Infrastructure Projects
19. END
IT Broadband Connec,vity Infrastructure Projects