SlideShare une entreprise Scribd logo
1  sur  21
Datacenter
Selection
Adam Rothschild <asr@packet.net>
Open-IX - Americas Interconnection Summit
San Diego, CA - April 2015
DISCLAIMERS
○ Personal experiences and opinions only, not those of the Open-IX Association, working
groups, or any employer.
○ Not intended as legal advice. Datacenter contracts are extremely complex and require
review by counsel.
○ Datacenters presented are completely fictitious. Any resemblances, living or dead, are
coincidental.
WHY DATACENTERS
MATTER○ Significant operational expenditure, often exceeding cost of IP transit or
interconnection.
○ Often selected by the “network person” or “vendor negotiator” (hence, this audience)
○ Can be a major source of downtime if planned poorly.
○ Power, Plumbing, and Ping is not an “attractive” topic like “cloud” or “SDN”, though it
underpins it; therefore not often discussed around these parts.
○ Lack of best-practice sharing among operators. Not a germane topic for a NANOG,
etc.
WHEN YOU’RE NOT
ALIGNED
CENSORED
WHEN YOU’RE NOT
ALIGNED: SANDY EDITION
Force majeure, or poor site selection by the
customer?
WHEN YOU’RE ALIGNED
VENDOR POSITIONING
RETAIL WHOLESALE
CHARACTERISTICS OF RETAIL
DATACENTER OR MMR
WHOLESALE
○ Power is billed at a fixed MRC, based on breakered (or capped) capacity.
○ Common increments of space are RUs, racks, or private cages.
○ Diverse meet-me room, with access to dozens of IP, lit services, dark fiber providers.
○ Cross-connection is a large profit center for the operator, and may carry significant MRC.
○ Access to 24 x7 remote hands for basic troubleshooting, rack & stack, managed services.
○ Limited options for power redundancy beyond N or N+1; so called “primary” and “redundant” power
feeds may terminate on common infrastructure.
CHARACTERISTICS OF
WHOLESALE DATACENTER
WHOLESALE
○ Power is metered and billed based upon consumption (KW/hr or mean KW/month).
○ Common increments of space are private cages or partitioned suites.
○ Limited providers on-site, but should connect to one or more dark fiber provider(s) with entrance
diversity. Tethering is common. May also offer extended cross-connect service to nearby MMR(s).
○ Cross-connection is not a profit center for the operator; commonly NRC to cover time & materials.
○ Access to remote hands may be limited. Clients typically provide their own operational staffing.
○ Greater options for power diversity (e.g. 2N[+n] designs). Some customization on power, cooling, and
rack designs to meet customer’s needs.
SCOPE OF THIS TALK
WHOLESALE
○ Most relevant to wholesale colocation, in the hundreds of KWs and larger.
○ Some elements are applicable to retail colocation, e.g. a cage, though you’re probably wasting your
and your account rep’s time if you’re using this method to quote out a single cabinet. 
○ Some elements are applicable to larger wholesale suites/pods in the MWs range, however further due
diligence may be helpful.
○ We’re not discussing greenfield construction, though the TCO comparatives may help.
RFP: INTRO AND BASICS
WHOLESALE
○ RFP should be short and sweet, while explaining your requirements. Should not exceed several
pages of core requirements.
○ Should be conducive to vendor providing concise, binary, responses, without the hassle of flowery
marketing narratives.
○ Should clearly state nature of customer’s business and use case; establish expectations for a
response and go-live date.
○ Should clearly establish search radius, leave no room for interpretation as to whether or not a
particular location is in-scope for consideration.
RFP: BUILD AND POWER
WHOLESALE
○ Explain clearly what type of equipment racks or cabinets you need to place, and quantity. Floor plan
and rack layout can be helpful as attachments. Establish provider’s “sweet spot” for density (W/ft^2 or
KW/cabinet) so you can tweak your layouts appropriately.
○ Establish “day one” and future (12mo, 24mo, …) power requirements, in terms of both base commit
and ceiling. Negotiate a ramp beneficial to both parties, if you’re not using all power initially.
○ Establish how power is metered and invoiced; base commitments vs. variable.
○ Establish mean Power Usage Effectiveness (PUE) for facility, and its impact on how power is billed.
○ Establish costs for installing incremental cabinets, NEMA receptacles.
RFP: COMMERCIAL TERMS
WHOLESALE
○ Establish term length. Long terms (>= 5 years) ensure stability and cost predictability for the
purchaser, as well as certainty for the vendor.
○ Establish YoY escalations, if applicable. Solidify language for additional pricing increases, e.g. notice
period, commensurate to increased costs from power utility.
○ Establish “look back” period for incorrect billings. Ensure it’s bilateral; same period for billing disputes
initiated by customer, and billing corrections issued by vendor…
RFP: CABLING
WHOLESALE
○ Establish rates (NRC and MRC) for all common types of cross-connections: Cat5e, SMF; are
increases permitted during the contract term?
○ Establish policies for running your own data connections inside your datacenter space, using your own
materials and labor.
○ Establish facility’s policy on unionized labor. Is there any type of non-electrical work (e.g. bolting of
cabinets, intra-suite data cabling) that you’re not allowed to perform by yourself?
○ Develop with the facility a mutually agreeable plan for wire tray placement, rack placement, cable
plant, etc.
RFP: COMMUNICATIONS
WHOLESALE
○ “Provider ABC is on-net” is, itself, not a complete answer:
○ Develop list of on-site IP and telco providers you’re looking to purchase from.
○ Drill down to determine which building entrance[s] are utilized; underlying dark fiber providers and
routes are into the street. Also look for convergence points further away.
○ Vendor KMZ files overlayed into Google Earth are your friends. Some vendors have commissioned
reports to help with this planning, also.
○ Discuss relative strengths and weaknesses of aerial vs. buried fiber.
RFP: OIX-2 CERTIFICATION
WHOLESALE
○ My employer (Packet) asks this of all RFP respondents.
○ We view OIX-2 as a good indicator of transparency in operations, willingness to promote a diverse
carrier/interconnection ecosystem.
○ We understand that certifying every single site in a provider’s portfolio won’t happen overnight,
however [un]willingness to certify a particular site is a telling conversation.
RFP: OTHER IDEAS
WHOLESALE
○ Review history of planned maintenance events for past 12+ months, and upcoming 3+ months.
○ Review history of unplanned site outages for past 24+ months.
○ Establish access methods/controls into the datacenter, and private cage or suite; multiple “factors”.
○ Review policy on CCTV placement, retention, customer access. Discuss placement of your own
cameras, to augment the provider’s systems.
○ Confirm that temperature and RH will be maintained in accordance with (e.g. ASHRAE) norms.
○ Review SLA threshold and remedies for loss of power or cooling.
FLOOD MAPS
Source: FEMA MSC
SUBJECTIVE ANALYSIS
WHOLESALE
SUBJECTIVE ANALYSIS (2)
WHOLESALE
Documents are here:
RFP: http://baremet.al/packet-dc-
rfp
TCO Model:
http://baremet.al/packet-dc-tco
Questions or comments:
asr@packet.net

Contenu connexe

Tendances

Intro to Project Calico: a pure layer 3 approach to scale-out networking
Intro to Project Calico: a pure layer 3 approach to scale-out networkingIntro to Project Calico: a pure layer 3 approach to scale-out networking
Intro to Project Calico: a pure layer 3 approach to scale-out networking
Packet
 

Tendances (20)

Intro to Project Calico: a pure layer 3 approach to scale-out networking
Intro to Project Calico: a pure layer 3 approach to scale-out networkingIntro to Project Calico: a pure layer 3 approach to scale-out networking
Intro to Project Calico: a pure layer 3 approach to scale-out networking
 
Metaswitch Project Calico
Metaswitch Project CalicoMetaswitch Project Calico
Metaswitch Project Calico
 
Replacing vCloud with OpenNebula
Replacing vCloud with OpenNebulaReplacing vCloud with OpenNebula
Replacing vCloud with OpenNebula
 
NetApp Hybrid Cloud with OpenNebula
NetApp Hybrid Cloud with OpenNebulaNetApp Hybrid Cloud with OpenNebula
NetApp Hybrid Cloud with OpenNebula
 
OpenNebulaConf2019 - Welcome and Project Update - Ignacio M. Llorente, Rubén ...
OpenNebulaConf2019 - Welcome and Project Update - Ignacio M. Llorente, Rubén ...OpenNebulaConf2019 - Welcome and Project Update - Ignacio M. Llorente, Rubén ...
OpenNebulaConf2019 - Welcome and Project Update - Ignacio M. Llorente, Rubén ...
 
Onug lunch talk may 12 2015 no video
Onug lunch talk may 12 2015 no videoOnug lunch talk may 12 2015 no video
Onug lunch talk may 12 2015 no video
 
KURMA - A Containerized Container Platform - KubeCon 2016
KURMA - A Containerized Container Platform - KubeCon 2016KURMA - A Containerized Container Platform - KubeCon 2016
KURMA - A Containerized Container Platform - KubeCon 2016
 
Policy driven SDN in CloudStack
Policy driven SDN in CloudStack Policy driven SDN in CloudStack
Policy driven SDN in CloudStack
 
CloudStack IPv6 in production
CloudStack IPv6 in productionCloudStack IPv6 in production
CloudStack IPv6 in production
 
Delivering Composable NFV Services for Business, Residential and Mobile Edge
Delivering Composable NFV Services for Business, Residential and Mobile EdgeDelivering Composable NFV Services for Business, Residential and Mobile Edge
Delivering Composable NFV Services for Business, Residential and Mobile Edge
 
OpenStack Telco Cloud Challenges, David Fick, Oracle
OpenStack Telco Cloud Challenges, David Fick, OracleOpenStack Telco Cloud Challenges, David Fick, Oracle
OpenStack Telco Cloud Challenges, David Fick, Oracle
 
Our journey with CloudStack
Our journey with CloudStackOur journey with CloudStack
Our journey with CloudStack
 
Open contrailmeetup
Open contrailmeetupOpen contrailmeetup
Open contrailmeetup
 
Container Networking Meetup March 31 2016
Container Networking Meetup March 31 2016Container Networking Meetup March 31 2016
Container Networking Meetup March 31 2016
 
OpenNebula from the Perspective of an ISP
OpenNebula from the Perspective of an ISPOpenNebula from the Perspective of an ISP
OpenNebula from the Perspective of an ISP
 
You Can Build Your OpenStack and Consume it Too
You Can Build Your OpenStack and Consume it TooYou Can Build Your OpenStack and Consume it Too
You Can Build Your OpenStack and Consume it Too
 
Why nfv and digital transformation projects fail!
Why nfv and digital transformation projects fail! Why nfv and digital transformation projects fail!
Why nfv and digital transformation projects fail!
 
Metaswitch and Intel: A Systematic Approach to NFV
Metaswitch and Intel: A Systematic Approach to NFVMetaswitch and Intel: A Systematic Approach to NFV
Metaswitch and Intel: A Systematic Approach to NFV
 
Deploying NGINX in Cloud Native Kubernetes
Deploying NGINX in Cloud Native KubernetesDeploying NGINX in Cloud Native Kubernetes
Deploying NGINX in Cloud Native Kubernetes
 
Interop2018 contrail ContrailEnterpriseMulticloud
Interop2018 contrail ContrailEnterpriseMulticloudInterop2018 contrail ContrailEnterpriseMulticloud
Interop2018 contrail ContrailEnterpriseMulticloud
 

Similaire à Open-IX Presentation: Datacenter Selection by Adam Rothschild

2015 Gartner Magic Quadrant Cloud Enabled Managed Hosting
2015 Gartner Magic Quadrant Cloud Enabled Managed Hosting2015 Gartner Magic Quadrant Cloud Enabled Managed Hosting
2015 Gartner Magic Quadrant Cloud Enabled Managed Hosting
Evan Blum
 
Arcus Advisors Report_Quality of Service
Arcus Advisors Report_Quality of ServiceArcus Advisors Report_Quality of Service
Arcus Advisors Report_Quality of Service
Scott Landman
 
das-level-2-training-resource-pdf1
das-level-2-training-resource-pdf1das-level-2-training-resource-pdf1
das-level-2-training-resource-pdf1
Ryan Tyson, MBA
 
Oracle Systems _ Kevin Mcisaac _ The IT Landscape has changes - have you_.pdf
Oracle Systems _ Kevin Mcisaac _ The IT Landscape has changes - have you_.pdfOracle Systems _ Kevin Mcisaac _ The IT Landscape has changes - have you_.pdf
Oracle Systems _ Kevin Mcisaac _ The IT Landscape has changes - have you_.pdf
InSync2011
 
Distributor magazine
Distributor magazineDistributor magazine
Distributor magazine
Beth Seal
 

Similaire à Open-IX Presentation: Datacenter Selection by Adam Rothschild (20)

2015 Gartner Magic Quadrant Cloud Enabled Managed Hosting
2015 Gartner Magic Quadrant Cloud Enabled Managed Hosting2015 Gartner Magic Quadrant Cloud Enabled Managed Hosting
2015 Gartner Magic Quadrant Cloud Enabled Managed Hosting
 
Tips To Find the Best Colocation Hosting Provider | Shared Hosting Providers ...
Tips To Find the Best Colocation Hosting Provider | Shared Hosting Providers ...Tips To Find the Best Colocation Hosting Provider | Shared Hosting Providers ...
Tips To Find the Best Colocation Hosting Provider | Shared Hosting Providers ...
 
BSN Security and Wireless presentation Feb 2019
BSN Security and Wireless presentation Feb 2019BSN Security and Wireless presentation Feb 2019
BSN Security and Wireless presentation Feb 2019
 
Liam Macintyre - APM Scotland Branch Conference 2023: Net Zero Nation and Sus...
Liam Macintyre - APM Scotland Branch Conference 2023: Net Zero Nation and Sus...Liam Macintyre - APM Scotland Branch Conference 2023: Net Zero Nation and Sus...
Liam Macintyre - APM Scotland Branch Conference 2023: Net Zero Nation and Sus...
 
Liam Macintyre - APM Scotland Branch Conference 2023: Net Zero Nation and Sus...
Liam Macintyre - APM Scotland Branch Conference 2023: Net Zero Nation and Sus...Liam Macintyre - APM Scotland Branch Conference 2023: Net Zero Nation and Sus...
Liam Macintyre - APM Scotland Branch Conference 2023: Net Zero Nation and Sus...
 
Moving to cloud a checklist of top tips to help you migrate to the cloud © ...
Moving to cloud   a checklist of top tips to help you migrate to the cloud © ...Moving to cloud   a checklist of top tips to help you migrate to the cloud © ...
Moving to cloud a checklist of top tips to help you migrate to the cloud © ...
 
SD-WAN: the Savings are in the Details
SD-WAN:  the Savings are in the DetailsSD-WAN:  the Savings are in the Details
SD-WAN: the Savings are in the Details
 
Arcus Advisors Report_Quality of Service
Arcus Advisors Report_Quality of ServiceArcus Advisors Report_Quality of Service
Arcus Advisors Report_Quality of Service
 
Cloudonomics in Advanced Cloud Computing
Cloudonomics in Advanced Cloud ComputingCloudonomics in Advanced Cloud Computing
Cloudonomics in Advanced Cloud Computing
 
Strategies for migration to public cloud
Strategies for migration to public cloudStrategies for migration to public cloud
Strategies for migration to public cloud
 
das-level-2-training-resource-pdf1
das-level-2-training-resource-pdf1das-level-2-training-resource-pdf1
das-level-2-training-resource-pdf1
 
Small Commercial Solar: Grow Your Business With This Untapped Sector
Small Commercial Solar: Grow Your Business With This Untapped SectorSmall Commercial Solar: Grow Your Business With This Untapped Sector
Small Commercial Solar: Grow Your Business With This Untapped Sector
 
Oracle Systems _ Kevin Mcisaac _ The IT Landscape has changes - have you_.pdf
Oracle Systems _ Kevin Mcisaac _ The IT Landscape has changes - have you_.pdfOracle Systems _ Kevin Mcisaac _ The IT Landscape has changes - have you_.pdf
Oracle Systems _ Kevin Mcisaac _ The IT Landscape has changes - have you_.pdf
 
How to reduce the cost of your WAN
How to reduce the cost of your WANHow to reduce the cost of your WAN
How to reduce the cost of your WAN
 
Understanding And Evaluating Colocation Data Centers
Understanding And Evaluating Colocation Data CentersUnderstanding And Evaluating Colocation Data Centers
Understanding And Evaluating Colocation Data Centers
 
Retrofit, build, or go cloud/colo? Choosing your best direction
Retrofit, build, or go cloud/colo?  Choosing your best directionRetrofit, build, or go cloud/colo?  Choosing your best direction
Retrofit, build, or go cloud/colo? Choosing your best direction
 
Retrofit, build, or go cloud/colo? Choosing your best direction
Retrofit, build, or go cloud/colo?  Choosing your best directionRetrofit, build, or go cloud/colo?  Choosing your best direction
Retrofit, build, or go cloud/colo? Choosing your best direction
 
Morgan Hill presentation Tayor Wessing Cambridge
Morgan Hill presentation Tayor Wessing CambridgeMorgan Hill presentation Tayor Wessing Cambridge
Morgan Hill presentation Tayor Wessing Cambridge
 
CF-Chapitre1.pdf
CF-Chapitre1.pdfCF-Chapitre1.pdf
CF-Chapitre1.pdf
 
Distributor magazine
Distributor magazineDistributor magazine
Distributor magazine
 

Dernier

Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
dharasingh5698
 

Dernier (20)

The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLPVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
 
Vivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design SpainVivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design Spain
 

Open-IX Presentation: Datacenter Selection by Adam Rothschild

  • 1. Datacenter Selection Adam Rothschild <asr@packet.net> Open-IX - Americas Interconnection Summit San Diego, CA - April 2015
  • 2. DISCLAIMERS ○ Personal experiences and opinions only, not those of the Open-IX Association, working groups, or any employer. ○ Not intended as legal advice. Datacenter contracts are extremely complex and require review by counsel. ○ Datacenters presented are completely fictitious. Any resemblances, living or dead, are coincidental.
  • 3. WHY DATACENTERS MATTER○ Significant operational expenditure, often exceeding cost of IP transit or interconnection. ○ Often selected by the “network person” or “vendor negotiator” (hence, this audience) ○ Can be a major source of downtime if planned poorly. ○ Power, Plumbing, and Ping is not an “attractive” topic like “cloud” or “SDN”, though it underpins it; therefore not often discussed around these parts. ○ Lack of best-practice sharing among operators. Not a germane topic for a NANOG, etc.
  • 5. WHEN YOU’RE NOT ALIGNED: SANDY EDITION Force majeure, or poor site selection by the customer?
  • 8. CHARACTERISTICS OF RETAIL DATACENTER OR MMR WHOLESALE ○ Power is billed at a fixed MRC, based on breakered (or capped) capacity. ○ Common increments of space are RUs, racks, or private cages. ○ Diverse meet-me room, with access to dozens of IP, lit services, dark fiber providers. ○ Cross-connection is a large profit center for the operator, and may carry significant MRC. ○ Access to 24 x7 remote hands for basic troubleshooting, rack & stack, managed services. ○ Limited options for power redundancy beyond N or N+1; so called “primary” and “redundant” power feeds may terminate on common infrastructure.
  • 9. CHARACTERISTICS OF WHOLESALE DATACENTER WHOLESALE ○ Power is metered and billed based upon consumption (KW/hr or mean KW/month). ○ Common increments of space are private cages or partitioned suites. ○ Limited providers on-site, but should connect to one or more dark fiber provider(s) with entrance diversity. Tethering is common. May also offer extended cross-connect service to nearby MMR(s). ○ Cross-connection is not a profit center for the operator; commonly NRC to cover time & materials. ○ Access to remote hands may be limited. Clients typically provide their own operational staffing. ○ Greater options for power diversity (e.g. 2N[+n] designs). Some customization on power, cooling, and rack designs to meet customer’s needs.
  • 10. SCOPE OF THIS TALK WHOLESALE ○ Most relevant to wholesale colocation, in the hundreds of KWs and larger. ○ Some elements are applicable to retail colocation, e.g. a cage, though you’re probably wasting your and your account rep’s time if you’re using this method to quote out a single cabinet.  ○ Some elements are applicable to larger wholesale suites/pods in the MWs range, however further due diligence may be helpful. ○ We’re not discussing greenfield construction, though the TCO comparatives may help.
  • 11. RFP: INTRO AND BASICS WHOLESALE ○ RFP should be short and sweet, while explaining your requirements. Should not exceed several pages of core requirements. ○ Should be conducive to vendor providing concise, binary, responses, without the hassle of flowery marketing narratives. ○ Should clearly state nature of customer’s business and use case; establish expectations for a response and go-live date. ○ Should clearly establish search radius, leave no room for interpretation as to whether or not a particular location is in-scope for consideration.
  • 12. RFP: BUILD AND POWER WHOLESALE ○ Explain clearly what type of equipment racks or cabinets you need to place, and quantity. Floor plan and rack layout can be helpful as attachments. Establish provider’s “sweet spot” for density (W/ft^2 or KW/cabinet) so you can tweak your layouts appropriately. ○ Establish “day one” and future (12mo, 24mo, …) power requirements, in terms of both base commit and ceiling. Negotiate a ramp beneficial to both parties, if you’re not using all power initially. ○ Establish how power is metered and invoiced; base commitments vs. variable. ○ Establish mean Power Usage Effectiveness (PUE) for facility, and its impact on how power is billed. ○ Establish costs for installing incremental cabinets, NEMA receptacles.
  • 13. RFP: COMMERCIAL TERMS WHOLESALE ○ Establish term length. Long terms (>= 5 years) ensure stability and cost predictability for the purchaser, as well as certainty for the vendor. ○ Establish YoY escalations, if applicable. Solidify language for additional pricing increases, e.g. notice period, commensurate to increased costs from power utility. ○ Establish “look back” period for incorrect billings. Ensure it’s bilateral; same period for billing disputes initiated by customer, and billing corrections issued by vendor…
  • 14. RFP: CABLING WHOLESALE ○ Establish rates (NRC and MRC) for all common types of cross-connections: Cat5e, SMF; are increases permitted during the contract term? ○ Establish policies for running your own data connections inside your datacenter space, using your own materials and labor. ○ Establish facility’s policy on unionized labor. Is there any type of non-electrical work (e.g. bolting of cabinets, intra-suite data cabling) that you’re not allowed to perform by yourself? ○ Develop with the facility a mutually agreeable plan for wire tray placement, rack placement, cable plant, etc.
  • 15. RFP: COMMUNICATIONS WHOLESALE ○ “Provider ABC is on-net” is, itself, not a complete answer: ○ Develop list of on-site IP and telco providers you’re looking to purchase from. ○ Drill down to determine which building entrance[s] are utilized; underlying dark fiber providers and routes are into the street. Also look for convergence points further away. ○ Vendor KMZ files overlayed into Google Earth are your friends. Some vendors have commissioned reports to help with this planning, also. ○ Discuss relative strengths and weaknesses of aerial vs. buried fiber.
  • 16. RFP: OIX-2 CERTIFICATION WHOLESALE ○ My employer (Packet) asks this of all RFP respondents. ○ We view OIX-2 as a good indicator of transparency in operations, willingness to promote a diverse carrier/interconnection ecosystem. ○ We understand that certifying every single site in a provider’s portfolio won’t happen overnight, however [un]willingness to certify a particular site is a telling conversation.
  • 17. RFP: OTHER IDEAS WHOLESALE ○ Review history of planned maintenance events for past 12+ months, and upcoming 3+ months. ○ Review history of unplanned site outages for past 24+ months. ○ Establish access methods/controls into the datacenter, and private cage or suite; multiple “factors”. ○ Review policy on CCTV placement, retention, customer access. Discuss placement of your own cameras, to augment the provider’s systems. ○ Confirm that temperature and RH will be maintained in accordance with (e.g. ASHRAE) norms. ○ Review SLA threshold and remedies for loss of power or cooling.
  • 21. Documents are here: RFP: http://baremet.al/packet-dc- rfp TCO Model: http://baremet.al/packet-dc-tco Questions or comments: asr@packet.net